The document is a comprehensive daily checklist for various systems at Bekasi Cyber Park, including chillers, power supply, and water pumps. It includes specific measurements and standards for temperature, pressure, and operational status across different time intervals. Additionally, it outlines responsibilities for inspection and maintenance by engineering and operational managers.

Uploaded by

Safar FX
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
4 views

History Card

The document is a comprehensive daily checklist for various systems at Bekasi Cyber Park, including chillers, power supply, and water pumps. It includes specific measurements and standards for temperature, pressure, and operational status across different time intervals. Additionally, it outlines responsibilities for inspection and maintenance by engineering and operational managers.

Uploaded by

Safar FX
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 9

CHECKLIST HARIAN AC SCREW

BEKASI CYBER PARK

Hari :
Tanggal :

CHILLER NO. MODEL UNIT : S/N :

Remark
NO DESCRIPTION Sat RANGE 10:00 12:00 14:00 16:00 18:00 20:00

1 Set Point Temperature C 7 - 10

2 Evaporator Leaving Temperature C 6 - 10

3 Evaporator Entering Temperature C 10 - 15

4 Suction Pressure Bar 1.8 - 3

5 Water Evap Pressure In Kg/cm3

6 Water Evap Pressure Out Kg/cm3

7 Water Evap Pressure Drop Kg/cm3

8 Condenser Entering Temperature C 0.4 - 1

9 Condenser Leaving Temperature C 23 - 30

10 Water Cond Pressure In Kg/cm3

11 Water Cond Pressure out Kg/cm3

12 Water Cond Pressure drop Kg/cm3 0.5 - 1

13 Discharge Pressure Bar 7.9 -11

14 Oil pressure 1/2 Bar

15 Oil Temperature C <110

16 Discharge Temperature C <110

17 Liquid Level % <5%

18 Incoming Volts V ± 10%

19 Control Volts V ± 10%

20 Total Amp A <512

21 Comp Load/ Unit Demand % 50 - 100

22 Oil Level 0/Full

Shift 1 List Temuan Dan Kegiatan Yang Dilakukan Diperiksa Oleh,

Shift 2

Shift 3 Spv. Engineering Operational Manager


DAILY REPORT FOR ABSORPTION CHILLER BEKASI CYBER PARK
DATE :
HEAT SOURCE : NATURAL GAS / FLUE GAS FROM GENSET ENGINE GAS MWM / SOLAR

NO INDICATOR STANDAR 8:00 11:00 14:00 16:00 19:00 22:00

1 Pressure Gas sebelum strainer (Bar), Samping Toilet 2,8 Bar


Hotel Aston
2 Pressure Gas sesudah strainer (Bar), samping toilet 2,8 Bar
Hotel Aston

NO INDICATOR STANDAR 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00 19:00 20:00 21:00

3 Pressure Gas sebelum Regulator (Kg/cm2) 3 Kg/cm2


4 Pressure Gas sesudah Regulator (mbar) 60 Mbar
5 Pressure Chiller 50 Psi
6 Pressure CT 22 Psi
7 Panel Pompa (Frekuensi) Hz 48 Hz
8 Panel Pompa (Voltage) Volt 380 Volt
9 Burner 0 - 9
10 Burner I / II I on II on
11 Chilled water inlet (Ke ABS) dalam Psi 60 Psi
12 Chilled water inlet (Ke ABS) dalam Celcius 16,4 Celcius
13 Chilled water outlet (Ke Gedung) dalam Psi 50 Psi
14 Chilled water outlet (Ke Gedung) dalam Celsius 11,4 Celcius
15 Delta T : No 10 - no 12 5 Celcius
16 Inlet ABS dari Cooling Tower dalam Psi 22 Psi
17 Inlet ABS dari Cooling Tower dalam Celcius 15 Celcius
18 Outlet ABS ke Cooling Tower dalam Psi 10 Psi
19 Outlet ABS ke Cooling Tower dalam Celcius 35 Celcius
20 Evaporation Temperature
21 Cooling water inlet
22 HPG Temperature
23 De - Crystallization Maks 60
24 Condenser Tube
25 LPG Temperature
26 Absorber Temperature
27 Flue Gas Temperature
28 Solution Concentration
29 Pembacaan inverter di dalam Panel
30 Pressure vacuum 0 Mpa
31 Dosing Pump on / off
32 Level Chemical di Drum Biru %
33 CT Barat Level Air Tekor atau Tidak Tidak Tekor
34 Filler CT Barat Kotor atau Tidak Tidak Kotor
35 Bak Drain CT Barat kotor atau tidak Tidak Kotor
36 Air CT Barat kotor atau tidak Tidak Kotor
37 CT Timur level air tekor atau tidak Tidak Tekor
38 Filler CT Timur Kotor atau Tidak Tidak Kotor
39 Bak Drain CT Timur kotor atau tidak Tidak Kotor
40 Air CT Timur kotor atau tidak Tidak Kotor
31 Nama Teknisi yang Melakukan Checklist
CHECKLIST HARIAN KWH METER PLN
BEKASI CYBER PARK
Hari / Tgl :

Lokasi :

AMPERE PANEL GEG AMPHERE PANEL MDV TEMP (°C) VOLT LVMDP T M (KV) AIR
JAM WBP LWBP
R S T R S T R.trafo Oil TRF RS ST TR R S T DW PDAM

08:00

10:00

12:00

14:00

16:00

18:00

20:00

22:00

24:00

02:00

04:00

06:00

shift 1

shift 2

Dibuat oleh Diperiksa oleh dketahui


shift 3

(…………………………………………………….) (…………………………………………………) (……………………………………………………………)


Spv engineering Chief.Engineering Operasional manager
POWER HOUSE
CHECK LIST PANEL

HARI :
TANGG:

P. AC 1 / COS P. CHILLER P. AC 2 / COS P. BLITZ P. PEN 1 / COS P. PEN 2 / COS


JAM KET
GEN PLN V A GEN PLN V A GEN PLN GEN PLN
08:00
10:00
12:00
14:00
16:00
18:00
20:00
22:00
24:00
02:00
04:00
06:00

GENSET NOMER
JAM CEK LIST URAIAN KETERANGAN
shift 1 1 2 3 4 5

Air Accu
shift 2 Air Radiator
Oli Mesin

shift 3 Diperiksa oleh Mengetahui

( ……………...…..… ) ( ……………...………... ) ( ……………...…… )


Spv. Engineering Chief Engineering OPR. Manager
HISTORY CARD
CATATAN PERBAIKAN DAN PERAWATAN UNIT
Peralatan : Peralatan :
Nomor : Nomor :
Lokasi : Lokasi :

No URAIAN PEKERJAAN NO WO PARAF No


Tanggal Tanggal

1 1

2 2

3 3

4 4

5 5

6 6

7 7

8 8

9 9

10 10

11 11

12 12

13 13

14 14

15 15

16 16

17 17

18 18

19 19

20 20

21 21

22 22
HISTORY CARD
CATATAN PERBAIKAN DAN PERAWATAN UNIT

URAIAN PEKERJAAN NO WO PARAF


CHECK LIST HARIAN CHILLER
BEKSI CYBER PARK
Hari / Tanggal :
CHILLER CHILLER CHILLER CHILLER CHILLER CHILLER CHILLER
1 2 3 4 5 6 7
JAM
COMP SENS COMP SENS COMP SENS COMP SENS COMP SENS COMP SENS COMP SENS
A B A B A B A B A B A B A B A B A B A B A B A B A B A B
10.00
12.00
14.00
16.00
18.00
20.00

CHILLER CHILLER CHILLER CHILLER CHILLER CHILLER CHILLER


8 9 10 11 12 13 14
JAM
COMP SENS COMP SENS COMP SENS COMP SENS COMP SENS COMP SENS COMP SENS
A B A B A B A B A B A B A B A B A B A B A B A B A B A B
10.00
12.00
14.00
16.00
18.00
20.00

Diperiksa Oleh Mengetahui


Shieft 1

Shieft 2
( ………………………… ) ( ………………………… ) ( ………………………… )
Spv.Engineering Chief Engineering Operasional Manager
CEK LIST HARIAN AIR BERSIH
BEKASI CYBER PARK

Hari / Tgl : Ket : Baik = √ Bising = O Rusak = X

Deep Well Transfer Pump Hydrant Pump Jockey Pump Diesel Pump PDAM Ground Tank Roof Tank
JAM Panel Control Pompa Panel Pompa Panel Control Poma Panel Control Poma Panel Control Poma Valve Volume Volume KET
FM Valve Valve
A/M V 1 2 A/M V 2 1 A/M V 1 2 A/M V 2 1 A/M V 1 2 O/C (M3)/ (M3)
7.00

8.00

9.00

10.00

11.00

12.00

13.00

14.00

15.00

16.00

17.00

18.00

19.00

20.00

22.00

24.00

02.00

04.00

06.00

Note :

Diperiksa Oleh Mengetahui


Shift 1

Shift 2

( ………………………… ) ( ………………………… ) ( ………………………… )


Shift 3
Spv Engineering Chief Engineering Center Manager
CHECK LIST HARIAN POMPA SUMMPIT
BEKASI CYBER PARK
Hari / Tanggal : Ket : Baik = (√) Bising = (O) Rusak = (X)

SUMMPIT HHPS BASEMENT RAM BASEMENT SUMMPIT SUMMPIT RB SUMMPIT SUMMPIT SUMMPIT SUMMPIT
JAM LOADING DOK DRIVE WAY UTARA NAIK TIMUR LG BARAT LG TIMUR ESCALATOR depan Gd.harno depan MCD NOER ALI TEKHNISI KETERANGAN
1 2 1 2 1 2 1 2 1 1 1 1 N T 1 2 1 2 1 2

07:00
09:00
11:00
13:00
15:00
17:00
19:00
21:00
23:00
01:00
03:00
05:00

NOTE :

Diperiksa Oleh Mengetahui


Shift 1

Shift 2

( ……………...…… ) ( ………………………… ) ( ………………………… )


Shift 3
Spv.Engineering Chief Engineering Operasional Manager