Free PMP Course: Performance Tips&Tricks
Free PMP Course: Performance Tips&Tricks
Performance Tips&Tricks
BEN HAMOUDA CONSULTING
by Ahmed Ben Hamouda
4
10 Test Questions
5
Correct Answer
Question 1 D
A project team uses the Internal Rate of Return (IRR) occasionally to select the project
projected to be most beneficial to the company. On one such occasion the IRR figures for the
four projects were:
Project A = 5%, Project B = 0%, Project C = 3% , Project D = 10%.
Which of these projects should be selected based on these IRR figures provided?
A. Project A
B. Project B
C. Project C
D. Project D
6
Correct Answer
Question 2 A
Given the following burndown chart, select the iteration where the team was working with
more velocity than planned.
A. Iteration 1
B. Iteration 4
C. Iteration 2
D. Iteration 3
7
Correct Answer
Question 3 C
During project execution, a project manager discovers that the budget at completion has
shifted significantly and is higher than expected.
A. Adjust the original budget estimates with the current cost variance.
B. Negotiate the project changes and adjust stakeholder expectations.
C. Perform a root cause analysis of the project performance.
D. Review the activity duration to reforecast the project completion date.
8
Correct Answer
Question 4 B
A project manager is leading a project which shows a trend to exceed the cost baseline.
A. Ask the project sponsor for assistance in getting the budget back on track.
B. Meet with the project team to analyze the actual cost to determine deviations.
C. Inform the stakeholders that the project will be finished over budget.
D. Issue a change request including the analysis to increase the budget
9
Correct Answer
Question 5 D
During the last sprint review, the stakeholder complained that the product was missing many
features they had been expecting. The project team argued that every increment met the
acceptance criteria and was approved by the stakeholder.
The cost performance index (CPI) of the project is 1.15 and the schedule performance index
(SPI) is 1.43.
A. Ask the project team to perform the modifications since the project budget and schedule
can support them.
B. Ask the stakeholder to submit a change request to increase the budget and time for the
modifications requested.
C. Explain to the stakeholder that since the acceptance criteria for every increment were met
the project can be closed.
D. Analyze the reason for the gap in understanding with both sides and negotiate a solution.
10
Correct Answer
Question 6 C
You are managing a project which was budgeted at 1,250,000$ and scheduled to be completed
within six months. During project execution, the sponsor asked you about the status of the
project. You collected the needed data to calculate earned value measurements. You found
that the project is 35% completed although it should be 40% completed. You have already
spent 550,000$ to reach this point in the project.
11
Correct Answer
Question 7 B
During measuring project performance for a product development project against project
baselines, you found that the schedule performance index (SPI) of 0.93 and the cost
performance index (CPI) of 0.82.
12
Correct Answer
Question 8 A
The project manager is analyzing project performance using earned value management tool.
He determines that the cost variance is -$10,000.
13
Correct Answers
Question 9 A&D
A. Adjust the working procedures to streamline and improve efficiency with the current
resources.
B. Change the critical path by replacing some critical path activities with activities that have
float.
C. Increase the number of resources to get more people involved and get activities done faster.
D. Rearrange the schedule so that some activities on the critical path can be done
concurrently to reduce the project duration.
E. Ask the resources to work overtime to accelerate the project and achieve better results.
14
Correct Answer
Question 10 A
You are managing a project that is experiencing cost overruns and schedule delays. The
Schedule Performance Index (SPI) is 0.85, and the Cost Performance Index (CPI) is 0.75.
A. The project is over budget and behind schedule, and if this trend continues, the final cost
will be higher than planned.
B. The project is under budget but behind schedule, requiring corrective action to improve
schedule performance.
C. The project is ahead of schedule but over budget, requiring cost control measures.
D. The project is within budget and on track to meet the deadline, requiring no corrective
action.
15
Thank You
for learning with us!
16