Updated_Water_Tank_Cleaning_Method_Statement

This document outlines the method statement for tank chlorination and sterilization at the 10th Mile Booster Station, detailing the procedures for cleaning, testing, and chlorination to meet health and safety standards. It includes the scope of work, required materials and equipment, work methodology, and responsibilities of personnel involved in the project. Additionally, it emphasizes health, safety, and environmental protocols to ensure safe operations on site.

Uploaded by

linnekergelau
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
9 views

Updated_Water_Tank_Cleaning_Method_Statement

This document outlines the method statement for tank chlorination and sterilization at the 10th Mile Booster Station, detailing the procedures for cleaning, testing, and chlorination to meet health and safety standards. It includes the scope of work, required materials and equipment, work methodology, and responsibilities of personnel involved in the project. Additionally, it emphasizes health, safety, and environmental protocols to ensure safe operations on site.

Uploaded by

linnekergelau
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 10

EMPLOYER:

KUCHING WATER BOARD


Jalan Batu Lintang,
93200 Kuching,
Sarawak,
Malaysia

CONSULTANT:

CONSULTANT SHC SDN BHD

CONTRACTOR:
COIS JAYA PELANGI SDN BHD

PROJECT:
Upgrading of 10th Mile Booster Station
(Contract No. KWB/CON.8/1/2023)
[PROJECT DETAIL]
Upgrading of 10th Mile Booster Station
SCALE:
TITLE:

Method Statement for Tank Chlorination and Sterilization NTS

Name Designation Signature


Prepared by: Project Engineer
Checked by: Project Manager

1
METHOD STATEMENT FOR TANK CHLORINATION AND STERILIZATION

1. Title
This method statement This method statement outlines the step-by-step procedure for the
cleaning, testing, and chlorination of the extended water tank, ensuring compliance with
health, safety, and quality standards at 10th Mile Booster Station no.2 – Upgrading of 10th
Mile Booster Station

2. Reference

Reference is made to the documents and drawings below:

i. Project Technical Specification – Upgrading of 10th Mile Booster Stations

3. Scope of Work

3.1 General Description

This method of statement highlights how general concreting work is carried out on
site. The scope of works includes formwork installation, reinforcement placing and
concreting works.

3.2 Plant, Tools& Equipment’s


Plant, tools and equipment to be used are as follow:

i. Excavator

ii. Concrete pump


iii. Concrete bucket
iv. Concrete vibrator
v. Water pump
vi. Mixer truck
vii. Wheelbarrow
viii. Electrical drills
ix. Leveling equipment
x. Miscellaneous hand tools

2
METHOD STATEMENT FOR TANK CHLORINATION AND STERILIZATION

3.3 Materials
Materials to be use:
i. Ready mix concrete;
ii. Mild Steel Formwork (RC Tank Wall extension only) and timber formwork for others;
iii. Reinforcement bars;

3.4 Site Planning


i. All plant and equipment must be checked at least one day earlier to avoid unnecessary
breakdown which can disrupt the whole process;

ii. Formworks, reinforcement, concrete cover, spacing, positions and cleanliness must be
checked before concreting carried out;

iii. Relevant inspection check list will be use;


iv. Design mix must be approved by the client and consultant and subsequent cube test to be
carried out. The 28 days test results must satisfy the design mix criteria;
v. Plan the location of constructions joints;
vi. Before commencement of concreting works, all the survey and pegging of the required
works area are to be marked;
vii. 2 concrete vibrators will be provided, 1 will be use during concrete pouring meanwhile
another 1 will be spare in case of break down;
viii. Ensure access to the area of concreting is safe. Excavation area required to be properly
barricaded to prevent fall. Contractor shall prepare required access for workers and
machineries into and around the works area;
ix. Pumping arrangement shall be adequate to ensure no delays in construction;
x. Concreting work is not allowed, if the concrete is ready for more than two (2) hours from
the start of mixing time;

3.5 Work Methodology


The erection of concreting work:
A. For Structure with Piling, Pile Cut Off
i. The elevation of pile cut off levels shall follow the reference drawings, piling plan and
foundation drawing spec;
ii. A level instrument shall be used for measurement of pile cut-off (PCO) elevation. Pile
head and starter bar length must follow according to IFC drawing;
3
METHOD STATEMENT FOR TANK CHLORINATION AND STERILIZATION

iii. For a neat pile head finishing, a concrete cutter shall be used to cut the pile. Any loose
concrete to be removed;
iv. The cut off pile shall be disposed to legal disposal area;
v. If cut off level at pile joint, shall refer to consultant for remedial works;
vi. To take as built for pile cut off position, if deviation more than 75mm shall refer to
consultant;
vii. During pile cutting, the top part of pile (longer than 1m) must hold by excavator using
chain/web sling to avoid any danger to worker;

B. Lean Concrete
i. The dimension of exaction and condition of compaction bottom surface shall check and
inspect prior to do lean concreting work
ii. Ready-mix concrete will be poured to required thickness of the lean concrete
iii. A manual tool shall be used to compact and level the concrete

C. Installation of Reinforcement Bar


i. Prior for rebar installation, incoming material of rebar shall be inspected to
correctness of size, dimension, cleanliness and fulfilled all the requirement.
ii. Rebar must be tie firmly using steel wire.
iii. To achieve minimum concrete cover as per drawing, sufficient concrete spacer to be
use. Concrete spacer must be equivalent grade with concrete material.

D. Pouring and Curing Concrete


i. Alignment and strength of formwork shall be inspected prior to concreting works etc.
“the installation of bracing supports (Timber post/Steel Post) for the MS formworks @
every 1.0m c/c for each MS formwork to prevent any concrete leakage” during the
concreting works.
ii. Arrangement of reinforcement-bar shall be inspected;
iii. Formwork and re-bar shall be clean up where all formwork and reinforcement
contained inside shall be clean and free from muddy water immediately before placing
of the concrete. Concrete level and concrete cover again to be inspect;
iv. Steel formwork shall be spray by suitable amount of water to avoid heat on formwork
surface during concrete pouring;
v. Water stops approve materials shall be install at adequate position for every concrete
4
METHOD STATEMENT FOR TANK CHLORINATION AND STERILIZATION

joint (at 1.2m height or 2.4m height subject to MS steel formwork installation) prior to
concreting works (RC Tank Wall extension).
vi. Check and ensure that ready-mix concrete is same grade as specified concrete prior to
pouring;
vii. Perform slump test for truck mixer. For every delivery, concrete slump more than
design require shall be rejected;
viii. A compressive strength test for every 20m3 delivery batch shall be taken as sample
(cube), each set with 6 sample of cubes, 3 for 7th days cube test and 3 for 28th days cube
test;
ix. The concrete shall be compacted using sufficient vibrators;
x. Immediately after compaction and 7 days thereafter the concrete shall be protected
against weather, including rain and from drying out;

E. Removal of Formwork
i. The removal of formwork shall comply to the minimum days as specified and without
damaging the concrete;
ii. After the task complete, the work area shall be cleaned;

3.6 Checklist/ Record


i. Approval chit
ii. Reinforce concrete inspection form; Item 1

5
METHOD STATEMENT FOR TANK CHLORINATION AND STERILIZATION

3.7 Organization, Responsibilities& Supervision

Designation Responsibilities
Contractor’s  Ensuring the quality of materials, resources, tools and equipment
Representative of the project are in good condition.
 Assessing quality provide by the consultants, suppliers and
subcontractors for the project.
 Inspect and review construction progress to ensure compliance
with quality requirement and method statement.
 Monitor quality of works done by site workers on daily basis.

Site Engineer  Maintain high standard quality of inspection, test and method for
all construction process.
 Review and maintain quality of all materials at site.
 Perform inspection and checking for quality at the site and ensure
activities are as per approved method statement and inspection
test& plan.
 Coordinate with KWB quality representative on site for inspection.
 Attending technical meeting.

Site Supervisors  Assist site engineer on implementation, monitoring and control of


quality.
 To report and discuss site activities and site problem involving
quality to site engineer.
 Ensure all subcontractor works completed in accordance to
specification and high quality.

6
METHOD STATEMENT FOR TANK CHLORINATION AND STERILIZATION

3.8 Manpower

i. Site Safety Supervisor 1


ii. Site Supervisor 1
iii. Operator 5
iv. Skill workers 3
v. General Worker 7

4. Health, Safety and Environment

4.1 References
i. Upgrading of 10th Mile Booster Station - Project Safety Plan

4.2 Health, Safety and Environment


Responsibility and procedures for health and safety working environment for the safe
operation described as follows:

i. To ensure all the workers and key personnel should wear appropriate Personal
Protective Equipment (PPE).
ii. PPE to be worn at all times when in the vicinity of working operations.
iii. Steel formwork and other related materials shall be stacked properly near the
working place;
iv. Scaffolding to be braced adequately, checked for the load carrying capacity and
ensure no overloading;
v. Lifting, manual transporting of conventional formwork materials must be carried ny
by experienced workers who are properly trained;
vi. Throwing of debris from height strictly prohibited;

vii. Minor accidents shall be treated with first aid and refer to nearby medical clinics
or hospitals if necessary.
viii. All accident must be recorded by Site Safety Supervisor as per HSE plan.

ix. Safety signboards and barricade will be in place.

7
METHOD STATEMENT FOR TANK CHLORINATION AND STERILIZATION

Appendix A

8
METHOD STATEMENT FOR TANK CHLORINATION AND STERILIZATION

Checklist