Document
Document
C.C.Lining
Was s scheduled for 18.12.2014. Out oftwo bidders, the lowest bid of ₹71.08
crore, (9.95% above
Updated estimatc of ₹64.64 crore) was accepted, and the work was awarded
to Sri P.
Executed, and the work order was issued on 08.06.2015 stipulating the work
to bc completed by
Could not be completed on tine. The Chief Engineer had approved three
EOT’s ‘ from 08.12.2016
Contractor had been paid an un-to-date payment of ₹71.16 crore (37h & part
RA Bill) leaving a
GST, idle charges, equitable rates during the cxtended period, ovcrhcad
charges, bank guarantee
Sharges, loss of profit, hire charges, land compensation, and 18% interest
(08.12.2020). Based on
Charges, and 18% interest on delayed payments were accepled, while the
rest were rejected
Audit noticed that consequent to delay in land acquisition, the contractor had
requested for
Lender rates, ata later date on 18.10.2021 had sought payment a the current
Schedule of Rates
(CSR) plus tcnder premium along with GST. The department agreed to pay
for quantities
Executed up to 2018-19 at the tender rates and for quantities beyond 2018-
19 at the 202 1-22 SR
Acordingly, the balance work amounting to ₹12.93 crore as per tender rates
(valued at ₹23.78
Crore arising due to the adoption of CSR rates in lieu of tender rates, a
supplementary agreement
Was executed on 20.02.2023. The work was stillin progress, the entire
payment of ₹23.78 crore