Updated_Water_Tank_Cleaning_Method_Statement
Updated_Water_Tank_Cleaning_Method_Statement
CONSULTANT:
CONTRACTOR:
COIS JAYA PELANGI SDN BHD
PROJECT:
Upgrading of 10th Mile Booster Station
(Contract No. KWB/CON.8/1/2023)
[PROJECT DETAIL]
Upgrading of 10th Mile Booster Station
SCALE:
TITLE:
1
METHOD STATEMENT FOR TANK CHLORINATION AND STERILIZATION
1. Title
This method statement This method statement outlines the step-by-step procedure for the
cleaning, testing, and chlorination of the extended water tank, ensuring compliance with
health, safety, and quality standards at 10th Mile Booster Station no.2 – Upgrading of 10th
Mile Booster Station
2. Reference
3. Scope of Work
This method of statement highlights how general concreting work is carried out on
site. The scope of works includes formwork installation, reinforcement placing and
concreting works.
i. Excavator
2
METHOD STATEMENT FOR TANK CHLORINATION AND STERILIZATION
3.3 Materials
Materials to be use:
i. Ready mix concrete;
ii. Mild Steel Formwork (RC Tank Wall extension only) and timber formwork for others;
iii. Reinforcement bars;
ii. Formworks, reinforcement, concrete cover, spacing, positions and cleanliness must be
checked before concreting carried out;
iii. For a neat pile head finishing, a concrete cutter shall be used to cut the pile. Any loose
concrete to be removed;
iv. The cut off pile shall be disposed to legal disposal area;
v. If cut off level at pile joint, shall refer to consultant for remedial works;
vi. To take as built for pile cut off position, if deviation more than 75mm shall refer to
consultant;
vii. During pile cutting, the top part of pile (longer than 1m) must hold by excavator using
chain/web sling to avoid any danger to worker;
B. Lean Concrete
i. The dimension of exaction and condition of compaction bottom surface shall check and
inspect prior to do lean concreting work
ii. Ready-mix concrete will be poured to required thickness of the lean concrete
iii. A manual tool shall be used to compact and level the concrete
joint (at 1.2m height or 2.4m height subject to MS steel formwork installation) prior to
concreting works (RC Tank Wall extension).
vi. Check and ensure that ready-mix concrete is same grade as specified concrete prior to
pouring;
vii. Perform slump test for truck mixer. For every delivery, concrete slump more than
design require shall be rejected;
viii. A compressive strength test for every 20m3 delivery batch shall be taken as sample
(cube), each set with 6 sample of cubes, 3 for 7th days cube test and 3 for 28th days cube
test;
ix. The concrete shall be compacted using sufficient vibrators;
x. Immediately after compaction and 7 days thereafter the concrete shall be protected
against weather, including rain and from drying out;
E. Removal of Formwork
i. The removal of formwork shall comply to the minimum days as specified and without
damaging the concrete;
ii. After the task complete, the work area shall be cleaned;
5
METHOD STATEMENT FOR TANK CHLORINATION AND STERILIZATION
Designation Responsibilities
Contractor’s Ensuring the quality of materials, resources, tools and equipment
Representative of the project are in good condition.
Assessing quality provide by the consultants, suppliers and
subcontractors for the project.
Inspect and review construction progress to ensure compliance
with quality requirement and method statement.
Monitor quality of works done by site workers on daily basis.
Site Engineer Maintain high standard quality of inspection, test and method for
all construction process.
Review and maintain quality of all materials at site.
Perform inspection and checking for quality at the site and ensure
activities are as per approved method statement and inspection
test& plan.
Coordinate with KWB quality representative on site for inspection.
Attending technical meeting.
6
METHOD STATEMENT FOR TANK CHLORINATION AND STERILIZATION
3.8 Manpower
4.1 References
i. Upgrading of 10th Mile Booster Station - Project Safety Plan
i. To ensure all the workers and key personnel should wear appropriate Personal
Protective Equipment (PPE).
ii. PPE to be worn at all times when in the vicinity of working operations.
iii. Steel formwork and other related materials shall be stacked properly near the
working place;
iv. Scaffolding to be braced adequately, checked for the load carrying capacity and
ensure no overloading;
v. Lifting, manual transporting of conventional formwork materials must be carried ny
by experienced workers who are properly trained;
vi. Throwing of debris from height strictly prohibited;
vii. Minor accidents shall be treated with first aid and refer to nearby medical clinics
or hospitals if necessary.
viii. All accident must be recorded by Site Safety Supervisor as per HSE plan.
7
METHOD STATEMENT FOR TANK CHLORINATION AND STERILIZATION
Appendix A
8
METHOD STATEMENT FOR TANK CHLORINATION AND STERILIZATION
Checklist
9
10