0% found this document useful (0 votes)
17 views

PMP Formulas-PMBOK6-v1b

The document outlines various formulas and metrics used in project management, particularly focusing on communication, estimating, earned value, and forecasting costs. Key formulas include the three-point estimate for activity duration, standard deviation calculations, and earned value metrics such as Cost Variance and Schedule Performance Index. It also provides guidelines for estimating costs at different project phases and calculating expected monetary value and net benefit.

Uploaded by

mamoied
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
17 views

PMP Formulas-PMBOK6-v1b

The document outlines various formulas and metrics used in project management, particularly focusing on communication, estimating, earned value, and forecasting costs. Key formulas include the three-point estimate for activity duration, standard deviation calculations, and earned value metrics such as Cost Variance and Schedule Performance Index. It also provides guidelines for estimating costs at different project phases and calculating expected monetary value and net benefit.

Uploaded by

mamoied
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Formulas TM

Variable Abbreviation / Name Formula

Project Manager Communication 90 %

Communication channels n(n-1) / 2 n = # of stakeholders

Normal Distribution 1 standard deviation = 1σ = 68.26 % 3σ = 99.73 %


1 SD = 1 sigma = 1σ 2σ = 95.46 % 6σ = 99.99985 %
SCHEDULE/COST – Estimating

Three point estimate for activity P = pessimistic, M = most For triangular distribution or simple average: EAD = (P + M + O) / 3
duration (EAD) or cost likely, O = optimistic For beta distribution, PERT or weighted average: EAD = (P + 4M + O) / 6

Standard Deviation of activity (or cost) SDactivity (or σactivity ) For beta distribution: (P – O) / 6

Variance of activity (or cost) Varactivity (or σ2 activity ) For beta distribution: ((P – O) / 6)2

Standard Deviation of Project SDproject (or σproject ) Var1 + Var2 + Var3 + …

Project Duration critical path activities only: (EAD1 + EAD2 + EAD3 + … ) + (# of sigma’s ∗ SDproject )

Estimating in Initiating Rough Order of Magnitude -25% to +75% from actual

Estimating early in Planning Budgetary / Top Down / -10% to +25% from actual
Analogous

Estimating late in Planning Definitive / Bottom-up -5% to +10% or +/-10% from actual

Expected Monetary Value EMV Probability ∗ Impact [$]

Net Benefit Net Benefit Σ EMV − cost

Variable Abbreviation Description Formula

Actual Cost AC Actual cost incurred for work


COST – Earned Value

performed (to date)

Earned Value EV Value of work performed (to date) Σ (PV of completed work)

Planned Value PV Budget assigned for work


performed (to date)

Cost Variance CV Measure of cost performance CV = EV – AC

Cost Performance Index CPI Measure of cost efficiency CPI = EV / AC

Schedule Variance SV Measure of schedule performance SV = EV – PV

Schedule Performance Index SPI Measure of schedule efficiency SPI = EV / PV

Budget At Completion BAC Budget assigned for planned work PROJECT COST BASELINE

Estimate To Complete ETC (for atypical variance) Assumes future work to be ETC = BAC – EV
performed as budgeted
COST – Forecasting

ETC (for typical variance) Assumes past performance to ETC = (BAC – EV) / CPI
continue throughout or ETC = EAC – AC
Estimate At Completion EAC Use when original est. is flawed EAC = AC + Bottom-up ETC

EAC (for atypical variance) Assumes future work to be EAC = AC + BAC – EV


performed as budgeted

EAC (for typical variance) Assumes past performance to EAC = AC + ETC = AC + (BAC – EV) / CPI
continue throughout or EAC = BAC / CPI
Variance At Completion VAC Forecast of variance VAC = BAC – EAC

To-Complete Performance Index TCPI Cost performance necessary to TCPI = (BAC – EV) / (BAC – AC)
achieve BAC or new EAC goal BASED ON BAC
Work remaining divided by funds or TCPI = (BAC – EV) / (EAC – AC)
remaining BASED ON NEW EAC

You might also like