The Procurement Status Report for the 167375 Marcus Hook Ethane Expansion outlines various packages, their timelines, and bidder information for civil, electrical, and instrumentation components. Key dates include bid issuance, due dates, and evaluation periods, with multiple bidders expressing intent to participate. The report highlights specific bidders for each package and notes on their status and recommendations.

Uploaded by

raju
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
22 views

PSR

The Procurement Status Report for the 167375 Marcus Hook Ethane Expansion outlines various packages, their timelines, and bidder information for civil, electrical, and instrumentation components. Key dates include bid issuance, due dates, and evaluation periods, with multiple bidders expressing intent to participate. The report highlights specific bidders for each package and notes on their status and recommendations.

Uploaded by

raju
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 16

Procurement Status Report

167375 Marcus Hook Ethane Expansion


Energy Transfer Partners L.P.: Marcus Hook, Pennsylvania
167375 Marcus Hook Ethane Expansion IFB Spec RFP Issued Bid Due Bid Eval PR Issue PR IFP Spec PO Award PO Drawing Delivery
Pkg. No. PO No. Engineer/Buyer/Supplier Received Date Approved Received Executed Submittal
CIVIL
STL-01 Joe Reetz P: 06-Sep-24 19-Sep-24 10-Oct-24 17-Oct-24 17-Oct-24 24-Oct-24 24-Oct-24 25-Oct-24 31-Oct-24
Structural Steel Tracey Mooney F: 27-Sep-24 01-Oct-24 16-Oct-24 05-Nov-24 07-Nov-24 14-Nov-24 14-Nov-24 15-Nov-24 21-Nov-24
TBD A: 27-Sep-24 01-Oct-24 16-Oct-24

Bidders Bid Received Award Notes / Comments


1 CTIW Oct 15 2024 12:00AM Will Bid
2 Dave Steel Company Oct 16 2024 12:00AM Will Bid
3 Markle Mfg Company of San Antonio Inc. Oct 7 2024 12:00AM Will Bid
4 Qualico Steel Oct 15 2024 12:00AM Will Bid
5 Spitzer Industries, Inc. Oct 14 2024 12:00AM Will Bid
STL-01A Joe Reetz P: 18-Sep-24 18-Sep-24 02-Oct-24 16-Oct-24 21-Oct-24 28-Oct-24 28-Oct-24 02-Nov-24 08-Nov-24
Early Works Structural Tracey Mooney F: 18-Sep-24 18-Sep-24 09-Oct-24 21-Oct-24 21-Oct-24 24-Oct-24 05-Nov-24 10-Nov-24 16-Nov-24
Steel AZCO A: 18-Sep-24 18-Sep-24 09-Oct-24 21-Oct-24 21-Oct-24 24-Oct-24

Bidders Bid Received Award Notes / Comments


1 AZCO Oct 9 2024 12:00AM X Will bid
ELEC
ELE-001 239082 Atul Arunkumar Shenoy P: 21-Feb-24 06-Mar-24 26-Apr-24 10-May-24 17-May-24 24-May-24 02-Jun-24 11-Jun-24 18-Jun-24
PDC Major Electrical Tracey Mooney F: 26-Feb-24 26-Feb-24 14-Jun-24 23-Jul-24 24-Jul-24 31-Jul-24 01-Aug-24 07-Aug-24 19-Aug-24
Equipment and Volta A: 26-Feb-24 26-Feb-24 14-Jun-24 23-Jul-24 24-Jul-24 31-Jul-24 01-Aug-24 07-Aug-24 19-Aug-24

Bidders Bid Received Award Notes / Comments


1 Eaton Corporation Apr 24 2024 12:00AM Bruce Nixon / (913) 972-2376 / [email protected]
2 Powell Apr 24 2024 12:00AM Matt Smith / (713) 948-4997 / [email protected]
Shortlisted
3 Protect Controls Inc. Apr 17 2024 12:00AM Al Walsh / (713) 742-7024 / [email protected]
4 Volta Apr 24 2024 12:00AM X Azam Jahangir / (832) 704-7333 /[email protected]
Shortlisted, Recommended Bidder
ELE-02 241448 Atul Arunkumar Shenoy P: 18-Mar-24 01-Apr-24 19-Apr-24 24-May-24 03-Jun-24 10-Jun-24 10-Jun-24 17-Jun-24 21-Jun-24
Transformers Tracey Mooney F: 18-Mar-24 22-Mar-24 05-Jun-24 10-Sep-24 10-Sep-24 10-Sep-24 16-Sep-24 18-Sep-24 18-Oct-24
Virginia Transformer Corp. A: 18-Mar-24 22-Mar-24 05-Jun-24 10-Sep-24 10-Sep-24 10-Sep-24 16-Sep-24 18-Sep-24 18-Oct-24

Bidders Bid Received Award Notes / Comments


1 Eaton Corporation Apr 18 2024 12:00AM Bruce Nixon / (913) 972-2376 / [email protected]
2 Hitachi Energy (Hitachi ABB Power Grids) Apr 15 2024 12:00AM Derek Owen / (816) 207-9951 / [email protected]
Shortlisted,
3 Niagara Transformer Corp. Apr 18 2024 12:00AM William Hanavan / (716) 896-6500 / [email protected]
4 Virginia Transformer Corp. Apr 19 2024 12:00AM X Ed Pando / (713) 898-2082 / [email protected]
Shortlisted - Terms were sent o John for review on 6/13. Recommended Bidder

DATE = Current Activity DATE = Within 7 Days DATE = Within 14 Days DATE = Plan Date Exceeded

Page 1 of 16 Tuesday, November 5, 2024


167375 Marcus Hook Ethane Expansion IFB Spec RFP Issued Bid Due Bid Eval PR Issue PR IFP Spec PO Award PO Drawing Delivery
Pkg. No. PO No. Engineer/Buyer/Supplier Received Date Approved Received Executed Submittal
ELE-05 242679 Atul Arunkumar Shenoy P: 06-Jun-24 07-Jun-24 28-Jun-24 09-Aug-24 12-Aug-24 15-Aug-24 15-Aug-24 20-Aug-24 30-Aug-24
13.2 KV Metal Enclosed Tracey Mooney F: 06-Jun-24 07-Jun-24 28-Jun-24 03-Sep-24 01-Oct-24 07-Oct-24 04-Oct-24 21-Oct-24 31-Oct-24
Capacitor Banks Eaton A: 06-Jun-24 07-Jun-24 28-Jun-24 03-Sep-24 01-Oct-24 07-Oct-24 04-Oct-24 21-Oct-24 31-Oct-24

Bidders Bid Received Award Notes / Comments


1 Eaton Jun 28 2024 12:00AM X Recommended Bidder, on the AML
2 GE Grid Solutions
3 Hitachi Energy (Hitachi ABB Power Grids) Jun 21 2024 12:00AM Will Bid
4 Northeast Power Systems, Inc. Jun 21 2024 12:00AM Will Bid
ELE-06 Jessica Scott P: 21-Jan-25 04-Feb-25 03-Mar-25 17-Mar-25 24-Mar-25 31-Mar-25 31-Mar-25 01-Apr-25 07-Apr-25
Heat Trace Tracey Mooney F: 21-Jan-25 04-Feb-25 03-Mar-25 17-Mar-25 24-Mar-25 31-Mar-25 31-Mar-25 01-Apr-25 07-Apr-25
TBD A:
Bidders Bid Received Award Notes / Comments
1 nVent
2 Thermon, Inc.
ELE-12 WeiChih Huang P: 25-Sep-24 09-Oct-24 05-Nov-24 12-Nov-24 19-Nov-24 26-Nov-24 26-Nov-24 27-Nov-24 04-Dec-24
T&D Tubular Steel Poles Elise Chouinard F: 30-Sep-24 03-Oct-24 17-Oct-24 08-Nov-24 15-Nov-24 22-Nov-24 22-Nov-24 23-Nov-24 30-Nov-24
TBD A: 30-Sep-24 03-Oct-24 17-Oct-24
06Aug24TM: Due to a design change in the poles, the package will be rebid.
Bidders Bid Received Award Notes / Comments
1 Dis-Tran Steel Oct 17 2024 12:00AM
2 Klute Steel Will Bid - Bid not Rec'd; have not been able to contact Klute
3 Sabre Oct 18 2024 12:00AM
ELE-13 Atul Arunkumar Shenoy P: 29-Apr-25 12-May-25 02-Jun-25 09-Jun-25 16-Jun-25 23-Jun-25 23-Jun-25 24-Jun-25 30-Jun-25
Load Shed Network Tie-in Tracey Mooney F: 29-Apr-25 12-May-25 02-Jun-25 09-Jun-25 16-Jun-25 23-Jun-25 23-Jun-25 26-Jun-25 30-Jun-25
Support (Consulting) TBD A:
Bidders Bid Received Award Notes / Comments
1 SEL Engineering Services, Inc.
ELE-14 Atul Arunkumar P: 19-May-25 02-Jun-25 20-Jun-25 27-Jun-25 07-Jul-25 14-Jul-25 14-Jul-25 15-Jul-25 21-Jul-25
Cable Elise Chouinard F: 20-May-25 03-Jun-25 23-Jun-25 30-Jun-25 08-Jul-25 15-Jul-25 15-Jul-25 16-Jul-25 22-Jul-25
TBD A:
ELE-21 Atul Arunkumar P: 19-May-25 03-Jun-25 23-Jun-25 30-Jun-25 08-Jul-25 15-Jul-25 15-Jul-25 16-Jul-25 22-Jul-25
Electrical Commodities Elise Chouinard F: 20-May-25 04-Jun-25 24-Jun-25 01-Jul-25 09-Jul-25 16-Jul-25 16-Jul-25 17-Jul-25 23-Jul-25
TBD A:
INSTR
ANL-01 242405 Ram Patel P: 18-Jul-24 18-Jul-24 09-Aug-24 23-Aug-24 30-Aug-24 09-Sep-24 09-Sep-24 10-Sep-24 16-Sep-24
Analyzer Systems Mangesh Bandiwadekar F: 18-Jul-24 19-Jul-24 13-Aug-24 20-Sep-24 25-Sep-24 30-Sep-24 01-Oct-24 03-Oct-24 08-Oct-24
Vector Controls and Auto A: 18-Jul-24 19-Jul-24 13-Aug-24 20-Sep-24 25-Sep-24 30-Sep-24 01-Oct-24 03-Oct-24 08-Oct-24
15Aug24: No category on the AML.
Bidders Bid Received Award Notes / Comments
1 Chemex Global No Bid No response.
2 Cherokee Intergration Solutions Aug 9 2024 12:00AM Bid recd. Bidder replied to all commercial queries.Commercial Bid tab updated based on final revised quote on
9/25.
DATE = Current Activity DATE = Within 7 Days DATE = Within 14 Days DATE = Plan Date Exceeded

Page 2 of 16 Tuesday, November 5, 2024


167375 Marcus Hook Ethane Expansion IFB Spec RFP Issued Bid Due Bid Eval PR Issue PR IFP Spec PO Award PO Drawing Delivery
Pkg. No. PO No. Engineer/Buyer/Supplier Received Date Approved Received Executed Submittal
3 Kaizen Controls Aug 9 2024 12:00AM Bid recd. Bidder replied to all commercial queries.Commercial Bid tab updated.
4 Vector Controls and Automation Group Aug 13 2024 12:00AM X PO being issued to Vector CAG.
ANL-02 Emely Rivas P: 31-Jan-25 14-Feb-25 06-Mar-25 20-Mar-25 27-Mar-25 03-Apr-25 03-Apr-25 04-Apr-25 10-Apr-25
Area Monitors & Flame Yateen Naik F: 10-Feb-25 24-Feb-25 14-Mar-25 28-Mar-25 04-Apr-25 11-Apr-25 11-Apr-25 14-Apr-25 18-Apr-25
Detectors TBD A:
15Aug24TM: No category on the AML.
Bidders Bid Received Award Notes / Comments
1 Detection & Measurement Systems
2 Det-Tronics
3 Eastern Controls
4 TechStar
CTL-01 241613 Ram Patel P: 29-May-24 31-May-24 25-Jun-24 08-Aug-24 15-Aug-24 22-Aug-24 22-Aug-24 09-Sep-24 13-Sep-24
DCS/SIS Hardware and Elise Chouinard F: 29-May-24 31-May-24 25-Jun-24 15-Aug-24 10-Sep-24 18-Sep-24 05-Sep-24 19-Sep-24 23-Sep-24
Configuration Services Applied Control A: 29-May-24 31-May-24 25-Jun-24 15-Aug-24 10-Sep-24 18-Sep-24 05-Sep-24 19-Sep-24 23-Sep-24
29Aug24TM: The terms and conditions are under review and evaluation. Bidders recommended by Client.
Bidders Bid Received Award Notes / Comments
1 Applied Control Jun 25 2024 12:00AM X Recommended bidder. On the AML
2 Prime Controls Jun 21 2024 12:00AM Will Bid
3 Rockwell Automation Jun 25 2024 12:00AM Will Bid. Extension given to 6/25. Shortlisted
ELM-01 Alexandra McGhee P: 09-Sep-24 23-Sep-24 04-Oct-24 25-Oct-24 08-Nov-24 15-Nov-24 15-Nov-24 25-Nov-24 02-Dec-24
Orifice Plates Elise Chouinard F: 15-Oct-24 17-Oct-24 14-Nov-24 05-Dec-24 19-Dec-24 26-Dec-24 26-Dec-24 05-Jan-25 12-Jan-25
TBD A: 15-Oct-24 17-Oct-24

Bidders Bid Received Award Notes / Comments


1 Eastern Controls On AML. Will bid. Bid extension granted to 11/11
2 Precision Flow Inc. On AML. Will bid
3 Rosemount On AML. Will bid. Bid extension granted to 11/14
ELM-02 Elaine Messiha P: 24-Sep-24 08-Oct-24 04-Nov-24 18-Nov-24 25-Nov-24 03-Dec-24 03-Dec-24 04-Dec-24 10-Dec-24
Temperature Elements & Elise Chouinard F: 15-Nov-24 29-Nov-24 26-Dec-24 10-Jan-25 17-Jan-25 29-Jan-25 29-Jan-25 30-Jan-25 06-Feb-25
Thermowells TBD A:
15Aug24TM: Not category on the AML
Bidders Bid Received Award Notes / Comments
1 Daily Instrument Corp
2 Eastern Controls
3 National Basic Sensor (NBS)
4 Rosemont
ELM-03 John McLeod P: 06-Aug-24 20-Aug-24 03-Sep-24 10-Sep-24 12-Sep-24 17-Sep-24 17-Sep-24 18-Sep-24 24-Sep-24
Venturi Flow Meters Yateen Naik F: 13-Aug-24 16-Aug-24 09-Sep-24 18-Oct-24 08-Nov-24 13-Nov-24 29-Oct-24 14-Nov-24 20-Nov-24
TBD A: 13-Aug-24 16-Aug-24 09-Sep-24 18-Oct-24 29-Oct-24
15Aug24TM: No category on the AML
Bidders Bid Received Award Notes / Comments
1 BADGER DAYLIGHT INGCORP. Aug 26 2024 12:00AM CQ#02 reply received.
2 Krohne No Bid KROHNE does not offer the Venturi product in the NAFTA market.
3 Wika Instrument LP Sep 9 2024 12:00AM Revised T&C received on 15/10.
DATE = Current Activity DATE = Within 7 Days DATE = Within 14 Days DATE = Plan Date Exceeded

Page 3 of 16 Tuesday, November 5, 2024


167375 Marcus Hook Ethane Expansion IFB Spec RFP Issued Bid Due Bid Eval PR Issue PR IFP Spec PO Award PO Drawing Delivery
Pkg. No. PO No. Engineer/Buyer/Supplier Received Date Approved Received Executed Submittal
ELM-04 Elaine Messiha P: 12-Sep-24 26-Sep-24 09-Oct-24 23-Oct-24 30-Oct-24 06-Nov-24 06-Nov-24 07-Nov-24 13-Nov-24
Ultrasonic Flow Meters Tina Huitrado F: 08-Oct-24 11-Oct-24 01-Nov-24 15-Nov-24 20-Nov-24 25-Nov-24 25-Nov-24 26-Nov-24 02-Dec-24
TBD A: 08-Oct-24 11-Oct-24 01-Nov-24
4NOV24: All bids are in and being reviewed for C&Es.
Bidders Bid Received Award Notes / Comments
1 Emerson No Bid On AML. Supplier advised equipment not in their product list, can't provide.
2 GE Panametrics Nov 1 2024 12:00AM On AML. Intent to bid recv'd. Bid extension to 11/1/24.
3 Siemens Oct 25 2024 12:00AM On AML. Intent to bid recv'd.
ELM-05 Ellaine Messiha P: 12-Sep-24 26-Sep-24 09-Oct-24 16-Oct-24 23-Oct-24 30-Oct-24 30-Oct-24 31-Oct-24 06-Nov-24
Vortex Flowmeter Yateen Naik F: 22-Oct-24 23-Oct-24 13-Nov-24 20-Nov-24 27-Nov-24 28-Nov-24 28-Nov-24 29-Nov-24 05-Dec-24
TBD A: 22-Oct-24 23-Oct-24
15Aug24TM: No category on the AML
Bidders Bid Received Award Notes / Comments
1 Emerson Will Bid
IND-01 Alexandra McGhee P: 17-Sep-24 01-Oct-24 21-Oct-24 04-Nov-24 11-Nov-24 18-Nov-24 18-Nov-24 19-Nov-24 25-Nov-24
Pressure & Temperature Yateen Naik F: 17-Dec-24 22-Dec-24 11-Jan-25 26-Jan-25 02-Feb-25 09-Feb-25 09-Feb-25 10-Feb-25 21-Feb-25
Gauges TBD A:
Bidders Bid Received Award Notes / Comments
1 Ashcroft On AML
2 Eastern Controls On AML
3 Swagelok On AML
4 Wika Instrument LP On AML
IND-02 Alexandra McGhee P: 25-Sep-24 09-Oct-24 29-Oct-24 05-Nov-24 12-Nov-24 19-Nov-24 19-Nov-24 20-Nov-24 26-Nov-24
Flow Sight Glass Yateen Naik F: 23-Sep-24 25-Sep-24 21-Oct-24 08-Nov-24 15-Nov-24 22-Nov-24 22-Nov-24 23-Nov-24 29-Nov-24
TBD A: 23-Sep-24 25-Sep-24 21-Oct-24

Bidders Bid Received Award Notes / Comments


1 Jacoby Tarbox (Clark-Reliance) Oct 21 2024 12:00AM On AML Clark-Reliance forwarded RFP documents to Setpoint.
2 John C. Ernst Co. On AML No bid
3 PT-Coupling Company No Bid On AML. No bid
IND-03 Emely Rivas P: 19-Aug-24 03-Sep-24 30-Sep-24 14-Oct-24 21-Oct-24 28-Oct-24 28-Oct-24 29-Oct-24 04-Nov-24
Magnetic Level Gauges Yateen Naik F: 24-Sep-24 27-Sep-24 18-Oct-24 08-Nov-24 15-Nov-24 22-Nov-24 22-Nov-24 23-Nov-24 29-Nov-24
TBD A: 24-Sep-24 27-Sep-24 18-Oct-24
15Aug24TM: No category on the AML
Bidders Bid Received Award Notes / Comments
1 Jerguson No Bid Bid received. CQ#01 issued
2 Magnetrol International, Inc. Robert Hotard who manages quotation will revert .
3 Magtech Oct 28 2024 12:00AM Emerson Will Bid. Bid extension granted to 10/17. Pre-0ffer technical queries resolved. Emely requested supplier
to submit offer without cryo valves
4 PTLF Process, LLC No Bid Bid received. CQ#01 issued

DATE = Current Activity DATE = Within 7 Days DATE = Within 14 Days DATE = Plan Date Exceeded

Page 4 of 16 Tuesday, November 5, 2024


167375 Marcus Hook Ethane Expansion IFB Spec RFP Issued Bid Due Bid Eval PR Issue PR IFP Spec PO Award PO Drawing Delivery
Pkg. No. PO No. Engineer/Buyer/Supplier Received Date Approved Received Executed Submittal
IND-05 Alexandra McGhee P: 25-Sep-24 09-Oct-24 29-Oct-24 05-Nov-24 12-Nov-24 19-Nov-24 19-Nov-24 20-Nov-24 26-Nov-24
Rotameters Mangesh Bandiwadekar F: 09-Oct-24 09-Oct-24 23-Oct-24 06-Nov-24 13-Nov-24 20-Nov-24 20-Nov-24 21-Nov-24 28-Nov-24
TBD A: 09-Oct-24 09-Oct-24 23-Oct-24

Bidders Bid Received Award Notes / Comments


1 Brooks Instrument Oct 23 2024 12:00AM On AML. Bid recd from AWC Inc.Commercial bid tab updated.
2 Eastern Controls No Bid On AML. No Bid
3 Endress+Hauser Oct 23 2024 12:00AM On AML. Bid recd. Commercial bid tab updated.Freight charges awaited.
4 Krohne Oct 22 2024 12:00AM On AML. Bid recd. Commercial bid tab updated.
MIS-99 Heath Jones P: 20-Sep-24 04-Oct-24 10-Oct-24 31-Oct-24 07-Nov-24 14-Nov-24 14-Nov-24 15-Nov-24 21-Nov-24
Operation Shelter Mangesh Bandiwadekar F: 15-Oct-24 21-Oct-24 08-Nov-24 29-Nov-24 06-Dec-24 14-Dec-24 14-Dec-24 17-Dec-24 21-Dec-24
TBD A: 15-Oct-24 21-Oct-24
15Aug24TM: No category on the AML
Bidders Bid Received Award Notes / Comments
1 Fortress Technology Will Bid. C&E sheet replied by us.
2 Hunter Buildings Will bid.Building specifications & technical datasheet is required by Bidder.
3 RedGuard, LLC Will bid. RFI Log replied by us.
PNL-01 Heath Jones P: 27-May-25 10-Jun-25 23-Jun-25 30-Jun-25 08-Jul-25 15-Jul-25 15-Jul-25 16-Jul-25 22-Jul-25
Field Junction Boxes and Yateen Naik F: 23-May-25 09-Jun-25 20-Jun-25 27-Jun-25 07-Jul-25 14-Jul-25 14-Jul-25 15-Jul-25 21-Jul-25
Miscellaneous Assemblies TBD A:
15Aug24TM: No category on the AML
Bidders Bid Received Award Notes / Comments
1 Reynolds Electric
2 Smith Panel
3 Wholesale Electric Supply Co.
TRN-01 Alexandra McGhee P: 25-Sep-24 09-Oct-24 12-Nov-24 04-Dec-24 11-Dec-24 18-Dec-24 18-Dec-24 19-Dec-24 30-Dec-24
Pressure, DP Level, Diff Tina Huitrado F: 13-Dec-24 27-Dec-24 31-Jan-25 27-Feb-25 06-Mar-25 13-Mar-25 13-Mar-25 14-Mar-25 20-Mar-25
Pressure Transmitters TBD A:
Bidders Bid Received Award Notes / Comments
1 Endress+Hauser On AML
2 Rosemont On AML
3 Yokogawa On AML
TRN-02 Elaine Messiha P: 17-Sep-24 01-Oct-24 04-Nov-24 25-Nov-24 03-Dec-24 10-Dec-24 10-Dec-24 11-Dec-24 17-Dec-24
DP Flow Transmitters Tina Huitrado F: 23-Oct-24 29-Oct-24 12-Nov-24 08-Dec-24 16-Dec-24 23-Dec-24 23-Dec-24 24-Dec-24 30-Dec-24
TBD A: 23-Oct-24 29-Oct-24

Bidders Bid Received Award Notes / Comments


1 Endress+Hauser On AML. Intent to bid recv'd.
2 Rosemont On AML. Intent to bid recv'd.
3 Yokogawa On AML
TRN-03 Elaine Messiha P: 08-Oct-24 22-Oct-24 25-Nov-24 17-Dec-24 27-Dec-24 06-Jan-25 06-Jan-25 07-Jan-25 13-Jan-25
Temperature Transmitters Tina Huitrado F: 03-Dec-24 17-Dec-24 20-Jan-25 11-Feb-25 21-Feb-25 03-Mar-25 03-Mar-25 04-Mar-25 10-Mar-25
TBD A:
Bidders Bid Received Award Notes / Comments

DATE = Current Activity DATE = Within 7 Days DATE = Within 14 Days DATE = Plan Date Exceeded

Page 5 of 16 Tuesday, November 5, 2024


167375 Marcus Hook Ethane Expansion IFB Spec RFP Issued Bid Due Bid Eval PR Issue PR IFP Spec PO Award PO Drawing Delivery
Pkg. No. PO No. Engineer/Buyer/Supplier Received Date Approved Received Executed Submittal
1 Endress+Hauser On AML
2 Rosemont On AML
3 Yokogawa On AML
TRN-05 Emely Rivas P: 28-Aug-24 12-Sep-24 09-Oct-24 23-Oct-24 30-Oct-24 06-Nov-24 06-Nov-24 07-Nov-24 13-Nov-24
Guided Wave Radar Tina Huitrado F: 11-Oct-24 15-Oct-24 06-Nov-24 20-Nov-24 27-Nov-24 04-Dec-24 04-Dec-24 05-Dec-24 11-Dec-24
Transmitters TBD A: 11-Oct-24 15-Oct-24

Bidders Bid Received Award Notes / Comments


1 Endress+Hauser On AML. Intent to bid recv'd. Extension granted to 11/6
2 Magnetrol International, Inc. On AML.
3 Rosemont On AML. Intent to bid recv'd. Extension granted to 11/6.
VLV-01 John McLeod P: 14-Aug-24 19-Aug-24 04-Sep-24 18-Sep-24 25-Sep-24 15-Oct-24 15-Oct-24 16-Oct-24 22-Oct-24
Control Valves Yateen Naik F: 14-Aug-24 19-Aug-24 06-Sep-24 28-Oct-24 04-Nov-24 11-Nov-24 11-Nov-24 12-Nov-24 18-Nov-24
Eastern Controls A: 14-Aug-24 19-Aug-24 06-Sep-24 28-Oct-24 04-Nov-24

Bidders Bid Received Award Notes / Comments


1 Eastern Controls Sep 4 2024 12:00AM X CQ#02 response received.revised quotation for 20 Tags received on 10/24
2 Fisher Sep 7 2024 12:00AM On AML. CQ#01 response received.
3 Flowserve Sep 4 2024 12:00AM On AML.The Ts&Cs are closed
4 MASONEILAN No Bid End user falls within the territory for Eastern Controls. Requested to issue RFP to Eastern Control
VLV-01A 243973 John McLeod P: 14-Aug-24 19-Aug-24 04-Sep-24 18-Sep-24 25-Sep-24 15-Oct-24 15-Oct-24 16-Oct-24 22-Oct-24
Early Works Control Valve Tracey Mooney F: 25-Sep-24 25-Sep-24 27-Sep-24 04-Oct-24 21-Oct-24 25-Oct-24 04-Oct-24 28-Oct-24 31-Oct-24
Eastern Controls A: 25-Sep-24 25-Sep-24 27-Sep-24 04-Oct-24 21-Oct-24 25-Oct-24 04-Oct-24 28-Oct-24 31-Oct-24

Bidders Bid Received Award Notes / Comments


1 Eastern Controls Sep 27 2024 12:00AM X Bid received.
2 Flowserve Sep 25 2024 12:00AM Bid received. Modified Flowdowns for BMcD review/acceptance on 10/9
VLV-02 Ram Patel P: 02-Oct-24 16-Oct-24 05-Nov-24 19-Nov-24 26-Nov-24 04-Dec-24 04-Dec-24 05-Dec-24 11-Dec-24
Pressure Safety Valves Mangesh Bandiwadekar F: 15-Nov-24 29-Nov-24 19-Dec-24 02-Jan-25 09-Jan-25 17-Jan-25 17-Jan-25 18-Jan-25 24-Jan-25
TBD A:
Bidders Bid Received Award Notes / Comments
1 Anderson Greenwood (Emerson) On AML
2 Consolidated On AML
3 Farris On AML
VLV-02A John McLeod P: 23-Sep-24 24-Sep-24 27-Sep-24 02-Oct-24 03-Oct-24 08-Oct-24 08-Oct-24 10-Oct-24 15-Oct-24
Early Works Pressure Tracey Mooney F: 23-Sep-24 25-Sep-24 09-Oct-24 06-Nov-24 07-Nov-24 12-Nov-24 12-Nov-24 14-Nov-24 19-Nov-24
Relieve Valve TBD A: 23-Sep-24 25-Sep-24 09-Oct-24

Bidders Bid Received Award Notes / Comments


1 Anderson Greenwood (Emerson) Oct 2 2024 12:00AM Puffer
2 Consolidated Oct 9 2024 12:00AM Setpoint
3 Farris Oct 9 2024 12:00AM Total
VLV-03 243518 Emely Rivas P: 01-Aug-24 05-Aug-24 16-Aug-24 30-Aug-24 09-Sep-24 16-Sep-24 16-Sep-24 17-Sep-24 23-Sep-24
On/Off Valves Mangesh Bandiwadekar F: 01-Aug-24 05-Aug-24 06-Sep-24 04-Oct-24 07-Oct-24 08-Oct-24 17-Oct-24 22-Oct-24 24-Oct-24
Tri-State Technical Sales A: 01-Aug-24 05-Aug-24 06-Sep-24 04-Oct-24 07-Oct-24 08-Oct-24 17-Oct-24 22-Oct-24 24-Oct-24

Bidders Bid Received Award Notes / Comments

DATE = Current Activity DATE = Within 7 Days DATE = Within 14 Days DATE = Plan Date Exceeded

Page 6 of 16 Tuesday, November 5, 2024


167375 Marcus Hook Ethane Expansion IFB Spec RFP Issued Bid Due Bid Eval PR Issue PR IFP Spec PO Award PO Drawing Delivery
Pkg. No. PO No. Engineer/Buyer/Supplier Received Date Approved Received Executed Submittal
1 Deacon Industrial Supply Co., Inc No Bid Will bid. 5 reminders sent for their quote but no response.
2 Miller Energy No Bid No Bid. Reason not specified.
3 MRC Global Sep 6 2024 12:00AM Bid recd.Bidder replied to all commercial queries. Commercial bid tab updated.
4 Tri-State Technical Sales Aug 26 2024 12:00AM X TBE recd recommending Tri-State. PO authorization is approved.PO being issued.
VLV-04 243237 Emely Rivas P: 10-Jul-24 17-Jul-24 14-Aug-24 09-Sep-24 16-Sep-24 23-Sep-24 23-Sep-24 24-Sep-24 27-Sep-24
Orbit Valves Yateen Naik F: 10-Jul-24 17-Jul-24 14-Aug-24 30-Sep-24 10-Oct-24 16-Oct-24 07-Oct-24 22-Oct-24 24-Oct-24
Sunbelt A: 10-Jul-24 17-Jul-24 14-Aug-24 30-Sep-24 10-Oct-24 16-Oct-24 07-Oct-24 22-Oct-24 24-Oct-24
15Aug24TM: No category on the AML
Bidders Bid Received Award Notes / Comments
1 Cameron (MRC Global) Aug 9 2024 12:00AM CQ#3- Reply received.
2 DNOW L.P. No Bid No Bid. Reason not specified.
3 Sunbelt Aug 13 2024 12:00AM X Bid recd. Revised T& C received on 02-Oct-24
VLV-08 Elaine Messiha P: 08-Aug-24 22-Aug-24 19-Sep-24 10-Oct-24 17-Oct-24 24-Oct-24 24-Oct-24 27-Oct-24 31-Oct-24
Pressure Regulators Mangesh Bandiwadekar F: 22-Aug-24 26-Aug-24 18-Sep-24 04-Nov-24 11-Nov-24 18-Nov-24 18-Nov-24 21-Nov-24 25-Nov-24
TBD A: 22-Aug-24 26-Aug-24 18-Sep-24 04-Nov-24

Bidders Bid Received Award Notes / Comments


1 Fisher Control Valves Sep 28 2024 12:00AM On AML.Revised offer recd on 10/16.Commercial bid tab updated.Redlines on GTC & price adder to warranty
extension awaited.
2 Master Control Systems, Inc. Sep 13 2024 12:00AM On AML. Partial offer received. Commercial Bid tab updated.Price adder to meet warranty period is awaited.
3 Miller Energy Sep 13 2024 12:00AM Revised offer recd. On 10/17.Commercial Bid tab updated. Reply to commercial points & RTD awaited.
4 Swagelok No Bid On AML. No bid as they said these are not Swagelok type regulators.
MECH
COM-01 234890 Michael Meyer P: 16-Feb-24 16-Feb-24 08-Mar-24 21-Apr-24 26-Apr-24 10-May-24 17-May-24 17-May-24 22-May-24
Centrifugal Compressors Tracey Mooney F: 16-Feb-24 16-Feb-24 25-Mar-24 17-May-24 22-May-24 05-Jun-24 06-Jun-24 06-Jun-24 14-Jun-24
Atlas Copco Compressors A: 16-Feb-24 16-Feb-24 25-Mar-24 17-May-24 22-May-24 05-Jun-24 06-Jun-24 06-Jun-24 14-Jun-24

Bidders Bid Received Award Notes / Comments


1 Atlas Copco Compressors LLC X Matt Gysel / (518)256-4921 / [email protected]/
FIL-01 239848 Michelle Cheng P: 20-May-24 18-Jun-24 09-Jul-24 23-Jul-24 30-Jul-24 06-Aug-24 06-Aug-24 23-Sep-24 30-Sep-24
Filters Tina Huitrado F: 17-May-24 22-May-24 14-Jun-24 29-Jul-24 02-Aug-24 09-Aug-24 09-Aug-24 19-Aug-24 23-Aug-24
Southwest Filter A: 17-May-24 22-May-24 14-Jun-24 29-Jul-24 02-Aug-24 09-Aug-24 09-Aug-24 19-Aug-24 23-Aug-24

Bidders Bid Received Award Notes / Comments


1 Pall Corporation Jun 14 2024 12:00AM Intent to bid received. Will submit quotation by 6/14.
2 Parker Hannifin Filtration (US), Inc. Jun 26 2024 12:00AM Late submittal of proposal.
3 Pentair Filtration Solutions LLC Jun 10 2024 12:00AM Intent to bid received. Bid extension approved to 14-Jun-2024.
4 Southwest Filter Jun 5 2024 12:00AM X Intent to bid received. Will submit quotation by 6/6. Recommended bidder.
FIL-02 240668 Michelle Cheng P: 20-May-24 18-Jun-24 09-Jul-24 23-Jul-24 30-Jul-24 27-Aug-24 27-Aug-24 29-Aug-24 05-Sep-24
CO2 Removal System Tina Huitrado F: 17-May-24 24-May-24 17-Jun-24 17-Jul-24 20-Aug-24 27-Aug-24 08-Aug-24 29-Aug-24 09-Sep-24
Pentair Filtration Solutions A: 17-May-24 24-May-24 17-Jun-24 17-Jul-24 20-Aug-24 27-Aug-24 08-Aug-24 29-Aug-24 09-Sep-24

Bidders Bid Received Award Notes / Comments


1 Celeros Flow Technology No Bid Declined to bid, sold its filtration buisness.
2 Filtration Group Jun 14 2024 12:00AM Will submit quotation by 6/14.
3 Parker Hannifin Filtration (US), Inc. No Bid Delined to bid, does not have a solution fo the equipment.

DATE = Current Activity DATE = Within 7 Days DATE = Within 14 Days DATE = Plan Date Exceeded

Page 7 of 16 Tuesday, November 5, 2024


167375 Marcus Hook Ethane Expansion IFB Spec RFP Issued Bid Due Bid Eval PR Issue PR IFP Spec PO Award PO Drawing Delivery
Pkg. No. PO No. Engineer/Buyer/Supplier Received Date Approved Received Executed Submittal
4 Pentair Filtration Solutions LLC Jun 17 2024 12:00AM X Intent to bid received. Bid extension approved to 6/14. Recommended bidder.
FLR-101 240662 Devan O'Dell P: 13-May-24 11-Jun-24 08-Jul-24 22-Jul-24 29-Jul-24 23-Aug-24 23-Aug-24 25-Aug-24 30-Aug-24
Flares Tina Huitrado F: 10-May-24 21-May-24 12-Jul-24 01-Aug-24 15-Aug-24 27-Aug-24 29-Aug-24 29-Aug-24 04-Sep-24
Zeeco, Inc. A: 10-May-24 21-May-24 12-Jul-24 01-Aug-24 15-Aug-24 27-Aug-24 29-Aug-24 29-Aug-24 04-Sep-24

Bidders Bid Received Award Notes / Comments


1 John Zink Intent to bid received. Extension approved to 6/14. Will submit a budgetary proposal on 6/28. Will submit a
quotation by 7/3.
2 Zeeco, Inc. Jun 21 2024 12:00AM X Intent to bid received. Will submit quotationon 6/14. Budgetary recv'd, exepcting firm bid by June 20th.
HEX-01 239784 Andrii Yevsieiev P: 01-May-24 13-May-24 03-Jun-24 17-Jun-24 24-Jun-24 01-Jul-24 01-Jul-24 02-Jul-24 09-Jul-24
Air Cooled Heat Elise Chouinard F: 03-May-24 06-May-24 24-May-24 18-Jul-24 23-Jul-24 09-Aug-24 09-Aug-24 13-Aug-24 16-Aug-24
Exchangers Fabsco Fin-Air, LLC A: 03-May-24 06-May-24 24-May-24 18-Jul-24 23-Jul-24 09-Aug-24 09-Aug-24 13-Aug-24 16-Aug-24

Bidders Bid Received Award Notes / Comments


1 E&C FinFans (Chart Industries) No Bid No Bid
2 Fabsco Fin-Air, LLC May 23 2024 12:00AM X
3 Kelvion Inc May 23 2024 12:00AM
4 Tek-Fins May 24 2024 12:00AM
HEX-02 240795 Andrii Yevsieiev P: 13-May-24 28-May-24 17-Jun-24 01-Jul-24 09-Jul-24 26-Aug-24 26-Aug-24 27-Aug-24 03-Sep-24
Shell & Tube Heat Elise Chouinard F: 08-May-24 14-May-24 30-May-24 22-Jul-24 12-Aug-24 30-Aug-24 14-Aug-24 30-Aug-24 05-Sep-24
Exchangers Godrej & Boyce A: 08-May-24 14-May-24 30-May-24 22-Jul-24 12-Aug-24 30-Aug-24 14-Aug-24 30-Aug-24 05-Sep-24

Bidders Bid Received Award Notes / Comments


1 Anup Engineering May 29 2024 12:00AM
2 Fabsco Shell & Tube, LLC May 29 2024 12:00AM
3 Godrej & Boyce May 29 2024 12:00AM X
4 Krueger May 30 2024 12:00AM
5 Ohmstede No Bid
6 Taylor Forge Engineered Systems May 30 2024 12:00AM
HEX-03 240271 Andrii Yevsieiev P: 21-May-24 19-Jun-24 10-Jul-24 17-Jul-24 31-Jul-24 26-Aug-24 26-Aug-24 27-Aug-24 03-Sep-24
Shell & Tube Heat Elise Chouinard F: 17-May-24 24-May-24 21-Jun-24 22-Jul-24 23-Jul-24 26-Aug-24 16-Aug-24 23-Aug-24 02-Sep-24
Exchangers Anup Engineering A: 17-May-24 24-May-24 21-Jun-24 22-Jul-24 23-Jul-24 26-Aug-24 16-Aug-24 23-Aug-24 02-Sep-24

Bidders Bid Received Award Notes / Comments


1 Anup Engineering Jun 14 2024 12:00AM X
2 Fabsco Shell & Tube, LLC Jun 21 2024 12:00AM
3 Godrej & Boyce No Bid
4 Krueger Jun 20 2024 12:00AM
5 Ohmstede No Bid
6 Taylor Forge Engineered Systems Jun 21 2024 12:00AM
HEX-04 241673 Raj Chhatrapati P: 21-May-24 19-Jun-24 10-Jul-24 24-Jul-24 09-Aug-24 16-Aug-24 16-Aug-24 19-Aug-24 23-Aug-24
Electric Heaters (MV) Elise Chouinard F: 21-May-24 24-May-24 21-Jun-24 23-Jul-24 26-Sep-24 27-Sep-24 13-Aug-24 04-Oct-24 18-Oct-24
Watlow A: 21-May-24 24-May-24 21-Jun-24 23-Jul-24 26-Sep-24 27-Sep-24 13-Aug-24 04-Oct-24 18-Oct-24

Bidders Bid Received Award Notes / Comments


1 Chromalox No Bid Will Bid - Expecting quote 7/19. Not received
2 Watlow Jun 21 2024 12:00AM X

DATE = Current Activity DATE = Within 7 Days DATE = Within 14 Days DATE = Plan Date Exceeded

Page 8 of 16 Tuesday, November 5, 2024


167375 Marcus Hook Ethane Expansion IFB Spec RFP Issued Bid Due Bid Eval PR Issue PR IFP Spec PO Award PO Drawing Delivery
Pkg. No. PO No. Engineer/Buyer/Supplier Received Date Approved Received Executed Submittal
HEX-05 241675 Sydni Fritts P: 03-Jun-24 05-Jun-24 27-Jun-24 09-Aug-24 16-Aug-24 23-Aug-24 23-Aug-24 26-Aug-24 30-Aug-24
Electric Heaters (LV) Elise Chouinard F: 03-Jun-24 05-Jun-24 27-Jun-24 07-Aug-24 26-Sep-24 30-Sep-24 20-Aug-24 04-Oct-24 18-Oct-24
Watlow A: 03-Jun-24 05-Jun-24 27-Jun-24 07-Aug-24 26-Sep-24 30-Sep-24 20-Aug-24 04-Oct-24 18-Oct-24

Bidders Bid Received Award Notes / Comments


1 Chromalox Jul 29 2024 12:00AM Not being evaluated due to late bid.
2 Gaumer Process No Bid No Bid - Cannot submit by 6/24
3 Watlow Jun 27 2024 12:00AM X Comments on Terms sent back 6/27.
HEX-101 241159 Andrii Yevsieiev P: 06-May-24 11-Jun-24 09-Jul-24 23-Jul-24 30-Jul-24 23-Aug-24 23-Aug-24 26-Aug-24 30-Aug-24
Ambient Vaporizer Tina Huitrado F: 01-May-24 07-May-24 28-May-24 12-Aug-24 15-Aug-24 27-Aug-24 04-Sep-24 10-Sep-24 18-Sep-24
Acme Cryogenics (CEXI - C A: 01-May-24 07-May-24 28-May-24 12-Aug-24 15-Aug-24 27-Aug-24 04-Sep-24 10-Sep-24 18-Sep-24
03SEPT24TH: awaiting IFP and financial review req'd by supplier registration.
12Aug24TH: Purchase Authorization will route for approval on 8/13. There is no catergory on the AML for this package.
Bidders Bid Received Award Notes / Comments
1 Acme Cryogenics (CEXI - Cryogenic Experts, Inc.) May 28 2024 12:00AM X Intent to bid received. Recommended bidder.
2 Chart May 24 2024 12:00AM Bid extension approved, 5/31/24.
3 Linde No Bid Declined to bid.
INT-01 240808 Sanjay Basnet P: 18-Jun-24 02-Jul-24 16-Jul-24 20-Aug-24 27-Aug-24 04-Sep-24 04-Sep-24 16-Sep-24 20-Sep-24
Internals Tina Huitrado F: 18-Jun-24 19-Jun-24 03-Jul-24 13-Aug-24 05-Sep-24 09-Sep-24 16-Aug-24 09-Oct-24 05-Nov-24
Koch-Glitsch, LP. A: 18-Jun-24 19-Jun-24 03-Jul-24 13-Aug-24 05-Sep-24 09-Sep-24 16-Aug-24 09-Oct-24 05-Nov-24
7OCT24TH: Awaiting final approval on T&Cs from Koch, they accepted the insurance language
30SEP24TH: Awaiting approval on T&Cs - insurance. Internal discussions.
24SEP24TH: Awaiting approval on T&Cs - insurance.
17SEPT24TH: Awaiting approval on T&Cs - insurance.
03SEPT24TH: Awaiting approval on T&Cs, open items LOL & insurance.
Bidders Bid Received Award Notes / Comments
1 Koch-Glitsch, LP. Jul 3 2024 12:00AM X Koch will submit on 7/10. Recommmended bidder.
2 Sulzer Chemtech Will not be able to submit a quotation until 7/5.
PMP-01 241189 Ubong Ekwere P: 15-May-24 22-May-24 29-May-24 12-Jun-24 22-Aug-24 29-Aug-24 29-Aug-24 30-Aug-24 06-Sep-24
API Pumps Tina Huitrado F: 24-Apr-24 26-Apr-24 12-Jun-24 18-Jul-24 04-Sep-24 09-Sep-24 22-Aug-24 10-Sep-24 10-Sep-24
CPC Pumps International A: 24-Apr-24 26-Apr-24 12-Jun-24 18-Jul-24 04-Sep-24 09-Sep-24 22-Aug-24 10-Sep-24 10-Sep-24
03SEPT24TH: Awaiting approval from BMcD legal on T&C exceptions to Atlas Copco T&Cs; quality docs for waiver.
12Aug24th: Awaiting Ts&Cs responses from the Supplier. No category on the AML.
Bidders Bid Received Award Notes / Comments
1 CPC Pumps International Jun 4 2024 12:00AM X Intent to bid received. Recommended bidder.
2 Flowserve Jun 12 2024 12:00AM Bid extension appproved for 17-May-2024. Technical bid recv'd, 5-22-24.
3 Goulds Pumps No Bid Declined to bid.
4 Sulzer May 29 2024 12:00AM Bid extension appproved for 17-May-2024.

DATE = Current Activity DATE = Within 7 Days DATE = Within 14 Days DATE = Plan Date Exceeded

Page 9 of 16 Tuesday, November 5, 2024


167375 Marcus Hook Ethane Expansion IFB Spec RFP Issued Bid Due Bid Eval PR Issue PR IFP Spec PO Award PO Drawing Delivery
Pkg. No. PO No. Engineer/Buyer/Supplier Received Date Approved Received Executed Submittal
PMP-02 243667 Ubong Ekwere P: 17-May-24 03-Jun-24 21-Jun-24 23-Aug-24 30-Aug-24 09-Sep-24 09-Sep-24 10-Sep-24 16-Sep-24
VS6 Pumps Tina Huitrado F: 01-May-24 06-May-24 07-Aug-24 25-Sep-24 17-Oct-24 23-Oct-24 25-Oct-24 25-Oct-24 08-Nov-24
Flowserve A: 01-May-24 06-May-24 07-Aug-24 25-Sep-24 17-Oct-24 23-Oct-24 25-Oct-24 25-Oct-24
15OCT24TH: Flowserve recommended, Proc VP to do full review before issuance of PR.
7OCT24TH: Awaiting revised bids from Sulzer & Flowserve, Suzler MPA flowdons accepted.
24SEP24TH: T&C Negotiations for MPA Flowdowns, awaiting supplier approval of our comments
12Aug24TM: Additional bids have been received and are under evaluation. No category on the AML
Bidders Bid Received Award Notes / Comments
1 Afton Pumps Inc. Jul 26 2024 12:00AM On AML
2 CPC Pumps International Jun 20 2024 12:00AM Not on the AML
3 DNOW L.P. Aug 7 2024 12:00AM Will submit on 8/5. Shortlisted. Not on the AML.
4 Flowserve May 30 2024 12:00AM X On the AML
5 Goulds Pumps No Bid Declined to bid.
6 Sulzer USA Aug 5 2024 12:00AM Shortlisted. On the AML
7 Sundyne LLC Aug 5 2024 12:00AM Will Bid. Budgetary recv'd 8/5/24. On the AML.
8 Torishima Pump Mfg. Co., Ltd. No Bid Following up with the Supplier.
PMP-03 Ubong Ekwere P: 13-May-24 11-Jun-24 01-Jul-24 28-Aug-24 05-Sep-24 12-Sep-24 12-Sep-24 13-Sep-24 19-Sep-24
ANSI Pumps Tina Huitrado F: 02-May-24 06-May-24 07-Aug-24 10-Oct-24 25-Oct-24 01-Nov-24 01-Nov-24 06-Nov-24 11-Nov-24
Flowserve A: 02-May-24 06-May-24 07-Aug-24 10-Oct-24 25-Oct-24 01-Nov-24 01-Nov-24
15OCT24TH: Flowserve recommended, Proc VP to do full review before issuance of PR.
7OCT24TH: Ongoing T&C negotiations for DXP & DNOW
24SEP24TH: T&C Negotiations for DXP & DNOW
13Aug24TM: Additional bids have been received and are under evaluation. No category on the AML
Bidders Bid Received Award Notes / Comments
1 DNOW L.P. Aug 7 2024 12:00AM Will Bid. Shortlisted. On AML.
2 DXP Enterprises, Inc. Aug 7 2024 12:00AM Will Bid. Shortlisted. On AML.
3 Flowserve May 31 2024 12:00AM X On AML.
4 Goulds Pumps No Bid Declined to bid, cannot meet design requirements.
5 Sulzer India No Bid Technical received on 8/5. On AML.
6 Torishima Pump Mfg. Co., Ltd. No Bid
SYS-03 240581 Robert McEvoy P: 10-May-24 11-Jun-24 22-Jul-24 05-Aug-24 23-Aug-24 30-Aug-24 30-Aug-24 03-Sep-24 09-Sep-24
Amine Regen System Tina Huitrado F: 09-May-24 14-May-24 11-Jun-24 19-Jul-24 23-Aug-24 26-Aug-24 23-Aug-24 29-Aug-24 06-Sep-24
Opero Energy A: 09-May-24 14-May-24 11-Jun-24 19-Jul-24 23-Aug-24 26-Aug-24 23-Aug-24 29-Aug-24 06-Sep-24

Bidders Bid Received Award Notes / Comments


1 Enerflex LTD Jun 11 2024 12:00AM Intent to bid received. Extension granted to 6/11.
2 Interstate Treading, Inc. Jun 4 2024 12:00AM Intent to bid received.
3 Joule Processing No Bid Company bought out by Plug Power, TBD if they can bid.
4 Opero Energy Jun 4 2024 12:00AM X Intent to bid received. Recommended bidder.
SYS-04 242567 Devan O'Dell P: 09-Aug-24 23-Aug-24 06-Sep-24 16-Sep-24 23-Sep-24 30-Sep-24 30-Sep-24 01-Oct-24 07-Oct-24
Flare Heat Shielding Elise Chouinard F: 14-Aug-24 15-Aug-24 28-Aug-24 19-Sep-24 23-Sep-24 24-Sep-24 24-Sep-24 07-Oct-24 08-Oct-24
Locker Heatshielding LTD A: 14-Aug-24 15-Aug-24 28-Aug-24 19-Sep-24 23-Sep-24 24-Sep-24 24-Sep-24 07-Oct-24 08-Oct-24
13Aug24TM: There is no caterogy on the AML for this package.
Bidders Bid Received Award Notes / Comments
1 Locker Heatshielding LTD X

DATE = Current Activity DATE = Within 7 Days DATE = Within 14 Days DATE = Plan Date Exceeded

Page 10 of 16 Tuesday, November 5, 2024


167375 Marcus Hook Ethane Expansion IFB Spec RFP Issued Bid Due Bid Eval PR Issue PR IFP Spec PO Award PO Drawing Delivery
Pkg. No. PO No. Engineer/Buyer/Supplier Received Date Approved Received Executed Submittal
SYS-05 Nathanael Marino P: 23-Sep-24 30-Sep-24 25-Oct-24 15-Nov-24 22-Nov-24 02-Dec-24 02-Dec-24 03-Dec-24 09-Dec-24
Fuel Gas Export Tina Huitrado F: 23-Sep-24 25-Sep-24 01-Nov-24 22-Nov-24 29-Nov-24 09-Dec-24 09-Dec-24 10-Dec-24 16-Dec-24
Compressors TBD A: 23-Sep-24 25-Sep-24 01-Nov-24
4NOV24: All bids in, reviewing proposals for C&Es.
Bidders Bid Received Award Notes / Comments
1 Cobey Nov 1 2024 12:00AM Intent to bid recv'd.
2 Compass No Bid Declined to bid.
3 Enerflex LTD Oct 25 2024 12:00AM Intent to bid recv'd.
4 RKG Consultants Oct 23 2024 12:00AM Intent to bid recv'd.
SYS-06 Michael Meyer P: 13-Sep-24 17-Sep-24 08-Oct-24 29-Oct-24 05-Nov-24 12-Nov-24 12-Nov-24 13-Nov-24 19-Nov-24
Amine Off Gas Tina Huitrado F: 13-Sep-24 17-Sep-24 23-Oct-24 13-Nov-24 20-Nov-24 27-Nov-24 27-Nov-24 28-Nov-24 04-Dec-24
Compressors TBD A: 13-Sep-24 17-Sep-24 23-Oct-24
4NOV24: Spitxer bid not recv'd, bid period has closed.
28OCT24TH: Spitzer to send bid this week.
Bidders Bid Received Award Notes / Comments
1 Cobey Oct 23 2024 12:00AM Intent to bid recv'd. Bid extension approved to 10/16/24.
2 Compass No Bid Declined to bid.
3 Enerflex Energy Systems Inc Oct 18 2024 12:00AM Intent to bid recv'd.
4 RKG Consultants No Bid Intent to bid recv'd. Not recived, bid period has closed.
SYS-07 Robert McEvoy P: 14-Oct-24 21-Oct-24 15-Nov-24 09-Dec-24 16-Dec-24 23-Dec-24 23-Dec-24 27-Dec-24 03-Jan-25
Fuel Gas Export Odorant Tina Huitrado F: 04-Oct-24 10-Oct-24 07-Nov-24 01-Dec-24 08-Dec-24 15-Dec-24 15-Dec-24 19-Dec-24 26-Dec-24
TBD A: 04-Oct-24 10-Oct-24
28OCT24TH: Lewa to provide by on 11/7/24, it was decided we would accept but determine if it's going to be evaluated further based on cost and techncial acceptance.
Bidders Bid Received Award Notes / Comments
1 Johnson March Systems, Inc. No Bid Declined to bid.
2 Lewa America, Inc. Requested bid extension to 10/31/24. Extension granted to 11/7.
3 Linc Energy Systems/GPL Odorizers Oct 24 2024 12:00AM
4 S&S Technical, Inc. Oct 21 2024 12:00AM Intent to bid recv'd.
5 YZ Systems No Bid Intent to bid recv'd.
TNK-01 241156 Hong M Cheng P: 10-Jun-24 11-Jun-24 25-Jun-24 31-Jul-24 08-Aug-24 22-Aug-24 29-Aug-24 03-Sep-24 09-Sep-24
Amine Storage Tank Tracey Mooney F: 10-Jun-24 11-Jun-24 25-Jun-24 31-Jul-24 08-Aug-24 09-Sep-24 16-Aug-24 09-Sep-24 23-Sep-24
Smith Tank & Steel A: 10-Jun-24 11-Jun-24 25-Jun-24 31-Jul-24 08-Aug-24 09-Sep-24 16-Aug-24 09-Sep-24 23-Sep-24
15Aug24TM: PA and waiver with the Client for approval.
Bidders Bid Received Award Notes / Comments
1 Apache Stainless Jun 25 2024 12:00AM Will Bid. Shortlisted.
2 Baker Tank Company c/o Altech Jun 25 2024 12:00AM Will Bid
3 Long Industries Jun 25 2024 12:00AM Will Bid. Shortlisted
4 Modem Welding
5 Smith Tank & Steel Jun 25 2024 12:00AM X Will Bid. Shortlisted. Recommended bidder, not on AML.
TWR-01 239736 Sanjay Basnet P: 11-Jun-24 10-Jul-24 06-Aug-24 20-Aug-24 27-Aug-24 04-Sep-24 04-Sep-24 16-Sep-24 20-Sep-24
Towers Tina Huitrado F: 17-Jun-24 18-Jun-24 08-Jul-24 17-Jul-24 23-Jul-24 09-Aug-24 09-Aug-24 13-Aug-24 13-Aug-24
Sauder Custom Fabricatio A: 17-Jun-24 18-Jun-24 08-Jul-24 17-Jul-24 23-Jul-24 09-Aug-24 09-Aug-24 13-Aug-24 13-Aug-24

Bidders Bid Received Award Notes / Comments


DATE = Current Activity DATE = Within 7 Days DATE = Within 14 Days DATE = Plan Date Exceeded

Page 11 of 16 Tuesday, November 5, 2024


167375 Marcus Hook Ethane Expansion IFB Spec RFP Issued Bid Due Bid Eval PR Issue PR IFP Spec PO Award PO Drawing Delivery
Pkg. No. PO No. Engineer/Buyer/Supplier Received Date Approved Received Executed Submittal
1 Arrow Tank No Bid Will bid, requested an extension to 7/10
2 BWFS Industries LLC Jun 28 2024 12:00AM
3 Contract Fabricators Jul 1 2024 12:00AM Will bid, requested an extension to 7/3
4 Kennedy Tank and Manufacturing Co., Inc. No Bid No Bid
5 Sauder Custom Fabrication Jul 8 2024 12:00AM X Will bid, requested an extension to 7/8
VSL-01 240316 Sanjay Basnet P: 30-Apr-24 30-Apr-24 24-May-24 10-Jun-24 17-Jun-24 24-Jun-24 24-Jun-24 25-Jun-24 01-Jul-24
Heavy Wall Vessels Tina Huitrado F: 26-Apr-24 30-Apr-24 30-May-24 17-Jul-24 23-Jul-24 23-Aug-24 08-Aug-24 23-Aug-24 27-Aug-24
Anup Engineering A: 26-Apr-24 30-Apr-24 30-May-24 17-Jul-24 23-Jul-24 23-Aug-24 08-Aug-24 23-Aug-24 27-Aug-24
12Aug24TH: The Purchase Authorization and AML Waiver is with the Client for approval.
Bidders Bid Received Award Notes / Comments
1 Anup Engineering May 14 2024 12:00AM X Shortlisted. Recommended bidder.
2 Contract Fabricators May 29 2024 12:00AM
3 Godrej & Boyce May 23 2024 12:00AM
4 Hooper Welding Enterprises, Ltd. May 16 2024 12:00AM
5 Praj Industries Limited May 30 2024 12:00AM Bid extension approved to 5/31.
6 Sauder Custom Fabrication May 14 2024 12:00AM Shortlisted
7 Schwartz Hautmont Construcciones Metalicas SA May 14 2024 12:00AM
8 Wooyang HC May 23 2024 12:00AM Shortlisted
VSL-02 240341 Sanjay Basnet P: 28-May-24 11-Jun-24 01-Jul-24 30-Jul-24 06-Aug-24 13-Aug-24 13-Aug-24 09-Sep-24 13-Sep-24
Cold Side Vessels Tina Huitrado F: 08-May-24 13-May-24 13-Jun-24 17-Jul-24 24-Jul-24 23-Aug-24 07-Aug-24 23-Aug-24 27-Aug-24
Anup Engineering A: 08-May-24 13-May-24 13-Jun-24 17-Jul-24 24-Jul-24 23-Aug-24 07-Aug-24 23-Aug-24 27-Aug-24
12Aug24TH: The Purchase Authorizationis and AML Waiver is with the Client for approval.
Bidders Bid Received Award Notes / Comments
1 Anup Engineering Jun 3 2024 12:00AM X Shortlisted. Recommended bidder.
2 Boardman Jun 11 2024 12:00AM Shortlisted.
3 BWFS Industries LLC No Bid Intent to bid received. Bid extension approved til 10-Jun-2024.
4 Contract Fabricators Jun 14 2024 12:00AM Extension granted to 6/13.
5 Godrej & Boyce No Bid Declined to bid, "too small for economical production at our works and cannot be competitive".
6 Gulf Coast Alloy Welding (GCAW) No Bid No response.
7 Praj Industries Limited No Bid Intent to bid received.
8 Sauder Custom Fabrication Jun 7 2024 12:00AM Intent to bid received. Extension granted to 6/7
9 Schwartz Hautmont Construcciones Metalicas SA May 31 2024 12:00AM
10 Wooyang HC Jun 13 2024 12:00AM Intent to bid received. Extenstion granted to 6/13.
VSL-03 240839 Michelle Cheng P: 13-May-24 28-May-24 10-Jun-24 15-Jul-24 22-Jul-24 29-Jul-24 29-Jul-24 30-Jul-24 05-Aug-24
Vessels Tina Huitrado F: 07-May-24 09-May-24 31-May-24 31-Jul-24 05-Aug-24 09-Aug-24 15-Aug-24 29-Aug-24 10-Sep-24
Gulf Coast Alloy Welding ( A: 07-May-24 09-May-24 31-May-24 31-Jul-24 05-Aug-24 09-Aug-24 15-Aug-24 29-Aug-24 10-Sep-24

Bidders Bid Received Award Notes / Comments


1 Boardman May 22 2024 12:00AM
2 BWFS Industries LLC No Bid
3 Gulf Coast Alloy Welding (GCAW) May 23 2024 12:00AM X Recommended bidder.
4 Modern Welding Company No Bid Declined to bid, supplier did not offer explanation.
5 Professional Projects Inc. May 31 2024 12:00AM

DATE = Current Activity DATE = Within 7 Days DATE = Within 14 Days DATE = Plan Date Exceeded

Page 12 of 16 Tuesday, November 5, 2024


167375 Marcus Hook Ethane Expansion IFB Spec RFP Issued Bid Due Bid Eval PR Issue PR IFP Spec PO Award PO Drawing Delivery
Pkg. No. PO No. Engineer/Buyer/Supplier Received Date Approved Received Executed Submittal
VSL-04 241258 Tara Brown P: 03-Jun-24 01-Jul-24 26-Jul-24 09-Aug-24 16-Aug-24 23-Aug-24 30-Aug-24 03-Sep-24 09-Sep-24
Double Walled Vessels Tina Huitrado F: 03-Jun-24 05-Jun-24 21-Jun-24 17-Jul-24 15-Aug-24 27-Aug-24 06-Aug-24 10-Sep-24 19-Sep-24
Professional Projects Inc. A: 03-Jun-24 05-Jun-24 21-Jun-24 17-Jul-24 15-Aug-24 27-Aug-24 06-Aug-24 10-Sep-24 19-Sep-24

Bidders Bid Received Award Notes / Comments


1 Boardman Jun 19 2024 12:00AM Intent to bid received. Requested bid extension to 26-June. Declined, supplier to provide budgetary and firm to
be sent next week.
2 BWFS Industries LLC No Bid No response.
3 Contract Fabricators Jun 19 2024 12:00AM Shortlisted.
4 Gulf Coast Alloy Welding (GCAW) Jun 21 2024 12:00AM
5 Modern Welding Company No Bid Declined to bid due to complexity and current workload
6 Professional Projects Inc. Jun 19 2024 12:00AM X Bid extension reqeusted to 26-June. Declined. Requested budgetary, andthey can follow up with a firm bid.
Shortlisted. Recommended bidder.
PIPING
CSH-01 Matthew Seymour P: 10-Dec-24 03-Jan-25 31-Jan-25 07-Feb-25 14-Feb-25 21-Feb-25 21-Feb-25 24-Feb-25 28-Feb-25
Cold Shoes Lynzy Ford F: 10-Dec-24 03-Jan-25 31-Jan-25 07-Feb-25 14-Feb-25 21-Feb-25 21-Feb-25 24-Feb-25 28-Feb-25
TBD A:
17Sep24TM: No category on the AML.
Bidders Bid Received Award Notes / Comments
1 APP Manufacturing Contact: Carrie Reese / Stephanie Ducote
713-956-2922
2 Industrial Material Corp Contact: Jayson Levy
409.744.4538
3 Rilco Manufacturing Contact: Bill Mahlman / Manu Nair
713-466-4777
ESC-01 Matthew Seymour P: 25-Nov-24 27-Dec-24 17-Jan-25 24-Jan-25 31-Jan-25 07-Feb-25 07-Feb-25 10-Feb-25 14-Feb-25
Engineered Commodities Lynzy Ford F: 25-Nov-24 27-Dec-24 17-Jan-25 24-Jan-25 31-Jan-25 07-Feb-25 07-Feb-25 10-Feb-25 14-Feb-25
TBD A:
17Sep24TM: No category on the AML.
Bidders Bid Received Award Notes / Comments
1 Ferguson Industrial Contact: John Lancaster
2 MRC Global Contact: Brenden Lackey
3 Relevant Industrial
4 Sunbelt Supply Co. Contact: Megan Stewart
FWS-01 Connor Chmielewski P: 10-Jan-25 07-Feb-25 27-Feb-25 06-Mar-25 13-Mar-25 20-Mar-25 20-Mar-25 21-Mar-25 27-Mar-25
Fire Water Specials Lynzy Ford F: 20-Jan-25 17-Feb-25 07-Mar-25 14-Mar-25 21-Mar-25 28-Mar-25 28-Mar-25 31-Mar-25 04-Apr-25
TBD A:
17Sep24TM: No category on the AML.
Bidders Bid Received Award Notes / Comments
1 Dooley Tackaberry Contact: Jonathan Sharpe
2 Ferguson
3 Hayden & Company Contact: Austin Prather

DATE = Current Activity DATE = Within 7 Days DATE = Within 14 Days DATE = Plan Date Exceeded

Page 13 of 16 Tuesday, November 5, 2024


167375 Marcus Hook Ethane Expansion IFB Spec RFP Issued Bid Due Bid Eval PR Issue PR IFP Spec PO Award PO Drawing Delivery
Pkg. No. PO No. Engineer/Buyer/Supplier Received Date Approved Received Executed Submittal
MAT-01 242007 Matthew Seymour P: 30-Aug-24 21-Sep-24 04-Oct-24 18-Oct-24 25-Oct-24 01-Nov-24 01-Nov-24 02-Nov-24 09-Nov-24 16-Nov-24
Early Firewater Valves Lynzy Ford F: 04-Sep-24 05-Sep-24 09-Sep-24 18-Sep-24 18-Sep-24 24-Sep-24 27-Sep-24 30-Sep-24 30-Sep-24
Hayden A: 04-Sep-24 05-Sep-24 09-Sep-24 18-Sep-24 18-Sep-24 24-Sep-24 27-Sep-24 30-Sep-24 30-Sep-24
17Sep24TM: No category on the AML.
Bidders Bid Received Award Notes / Comments
1 Dooley Tackaberry Sep 9 2024 12:00AM Contact: Jonathan Sharpe/Maribel Shoen - ITB recv'd 9/4
2 Hayden Sep 9 2024 12:00AM X **Recommended** HC090424QBW
Contact: Jonathan Walker - ITB recv'd 9/4
3 MRC Sep 9 2024 12:00AM Contact: Brenden Lackey/Downstream Valve Co.
4 Sunbelt Supply Co. Sep 9 2024 12:00AM Contact: Mike Willeford/Megan Stewart - ITB recv'd 9/5
MAT-02 242190 Matthew Seymour P: 30-Aug-24 21-Sep-24 04-Oct-24 18-Oct-24 25-Oct-24 01-Nov-24 01-Nov-24 02-Nov-24 08-Nov-24
Bulk Material (HDPE Early Lynzy Ford F: 09-Sep-24 11-Sep-24 18-Sep-24 20-Sep-24 25-Sep-24 26-Sep-24 02-Oct-24 02-Oct-24 02-Oct-24
Works) Ferguson Industrial A: 09-Sep-24 11-Sep-24 18-Sep-24 20-Sep-24 25-Sep-24 26-Sep-24 02-Oct-24 02-Oct-24 02-Oct-24
17Sep24TM: No category on the AML.
Bidders Bid Received Award Notes / Comments
1 Ferguson Sep 17 2024 12:00AM **RECOMMENDED**
Contact: Chris Lofton
2 Gajeske, Inc. Sep 19 2024 12:00AM Contact: Mike Pryor
3 ISCO Industries Inc. Sep 13 2024 12:00AM Contact: Richard Coombs
4 MRC Sep 18 2024 12:00AM Contact: Brenden Lackey
MVL-01 Matthew Seymour P: 03-Sep-24 24-Sep-24 14-Oct-24 04-Nov-24 11-Nov-24 18-Nov-24 18-Nov-24 19-Nov-24 25-Nov-24
Manual Valves (Module & Lynzy Ford F: 01-Nov-24 08-Nov-24 28-Nov-24 19-Dec-24 26-Dec-24 03-Jan-25 03-Jan-25 04-Jan-25 10-Jan-25
Off Module) TBD A: 01-Nov-24
17Sep24TM: No category on the AML.
Bidders Bid Received Award Notes / Comments
1 Ferguson Contact: Megan Daly
2 MRC Contact: Brenden Lackey
3 Sunbelt Supply Co. Contact: Megan Stewart
4 Superior Valve Co. Contact: Key Runge
MVL-03 Matthew Seymour P: 19-Aug-24 17-Sep-24 07-Oct-24 14-Oct-24 21-Oct-24 28-Oct-24 28-Oct-24 29-Oct-24 04-Nov-24
Manual Valves (Cryogenic) Lynzy Ford F: 25-Nov-24 12-Dec-24 01-Jan-25 08-Jan-25 15-Jan-25 22-Jan-25 22-Jan-25 23-Jan-25 29-Jan-25
TBD A:
17Sep24TM: No category on the AML.
Bidders Bid Received Award Notes / Comments
1 Ferguson Industrial Contact: Chris Fadden
2 MRC Global Contact: Brenden Lackey
3 Sunbelt Supply Co. Contact: Megan Stewart

DATE = Current Activity DATE = Within 7 Days DATE = Within 14 Days DATE = Plan Date Exceeded

Page 14 of 16 Tuesday, November 5, 2024


167375 Marcus Hook Ethane Expansion IFB Spec RFP Issued Bid Due Bid Eval PR Issue PR IFP Spec PO Award PO Drawing Delivery
Pkg. No. PO No. Engineer/Buyer/Supplier Received Date Approved Received Executed Submittal
MVL-04 Matthew Seymour P: 26-Aug-24 17-Sep-24 30-Sep-24 07-Oct-24 11-Oct-24 12-Oct-24 14-Oct-24 14-Oct-24 18-Oct-24
Manual Valves (Early Lynzy Ford F: 26-Sep-24 30-Sep-24 10-Oct-24 24-Oct-24 25-Oct-24 01-Nov-24 04-Nov-24 05-Nov-24 09-Nov-24
Works) TBD A: 26-Sep-24 30-Sep-24 10-Oct-24 24-Oct-24 25-Oct-24 01-Nov-24 04-Nov-24 05-Nov-24
Ferguson - - 12-14 weeks Steam traps - 6-8 weeks Victaulic - 1-2 weeks CS/SS valves
Sunbelt - - 2-5 weeks
MRC - 4-6 weeks
Bidders Bid Received Award Notes / Comments
1 Ferguson Industrial Oct 10 2024 12:00AM Contact: Megan Daly; John Lancaster - ITB recv'd 10-1-24
2 MRC Global Oct 11 2024 12:00AM Contact: Brenden Lackey; Taylor Hart - iTB recv'd 10-1-24
3 Sunbelt Supply Co. Oct 10 2024 12:00AM Contact: Mike Willeford; Megan Stewart - ITB recv'd 10-1-24
PSC-01 Matthew Seymour P: 31-Mar-25 28-Apr-25 16-May-25 23-May-25 02-Jun-25 09-Jun-25 09-Jun-25 13-Jun-25 19-Jun-25
Pipe Specials Lynzy Ford F: 08-Apr-25 06-May-25 27-May-25 03-Jun-25 10-Jun-25 17-Jun-25 17-Jun-25 18-Jun-25 24-Jun-25
TBD A:
Bidders Bid Received Award Notes / Comments
1 Ferguson Contact: John Lancaster
2 MRC Global Contact: Brenden Lackey
3 Sunbelt Supply Co. Contact:
SFP-01 Matthew Seymour P: 26-Aug-24 17-Sep-24 11-Oct-24 25-Oct-24 01-Nov-24 08-Nov-24 08-Nov-24 11-Nov-24 15-Nov-24
Shop Fabriacted Pipe Melanie Wakeland F: 13-Sep-24 13-Sep-24 13-Sep-24 13-Sep-24 18-Oct-24 24-Oct-24 06-Nov-24 11-Nov-24 14-Nov-24
(Early Works) TBD A: 13-Sep-24 13-Sep-24 13-Sep-24 13-Sep-24 18-Oct-24 24-Oct-24

Bidders Bid Received Award Notes / Comments


1 AZCO Oct 10 2024 12:00AM
SFP-02 Matthew Seymour P: 31-Mar-25 21-Apr-25 09-May-25 23-May-25 02-Jun-25 09-Jun-25 09-Jun-25 10-Jun-25 16-Jun-25
Shop Fab Pipe (Off Melanie Wakeland F: 08-Apr-25 29-Apr-25 19-May-25 03-Jun-25 10-Jun-25 17-Jun-25 17-Jun-25 18-Jun-25 24-Jun-25
Modules) TBD A:
Bidders Bid Received Award Notes / Comments
1 AZCO
2 EPIC Piping
3 Fabricated Pipe Inc. Contact: Tien Nguyen/Dustin Polito
4 Globe Mechanical Pipe Fabrication Contact: Brandon Wood
5 Gulf Coast Fabricators Contact: Chris Caffey
6 TEAM Industries Contact: Gene Nikstad
7 Turner Industries Group Contact: David Templeton
SFP-03 Matthew Seymour P: 16-Dec-24 17-Jan-25 06-Feb-25 13-Feb-25 20-Feb-25 27-Feb-25 27-Feb-25 28-Feb-25 06-Mar-25
Shop Fabricated Pipe Lynzy Ford F: 16-Dec-24 17-Jan-25 06-Feb-25 13-Feb-25 20-Feb-25 27-Feb-25 27-Feb-25 28-Feb-25 06-Mar-25
(HDPE) TBD A:
Bidders Bid Received Award Notes / Comments
1 Ferguson Contact: Chris Lofton or Philip Comraterie
2 Gajeske, Inc. Contact: Mike Pryor
3 ISCO Industries Inc. Contact: Scott Brady

DATE = Current Activity DATE = Within 7 Days DATE = Within 14 Days DATE = Plan Date Exceeded

Page 15 of 16 Tuesday, November 5, 2024


167375 Marcus Hook Ethane Expansion IFB Spec RFP Issued Bid Due Bid Eval PR Issue PR IFP Spec PO Award PO Drawing Delivery
Pkg. No. PO No. Engineer/Buyer/Supplier Received Date Approved Received Executed Submittal
SHG-01 Matthew Seymour P: 24-Jun-25 16-Jul-25 05-Aug-25 12-Aug-25 19-Aug-25 26-Aug-25 26-Aug-25 27-Aug-25 03-Sep-25
Engineered Supports Lynzy Ford F: 24-Jun-25 16-Jul-25 05-Aug-25 12-Aug-25 19-Aug-25 26-Aug-25 26-Aug-25 27-Aug-25 03-Sep-25
TBD A:
17Sep24TM: No category on the AML.
Bidders Bid Received Award Notes / Comments
1 APP Manufacturing
2 ASC Engineered Solutions
3 Piping Technology & Products
SSH-01 Matthew Seymour P: 31-Mar-25 28-Apr-25 16-May-25 23-May-25 02-Jun-25 09-Jun-25 09-Jun-25 13-Jun-25 19-Jun-25
Safety Showers Lynzy Ford F: 08-Apr-25 06-May-25 27-May-25 03-Jun-25 10-Jun-25 17-Jun-25 17-Jun-25 18-Jun-25 23-Jun-25
TBD A:
17Sep24TM: No category on the AML.
Bidders Bid Received Award Notes / Comments
1 DNOW L.P.
2 Ferguson Industrial
3 Sunbelt Supply Co.
SST-01 Matthew Seymour P: 31-Mar-25 28-Apr-25 16-May-25 23-May-25 02-Jun-25 09-Jun-25 09-Jun-25 10-Jun-25 16-Jun-25
Sample Stations Lynzy Ford F: 08-Apr-25 06-May-25 27-May-25 03-Jun-25 10-Jun-25 17-Jun-25 17-Jun-25 18-Jun-25 24-Jun-25
TBD A:
Bidders Bid Received Award Notes / Comments
1 Sentry Equipment Co
2 Swagelok
3 Texas Sampling
STR-01 Matthew Seymour P: 08-Apr-25 06-May-25 27-May-25 03-Jun-25 10-Jun-25 17-Jun-25 17-Jun-25 18-Jun-25 24-Jun-25
Strainers Lynzy Ford F: 08-Apr-25 06-May-25 27-May-25 03-Jun-25 10-Jun-25 17-Jun-25 17-Jun-25 18-Jun-25 24-Jun-25
TBD A:
Bidders Bid Received Award Notes / Comments
1 Ferguson Industrial Contact: Megan Daly
2 MRC Global Contact: Brenden Lackey
3 Sunbelt Supply Co. Contact: Megan Stewart

DATE = Current Activity DATE = Within 7 Days DATE = Within 14 Days DATE = Plan Date Exceeded

Page 16 of 16 Tuesday, November 5, 2024