B. Com. IV Sem MTC Section A
B. Com. IV Sem MTC Section A
ABST
Semester IV
Section – A
Types of contract
1) Fixed Price Contract: The contractor agrees to a fixed contract price or rate.
2) Cost Plus Contract: Under cost plus contract, the contract price is ascertained by adding
a percentage of profit to the total cost of the work. Such type of contracts are entered into
when it is not possible to estimate the contract cost with reasonable accuracy due to
unstable condition of material, labour services, etc.
3) Contract with Escalation Cost: If during the period of execution of a contract, the
prices of materials, or labour etc., rise beyond a certain limit, the contract price will be
increased by the agreed amount. Inclusion of such a clause in a contract deed is called as
“escalation clause”.
2) Incomplete Contract
a) If Loss, Amount transferred to P&L Account
b) If Profit, Some amount transferred to P&L Account and balance kept in reserve
(WIP a/c) as follows:
i) Work Certified is Less Than 25 Percent of Contract:
In this case no profit should be taken to profit and loss account.
ii) Work Certified is equal to or More Than 25 Percent But Less Than 50
Percent of Contract:
In this case amount transferred to the profit and loss account is calculated as
follows:
Estimated 1 Cash Received
X X
Profit 3 Work Certified
B. Commercial Method:
Per Passenger Total Average Passenger
= x
or Tone km Distance or Weight
Illustration: Calculate on the basis of the following information (a) Absolute
Tone-Km and (b) Commercial Tone-Km:
Route of Journey Distance (Km.) Weight Carried (Tones)
Jaipur to Ajmer 130 20
Ajmer to Bhilwara 137 16
Bhilwara to Udaipur 200 10
Udaipur to Jaipur 467 NIL
Solution:
A. Absolute Method: Σ (Actual Distance x Actual Weight)
Tone-Km = (130 x 20) + (137 x 16) + (200 x 10) + (467 x 0)
= 2600 + 2192 + 2000 + 0 = 6792 Ton-km