E-TENDER DOCUMENT
VOLUME-I
Pre-Qualification (Technical) Bid
NAME OF WORK: Operation & maintenance of 37.50 MLD STP based on
Sequential Batch Reactor Technology established in Sector-
10B Vrindavan Yojna no-2, Lucknow.
Tender Notice No. : 1063/M-13/118 Dated 12.03.2025
Important Dates
a) Publishing Date : 17.03.2024
b) Document downloads start date : 17.03.2024 (4:00 P.M.)
c) Bid submission start date : 17.03.2024 (4:00 P.M.)
d) Pre Bid Metting : 24.03.2025 (11:30 A.M.)
d) Bid submission closing date : 02.04.2025 (5:00 P.M.)
e) Opening date of Technical Bid : 03.04.2025 (12:30 P.M.)
f) Opening date of Financial Bid : rduhdh fufonk tkWpksijkUr
EXECUTIVE ENGINEER
CONS. DIV.LUCKNOW-05 UPHDB
LUCKNOW
CONTRACTOR
TECHNICAL BID
1. The complete following information must be filled in the following format by the bidder in
technical bid, otherwise the bid will be treated incomplete and will be liable for rejection.
without cost of bid document and earnest money deposit, bid will be treated incomplete and will
be rejected.
SN Particulars Information to be filled by the tenderer
E-mail Address
Website
2.1 Only those contractors / Firms having O & M experience of SBR based STP of minimum 30.00
MLD capacity-1 nos or 18.75 MLD capacity-2 nos or 15 MLD capacity-03 nos for the period
of minimum 02 year in Govt./ Semi Govt /PSU organization within last 5 years.
2.2 tender Information and Instructions for Tenderers posted on Website(s) shall form part of
Tender Document..
3.0 Those intending tenderers / contractors not registered on the website i.e.
www.etender.up.nic.in , are required to get registered beforehand. If needed they can be
imparted training on online tendering process as per details available on the website i.e.
www.etender.up.nic.in.
4.0 The intending tenderer must have class-III digital signature to submit the E-tender.
5.0 The Tender Document as uploaded can be viewed and downloaded free of cost by anyone
including intending tenderer. But the E-tender can only be submitted after uploading the
mandatory scanned documents such as a RTGS from any Nationalized Bank against EMD &
All other documents shall be as per Notice Inviting e-tender.
d) Technical specification
f) Bill of Quantities
g) Drawings
i) Corrigendum, if any
7.0 The tenderers are required to quote strictly as per terms and conditions, specifications,
standards given in the tender documents and not to stipulate any deviations.
8. After submission of the tender the tenderer can re-submit revised tender any number of
times but before last time and date of submission of tender as notified.
9. When it is desired by UPAVP to submit revised financial tender then it shall be mandatory to
submit revised financial tender. If not submitted then the tender submitted earlier shall
become invalid.
10. On opening date, the tenderer can login and see the tender opening process.
11. Contractor can upload documents in the form of JPG format and PDF format.
12. Contractor to upload scanned copies of all the documents including valid EPF registration/
GST registration/ PAN No. As stipulated in the tender document.
13. If the contractor is found ineligible after opening of tenders, his tender shall become invalid
and cost of tender document and processing fee shall not be refunded.
14. If any discrepancy is noticed between the documents as uploaded at the time of submission
of tender and hard copies as submitted physically by the contractor the tender shall become
invalid and cost of tender document and processing fee shall not be refunded.
15. Notwithstanding anything stated above, UPAVP reserves the right to assess the capabilities
and capacity of the tenderer to perform the contract, in the overall interest of UPAVP. In
case, tenderer’s capabilities and capacities are not found satisfactory, UPAVP reserves the
right to reject the tender.
16. Certificate of Financial Turn Over: At the time of submission of tender, the tender shall
upload Affidavit/ Certificate from Chartered Accountant mentioning Financial Turnover of
last 3 years or for the period as specified in the tender document and further details if
required may be asked from the tenderer after opening of technical tenders. There is no
need to upload entire voluminous balance sheet.
17. In case of Percentage Rate Tender, Contractor must ensure to quote single percentage rate.
The column meant for quoting rate in figures appears in pink colour and the moment rate is
entered, it turns sky blue. The Rate shall be Quoted upto 2 Decimals.
In addition to this, while selecting any of the cells a warning appears that if any cell is left blank
the same shall be treated as “0”. Therefore, if any cell is left blank and no rate is quoted by the
tenderer, rate of such item shall be treated as “0” (ZERO).
18.0 List of Documents to be scanned and uploaded within the period of tender submission:
MEMORANDUM
Name of Work : Operation & maintenance of 37.50 MLD STP based on Sequential Batch
Reactor Technology established in Sector-10B Vrindavan Yojna no-2,
Lucknow.
Estimated Cost : As per Tender.
Cost of Tender Set : Rs. 3000.00 + (GST)
Earnest Money : Rs. 2.00 Lacs
Time of Completion : 01Years
Should this tender be accepted, I/We hereby agree to abide by and fulfill all the terms and
provision of the conditions of contract annexed to the approved set of contract document, or in default
there to forfeit and pay to the U.P.A.V.P. or their successors in office the sum of money mentioned in
the said conditions.
The sum of Rs. 2.00 Lacs (Rupees Two Lac Only) is here with forwarded as earnest
money, the full value of which shall be retained by the Parishad on account the security deposited
specified in clause 1 of the conditions of contract.
INDEX
Pages
S. No. Particulars Remarks
From To
1. Instruction toTenderer 9 13
2. Requirment for Pre-Qualification 14 16
3. Appendix 'A' 17 17
4. Appendix 'B' 18 18
5. Appendix 'C' 19 19
6. Appendix 'D' 20 20
7. Appendix 'E' 21 21
8. Appendix 'F' 22 22
9. Appendix 'G' 23 24
10. Appendix 'H' (Agreement Form) 25 25
11. Appendix 'I' 26 26
13. General Terms &Conditions 27 27
14. Special Conditions 28 32
15. Other Conditions 33 35
16. Scope of work (O&M) 36 55
17. List of Machinary & Equpiment at STP 56 67
18. GPW – 9 68 83
19. Tender Notice 84 84
20. Layout Plan & Other Maps 85 88
1. On line Item rate from only contractors / Firms having O & M experience of SBR based STP of
minimum 30.00 MLD capacity-1 nos or 18.75 MLD capacity-2 nos or 15 MLD capacity-03 nos for the
period of minimum 02 year in Last 5 years Govt. / Semi Govt /PSU organization of relevant field
are invited for the work of “Operation & maintenance of 37.50 MLD STP based on Sequential
Batch Reactor Technology established in Sector-10B Vrindavan Yojna no-2, Lucknow.”
2. The tender document as uploaded can be seen on website www.etender.up.nic.in and can be
downloaded free of cost.
5. Interested Firms/contractor who wish to participate in the tender has also to make following
payments in the form of RTGS of any Scheduled Bank and to be scanned and uploaded to the e-
Tendering website www.etender.up.nic.in within the period of tender submission:
Cost of Tender Document – Rs. 3000.00 + (GST).
shall have to be transferred through RTGS as per E- tender NIT
The tender for the works shall remain open for acceptance for a period of Ninety (90) days from
the date of opening of financial tender. If any tenderer withdraws his tender before the said period
0r issue of letter of acceptance, whichever is earlier, or makes any modifications in the terms and
conditions of the tender which are not acceptable to the UPAVP, then the UPAVP shall, without
prejudice to any other right or remedy, be at liberty to forfeit the said earnest money as aforesaid.
Further the tenderers shall not be allowed to participate in the retendering process of work. The
tendrer has to give the validity of his tender for three months on Rs 100/= non judicial
stamp paper & 1/= revenue stamp on it duly signed as per annexure attached.
9. ACCEPTANCE OF TENDER
UPAVP reserves the right to reject any or all the tenders in part or full without assigning any reason
whatsoever. UPAVP does not bind itself to accept the lowest tender. The UPAVP reserves the right
to award the work to a single party or split the work amongst two or more parties as deemed
necessary without assigning any reason thereof. The Contractor is bound to accept the part work
as offered by UPAVP after split up at the quoted/negotiated rates.
10. The tenders shall be strictly as per the conditions of contract. Tenders with any additional
condition(s)/modifications shall be rejected.
11 The witnesses to the Tender/Contract Agreement shall be other than the tenderer/ tenderers
competiting for this work and must indicate full name, address, and status/occupation with dated
signatures.
12. The acceptance of tender will rest with the UPAVP who does not bind itself to accept the lowest
tender and reserves to itself the right to reject any or all the tenders received without assigning
any reason thereof. Tenders in which, any of the prescribed conditions are not fulfilled or found
incomplete in any respect are liable to be rejected.
13. On acceptance of tender, the name of the accredited representative(s) of the contractor who
would be responsible for taking instructions from Engineer-in-Charge or its authorized
representative shall be intimated by the contractor within 07 days of issue date of letter of Awards
by UPAVP.
15. The time of completion of the entire work, as contained in contract shall be as mentioned in
“Memorandum", which shall be reckoned from the 10th day after issue of the letter of Award by
the UPAVP.
16. Canvassing whether directly or indirectly, in connection with tenderers is strictly prohibited and the
tenders submitted by the contractors who resort to canvassing will be liable for rejection.
The tender award, execution and completion of work shall be governed by tender documents
consisting of (but not limited to) Letter of Award/Letter of work order, Bill of Quantities, Special
Conditions of Contract, General Conditions of Contract Specifications, Drawings. The tenderers shall
be deemed to have gone through the various conditions including sub-soil water conditions,
topography of the land, drainage and accessibility etc. or any other condition which in the opinion
of contractor will affect his price/rates before quoting their rates. No claim whatsoever against the
foregoing shall be entertained.
17. The drawings with the tender documents are Tender Drawing and are indicative only.
18 ADDENDA/ CORRIGENDA
Addenda/Corrigenda to the tender documents may be issued prior to the date of submission of the
tender to clarify or effect modification in specification and/or contract terms included in various
tender documents. The tenderer shall suitably take into consideration such Addenda/Corrigenda
while submitting his tender. The tenderer shall return such Addenda/ Corrigenda duly signed and
stamped as confirmation of its receipt & acceptance and submit along with the tender document. All
addenda/ Corrigenda shall be signed and stamped on each page by the tenderer and shall become
part of the tender and contract documents.
The Bidders are to quote O&M Cost and provide Functional Guarantee based on the following data which shall
be used for technical evaluation of qualifying Bids:
BOD : 200 mg/l
TSS : 250 mg/l
23 Contract Period
The total Contract Period shall be as follows:
O&M Period : 12 Months
The setting and nature of all offices, huts, access road to the work areas and all other temporary
works as may be required for the proper execution of the works shall be subject to the approval of
the Engineer- in-charge.All the equipments, labour, material including cement, reinforcement and
the structural steel required for the enabling/ temporary works associated with the entire Contract-
shall have to be arranged by the Contractor only. Nothing extra shall be paid to the Contractor on
this account.
Tenderer’s attention is drawn to the fact that during the period, the tenders are under
consideration, the tenderers are advised to refrain from contacting by any means, the UPAVP
and/or his employees/ representatives on matters related to the tender under consideration and
that if necessary, UPAVP will obtain clarifications in writing or as may be necessary. The tender
evaluation and process of award of works is done by duly authorized Tender Scrutiny Committee
and this committee is authorized to discuss and get clarification from the tenderers.
1. As per tender Not Less than 100.00 Lacs. Not Less than 12.00 Lacs.
Proof of liquid asset duly certified from banker shall be submitted (original or attested) in Appendix B.
The certificate issued from Bank shall be current (not older than six months from the date of opening
Bid).
The Contractor shall provide the key personnel for performance run minimum qualification and
experience as given below.
The declaration for the technical staff by the contractor will be given in the form attached as Appendix
„D‟ (in the presence of Notary public with details of the required staff).
Executive Engineer
Construction Div.Lucknow-05
U.P.H.D.B. Lucknow
1 2 3 4 5 6 7
Total
Note: Attested Photocopies or original must be attached with this annexure as proof of work done.
Contractor..
APPENDIX “B”
The turn over during the year…………………………….in their accounts have been over
Rs. ………………….Lacs. on the basis of information available with us . We assess their liquid
assets not less than Rs………………………..Lacs
Sl. Particulars of Machinery Tools and Plants, Qty Estimated Cost Approximate
No. Centering and Shuttering (Rs.) Age in Years
& Months
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
I/we undertake that above machineries and tools & plants will remain in good working condition
and in useable form throughout the currency of work.
I/we further undertake that if, there any reduction in the equipments below the limit required for
pre qualification I/we inform Executive Engineer / UPHDB to whom application for pre qualification is
being made within 3 days of its occurance and arrange to make it up within another one week, failing
which the UPHDB will be free to impose any penalty that it may deemed fit which will be final and
binding upon me/us.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
I/we understand that well experience one graduate and one diploma holder as directed by E/I will have
to be deployed by us on the work throughout in case we are entrusted with the execution of the work in
question.
I/We further understand that in the event of non-presence of such engineers the U.P.Housing &
Development Board shall deduct @ 30000.00( Rs. Thirty Thousand) for Degree holder Engineer &
25000.00 (Rs. Twenty Five Thousand) Diploma holder Engineer as the case may be per months from
our bills, which will not be refundable.
I/We further understand that the decision of E/I of the works regards to presence and/or absence of our
our Engineer from the work shall be final and binding upon us.
Warranty Declaration
(On Rs. 100.00 Non Judicial Stamp Paper)
Tenderer/Contractor
Name & Address of the Contractor
AGREEMENT FORM
(For Validity of Rates: To be given on Rs.100.00 Non Judicial Stamp Paper with Rs.1.00 Revenue
stamp Affixed on it and Signed)
And the tenderer hereby also agrees that if subsequent to the submission of his tender the
tenderer amends, alters or modifies the content of this tender which is not acceptable to the U.P.
Housing and Development Board then the tenderer shall be for purpose of the aforesaid conditions,
deemed to have drawn his proposal.
Witness :
1. ................................. Signed By
'kiFkh dk gLrk{kj
iwjk uke
irk
xokg %
1- gLrk{kj---------------------------------------------
uke----------------------------------------------------
irk----------------------------------------------------
-----------------------------------------------------------
2- gLrk{kj---------------------------------------------
uke----------------------------------------------------
irk----------------------------------------------------
-----------------------------------------------------------
1.
2.
3.
4.
5.
Earnest Money is required to be deposited in the shape of RTGS of the any nationalised bank of India duly
pledged in favour of „EXECUTIVE ENGINEER CONSTRUCTION DIVISION Lucknow-05. U.P. HOUSING &
DEVELOPMENT BOARD LUCKNOW‟ with Pre Qualification Bid.
Earnest Money deposited shall be Rs. 2.00 Lacs and the security money shall be 10% of the bonded cost of
the work. The E.M.D. shall be converted into security amont in respectfull of successful tenderer.the balance
amount can be accepted in the shape FDR/CDR any nationalised bank of India duly pledged in the favour of
„EXECUTIVE ENGINEER CONSTRUCTION DIVISION Lucknow-05 U.P. HOUSING & DEVELOPMENT
BOARD LUCKNOW‟.
Tender of the firms who have litigation in court of Law against UPHDB, will not be considered.
Tender of the firms are liable to be rejected who have failed to complete the work timely and work is still
pending for more than one year in the UPHDB.
Executive Engineer Cons.Div. Lko-05/Competent authority reserves right to reject any or all tender without
assigning any reason.
If bidding firms consider to be exempted from uploading any document as required in the bid documents, then
in support of that's exemption, the bidding firm will have to upload the copy of exempation letter
Firms forming joint venture for qualifying in the pre qualification bid of said tender are not eligible.
Executive Engineer
UPHDB
GENERAL
1. These special conditions shall be read in conjunction with the General Conditions of the contract.
Where the provisions of these special conditions are at variance with the provisions of the General
Conditions of the contract, the provisions of these special conditions shall take precedence.
2. The contractor is expected to be well conversant with the conditions of GPW Form 9 as applicable
to works (General conditions of the contract) which shall be part of the agreement.
3. The Tenderer‟s are advised to see carefully the site of work before actually submitting their tender.
The Location of work site at, Lucknow under the scope of this tender can be seen in the office of the
Executive Engineer Construction Division Lucknow-05 U.P. Housing & Development Board,
Lucknow on any working day or on Parishad website www.upavp.com.
Executive Engineer
vf/k'kklh vfHk;Urk
Operating Sewage Treatment Plant to maintain the quality of treated sewage within the
standards prescribed in the Tender, operate electrical equipment during power failures by
operating generators, operate the Centrifuge for sludge drying and treat incoming sewage at
prescribed standards through optimal dosing.
Carrying out daily cleaning of grit channels and removal of screenings and disposal of
floating matter in grit dewatered sludge out of premises.
Carrying out continuous flow measurements of treated & untreated sewage and recording the
same online / offline.
Collecting samples of influent and effluent and analyzing them daily to determine the quality
of sewage and performance of the treatment plant and
Providing security for facilities and system at all times.
b. Contingency Plan
Developing and implementing contingency plans in respect of responses to natural disasters,
periods of power failure, storm water inflow into sewers during monsoon, de-silting of units of
treatment plants, constraint operations or other similar emergencies to maintain the quality of
treated sewage.
c. Energy Audit
The Operator shall take all necessary measures to minimize the power consumption in carrying out its
operations. The energy audit operations shall include, but not be limited to the following.
Reducing electricity consumption by regulating equipment operation through suitable
modifications to the operating schedules.
Maintaining power factor and demand to avoid penalty
Installing more efficient pumping equipment and following better maintenance practices for
electrical installation.
The Contractor shall also advise the Employer from time to time, on improving the quality of
operations, reduction in water / energy losses and betterment practices.
3. Replacing
The Contractor shall utilize the office space, provided by the Employer to establish its
monitoring and reporting office along with computer and peripherals. It shall also obtain a
telephone connection and maintain the same through the Contract period. All data transfers and
updates made to the Employer shall be affected through the said telecommunications medium.
The Contractor shall carry out all reporting indicated below and as set out in this Contract. The
reporting shall include, but not be limited to the following
Daily summary of Operations at Sewage Treatment Plant – A daily report of operation of the
diffuses, agitators, decanter and other equipment at the sewage treatment plants providing
information on the quantity of sewage treated, hours of operation of equipment, energy
consumed and use of chemicals.
Sewage Quality Monitoring – A daily report monitoring the quality of raw and treated
sewage through the analysis of samples.
Sewer / Storm Water Drains / wet well & other units etc. Monthly cleaning report sewer /
storm water drain de-silted and record of silt disposed at disposal sites.
4. Employer‟s Responsibilities
The Employer shall be responsible for procuring obtaining and maintaining Employer
Clearances required, however that the Contractor shall be responsible for maintaining the
The Employer shall supervise the Contractor‟s Operations at all times and notify the Contractor
of any defects that are found. Such checking shall not affect the Contractors responsibilities. The
Engineer may instruct the Contractor to search for a defect and to uncover and test any work that
the Employer considers may have a defect.
The Employer shall be responsible for:
Energy charges and treated effluent testing charges from State PCB if required.
Maintaining administrative control over the personnel, facilities and system.
5. Contractors Responsibilities
The Contractor shall maintain properly and keep intact all assets / works/facilities / system of the
Employer throughout the Contract period and shall hand over the same in good working
condition at the end of the Contract. The Contractor shall not modify or alter any operations
regarding the facilities and / or system without prior written permission of the Employer or its
representative.
The Contractor shall procure all spare parts required for the maintenance of equipment
excluding those to be supplied by the Employer. The Contractor shall warrant to the effect that
all the spares shall be procured from the authorized sources and be of the best quality and fit for
the purpose for which it is being used.
The Contractor is expected to carry out the work in such a manner as not because any damage to
public property on account of negligence or otherwise. The Contractor shall be fully responsible
for making good the damages so caused by him entirely at his own cost.
The assets / works / facilities / systems of the Employer shall be at the risk and in the sole charge
of the Contractor and it shall be responsible for making good any loss or damage there to arising
from any cause whatever including that due to a theft or robbery.
The Contractor shall provide adequate engineering equipment, maintenance staff, inventories
plant and machinery and all other things, whether of a temporary or permanent nature required
for carrying out operations under the Contract.
The Contractor shall carry out its Operations, so far as compliance with the requirement of the
Contract permits, so as not to interfere unnecessarily or improperly with:
- The convenience of the public
- The access to use and occupation of public or private roads and footpaths to or of properties.
Permissions: The Contractor shall obtain all required permissions, sanctions clearances and
permits for carrying out its Operations, including Contractors clearances by self at own cost and
shall be fully responsible for carrying out the operations in a safe and secure manner, consistent
with the law of the land, laws and regulations regarding such facilities and / or System and
directives of any Authority and planning permissions.
Discoveries: All fossils, coins, articles of value or antiquity and structures and other remains or
things of geological or archaeological interest discovered on the Site shall as between the
Employer and the Contractor, be deemed to be the absolute property of the Employer. The
Contractor shall take reasonable precautions to prevent its workmen or any other persons from
removing or damaging any such article or thing and shall, immediately upon discovery thereof
and before removal, acquaint the Engineer of such discovery and carry out the Employer
instructions for dealing with the same.
The Contractor shall be responsible for payment of reinstatement charges for roads, footpaths
and land as per the Employer‟s rates.
The Contractor shall take full responsibility for the adequacy stability and safety of all Site
operations.
The Contractor shall not employ in connection with the operations any child who has not
completed his/her fifteenth year of age. It shall also not employ an adolescent who has not
completed his / her eighteenth year unless he/she is certified fit for carrying out operations as an
adult as prescribed under clause b) of such section (2)(of Section 69 of the factories Act 1948.
The Contractor shall provide its staff, a minimum of two sets of uniforms with the titles the
Employer inscribed on the back and subject to approval of the Employer. Each worker on duty
shall wear a clean uniform whenever on duty.
The Contractor shall be required by the Engineer deliver to it, to such forms and at such
intervals as the Engineer may prescribed a return showing the numbers of the several classes of
staff employed by the Contractor on the site and such other information as the Engineer may
require.
If the Employer asked the Contractor to remove a person who is a member of the Contractor‟s
staff stating the reasons, the Contractor shall ensure that the person leave the site within seven
(7) days and has no further connection with operations under the Contract.
At all times during continuance of the Contract, the Contractor and its sub-contractors
shall abide by all existing and future labour enactment and rules made there under,
regulations, notifications and bye-laws of the Central, State or Local Government. The
If the Employer is caused to pay or reimburse such amounts as may be necessary to carry or
observe, or for non-observance of the provisions stipulated in the notifications/bye-
laws/acts/rules/regulations including amendments if any, on the part of the Contractor and in
connection with labour enactment, the Engineer shall have the right to deduct any money due to
the Contractor including its amount of security deposit. The Engineer shall also have the right to
recover from the Contractor, any sum required or estimated to be required for making good the
loss or damage suffered by the Employer.
B. Contractor‟s Superintendence
The Contractor shall provide all necessary superintendence while carrying out its operations and
as long thereafter as the Employer may consider necessary for the proper fulfilling of the
Contractor‟s obligations under the Contract. The Contractor shall nominate a competent and
authorized representative (Contractor Representative) approved of by the Engineer which
approval may at any time be withdrawn. The Contractor‟s Representative shall give its whole
time to the superintendence of the operations. The Contractor‟s Representative shall receive, on
behalf of the Contractor, instructions from the Engineer which shall be deemed received by the
Contractor.
Management Meetings:
Either the Employer or the Contractor may require the other to attend a management meeting.
The business of a management meeting shall be to review the plans for remaining Operations
and to deal with matters raised in accordance with any advice. The Employer shall record the
business of management meetings and is to provide copies of its record to those attending the
meeting and to the Employer either at the management meeting or after the management
meeting and stated in writing to all who attended the meeting.
The Employer may instruct the Contractor to rectify defects and deficiency in its Operations.
Alternatively, the Employer shall carry out the operations on its own and deduct the amount
incurred in attending to such defaults from the next payment due to the operation. The deduction
of such damages shall not relieve the Contractor from its obligations to carry out the operations,
or from any other of its obligations and liabilities under the Contract.
The Contractor is also expected to carry out the instructions of the Engineer or its representative
from time to time, maintain the System in accordance with good Operating Practices attend to
Customer complaints, refrain from offering operations without due authorization where so
required and follow other requirements under this Contract.
The Contractor shall be subject to the following liquidated damages and penalties for its failure
to carry out its operations as indicated below:
Basis of
Penalty Benchmark Penalty Value
Penalty
Failure to maintain Up to 2 Occurrence/month UPHDB
pH/BOD/COD/TSS within 2 to 5 Occurrences/month ` 1,000/- per Occurrence
prescribed limits. Detected as per
reports of daily samples sent to 5 to 10 Occurrences/month ` 10,000/- per Occurrence
PCB by the Employer and outlet
quality to be achieved as per Above 10 Occurrences/month Termination
Tender provisions
Over Power Consumed: For power increased beyond 2.00/ KW.hr of extra
The Contractor has to establish current Base Level based on power consumed
and get approved from the Effluent Discharge Schedule Or
Engineer-in-charge the “Maximum and persisting over a two- @ Prevailing Tariffs
Guaranteed Power Consumption” month Billing Period applied by State
for entire Plant. Electricity Authority
whichever is higher.
Inadequate maintenance of Plant / For each Case detected. ` 1000/- per Occurrence
Facilities
Inappropriate de-silting of Sewers Per Occurrence ` 1,000/- per Occurrence
and clearing of silt in Premises.
Inadequate Contingency Plan For each Case submitted. ---
Delay in recording of Energy Per Occurrence ` 1000/- per Occurrence
Meter Reading, Power Failure
Time or Diesel Consumption
Duty Staff not wearing uniform or Per Occurrence ` 1000/- per Occurrence
it being dirty.
Non compliance of Customer‟s Per Occurrence ` 1000/- per Occurrence
complaints in time or adequately.
Non-operating any working 1000/-per Drive hour
Equipment/Drive more than 4 after permissible limit
more than 4 hours
hours except the Equipment/ of4 hours
Drive under maintenance
8. Confidentiality
The Contractor shall cause the persons related to the Operator not to, without the prior written
consent of the Employer, at any time, divulge or disclose to any person or use for any purpose
unconnected with the operations, proprietary material under this contraction. This shall not
apply to information.
The Contract shall, whenever required take necessary steps to ensure that all persons employed
by it, under this Contract comply with the Indian Official Secrets Act 1923 (XIX of 1923) and
agree that it applies to them and shall continue to apply even after completion of this Contract.
No photographs of the Facilities or System or any part there of or equipment employed thereon
shall be taken or permitted by the Contractor to be taken by any of its employees or any
employees of its sub-Contractor without the prior approval of the Engineer in writing and no
such photographs shall be published or otherwise circulated without the approval of the
Engineer in writing.
The Employer shall use its best efforts to ensure that the confidential proprietary information
relating to the Contractor is not made public. However, the Employer shall not be liable in any
manner whatsoever in case such information becomes public.
9. Assignment
The Contractor shall not subcontract the whole of the operations or a substantial part thereof.
Except where otherwise provided by the Contract, the Contractor shall not subcontract any part
of the operations without the prior consent of the Engineer. Any such consent shall not relieve
the Contractor from any liability or obligations under the Contract and it shall be responsible for
the acts, defaults and neglects of any subcontractor, its agents, servants or workmen as fully as if
they were the acts, defaults or neglects of the Contractor, its agents, servants or workmen.
b) An event of default on the part of its Contractor being unable to fulfil its services obligations
under the Contract shall be deemed as a serious default and is said to have occurred doubts
any of the following causes.
c) The Engineer certifies to the Employer with a copy to the Contractor that in its opinion the
Contractor
Has repudiated the Contractor.
Without reasonable excuse has failed to commence Operations in accordance with the
Contract and pursuant to the Commencement date; or failed to complete the Operations
within the time stipulated for completion.
f) Contractor persistently fails to follow. Good operating practices in execution of the Contract.
g) If the Contractor changes the use to which any part or whole of the Site is put or initiates a
variation without the required approval of the Engineer.
h) The Contractor stops providing the operation for one day and the stoppage has not been
authorized by the Engineer.
i) The Engineer gives notice that failure to correct a particular defect is a fundamental breach
of Contract and the Contractor fails to correct it within a reasonable period of time
determined by the Engineer.
l) The Contractor, in the judgement of the Employer has engaged in Corrupt Practices
fraudulent Practices in competing for or in carrying out the Operations under the Contract.
m) If the Contract fails to obtain or keep in force the insurance requirements under this Contract.
n) The Contractor (in case of a consortium) has modified the composition of the consortium
and/or the responsibility of each member of the consortium without prior approval of the
Employer.
b) If the Contract is terminated because of an Contractor‟s event of default, the Employer shall
be entitled to invoke the Security Deposit and carry out the Operations through a successor
Contractor or departmentally and at the risk and cost of the Contractor. If the total amount
due to the Employer exceeds any payment due to the Contractor the difference shall be a
debt payable to the Employer,
c) If the Contract is terminated because of an Contractor‟s event of default, all materials on the
site, plant, equipment and temporary works shall be deemed to be the property of the
Employer.
d) Unless prohibited by law, the Contractor shall, if so instructed by the Engineer within 3 days
of such entry and terminated referred to, assigns to the Employer the benefit of any Contract
for the supply of any goods or materials or operations which the Contractor may have
entered into for the purposes of the Contract.
b) The Employer does not give access to part of the Site by the commencement date.
c) The Employer does not make a payment certified by the Engineer within 90 days from the
day of receipt of the Engineer‟s Certificate.
d) The Engineer instructs the Contractor to stop providing the operations and the instruction is
not withdrawn within 3 days and
2. If the Employer, before the expiry of the above notice period, or immediately thereafter
removes the cause of its default, the Contractor‟s entitlement shall lapse in respect of such
defaults, and the Contractor shall continue with / resume normal working as soon as is
reasonably possible.
B. Indemnification
1. The Contractor shall indemnify and keep indemnified the Employer against all losses and
claims for injuries or damage t any property whatsoever which may arise out of or in
consequence of the operations and against all claims, demands, proceedings, damages, costs,
charges and expenses whatsoever in respect of or in relation thereto.
2. The Contractor shall at all times indemnify the Employer against all claims, damages or
compensation under the provision of:
Payment of wages Act 1936
Minimum Wages Act 1948
the Employers Liability Act 1938
The Workmen‟s Compensation Act 1923
Industrial Dispute Act 1947.
Indian Factories Act 1948 and
Maternity Benefit Act 1961.
Or any modifications thereof and rules made there under from time to time or as a consequence
or any accident or injury to any workman or other persons in or about the Operations, whether in
the employment of the Contractor or not save and except where such accident or injury have
resulted from any act of the Employer, their agents or servants and also against all cost, charges
and expenses of any suit, action of proceedings arising out of such accident or injury and against
all sum and sums which may with the consent of the Contractor be paid to comprise or
compound any such claim without limiting its obligations and liabilities as above provided. The
Contractor shall insure against all claims damages or compensation payable under the various
acts mentioned above or any modifications thereof or any other law relating thereto.
C. Insurance
The Contractor shall provide in the joint names of the Employer and the Contractor insurance
cover from the Commencement date to one year beyond the end of the Contract Period for the
Contractor‟s risks covering:
[Type text] Page 46
U.P. HOUSING & DEVELOPMENT BOARD
Loss of or damage of property (except the Facilities, System and Equipment) in connection
with the Contract.
Personal injury or death; and
The Contractor‟s All risk (CAR) Insurance Policy.
The covers shall be obtained from the Directorate of Insurance, Uttar Pradesh State only.
The Contractor may at its own discretion provide for the following insurance covers
Loss or damage to the Facilities and / or System and
Loss of or damage to equipment.
Such cover may be taken either from the Directorate of Insurance, UP State or from any other
Insurance company with the approval of the Employer.
The Contractor shall deliver policies and certificates to the Engineer for an approval before the
Commencement Date. All such insurance shall provide for compensation to be payable in the
types and proportions of currencies required to rectify the loss or damage incurred.
If the Contractor or any of its Subcontractors does not provide any of the policies and
certificates required, the Employer may affect the insurance, which the Contractor should have
provided and recover the premiums the Contractor has paid from payments otherwise due to the
Contractor or, if no payment is due, the payment of the premiums shall be a debt due to the
Employer.
Alterations to the terms of insurance shall not be made without the approval of the Engineer and
both parties shall at all times comply with any conditions of the insurance policies.
The Contractor shall be under no liability whatsoever in consequence of any of the Force
Majeure events referred to in this clause whether by way of indemnity or otherwise.
If the Contract is frustrated by a Force Majeure event, the Employer shall certify that the
Contract has been frustrated. The Contractor shall make the site safe and stop operations as
quickly as possible after receiving this certificate.
The obligations and liabilities of the parties under this Contract would continue as long as
Force Majeure event does not impede the performance.
There shall be no penalty / liquidated damages applicable in the period of subsistence of a
Force Majeure.
The Contractor shall supply to the Engineer a detailed account of the total amount that the
Contractor considers payable under the Contract before the end of the Contract Period. The
Engineer within 28 days of receiving the Contractor‟s account shall certify any final payment
that is due to the Contractor, or indicate to the Contractor the corrections or additions that are
necessary. If the final account is still unsatisfactory, after the Contractor resubmits it, the
Engineer shall decide on the amount payable to the Contractor and issue a payment certificate.
The Employer shall any time, within a period of 90 days from the Completion Date or
Termination Date as applicable, carry out an independent assessment of the facilities and / or
system departmentally or through a Successor Contractor. Any deficiencies in the facilities and/
or System shall be made good by or at the cost of the Contractor so as to bring the facilities and
or /system into Good Repair and proper working condition as handed over at the
Commencement Date and subsequent works done pursuant and normal wear and tear excepting.
ii. Annual
Leakages in structures
Ladders
Railings
Overflow drain.
i. Daily
Screens/ Grit Channels
Moving parts of screens and grit removal equipment, Blowers /Agitators / Pumps/
Agitators /Return Sludge pumps/ Chemical mixer/Centrifuge/Decanter
Stuffing box
Bearing and
Vibration, balancing on Decanter, chemical dosing and mixing, Motors
[Type text] Page 49
U.P. HOUSING & DEVELOPMENT BOARD
Contact tightness
Cable insulation near the lugs.
Panels Breaker and Starter
Contacts of relay and circuit breaker and
Setting of over-current relay, no-volt coil and tripping mechanism and off in the dash pot
relay.
Transformer Sub-station
Ground Operated Dis-connectors (GOD)
Contacts of GOD and of Over Current (OC) relays
Radiators and Earth pit
ii. Monthly
Screens and Grit channels
Chains in mechanically operated components
Screens performance
Transformer
Oil in transformer
Relay alarm circuit
Load (Amperes) and
Voltage
iii. Quarterly
Transformer
Bushing and
Dehydrating breathers
v. Annual
Paint screens, grit removal mechanism, scrapers, scrapers , motors, pipes,
Valves, fittings agitators and inlet/outlet weirs with two coats of anticorrosive paints.
Replace worn out parts of mechanical equipment in sewage treatment plant.
Follwing miscellaneous work shall also be coverd under the Scope of work O&M
1 Disposal of Sludge/Screenings/Debris
The screenings/debris/dried sludge cakes from the STP shall be disposed off by the Contractor to a
suitable location which is away from the residential area. The place of sludge disposal shall be as per
the decision of the Engineer In-charge, within a radius of 15 kms from the plant. The responsibility of
sludge withdrawal and disposing off lies with the Contractor within the operation and maintenance
period. The Contractor should explore the possibility promoting it as manure.
3 Safety Equipment:
Safety Equipments should be provided at STP as per the recommendation of Inspector of
Industries. Contractor shall also take care of safety compliance as applicable from time to time
as per safety rules/Factory act/Indian Electricity regulations/manuals/manufacturer's special
instructions.
The Bidder shall also dispose-off the sludge, screenings, grit and any other material, as per
specifications and to the satisfaction of the Engineer In-charge. It is to be noted that all costs
for disel & genset during the O&M period.
The Bidder shall provide on job training to the Employer staff as per specifications.
The Bidder shall, at no extra cost to the Employer, repair and re-condition all the required
mechanical equipments in the concluding year of the O & M period and Hand over the facility
to the Employer in proper & fully working condition.
The Bidders are to quote O&M Cost and provide Functional Guarantee based on the following data
which shall be used for technical evaluation of qualifying Bids:
BOD : 200 mg/l
TSS : 250 mg/l
6 Contract Period
The total Contract Period shall be as follows:
O&M Period : 12 Months
19. The Bidder shall carry out the sampling tests of raw sewage by themselves to ascertain the raw
sewage quality for treatment process.
1 pH : 6.0 to 8.0
2 Biochemical Oxygen Demand (BOD5) : =< 10 mg/l
3 Chemical Oxygen Demand (COD) : =< 100 mg/l
4 Total Suspended Solids (TSS) : =< 20 mg/l
5 Total Phosphorous (TP) : =< 1 mg/l
6 Total Nitrogen (TN) : =< 10 mg/l
7 Ammonical Nitrogen (NH3-N) : =< 1 mg/l
8 Fecal Coliform : =< 100 MPN/100 ml
9 Oil and Greases : =<10 ml
3. The Operation & Maintenance of Civil and E&M works will be executed as per above
mentioned departmental specifications.
3. The works are related for sewerage schemes.
4. Tenderers are advised to quote the rates according to geographic condition of site of work
5. It will be the sole responsibility of firm to inform concerning Engineer in charge for
quality assurance of Operation & Maintenance time to time.
6. The Engineer in charge will issue a certificate to the firm that satisfaction of Operation
& Maintenance per month.
7. The firm will be responsible for any negligence for Operation & Maintenance of S.T.P.
break down, accident leakage/breakage and any type of the defect of materials due to
manufacturing defect or bad workmanship and defective civil works for the repair and
maintenance.
8. It is assumed by the department that there will be no leakage/breakage default in STP
so, any charges, whatsoever, shall have to be borne by the firm shall not be paid by the
department in any case on account of repair and maintenance during the maintenance
period.
19 The tenderer should have to submit under taking of satisfactory performance for
Operation & Maintenance of 37.50 MLD STP as per CPCB, UPPCB norms and
guide lines issued by NGT time to time.
20. The tenderer are requested to quote firm and fix rates in Indian Rs for each item as
mentioned in schedule “B” of the tender document.
21. The rates will not be subjected to any escalation at a later stage and agreement of
contract rate will made for 01 years.
22. However bifurcation of rates should be clear mentioned and percentage of taxes,
excise duties or any other statuary levy on the furnished product included in the rates
should be clearly mentioned in the commercial offer.
23. The tenderer should have to submit Testing Reports of Treated Sewer after every
fifteen days/ as required by E/I. from the laboratory of UPPCB/CPCB/IIT Lab/any Govt.
Recognized laboratory /Govt. Institution.
24. Log Book should be maintained for Per day solid waste Material.
25. Sludge generation record book should be maintained for Per day solid waste Material.
26. Contractor have to submit a list of Working as well as stand by/spare Equipment list
with monthly payment bill.
27. Testing report of treated sewage in STP Lab on daily basis should be submitted with
monthly bill.
28. All the testing report of the treated sewage water to be uploaded online system on daily
and mobile application should also be maintain for the STP.
DIFFUSERS
1 TYPE OF DIFFUSER FINE BUBBLE TUBULAR
TYPE
2 MAKE AS PER NIT
3 MATERIAL OF DIFFUSER AS PER NIT
4 DIA. AND LENGTH OF EACH DIFFUSER DURING DETAILED
ENGINEERING
5 AIR FLOW THROUGH EACH DIFFUSER (NM3/ HR) DURING DETAILED
ENGINEERING
6 TOTAL NO. OF DIFFUSERS (NOS.) DURING DETAILED
ENGINEERING
AIR BLOWERS
1 TYPE OF AIR BLOWER CENTRIFUGAL AIR TURBO
BLOWER
2 MAKE AS PER NIT
3 NO. OF WORKING BLOWERS (NO.) 2.00
4 NO. OF STAND BY BLOWERS (NO.) 1.00
5 CAPACITY OF BLOWER (NM3/HR) 7700.00
6 HEAD OF BLOWER (KG./CM2) 0.66
7 MOTOR RATING (HP) 270.00
CHLORINATION SYSTEM
CHLORINE CONTACT TANK
1 DESIGN PEAK FLOW (M3/HR) 1562.50
2 HYDRAULIC RETENTION TIME (MINUTES) 30.00
3 LIQUID DEPTH (M) 3.00
4 LENGTH (M) 22.00
5 WIDTH (M) 10.50
6 TOP WATER LEVEL (M) 118.12
7 NUMBER OF BAFFLES (NOS.) 8.00
CENTRIFUGE
1 CAPACITY (M3/HR) 19.00
2 TYPE SOLID BOWL
3 FEED SLUDGE CONSISTENCY (%) 0.8 - 1%
4 DEWATERED SLUDGE CONSISTENCY (%) UP TO 20 %
5 QUANTITY (WORKING + STANDBY) 3 (2 + 1)
6 MATERIAL OF CONSTRUCTION AS PER NIT
7 MOTOR RATING (HP) 30.00
List of Machnine /Equpment with their rating & quantity instal at 37.50 MLD Sewer
Treatment Plant at Sector-10 Vrindavan Yojna Lucknow.
S.No DESCRIPTION OF EQUIPMENT RATING NO'S PROVIDED
(KW) Workng Stand By
1 MECH FINE SCREEN 1.50 2 0
2 SCREEN CONVEYOR 1.50 1 0
3 GRIT CHAMBER 0.37 2 0
4 RAKE CLASSIFIER 1.50 2 0
5 ORGANIC RETURN PUMP 0.75 2 0
6 SBR BASIN GATES 0.75 4 0
7 SBR AIR BLOWERS 196.00 2 1
8 BUTTERFLY VALVE 450 NB 0.75 6 0
9 BUTTERFLY VALVE 150 NB 0.37 2 2
10 DECANTERS 0.75 1 3
11 RAS PUMPS 3.70 2 2
12 SAS PUMPS 5.50 2 2
13 KNIFE GATE VALVE 200 NB 0.25 1 3
14 CHLORINE BOOSTER PUMPS 3.70 1 1
15 CHLORINE ADSORPTION BLOWER 3.70 1 0
16 SLUDGE SUMP AIR BLOWERS 7.50 1 1
17 BUTTERFLY VALVE 80 NB 0.18 1 1
18 CENTRIFUGE FEED PUMPS 3.70 2 1
19 KNIFE GATE VALVE 100 NB 0.18 2 1
20 CENTRIFUGES 22.00 2 1
21 POLY TANK AGITATORS 0.37 1 1
22 POLY DOSING PUMPS 0.37 2 1
23 CHEMICAL TANK AGITATORS 0.75 1 1
24 CHEMICAL DOSING PUMPS 0.37 2 1
25 SERVICE WATER PUMP 10.00 1 0
26 LIGHTING/VENTILATION/EXHAUST 32.00 1 0
FANS ETC
27 SLUDGE DRYING SYSTEM
27 SOLAR SLUDGE DRYING MACHINE 14.00 1 0
28 AXIAL FAN 0.79 14 0
29 ROOF VENTILATION MOTOR 0.25 2 0
TOTAL 64 23