PMP Formulas-PMBOK6-v1b
PMP Formulas-PMBOK6-v1b
Three point estimate for activity P = pessimistic, M = most For triangular distribution or simple average: EAD = (P + M + O) / 3
duration (EAD) or cost likely, O = optimistic For beta distribution, PERT or weighted average: EAD = (P + 4M + O) / 6
Standard Deviation of activity (or cost) SDactivity (or σactivity ) For beta distribution: (P – O) / 6
Variance of activity (or cost) Varactivity (or σ2 activity ) For beta distribution: ((P – O) / 6)2
Project Duration critical path activities only: (EAD1 + EAD2 + EAD3 + … ) + (# of sigma’s ∗ SDproject )
Estimating early in Planning Budgetary / Top Down / -10% to +25% from actual
Analogous
Estimating late in Planning Definitive / Bottom-up -5% to +10% or +/-10% from actual
Earned Value EV Value of work performed (to date) Σ (PV of completed work)
Budget At Completion BAC Budget assigned for planned work PROJECT COST BASELINE
Estimate To Complete ETC (for atypical variance) Assumes future work to be ETC = BAC – EV
performed as budgeted
COST – Forecasting
ETC (for typical variance) Assumes past performance to ETC = (BAC – EV) / CPI
continue throughout or ETC = EAC – AC
Estimate At Completion EAC Use when original est. is flawed EAC = AC + Bottom-up ETC
EAC (for typical variance) Assumes past performance to EAC = AC + ETC = AC + (BAC – EV) / CPI
continue throughout or EAC = BAC / CPI
Variance At Completion VAC Forecast of variance VAC = BAC – EAC
To-Complete Performance Index TCPI Cost performance necessary to TCPI = (BAC – EV) / (BAC – AC)
achieve BAC or new EAC goal BASED ON BAC
Work remaining divided by funds or TCPI = (BAC – EV) / (EAC – AC)
remaining BASED ON NEW EAC