chapter 6 resource planning systems
chapter 6 resource planning systems
which went live in January, is bringing the complexity of its highly customized products under
control.
Ermanno Porro, Sanlorenzo general manager, explains that the specialist yacht builder's move
into making 28-35m plastic and fiberglass yachts, 40m aluminum super-yachts and 44m steel
It also needed to improve monitoring of production steps on the shop floor, and all the way
from
order to delivery. And the system had to support a program to optimize and manage custom
He says Sanlorenzo chose ERP Visual for its ability to manage complex manufacturing
environments, as well as to streamline order management and workflow. The company also
needed ability to transfer two-way data with Microsoft Project, its preferred live management
system.
“Our business is centered on producing highly prestigious yachts that are tailored to the precise
requirements of our customers. ERP Visual will help us improve our order management
process,”
says Porro. “We liked Infor because it enables us to extend our ERP solution with other
modules
meet demand. In the context of resource planning, capacity refers to the maximum
production plan with capacity; this directly affects how effectively the organization
deploys its resource in producing goods and services. Developing feasible operations
schedules and capacity plans to meet delivery due dates and minimize waste in
dates and eliminate waste is becoming more complex. The problem is compounded in an
integrated supply chain, where a missed due date or stockout cascades downstream,
magnifying the bullwhip effect and adversely affecting the entire supply chain.
to balance capacity and output. Capacity may be stated in terms of labor, materials or
equipment. With too much excess capacity, production cost per unit is high due to idle
workers and machinery. However, if workers and machinery are stressed, quality levels
are likely to deteriorate. Firms generally run their operations at about 85 percent capacity
to allow time for scheduled repairs and maintenance and to meet unexpected increases
in demand.
demonstrate the hierarchical planning process. This chapter also discusses the evolution
of the manufacturing planning and control system from the material requirements
Operations Planning
Operations planning is usually hierarchical and can be divided into three broad categories: (1)
long-range, (2) intermediate or medium-range and (3) short-range planning horizons. While the
distinctions among the three can be vague, long-range plans usually cover a year or more, tend
to be more general, and specify resources and outputs in terms of aggregate hours and units.
Medium-range plans normally span six to eighteen months, whereas short-range plans usually
cover a few days to a few weeks depending on the type and size of the firm. Long-range plans
are established first and are then used to guide the medium-range plans, which are
subsequently used to guide the short-range plans. Long-range plans usually involve major,
strategic decisions in capacity, such as the construction of new facilities and purchase of capital
equipment, whereas medium-range plans involve minor changes in capacity such as changes in
employment levels. Short-range plans are the most detailed and specify the exact end items
and quantities to make on a weekly, daily or hourly basis. Figure 6.1 shows the planning
horizons and how a business plan cascades into the various hierarchical materials and capacity
plans. The aggregate production plan (APP) is a long-range materials plan. Since capacity
expansion involves the construction of a new facility and major equipment purchases, the
aggregate production plan’s capacity is usually considered fixed during the planning horizon.
The aggregate production plan sets the aggregate output rate, workforce size, utilization and
inventory and/or backlog levels for an entire facility. The master production schedule (MPS) is a
medium-range plan and is more detailed than the aggregate production plan. It shows the
quantity and timing of the end items that will be produced. Material requirements planning
(MRP) is a short-range materials plan. MRP is the detailed planning process for component
parts to support the master production schedule. It is a system of converting the end items
from the master production schedule into a set of time-phased component part requirements.
Material requirements planning was first developed in the 1960s. As it gained popularity
among manufacturers in the 1980s and as computing technologies emerged, MRP
grew in scope into manufacturing resource planning (MRP-II). MRP-I] combined MRP
planning and other operations planning software modules. Eventually, the MRP-II system
evolved into enterprise resource planning (ERP) in the 1990s.
Distribution requirements planning (DRP) describes the time-phased net requirements from
central supply warehouses and distribution centers. It links production with
annual business plans and demand forecasts into a production plan for all products.
As shown in Figure 6.1, demand management includes determining the aggregate demand
based on forecasts of future demand, customer orders, special promotions and safety
stock requirements. This forecast of demand then sets the aggregate utilization, production
rate, workforce levels and inventory balances or backlogs. Aggregate production
plans are typically stated in terms of product families or groups. A product family consists
processes. For example, an all-terrain vehicle (ATV) manufacturer who produces both
automatic and manual drive options may group the two different types of ATVs
together, since the only difference between them is the drive option.
Production processes and material requirements for the two ATVs can be expected to be very
similar
The planning horizon covered by the APP is normally at least one year and is usually
extended or rolled forward by three months every quarter. This allows the firm to see its
capacity requirements at least one year ahead on a continuous basis. The APP disaggregates
the demand forecast information it receives and links the long-range business plan to the
medium-range master production schedule. The objective is to provide
sufficient finished goods in each period to meet the sales plan while meeting financial
Costs relevant to the aggregate planning decision include inventory cost, setup cost,
machine operating cost, hiring cost, firing cost, training cost, overtime cost and costs
incurred for hiring part-time and temporary workers to meet peak demand. There are
three basic production strategies that firms use for completing the aggregate plan: (1)
the chase strategy, (2) the level strategy and (3) the mixed strategy. Example 6.1 provides
an illustration of an APP.