PMP Earned Value Management (EVM) Calculation Explained
PMP Earned Value Management (EVM) Calculation Explained
Planned Value (PV) — The budgeted value of the work completed so far at a specific date
example: at end of week 4, altogether 4 houses should be completed, the PV is US$4000
Earned Value (EV) — The actual value of the work completed so far at a specific date (refer to the “Notes on Earned Value Measurement”
section below)
example: by end of week 4, only 3 houses are completed, the EV is US$3000
Actual Cost (AC) — The total expenditure for the work so far at a specific date
example: by end of week 4, US$4000 was spend, the AC is US$4000
EVM is based on monitoring these three aspects along the project in order to reveal the health of the project with the following indices:
Schedule Variance (SV) — difference between PV and EV, to tell whether the project work is ahead of / on / behind schedule
SV = EV – PV
If the project is behind schedule the SV will be negative (i.e. achieved less than what planned)
If the project is on schedule the SV = 0
If the project is ahead of schedule the SV will be positive (i.e. achieved more than what planned)
example: by end of week 4, the SV = EV – PV = US$3000 – US$4000 = -US$1000 (behind schedule)
Schedule Performance Index (SPI) — ratio between EV and PV, to reflect whether the project work is ahead of / on / behind schedule in
relative terms
SPI = EV/PV
If the project is behind schedule the SPI < 1 (i.e. achieved less than what planned)
If the project is on schedule the SPI = 1
If the project is ahead of schedule the SPI > 1 (i.e. achieved more than what planned)
example: by end of week 4, the SPI = EV/PV = US$3000/US$4000 = 0.75 (behind schedule)
Cost Variance (CV) — difference between EV and AC, to tell whether the project work is under / on / over budget
CV = EV – AC
If the project is over budget the CV will be negative (i.e. achieved less than spent)
If the project is on budget the CV = 0
If the project is under budget the CV will be positive (i.e. achieved more than spent)
example: by end of week 4, the CV = EV – AC = US$3000 – US$4000 = -US$1000 (over budget)
Cost Performance Index (CPI) — ratio between EV and AC, to reflect whether the project work is under / on / over budget in relative terms
CPI = EV/AC
If the project is over budget the CPI < 1 (i.e. achieved less than spent)
If the project is on budget the CPI = 1
If the project is under budget the CPI > 1 (i.e. achieved more than spent)
example: by end of week 4, the CPI = EV/AC = US$3000/US$4000 = 0.75 (over budget)
Note both SV and SPI / CV and CPI give similar information on schedule / budget but the indices will give more insights into the actual performance
with a meaning comparison.
From my experience, the most difficult process of solving EVM problems for PMP® Exams is to identify the PV, EV and AC from the wordy
calculation questions. Then you will just have to recall the correct formula to substitute the values into to get the answer — the question will usually
ask you directly about the actual indices to get.
Estimate at completion (EAC) — as the project goes on, there may be variations into the actual final cost from the planned final cost, EAC is a
way to project/estimate the planned cost at project finish based on the currently available data
The following formulas can be used to calculate EAC based on which information and conditions given in the question:
EAC = BAC/CPI
If we believe the project will continue to spend at the same rate up to now
The delay is caused by reasons which is likely to continue (e.g. labour with less skilled than expected)
example: the EAC for the housing project = US$10000 / 0.75 = US$13333
EAC = AC + (BAC-EV)
If we believe that future expenditures will occur at the original forecasted amount (no more delays of the same kind in future)
The delay might be caused by some unforeseen reasons (e.g. typhoon) which is not likely to happen again
example: the EAC for the housing project = US$4000 + (US$10000 – $3000) = US$11000
EAC = AC + [(BAC-EV)/(SPI*CPI)]
If we believe that both current cost and current schedule performance will impact future cost performance
The performance of the project will continue with sub-prime standards (over budget and behind schedule)
This formula is less likely to be used for the PMP® Exam
example: the EAC for the housing project = US$4000 + [(US$10000 – $3000)/(0.75*0.75)] = US$16444
To Complete Performance Index (TCPI) — the efficiency needed to finish the project on budget, it is the ratio between budgeted cost of work
remaining and money remaining
TCPI = (BAC-EV)/(BAC-AC)
Use this equation if the project is required to finish within BAC
example: the TCPI for the housing project at end of week 4 = (US$10000 – US$3000) / (US$10000 – US$4000) = 1.167
TCPI = (BAC-EV)/(EAC-AC)
Use this equation if the project is required to finish within new EAC
example: the TCPI for the housing project at end of week 4 with new EAC US$13333 = (US$10000 – US$3000) / (US$13333 –
US$4000) = 0.75
It is likely that you will not be tested on the more difficult ways of measuring earned values. These are included here for your reference only.
Physical Measurement — directly transform the physical measurement of the amount of work completed into EV
example: building 10 houses each has a value of US$1000 expected to be completed in 10 weeks in proportion, earned value of 3 house
built is US$3000
Percentage Complete — directly transform the percentage of the amount of work completed into EV
example: building 10 houses each has a value of US$1000 expected to be completed in 10 weeks in proportion, earned value of 30%
complete is US$3000
Weighted Milestone — a EV is assigned to the 100% completion of each milestone of the work packages with prior agreement with
stakeholders
Fixed Formula — a specific percentage of the overall PV is assigned to the start of a work package and the remaining assigned
upon completion; these must be agreed upon in the project management plan
EVM Charts
In common practices, EVM will also involve plotting the values on a graph in order to help stakeholders concerned to visualize the progress and the
health of the project. More often than not you will find the EV, AC and PV plotted on a graph and you will be asked on the interpretation of the
graph.
If EV line is below PV, the project is behind schedule; if EV is above PV, the project is ahead of schedule.
If AC line is below EV, the project is within budget; if AC is above EV, the project is over budget.
Below is an example of the EVM charts you would be likely to encounter in your PMP® Exam — solid lines represent actual figures while dotted
lines represent forecasted figures:
Judging from the chart above, we can infer that the project is currently over budget and behind schedule.
= 1 On budget
CPI = EV/AC > 1 Under budget
EAC = AC + BAC – EV
the variance is caused by a one-time
Estimate at Completion (EAC) if BAC AC = Actual Cost
event and is not likely to happen
remains the same BAC = Budget at completion
again
EV = Earned Value
EV = Earned value
AC = Actual Cost
2. Top Tips for Tackling PMP EVM Questions (20+ Practice Questions Included)
6. PMP Certification Study Notes 2/3 - Project Management Processes and Knowledge Areas