0% found this document useful (0 votes)
62 views1 page

JCD-SPMI-MBL1-BLD-C-0168

The document is a Request For Inspection (RFI) for the Jeddah Central Development Project, specifically regarding the inspection of form work for concrete foundation blocks in the Saher area. The inspection is scheduled for October 14, 2024, at 11:00 AM, and the contractor has confirmed that the work is complete and complies with specifications. Verification from project representatives is required to ensure the work meets contract requirements.

Uploaded by

Hussan Ali
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
62 views1 page

JCD-SPMI-MBL1-BLD-C-0168

The document is a Request For Inspection (RFI) for the Jeddah Central Development Project, specifically regarding the inspection of form work for concrete foundation blocks in the Saher area. The inspection is scheduled for October 14, 2024, at 11:00 AM, and the contractor has confirmed that the work is complete and complies with specifications. Verification from project representatives is required to ensure the work meets contract requirements.

Uploaded by

Hussan Ali
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

JEDDAH CENTRAL DEVELOPMENT PROJECT (JCDC)

Request For Inspection (RFI)


RFI #: JCD-SPMI-MBL1-BLD-C-0168 Date: 14-oct-24
SITE PREPARATION AND MARINE INFRASTRUCTURE WORKS
Contractor: Modern Building Leaders Contract Title : Contract No. : 440004-01
Struc. Arch. Civil HVAC Fire Fighting Elec. Low Current Earth work Other ____________
For Building:

Storm Water Sanitary Sewer Elec. Telecom. Water Irrigation Roads LndScp. Other ____________
For Infra.:

DETAILS OF SCHEDULE INSPECTION Section A

Neighborhood.: Zone/Area: Lot/Street: Level: Axis/Grid:

Saher area

Works to be Inspected : Inspection of Form work foundation blocks


Inspection Required Date / Time: 14-Oct-2024 ,11:00am Hold Point Witness Point
Spec./Drawing Ref.:

Description of inspection: Inspection of Form work cast in situ Concrete foundation blocks at Saher area MOD JCD project as per
attached documents.

Coordination of other Trades


Structural Eng. Architectural Eng. Plumbing Eng. HVAC Eng. Fire Fighting Eng. Electrical Eng. Infra. Eng. Landscape Eng. Other________ Other________

N/A N/A N/A N/A N/A N/A N/A N/A

CONFIRMATION OF CONTRACTOR'S Q.C. INSPECTION Section B

Contractor has verified that the work to be inspected is complete and in compliance with Specifications, Approved Drawings, Method Statement and Quality Control Plan, ITP & Quality Checklist
Yes No

Note: If NO, any deviation from Specifications, Approved Drawings, Method Statement and Quality Control Plan to be recorded below.

Any NCR Issued for same inspection location: Yes No

Open Closed
If YES, NCR No.: Date:

Contractor QA/QC Name: Signature: Date/Time:

JCDC CMT Section C


JCDC CMT representative has verified that the work is ready for inspection and conforms to the project requirements. This verification does not relieve the Contractor of any of his responsibilities for making the work conform to the requirements of the Contract.

No Objection Objection / Reason

Name: Signature: Date/Time:

JCDC QMD Section D


JCDC QMD representative has verified that the work is ready for inspection and conforms to the project requirements. This verification does not relieve the Contractor of any of his responsibilities for making the work conform to the requirements of the
Contract.

No Objection Objection / Reason

QUALITY INSPECTOR
Name: Signature: Date/Time:

Distribution: JCDC CMT JCDC QMD

JCD/PJ/QUA/AP-001 Rev. 01
JCD/PJ/QUA/F-008 Rev. 01