Module 6 - Equipment Planning
Module 6 - Equipment Planning
Academy
One family of construction machines used for excavation is broadly classified as a crane-
shovel as indicated by the variety of machines in Figure. The crane-shovel consists of
three major components:
• a carrier or mounting which provides mobility and stability for the machine.
• a revolving deck or turntable which contains the power and control units.
• a front end attachment which serves the special functions in an operation.
The type of mounting for all machines in Figure is referred to as crawler mounting,
which is particularly suitable for crawling over relatively rugged surfaces at a job site.
Other types of mounting include truck mounting and wheel mounting which provide
greater mobility between job sites, but require better surfaces for their operation. The
revolving deck includes a cab to house the person operating the mounting and/or the
revolving deck. The types of front end attachments in Figure might include a crane with
hook, claim shell, dragline, backhoe, shovel and pile driver.
A tractor consists of a crawler mounting and a non-revolving cab. When an earth moving
blade is attached to the front end of a tractor, the assembly is called a bulldozer. When
a bucket is attached to its front end, the assembly is known as a loader or bucket loader.
There are different types of loaders designed to handle most efficiently materials of
different weights and moisture contents.
The function of grading equipment is to bring the earthwork to the desired shape and
elevation. Major types of grading equipment include motor graders and grade trimmers.
The former is an all-purpose machine for grading and surface finishing, while the latter
is used for heavy construction because of its higher operating speed.
Blasting requires the use of explosives, the most common of which is dynamite.
Generally, electric blasting caps are connected in a circuit with insulated wires. Power
sources may be power lines or blasting machines designed for firing electric cap circuits.
Also available are nonelectrical blasting systems which combine the precise timing and
flexibility of electric blasting and the safety of non-electrical detonation.
Tractor-mounted rippers are capable of penetrating and prying loose most rock types.
The blade or ripper is connected to an adjustable shank which controls the angle at the
tip of the blade as it is raised or lowered. Automated ripper control may be installed to
control ripping depth and tip angle. In rock tunneling, special tunnel machines equipped
with multiple cutter heads and capable of excavating full diameter of the tunnel are now
available. Their use has increasingly replaced the traditional methods of drilling and
blasting.
Basic types of equipment for paving include machines for dispensing concrete and
bituminous materials for pavement surfaces. Concrete mixers may also be used to mix
Portland cement, sand, gravel and water in batches for other types of construction
other than paving. A truck mixer refers to a concrete mixer mounted on a truck which is
capable of transporting ready mixed concrete from a central batch plant to construction
sites. A paving mixer is a self propelled concrete mixer equipped with a boom and a
bucket to place concrete at any desired point within a roadway. It can be used as a
stationary mixer or used to supply slip form pavers that are capable of spreading,
consolidating and finishing a concrete slab without the use of forms.
(1) operators such as cranes, graders, etc. which stay within the confines of the
construction site, and
(2) haulers such as dump trucks, ready mixed concrete truck, etc. which transport
materials to and from the site.
In both cases, the cycle of a piece of equipment is a sequence of tasks which is repeated
to produce a unit of output. For example, the sequence of tasks for a crane might be to
fit and install a wall panel (or a package of eight wall panels) on the side of a building;
similarly, the sequence of tasks of a ready mixed concrete truck might be to load, haul
and unload two cubic yards (or one truck load) of fresh concrete.
1. Size of the job: Larger volumes of excavation will require larger excavators, or smaller
excavators in greater number.
2. Activity time constraints: Shortage of time for excavation may force contractors to
increase the size or numbers of equipment for activities related to excavation.
3. Availability of equipment: Productivity of excavation activities will diminish if the
equipment used to perform them is available but not the most adequate.
4. Cost of transportation of equipment: This cost depends on the size of the job, the
distance of transportation, and the means of transportation.
5. Type of excavation: Principal types of excavation in building projects are cut and/or
fill, excavation massive, and excavation for the elements of foundation. The most
adequate equipment to perform one of these activities is not the most adequate to
perform the others.
6. Soil characteristics: The type and condition of the soil is important when choosing the
most adequate equipment since each piece of equipment has different outputs for
9. Characteristics of haul units: The size of an excavator will depend on the haul units if
there is a constraint on the size and/or number of these units.
10. Location of dumping areas: The distance between the construction site and
dumping areas could be relevant not only for selecting the type and number of haulers,
but also the type of excavators.
11. Weather and temperature: Rain, snow and severe temperature conditions affect
the job-site productivity of Labour and equipment.
By comparing various types of machines for excavation, for example, power shovels are
generally found to be the most suitable for excavating from a level surface and for
attacking an existing digging surface or one created by the power shovel; furthermore,
they have the capability of placing the excavated material directly onto the haulers.
Another alternative is to use bulldozers for excavation.
The choice of the type and size of haulers is based on the consideration that the number
of haulers selected must be capable of disposing of the excavated materials
expeditiously. Factors which affect this selection include:
1. Output of excavators: The size and characteristics of the excavators selected will
determine the output volume excavated per day.
2. Distance to dump site: Sometimes part of the excavated materials may be piled up in
a corner at the job-site for use as backfill.
3. Probable average speed: The average speed of the haulers to and from the dumping
site will determine the cycle time for each hauling trip.
4. Volume of excavated materials: The volume of excavated materials including the part
to be piled up should be hauled away as soon as possible.
Resource Loading
Resource Aggregation
• Resource aggregation totals each type of resource used in the schedule for each
time unit between scheduled project start and finish.
• Look at the early and late start and finish dates.
• Remember your resource requirements for the critical path doesn’t change only
the float activities
• You like to see a bell curve on your resource aggregation always keeping in mind
the early and late dates on the items with float.
Time-and-Resource-Constrained Scheduling
Resource Leveling
For example, if the first knowledge automation system suggests a conventional scraper
for the job, the second module allows the user to choose a specific model such as a CAT
657G. It then provides the simulation program with cycle time, capacity, and the cost
information for this model. The knowledge automation system provides a simplified
The most appropriate procurement process for any particular project is one that
complements the delivery model and form of contract and is most likely to identify a
preferred tendered/respondent that has the financial capacity, technical capability and
other attributes required to deliver the particular works or services.
The importance of tailoring the procurement process to meet the project requirements
cannot be overstated. In particular, given the unique characteristics of the various
delivery models and contract forms, a ‘one size fits all’ approach to procurement is
simply impractical. As explained by Bremen(2002):
A construction manager needs to insure that resources required for and/or shared by
numerous activities are adequate. Problems in this area can be indicated in part by the
existence of queues of resource demands during construction operations. A queue can
be a waiting line for service. One can imagine a queue as an orderly line of customers
waiting for a stationary server such as a ticket seller. However, the demands for service
might not be so neatly arranged. For example, we can speak of the queue of welds on a
building site waiting for inspection. In this case, demands do not come to the server, but
a roving inspector travels among the waiting service points. Waiting for resources such
as a particular piece of equipment or a particular individual is an endemic problem on
construction sites. If workers spend appreciable portions of time waiting for particular
tools, materials or an inspector, costs increase and productivity declines. Insuring
In the construction industry, a general rule of thumb is that if you don't use a piece of
equipment more than 60 to 70 percent of the time, you should consider renting.
However, if your operation rate exceeds that threshold, consider purchasing or leasing
the equipment. Take the long view and think of future needs-if renting a machine costs
as much or more than owning it, then it's time to buy.
Another consideration that weighs in favor of the purchase option is whether there are
significant cost consequences if you don't have the right equipment immediately
available. For example, would your service trucks be unable to perform a field repair
without welding or generator power, thus idling a critical piece of equipment and
disrupting the job schedule? How versatile is the piece of equipment? If the machine is
used throughout your company on numerous types of jobs, odds are it makes sense to
buy.
Conversely, working with an up-to-date rental house or distributor allows you to gain
experience with new equipment and make head-to-head comparisons before purchase.
Upgrading to new technology might enable you to bid a job more competitively (such as
increasing productivity, reducing fuel costs, improving quality, etc.). Renting offers a
If the value of the equipment rental compared to the total project is low, then the "lost"
profits due to renting are almost immaterial. Conversely, if the equipment costs
comprise a large portion of the job's budget, then a contractor who owns his or her
equipment operates at a competitive advantage.
There are also financial and bookkeeping factors to consider. Rental expenses can be
billed back to the customer or deducted annually as a business expense. Buying a piece
of equipment, however, is a capital expense that must be treated as such at tax time.
You can't deduct the purchased equipment's entire expense during the year in which it
was purchased. The capital costs are then amortised or depreciated over the useful life
of the piece of equipment.
Equipment manufacturers and dealers are working to provide business owners with low
financing to make it more attractive to buy equipment. Many dealers/manufacturers are
even offering zero percent financing over specific time periods and on purchases of
certain sizes.
If you make the decision to purchase a piece of equipment, do your research comparing
different brands and models. Certain machines hold their value much better than other
machines in the same product category and will be worth more when you sell it later.
Especially if you like to cycle in new equipment over a set time period, selecting the
right machine based on annual depreciation and performance might be the financial
difference in the rent/buy decision. Similarly, used equipment available on the market is
typically of a higher quality than it was in the past, especially with dealers and
manufacturers offering certified used equipment.
When considering financial decisions, many contractors overlook the total cost of
equipment management. For example, if you're based in Chicago and successfully bid on
If renting is the best way to go, you need to decide whether to rent from a distributor or
a rental house. There are considerations for both: Rental houses tend to focus on core
construction equipment. Their staff is knowledgeable about a wide range of equipment
and may serve a greater geographical area (if your work is taking you out-of-state or
across country). Distributors tend to have all of the newest releases and specialise in
certain types of equipment, but service may be limited to a specific geographical area.
Do your homework, and you'll find the right fleet of equipment whether you work
locally or nationally.