EEng6021 Lec 02 Planning
EEng6021 Lec 02 Planning
B. Operational planning
1
C. Expansion planning
A reliable power system is due to well done planning
Reliability Planning
Power System Studies, a Time-horizon Perspective
Expansion
1 year – 10 years Power System Planning planning
unitcommitment Operational
planning
Minutes –
Economic dispatch & OPF
weeks
Automatic Generation
Control
Milliseconds
Power System Dynamics
Control
- seconds
system
Power
Power flow
Control
Nanoseconds–
Power System Transients
micro seconds
A. Introduction: Power system planning
Power system planning is part of a more general problem, that of energy
and economic development planning.
Its objective is therefore to determine a minimum cost strategy for long-
range expansion of the generation, transmission and distribution systems
adequate to supply the load forecast within a set of technical, economic and
political constraints.
Traditionally, power system planning had been mainly related to
generation expansion planning. This is due mainly to that the perception of
fact that investment in transmission lines is a relatively small fraction of the
investment in the construction of power systems.
A. Introduction: Power system planning
• 𝑷𝒎𝒊𝒏
𝑮𝒊 ≤ 𝑷𝑮𝒊 ≤ 𝑷𝒎𝒂𝒙
𝑮𝒊
Similarly, the maximum and minimum reactive power generation of a source is limited.
The maximum reactive power is limited because of overheating of rotor and minimum is
limited because of the stability limit of machine.
Hence the reactive power generation cannot be outside the range stated by inequality,
• 𝑸𝒎𝒊𝒏
𝑮𝒊 ≤ 𝑸𝑮𝒊 ≤ 𝑸𝒎𝒂𝒙
𝑮𝒊
Economic Dispatch: Formulation
• Voltage Constraints
• 𝑽𝒎𝒊𝒏
𝑮𝒊 ≤ 𝑽𝑮𝒊 ≤ 𝑽𝒎𝒂𝒙
𝑮𝒊
• 𝜹𝒎𝒊𝒏 ≤ 𝜹 ≤ 𝜹𝒎𝒂𝒙
Economic Dispatch: Formulation
i.e. 𝑮 ≥ 𝑷𝒑 + 𝑷𝒔𝒐
The flow of active and reactive power through the transmission line
should be less than its thermal capability of the circuit and is expressed
as, 𝑪𝒑 ≤ 𝑪𝒑 𝒎𝒂𝒙
• 𝑻𝒎𝒊𝒏
𝒌 ≤ 𝑻𝒌 ≤ 𝑻𝒎𝒂𝒙
𝒌
𝒎𝒊𝒏
• where 𝑻𝒌 is the transformer tap 𝒌, 𝑻𝒌 is the minimum of
transformer tap 𝒌 and 𝑻𝒎𝒂𝒙
𝒌 is the maximum of transformer tap 𝒌.
𝑇 𝑁 𝑇 𝑁
min 𝐹 𝑃𝑖𝑡 , 𝑈𝑖𝑡 , 𝑆𝐶𝑖𝑡 , 𝑆𝐷𝑖𝑡 = 𝐹𝑖 𝑃𝑖𝑡 + 𝑆𝐶𝑖𝑡 1 − 𝑈𝑖𝑡−1 𝑈𝑖𝑡 + 𝑆𝐷𝑖𝑡 1 − 𝑈𝑖𝑡−1 𝑈𝑖𝑡−1
𝑡=1 𝑖=1 𝑡=1 𝑖=1
𝑡 2
where 𝐹𝑖 𝑃𝑖𝑡 = 𝛼 + 𝛽𝑃𝑖𝑡 + 𝛾 𝑃𝑖
Subject to : Minimum down-time:
power balance constraints: 𝑜𝑓𝑓(𝑡−1) 𝑡
𝑁
𝑇𝑖 − 𝑇𝑖,𝑑𝑜𝑤𝑛 𝑈𝑖𝑡 − 𝑈𝑖𝑡−1 ≥ 0.
𝑈𝑖𝑡 𝑃𝑖𝑡 = 𝑃𝑑𝑡 Ramp rate
𝑖=1
𝑢𝑝,𝑚𝑎𝑥
Spinning reserve constraints: 𝑃𝑔 𝑖, 𝑡 − 𝑃𝑔 𝑖, 𝑡 − 1 ≤ 𝑃𝑔𝑖 ;
𝑁
𝑑𝑜𝑤𝑛,𝑚𝑎𝑥
𝑃𝑑𝑡 + 𝑃𝑟𝑡 − 𝑃𝑖,𝑚𝑎𝑥 𝑈𝑖𝑡 ≤ 0 𝑃𝑔 𝑖, 𝑡 − 1 − 𝑃𝑔 𝑖, 𝑡 ≤ 𝑃𝑔𝑖
𝑖=1 Startup cost
Generation limits: 𝑜𝑓𝑓(𝑡−1)
−𝑇𝑖
𝑆𝐶𝑖𝑡 = 𝑋𝑖 + 𝛿𝑖 1 − exp
𝑃𝑖,𝑚𝑖𝑛 𝑈𝑖𝑡 ≤ 𝑃𝑖𝑡 ≤ 𝑃𝑖,𝑚𝑎𝑥 𝑈𝑖𝑡 𝐾𝑖
Minimum up-time: On/offline minimum level constraints
𝑇𝑖
𝑜𝑛(𝑡−1) 𝑡
− 𝑇𝑖,𝑢𝑝 𝑈𝑖𝑡−1 − 𝑈𝑖𝑡 ≥ 0. 𝑃𝑖𝑡 = 𝑃𝑖,𝑚𝑖𝑛 ,
𝑖𝑓 𝑈𝑖𝑡−1 = 0 𝑎𝑛𝑑 𝑈𝑖𝑡 = 1 OR 𝑈𝑖𝑡 = 1 𝑎𝑛𝑑 𝑈𝑖𝑡+1 = 0
B. Operational planning
deviation.
Optimal AC power flow
Optimal AC power flow is an extension of a conventional economic dispatch
that aims at determining the optimal settings of control variables while
respecting various constraints.
General optimal power flow problem Minimize 𝐹 (𝑥, 𝑢)
Subject to
𝑔 (𝑥, 𝑢) = 0
ℎ ( 𝑥, 𝑢) ≤0
𝑔(𝑥, 𝑢) represents nonlinear equality constraints (power flow equations) and ℎ(𝑥,
𝑢) is nonlinear inequality constraints on the vectors 𝑥 and 𝑢.
The vector 𝑥 represents non-control parameter. Those that are nor decision
26
variables.
The vector 𝑢, on the other hand, are variables we are trying to find their optimal
settings. They are also called control variables.
Optimal AC power flow
Minimize
Subject to constraints
29
Optimal power flow – active power loss minimization
where
=
30
Objective is minimization of
𝑚𝑖𝑛𝑖𝑚𝑖𝑧𝑒 𝐶𝑔𝑖
𝑖=1
Subject to constraints
B. Operational planning
IV. Real-time operation:
Electric power system planning is focused on defining and
sizing the necessary facilities to reach all users according
to certain quality standards.
During real-time operation, all the electrical magnitudes
34
36
Structure of power system planning
State planning & energy policy
Energy Planning
Load forecasting
Generation planning
Network planning
Structure of power system planning
Energy plan is a statement of the choices made by decision-makers at any one
point in time in order to meet specific goals and objectives.
Energy
Economic
demand
analysis
analysis Supply/
Impact Review
demand
evaluation evaluation
Energy Energy balance
resource technology
evaluation evaluation
Integrated analysis
Iteration
Data base development
solution.
C. Expansion planning
Models and Methods:
Electric power companies develop mathematical models and
methods for expansion planning of electric power industry as the
following conventional directions, as example;
Transformation of methodological principles;
Generation expansion planning; 43
development strategy
2. Generation expansion planning;
Some authors do not regard the generation expansion planning problem as
pressing and assume that the market mechanisms should give the necessary
economic signals to the investors to invest in the construction of new power
plants.
However, this viewpoint is supported by fewer researchers, since a deeper
analysis and the existing practice show that the market is “shortsighted” and
45
there is a need to foresee the corresponding mechanisms to improve the
investment attractiveness of new power plants and reduce the financial risks
to investors.
2. Generation expansion planning;
society as a whole.
This promising approach needs further analysis and elaboration.
C. Expansion planning
Another approach for network expansion planning:
Load flow-based technique
Market based technique
Adequacy based technique
61
C. Expansion planning
Algorithms to solve expansion planning problems:
Linear programing
Nonlinear programming
Mixed integer linear programming
Bi-level programming model
Interior point method 62
Heuristic algorithms/AI
etc…
C. Expansion planning
63
𝑥 𝑏𝑖𝑛𝑎𝑟𝑦 . (3)
Lower level Con
𝑝 ∈ 𝑎𝑟𝑔𝑚𝑖𝑛 𝑏1 𝑝: 𝐴2 𝑥 + 𝐵2 𝑝 ≤ 𝑏2 , 𝑝 ≥ 0 . (4)
The upper level objective function 𝑓 𝐺𝐸𝑃 (𝑥, 𝑝) is to maximize the profit of
generation companies, which can be estimated as
The first term in the objective function is the estimated revenue from selling
70
power generation at the locational marginal prices. The second term in the
objective function is the O&M cost for existing and new generators, and the third
term is the investment cost for new generators.
All future cost terms are discounted to the current year to calculate the net
present value.
All fixed and variable investment costs are amortized so that investments
towards the end of planning horizon would not be disincentivized, since only
part of the investment cost appropriated for the planning horizon was
calculated to offset the benefit of the investment.
71
The upper level constraints (2) and (3) are defined as follows:
72
Here, constraints (6) and (7) allow the retirement of existing generators and
investment of new generators;
Constraint (8) imposes a renewable portfolio standard type of requirement on
the minimal percentage of generation capacity being renewable;
Constraint (9) imposes a generation adequacy requirement, where the total
generation capacity for each year must exceed 120% of predicted peak
demand; and
73
74
The lower level objective function (11) is to minimize the production cost and
75
(3)
(4)
77
(5)
(6)
(7)
C. Expansion planning
where, the objective function (1) is to minimize the total investment
cost.
The nodal balance equation is shown in (2), where the net power
injection at a bus is equal to the total loads connected to the bus.
As shown in (3) and (4) respectively, the active power flows for
existing lines are determined by the product of the line susceptance bk
78
and the voltage phase angle difference θk, while for prospective lines,
the big-M method needs to be applied to avoid the presence of
nonlinear terms.
C. Expansion planning
If a prospective line is selected, i.e., zk is 1, then (4) is forced to be an equality
constraint as (3), otherwise, zk is 0; the positive number Mk guarantees that (4)
is not binding.
Constraints (5) and (6) limit the active power on existing lines and prospective
lines respectively. If a prospective line is selected, then (6) is the same as (5),
otherwise, the power flow is forced to be zero.
The generator output limit is enforced by (7). 79
Assignment