This document outlines the examination details for the Operation Research subject at Gujarat Technological University, including the date, time, total marks, and instructions for students. It contains a series of questions related to various topics in operation research, such as optimization problems, dynamic programming, queuing theory, game theory, and project management techniques. Students are required to attempt all questions and make suitable assumptions where necessary.

Uploaded by

123vin4i
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
43 views3 pages

Gujarat Technological University

This document outlines the examination details for the Operation Research subject at Gujarat Technological University, including the date, time, total marks, and instructions for students. It contains a series of questions related to various topics in operation research, such as optimization problems, dynamic programming, queuing theory, game theory, and project management techniques. Students are required to attempt all questions and make suitable assumptions where necessary.

Uploaded by

123vin4i
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Seat No.: ________ Enrolment No.

___________

GUJARAT TECHNOLOGICAL UNIVERSITY


BE - SEMESTER–V (NEW) EXAMINATION – WINTER 2023
Subject Code:3151910 Date:18-12-2023
Subject Name: Operation Research
Time:10:30 AM TO 01:00 PM Total Marks:70
Instructions:
1. Attempt all questions.
2. Make suitable assumptions wherever necessary.
3. Figures to the right indicate full marks.
4. Simple and non-programmable scientific calculators are allowed.

Marks
Q.1 (a) What is Operation Research? Discuss the scope of operation research in brief. 03
(b) Explain how and why operation research have been valuable in adding executive 04
decision
(c) A pen manufacturer has two models. A basic model (A) and a standard model 07
(B). Each pen of type B takes twice as long as one of type A and the company
would have time to make a maximum of 2000 pen per day if only the basic model
A is produced. Supply of plastic is sufficient to produce 1500 pen per day both
A and B combined.
The standard version of pen B requires additional accessories of which there are
600 set per day available.
If the company makes a profit of Rs 3 and Rs 5 per pen of type A and B
respectively, how many pens of type A and B each will have to be produced to
maximize the profit?

Q.2 (a) Explain the relationship between stages and states in dynamic programming 03
(b) Define the following terms associated with customers waiting in queue. 04
Balking, Reneging, Jockeying, Collusion
(c) A manufacturing company produce two product A and B. Each product 07
undergoes through operation on machine X and Y. The time required to perform
these operations with the available capacity of machines X and Y in a given
quarter are given below. The market survey has predicted that not more than 450
units of product A and not more than 250 of product B can be sold in the given
quarter. The company wants to determine the product mix to maximize profit.
The unit profits for product A and B are Rs 20 and Rs 40 respectively.

Machine Product time required per unit Available capacity (Hrs)


A B
X 1.5 Hrs. 1 Hrs. 750
Y 1 Hrs. 3 Hrs. 900
Profit Rs 20 Rs 40

Formulate the problem and solve graphically.


OR
(c) Minimize 𝑧 = 3𝑥1 + 5𝑥2 07

Subject to 4𝑥1 + 2𝑥2 ≤ 12


2𝑥1 + 2𝑥2 = 10
2𝑥1 + 5𝑥2 ≥ 10
Use Big – M method to solve the LPP.
1
Q.3 (a) What do you understand by a balanced and unbalanced transportation problem? 03
How unbalanced problem is tackled?
(b) Explain the steps in volved in Modified Distribution method 04
(c) A captain of cricket team has to allot five middle order batting position to five 07
batsmen. The average runs scored by each batsman at this position are given in
table.
Batting Position
III IV V VI VII
A 40 40 35 25 50

Batsman
B 42 30 16 25 27
C 50 48 40 60 50
D 20 19 20 18 25
E 58 60 59 55 53

Make the assignment so that the expected total average runs scored by these
batsmen are maximum.
OR
Q.3 (a) Explain the difference between a transportation problem and an assignment 03
problem.
(b) Describe the mathematical formulation of an assignment problem. 04
(c) Manufacturing firm has three plant A, B and C and three ware house P, Q and R. 07
Their plants capacities and ware house demand and transportation cost per unit
is shown in table.

To
P Q R Capacity
From
A 11 9 6 40
B 12 14 11 50
C 10 8 10 40
Demand 55 45 30 130

Find the most economical shipment to minimize the total transportation costs.
There is no condition any plant can transport the product to any ware house.
Q.4 (a) What is strategy? Explain the difference between pure and mixed strategy. 03
(b) Customer arrives at barber’s shop according to poisson process with a mean inter 04
arrival time of 20 minutes. Customer spend an average time of 15 minutes in the
barber’s chair.
1. What is the probability that a new arrival need not to wait for the barber
to be free?
2. What is the expected number of customers in the barber’s shop?
3. How much time can a customer expect to wait for his turn?
4. How much time can a customer expect to spend in the shop?
(c) A manufacturer, find from his past records that the costs per year associated with 07
a machine with a purchase price of Rs 50,000 are as given below:

Year 1 2 3 4 5 6 7 8
Running cost Rs 15000 16000 18000 21000 25000 29000 34000 40000
(Maintenance
Cost)
Scrap Value 35000 25000 17000 12000 10000 5000 4000 4000

Determine the optimum policy.


OR
Q.4 (a) What do you understand by zero sum with reference to game theory? Explain 03
saddle point in brief.
2
(b) Describe kendell’s notation in respect of queuing theory 04
(c) Assume that present value of one rupee to be spent in a year’s time is Rs 0.90 07
and capital cost of equipment is Rs 6000. Running costs are given in the table:

Year 1 2 3 4 5 6 7
Running Cost 1000 1200 1600 2000 2600 3200 4000

When should the machine be replaced?


Q.5 (a) Explain various steps involved in decision making. 03
(b) Differentiate between CPM and PERT 04
(c) A project schedule has the following characteristic: 07

Activity Duration Activity Duration


1-2 3 4-8 6
1-4 2 5-6 5
1-7 1 6-9 4
2-3 3 7-8 4
3-6 2 8-9 5
4-5 4

Construct a network diagram and find critical path, total duration of the project,
various time estimates.
OR
Q.5 (a) What is the difference between decision making under certainty, under 03
uncertainty and under risk
(b) Define: Activity, Event, Dummy activity, Float 04
(c) A small project is composed of 7 activities whose time estimates are listed in the 07
below table. Activities are identified by their beginning and ending nodes
members

Activity 1-2 1-3 1-4 2-5 3-5 4-6 5-6


Time Optimistic 1 1 2 1 2 2 3
Estimates Most Likely 1 4 2 1 5 5 6
Week Pessimistic 7 7 8 1 14 8 15

1. Draw Project Network


2. Find the expected duration and variance for each activity
3. What is the expected project length and standard deviation?
4. What is the probability that the project will be completed 3 weeks later
than the expected time?

*********