HCL
HCL
ACKNOWLEDGEMENT
SUMMARY
CONTENTS
5.0 CONCLUSION
6.0 REFERENCE
2)Smelter
Plant Location Metal capacity
(tonnes per annum)
Khetri Copper Rajasthan 31,000
Complex
Indian Copper Jharkand 20,500
Complex
4) Geological Reserves:
On Going Project-:
of capacity 10,000 MT. Ore is withdrawn from this bin with the
help of belt feeders and fed to the ball mills.
Single stage wet grinding is done with the help of four nos. ball
mills each of size 3810x5791 mm, operating in close circuit with
660 mm hydro cyclones. Mills are over flow type and lined with
replaceable rubber liners. CI grinding media of 80 mm dia is
charged inside the mills for grinding of ore.
Before starting the crusher, check the following and make sure
that they are in satisfactory condition.
Check the oil level in the settler ;it should not be below 1.2
Check the tension of V belts; all the belts should be tight.
Check the crushers crushing chamber; there should be no
material in it.
Check the grease lubricating system for its proper functioning.
Start any one of the oil pump and observe the delivery line oil
pressure to be not less than 1.0kg/cm2 and not more than
2.0kg/cm2 .
Wait for 5-10 min, so that oil circulation stabilishes.
Check the drain pipe oil temp. ,it should be below 600 C.
Check the drain pipe oil temp. from counter shaft , it should be
below 600 C.
Check the oil pressure before and after the filter; the difference
should not be more than 0.3kg/cm2 .
If the oil temp. is more than 60-650 C pass the oil through the
heat exchanger and observe that , water inlet pressure is less by
0.3kg/cm2 to the oil outlet pressure.
Start the crusher main drive .
Observe for any knocking or abnormal sound from the crusher
,there should be no such abnormal sound .
Count the number of rotation of the crusher with the ore
FLOW CHART
PRIMARY CRUSHER (870 TPH)
-1200mm GYRATORY CRUSHER
-140 mm
4TH FLOOR
INTERMEDIATE LEVEL
(CRUSHING ZONE)
2ND FLOOR
HOPPER ( GAMMA RAY INDIACTOR )
LUBRICATION SYSTEM
GROUND LEVEL
CONVEYOR SYSTEM
INDIAN SCHOOL OF MINES, DHANBAD
MALANJKHAND COPPER PROJECT, HINDUSTAN COPPER LIMITED
Idlers
Belt
Pulley Arrangement
Pull cord
2.3.1>IDLERS
Pictorial view of carrying Idlers
.2 IDLER SPECIAFICATION
Number of Carrying Idlers-(199-10%)*3=540
Number of Return Idlers-(199/2)=100
Gab b/w two carrying idlers = 1000mm
Gab b/w two Return idlers =2000mm
2.3.2>BELT
Length of belt -398m
Commonly named as primary belt
Width of belt -1400mm
Nylon is used to give strength and flexibility
Thickness of belt is 24mm
Notation –M24
RUBBER PLY
NYLON PLY
RUBBER PLY
2.3.3>PULLEY ARRANGEMENT
Total no. of pulley in primary conveyor-12
(2 )HEAD PULLLEY
7
HEAD BEND PULLEY (9)
5 8
TAIL BEND
PULLEY (11)
6
TAIL SCUP
PULLEY (12)
8
TAKE UP PULLEY
SYSTEMATIC PULLEY ARRANGEMENT OF (10)
PRIMARY CONVEYOR
MOTOR
There are basically two motor attached to pulley No. 6
and 8
M1- PULLEY 6 M2-PULLEY 8
150 hp 150 hp
1485 rpm 1485rpm
188A 186A
V-415V V-415V
Frequency- 50 Hz Frequency- 50 Hz
GEAR BOX
ELECON Mgf.
SERIAL NO-WHG33992LH
TYPE-SCN-355
SPEEED RATIO- 45:1
FLUID COUPLING
Used to reduce Energy
To safe motor during the condition of high load
Act as best energy saver
SPECIFICATION-:
Before starting the Apron Feeder, check the following and make
sure that they are in satisfactory condition.
Check all the bolts and nuts of all units and see that they are all
tight.
Lubricate where it is necessary.
Check for the pressure of any big boulder being jammed in the
hopper or on the apron feeder, Remove it .
Tighten screw take on just enough to ensure a smooth
transition of pan line on the first return roller .
Check bearings temperature , it should be within 35-550 C, After
making sure about the above points, see that the conveyor to
which the apron feeder is feeding is running .
Now, start the apron chain drive ,and feed.
TRACK ROLLER
MOTION
TRACK CHAIN
TAILING PRODUCT
TRETURN ROLLER
RECEIEVING CHUTE
ELECTROMAGNET
FEED
Secondary crusher
Secondary crusher
BELT 5
Before starting the crusher, check the following and make sure
that they are in satisfactory condition
Check the oil level in settler Tank- it should be more than 2/3 cm.
above the suction pipe.
Start the oil pump.
Check the oil filter inlet and outlet pressure. The difference
between the two should be u8nder 0.3Kg/cm2. If it is more than
that, rotate the filter. If there is no improvement then the filter
has to be cleaned.
Check the temp. of oil inside the tank. It should be below 50 0C.
If it is more than that, the heat exchanger to be taken into circuit.
Heat exchanger water pressure to be left preferably below the oil
pressure to avoid mixing of water into oil through any leakages.
Oil pressure should be 0.4 to 2 Kg/cm2.
Temp. of oil leaving the crusher should be below 60 0C.
Check the coupling pad & bolts.
Start crusher motor.
Check the crushing head RPM it should be below 10.
Check if there is any abnormal sound or vibration.
Open hydraulic seal water until the clear water comes out from
the outlet. Quantity of Hydraulic seal water should be within 36 to
45 Lit/Min.
Start feeding.
TERTIARY CONE
-40mm -12mm
CRUSHER
Before starting the crusher, check the following and make sure
that they are in satisfactory condition
Temp difference in between the oil entering the crusher & leaving
the crusher should in between 1 &3 0F. if the temp difference is
more than 5 0F crusher should be check for any fault.
Check the V-belt tension of the crusher.
Start the crusher motor.
Check the RPM of crushing head & motor current.
Check if there is any abnormal sound or vibrations.
Open the Hydraulic seal water & wait till the clear water comes
out from the out-let.
Start feeding.
BELT 1
Used to carry feed from COS to secondary crusher
SECONDARY
CRUSHER
BELT 2
Used to carry Crushed product from secondary
and tertiary crusher to conveyor belt 3
BELT 3
BELT 3
Used in transferring belt 2 product to belt 4
BELT 4
Carry (-40mm) feed from belt 3 to surge bin S1,S2,S3
S1 S2 S3
BELT 5
Carry the -12mm product from screening to FOB
(fine ore bin)
Before the starting the ball mill check the following and make sure
that they are in satisfactory condition
Check the oil level of the main bearings, Check the oil wipers, light
contact with the bearing.
Check the temp. & grease of pinion & drive shaft pillow blocks. It
should not be very hot.
Check the oil spray system to the girth gear. Be sure that it
operate properly and check that there is lubricant in the
container. Air pressure require for spray is 6 Kg/cm2.
Open the water cooling valves and adjust it to satisfactory flow
rate (20 Gal. / Min.)
Start the reducer box oil pump and make sure that oil is
circulating.
Start the Hydraulic lift, at the trunnion bearings, observe the
pressure gauge. The pressure increases and then drops a little.
Inform the ground-ore pump area operator and start the main-
drive of the mill.
Observe that the mill starts smoothly.
Check the oil distribution in the trunnion bearing.
Start feeding the fine ore and water. Adjust these two to required
values.
Flotation cells are used to separate out the copper sulphide particles
as a forth containing these minerals, leaving the pulp depleted of it.
There are several stages of flotation operation
DETAILS
Cell Type & Size - 300 CFT double-overflow flotation cells.
No. of cells - 4 rows of 12 cells each, the first 7 are
rougher
& second 5 are scavenger
Drive Motor - 30 HP, 1000 RPM
V-belt used - C – 168 fenner.
Forth paddle drive - ¾ H.P. 28 RPM
Addition of Xanthate in Mill feed to increase conditioning time.
Diversion of Concentrate of first Scavenger Cell as Rougher
Concentrate to avoid recirculation.
Removal of old and inefficient recleaner cell (Fagergren cell) of
60 ft3 by efficient and bigger 300 ft 3 cell (Denver D-R cell).
Diversion of highly floatable minerals (high kinetic minerals)
from the first rougher cell concentrate directly to the thickener.
This procedure is adhered when the head grade that is being
treated is more than 1.0%Cu.
DETAILS
No. of cells - 4 rows contain 1 cleaning cell each, and 1
for Recliner
Drive motor - 15 KW 1470 RPM
V-belt used - B-120
4.0 CONCLUSION
Malanjkhand copper project is a growing
project which is to be expanded in few year . The copper grade is
still not good ,it is about 0 .95% which is very costly ,but recently
many changes has to done in MCP such as changing of filter
,earlier it was Disc filter but changed to ceramic vaccum fliter
(China filter).One other hand thickner is also going to be
changed to High rate thickner ,by doing such changes time
reduce .Their is work going on in planning of underground mine
in MCP hence the project will be expanded to large extent.
We are very thankful to Research and Development department
of MCP as they guided us pretty well.
Earlier we were having theoritical knowledge of crushers and
other equipments used in metal processing but now undergoing
training in prestigious company help us enhancing our concepts
theoretically as well as practically .To a student this plant is a
good place to gain expirence in industry .
5.0 REFERENCE
Research and development department of MCP.
Ajay Giri (CM,Conc.)
Kunal ku. Rajak, Sumit Sinha, Ranvijay Singh .
Shubharaj ( Ju.Manager)
Figure 3: Illustration of the flow chart used in the Web application to generate the global estimation error
(GEE).
12
Shape factor-:Shape factor is the ratio of the volume of the sampled particles
having the characteristic dimension d to the volume of the cube having the
same dimension
13
Here
aL= av. Concentration of lot
= concentration of the analyte in the critical particle
14
(FSE Eq.)
V= the sampling variance
15
SFSE2= fgcld3/MS
= 0.5*0.25*c*(dl/d)0.5d3/MS
=0.5*0.25*c*dl0.5d2.5/MS
=0.5*0.25*19.3/10-0.6*(10-3)0.5*(1.27)2.5/MS
Which is not possible ,the gold is very fine and it is well known by experiment
that sample of few k are all it takes to get an acceptable reproducibility.
SFSE2=fgcld3/MS
l=(dl/d)0.5, l= SFSE2*MS/fgcd3
dl= 3.9 *10-9= 0.39 A0, which is absurd result.
Hence from experimental evidence ,it is proved that Gy’s formula is inaccurate
18
7.0 CONCLUSION
From the report it is cleared that Gy’s sampling theory still not
adopted as accurate one .As we saw that the formula given by Gy’s
totally consists of assumption and factor used did not give better
result and also from the experimental data shown ,it is cleared that
the formula for calculating fundamental sampling error is inaccurate
.Number of process control, product uality control for consumer
safety and environmental control are being carried out with the
help of sampling theory developed by Pierre Gy. Examining and
designing sampling procedures normally decreases the probability
of error in sampling, sampling equipment should be correct,
sampling procedures should be examined by trained person in
regular interval .Hence at last it is concluded that sampling is
19
8.0 REFERENCE:
6)The most common error in applying ‘Gy’s Formula’ in the theory of mineral
sampling, and the history of the liberation factor
by D. François-Bongarçon* and P. Gy†
20