silt trap
silt trap
The Contractor shall provide and maintain everything necessary for proper protection of
materials and Works from any damage by weather, carelessness or otherwise. Any
damage caused shall be made good at the Contractor’s own cost to the approval of the
S.O.
23.1 The Contractor shall at all times comply with the provisions of all statutes and other
related legislation currently in force regarding the environment, safety and health
as listed in APPENDIX A/1 including any revisions to the current regulations.
23.2 The Contractor shall be liable for and shall indemnify the Government against any
damages, expenses, liability, losses, claims, prosecution, proceedings, fines and
penalties caused by any non-compliance or contravention of the above legislation
and regulations.
24.1 The Contractor shall execute the Erosion and Sediment Control Plan (ESCP) and
all control measures as shown on the Drawings in such a manner and order as
directed by the S.O. that will minimize accelerated erosion and sedimentation
during the construction phase. The Contractor shall be responsible for compliance
with MSMA relating to erosion and sediment control.
24.2 The Contractor shall execute ESCP which provides for inspection of erosion and
sediment control devices and facilities on a weekly basis and following precipitation
events, as well as maintenance, replacement or repairs to inadequate or damaged
controls and devices to ensure effective and efficient operation.
24.3 The contractor shall maintain all the temporary works regularly throughout the
construction period, or as directed by the S.O. and making good of any damaged
portions during the course of the works.
24.4 The Contractor shall make proper provision for the drainage of surface water from
the work site including rainwater from surrounding areas which drain on to the site.
24.5 The Contractor shall provide, form, fix and maintain such pumps, chutes, walls,
drains, bunds and other temporary works necessary for the proper drainage of the
Site so that no ponding, flooding or other damage or disturbance is caused to
areas surrounding the works throughout the duration of the Contract.
24.7 The Contractor shall construct construction stabilization access as shown on the
Drawing unless otherwise directed by the S.O. for reducing tracking of mud and dirt
onto public’s roads by Contractor’s vehicles. The construction stabilization access
can be made from aggregates, asphaltic concrete and concrete based on
longevity, required performance and site condition. The use of asphalt concrete
grindings for stabilized construction access/roadway shall be not allowed.
Stabilized construction access shall be maintained by the Contractor until
@HAKCIPTA JKR