Thesis Winnie
Thesis Winnie
BY WINNIE MUTENHABUNDO
In
SUPERVISOR: MR CHIRINDA
EXTERNAL EXAMINER:…………………………….
JUNE 2012
Process optimization using Design for Environment concept in the input material of the
disperser unit
DECLARATION
In presenting this reporting in partial fulfilment of the requirements for the degree of
Master of Science at the University of Zimbabwe, I do hereby declare that this research
project is my original work except where sources have been acknowledged. I agree that
permission for extensive copying of this report for scholarly purposes be granted by the
head of my department or by his/her representatives. It is understood that copying or
publication of this report for financial gain shall not be allowed.
University Of Zimbabwe
Mount Pleasant
Harare
Zimbabwe
Signature:………………………
i
Process optimization using Design for Environment concept in the input material of the
disperser unit
ACKNOWLEDGEMENTS
I wish to express my heartfelt gratitude to Astra Paints management for granting the
permission to carry out my research work at their company and its staff who worked
beyond their job descriptions in making the project a success.
It would have been impossible for me to successfully complete this research work
without the guidance of my supervisors, Mr Chirinda and Mr Chikuku. Thank you very
much for the light, I am so grateful.
To Mr Mugwindiri, your guidance and patience is not found in many, I appreciate that
and may you continue with the good spirit.
I would also like to extend my gratitude to the Harare Institute of Technology staff for
their unwavering support during the studies, thank you guys.
To Irene Kamutero, thank you for opening the avenues, God bless.
I am most indebted to my husband, Rodgers, for the support throughout the study, i know
it wasn’t easy neither was it a nice experience for you.
ii
Process optimization using Design for Environment concept in the input material of the
disperser unit
ABSTRACT
This project is aimed applying the Design for Environment concept for the optimization
of the input material operation of the PVA paint disperser. Initially, waste streams were
identified; the levels of powder raw material dust emissions were assessed as well as their
impacts to the plant operator. The researcher set their objectives seeking to reduce these
negative effects.
DFE tools were applied thus a Cleaner Production Assessment was done to identify,
quantify and find options to minimize wastes. Dust emission levels were determined
using the air sampling pump technique. ISO 14 001 was used as a tool to improve
environmental performance. Life Cycle Assessment was done to assess the
environmental aspects and potential impacts associated with the feeding process.
Emphasis was made on the reduction and recovering options to reduce environmental
impact.
The assessments of Cleaner Production and Life Cycle carried out resulted in the
identification of a DFE product that reduces dust emissions. Implementation of ISO 14
001 at Astra Paints improves environmental performance thus consequently reducing
risks and related potential health effects. A DFE product was synthesized and
recommended for further development.
The researcher therefore recommends DFE technology for process optimization not only
at the company under study but other manufacturing entities.
iii
Process optimization using Design for Environment concept in the input material of the
disperser unit
TABLE OF CONTENTS
DECLARATION.............................................................................................................. I
ACKNOWLEDGEMENTS.............................................................................................II
ABSTRACT....................................................................................................................III
TABLE OF CONTENTS................................................................................................IV
LIST OF FIGURES........................................................................................................ IX
CHAPTER ONE:...............................................................................................................1
INTRODUCTION..............................................................................................................1
1.0 INTRODUCTION.................................................................................................1
1.1 PROBLEM STATEMENT......................................................................................1
1.2 BACKGROUND....................................................................................................2
1.2.1 Paint manufacturing process.............................................................................2
1.2.2 PVA paint plant.................................................................................................4
1.2.3 Health impacts of powder raw materials..........................................................7
1.3 DESIGN FOR THE ENVIRONMENT...................................................................8
1.4 PROBLEM DEFINITION...................................................................................12
1.4.1 Project Aim and Objectives.............................................................................12
1.4.2 Project Justification.........................................................................................12
1.5 PROPOSITION...................................................................................................13
1.6 PROJECT SCOPE...............................................................................................13
1.7 CORE QUESTIONS............................................................................................13
1.8 METHODOLOGY...............................................................................................13
1.9 PROJECT PLANNING........................................................................................14
1.10 PROJECT BUDGET...........................................................................................15
1.11 PROJECT COMMUNICATION..........................................................................15
1.12 PROJECT CONTROL.........................................................................................16
1.13 CONCLUSION....................................................................................................16
CHAPTER TWO:............................................................................................................17
LITERATURE REVIEW...............................................................................................17
2.0 INTRODUCTION................................................................................................17
2.1 PAINT MANUFACTURING...............................................................................17
2.1.1 Production processes.......................................................................................17
iv
Process optimization using Design for Environment concept in the input material of the
disperser unit
v
Process optimization using Design for Environment concept in the input material of the
disperser unit
CLEANER PRODUCTION............................................................................................85
4.0 INTRODUCTION................................................................................................85
4.1 PVA PLANT.........................................................................................................85
4.2 CLEANER PRODUCTION ASSESSMENT.........................................................85
4.2.1 Management commitment................................................................................85
4.2.2 Project Team....................................................................................................86
4.2.3 Working Environment and Environmental Issues of the plant........................87
4.2.4 Raw Material Audit.........................................................................................88
4.2.5 Establishing a focus.........................................................................................91
4.2.6 Material balance..............................................................................................91
4.2.7 Pollution Audit of the plant.............................................................................92
4.2.8 Identification for Cleaner Production Opportunities......................................96
4.2.9 Cleaner Production Opportunities..................................................................97
4.2.10 Options of Cleaner Production Opportunities.............................................99
4.2.11 Feasibility Analysis....................................................................................100
4.3 CONCLUSION..................................................................................................101
CHAPTER FIVE:..........................................................................................................102
ENVIRONMENTAL MANAGEMENT SYSTEM....................................................102
5.0 INTRODUCTION..............................................................................................102
5.1 IMPLEMENTING ISO14001............................................................................102
5.1.1 Introduction to Astra Paints..........................................................................105
5.1.2 Environmental management system..............................................................105
5.1.3 Environmental policy.....................................................................................105
5.1.4 Planning.........................................................................................................106
5.1.5 Implementation and operation......................................................................107
5.1.6 Checking and corrective action.....................................................................111
5.1.7 Management review.......................................................................................112
5.2 CONCLUSION..................................................................................................113
CHAPTER SIX:.............................................................................................................114
LIFE CYCLE ANALYSIS............................................................................................114
6.0 INTRODUCTION..............................................................................................114
6.1 METHODOLOGY FOR LCA............................................................................114
vi
Process optimization using Design for Environment concept in the input material of the
disperser unit
vii
Process optimization using Design for Environment concept in the input material of the
disperser unit
LIST OF TABLES
Table Page
Table1.1: Project schedule………………………………………………………………. 12
Table 1.2: Project budget................................................................................................... 13
Table 1.4: Project control document................................................................................. 14
Table 2.1: Paint Manufacturing Process Wastes............................................................... 20
Table 2.2: Waste minimization options............................................................................. 24
Table 2: ISO 14000 series................................................................................................. 59
Table 4.1: Project team…………………………………………………………………. 83
Table 4.2: Process inputs and outputs............................................................................. 84
Table 4.4: Concentration of Dust in Various Sections..................................................... 89
Table 4.3: Limit Values of Dust Exposure (TWA/8hrs)............................... 89
Table 4.5: Comparison of area dust concentration with personal dose concentration.......... 91
Table 4.4: Cleaner Production Opportunities....................................................................... 94
Table 4.5: Cleaner Production Opportunities Analysis........................................................ 95
Table 4.6: Rating of Cleaner Production Options............................................................... 97
Table 6.1: Raw material usage............................................................................................ 115
Table 7.1: Decision matrix………………………………………………………………. 124
viii
Process optimization using Design for Environment concept in the input material of the
disperser unit
LIST OF FIGURES
Figure Page
Fig1.1: Smaller Scale Production PVA Plant Layout.................................................... 4
Fig1.2: DFE Implementation Commitment Progression................................................ 9
Fig 1.3: Gantt Chart………………………………………………………………………. 13
Fig 2.1: Paint Manufacturing Process……………………………………………………. 18
Fig 2.2: DFE and Sustainable Development...................................................................... 27
Fig 2.3: Steps to Implement DFE...................................................................................... 34
Fig 2.4: Steps and Tasks in the CPA Process.............................................................. 43
Fig 3.1: The Cleaner Production Assessment Methodology……………………………. 75
Fig 3.2: Plan-Do-Check-Act Cycle of the Management System………………………… 76
Fig 3.3: Steps for Life Cycle Assessment………………………………………………… 77
Fig 4.1: Organogram............................................................................................................. 82
Fig 4.2 Material Cost and Usage......................................................................................... 84
Fig 4.3: Paint Manufacturing Process.................................................................................. 85
Fig 4.4: Paint Manufacturing With Raw Material Input, Output and Waste.................... 86
Fig 4.5 Dust Concentration................................................................................................. 87
Fig 4.6: Material Balance................................................................................................... 88
Fig 4.7: Observed Dust Concentration............................................................................... 90
Fig 4.8: Area Dust Concentration versus Personal Dose Concentration.......................... 91
Fig 4.9: Ishikawa Diagram for Dust Creation...................................................................... 92
Fig 5.1: Management Structure............................................................................................ 103
Fig 6.1: Life Cycle of Feeding Process................................................................................ 111
Fig 6.2: Dust Concentration.................................................................................................. 114
ix
Process optimization using Design for Environment concept in the input material of the
disperser unit
Fig 6.3: Material Consumption for SUP1, DUP1 and ACW............................................... 115
Fig 6.4: Air Emissions of the Feeding Operation Life Cycle - Comparison of Scenarios.... 116
Fig 7.1: Pneumatic Vibro-Feeder.......................................................................................... 119
Fig 7.2: Vertcal Screw Conveyor.......................................................................................... 121
Fig 7.3: Pin Feeder................................................................................................................ 123
x
Process optimization using Design for Environment concept in the input material of the
disperser unit
CHAPTER ONE:
INTRODUCTION
1.0 INTRODUCTION
Astra Paints commenced business in Harare as Herbert Evans paint in 1947. Through the
years, it merged with other paint companies like Titanium Paints to eventually become
Plascon Paints, whose majority stake was then acquired by the government of Zimbabwe
through the Reserve Bank of Zimbabwe in 1983. The paint concern was then renamed
Astra Paints in line with the larger group, Astra Corporation. Astra Paints (PVT) Ltd
operates under a diverse portfolio of business managed by Astra Holdings Limited.
Today Astra Paints, through its Bulawayo and Harare plants, is the country’s largest
comprehensive manufacturer of domestic, industrial, automotive and wood coatings.
Astra Paints Harare is a manufacturer of polyvinyl acetate (PVA) paint, enamel paint and
tints. The total daily production volume for the Harare factory ranges from 4000 to
13000litres.
1
Process optimization using Design for Environment concept in the input material of the
disperser unit
1.2 BACKGROUND
b. Premix
In general two mixes are made for each product, (the mill base and the let down
vehicle).The mill base is a premix of the pigment with resin, solvents, and additives to
form a paste. Premixing is done using high speed dispersion mills which are commonly
referred to as the diafs.
c. Pigment Dispersion
This is a physical process where particles of the pigment are ground and dispersed
throughout the mixture. The functions of dispersion are disruption, wetting, mixing and
stabilisation of the pigments. If the paint is to be for industrial use, it usually is then
routed into a sand mill, a large cylinder that agitates tiny particles of sand or silica to
grind the pigment particles, making them smaller and dispersing them.
d. Dispersion tests
Experience will tell the operator approximate time required for dispersion to be
completed. A sample of the batch is taken to the laboratory to test the degree of
dispersion. The most commonly used test of dispersion is the grind gauge. If the
2
Process optimization using Design for Environment concept in the input material of the
disperser unit
dispersion fails the test the process goes back to disperse a bit longer. If it passes the
process moves on to the next stage for colour tests.
e. Colour tests
3
Process optimization using Design for Environment concept in the input material of the
disperser unit
However before colour testing is done there is need to let a sample of mill base down,
(dilute/thin it) with some let down vehicle. This is done because the let-down process
may affect the particle size if it is not properly done, and this will in turn change the
optical properties of the paint. Colour testing is done mainly by visual comparison of the
test sample and a standard specimen held by the Quality control department. The use of
computers in colour testing (colour eye) has also being taken up widely in the paint
manufacturing. If the batch fails the test there might be need to make more additions of
pigment and the process goes back to dispersion to correct the defect.
f. Let-down
If the batch passes colour tests, let-down of the whole batch then follows. It is important
to first have the batch pass colour tests before letting down because it is not usually
possible to re-disperse the batch since the viscosity will be too low.
g. Specification tests
The complete pain now goes through specification tests set by the customer’s
specification for example coming up with a special tint to suit the customer’s special
colour requirements. If these tests fail there has to be a decision to whether the batch can
be reworked into something saleable, this can mean going back to work on the
reformulation. A highly costly scenario may happen if the batch can not be reworked into
any other product, this will mean the batch will have to be disposed.
h. Filling
If all tests have been passed the final product goes to filling where it is packaged in
respective appropriate containers and finally sends to the dispatch warehouse or direct to
the customer.
4
Process optimization using Design for Environment concept in the input material of the
disperser unit
This plant for water-based paints has two sections. The first section is for large volume
production and it is on ground floor. It consists of a huge master mix tank, two let down
tanks and water pipes. The other section is on the first floor where smaller quantities of
water-based paints are produced. This plant consists of two dispersers, a dust extractor,
an elevator and water pipes. The layout of the plant is shown in Fig 1.2 that follows.
valve
valve
Finishing tanks
Gate valve
To filling bay
filter pump
5
Process optimization using Design for Environment concept in the input material of the
disperser unit
Inorganic pigments include earth, ochres, clay, clay, titanium dioxide, strontium
chromate and mineral compounds. The medium is the liquid or solid material in which
the pigment is dispersed and suspended to produce the complete formulation of the
coating and for the PVA paints, water is used as a medium. Additives are a wide variety
of ingredients added in small amounts for a variety of purposes. Types of additives
include polymerisation modifiers, viscosity modifiers and surface tension modifiers. The
major powdered raw materials used in the plant include Amorphous Silica, Titanium
oxide, dolomite, chromium oxide and kaolin.
Production operations
PVA paint is manufactured at both large and small scale and the operations involved are
as follows;
Large scale production
For large scale production, a forklift carries one tonne palletized raw materials from
the storeroom, elevate them to a 4metre height and then deposit them at a floor
surrounding the master mix tank rim. There are four operators who work in this
section. Two people will take a bag (40 or 25kg in weight depending on the material
being fed) and had it over to other two people who will open them up and pour into
the mixer. The empty bags are piled on the empty pallet and then taken by a forklift to
the waste bin.
6
Process optimization using Design for Environment concept in the input material of the
disperser unit
As the operators load powders into mixing vessels, a lot of dust is emitted and some
spillages occur as well. The powders that fly out as dust and the spills result in pollution
and wastes. The exposure to powders through breathing or body contact is a health
hazard to the operator and the environment.
Some of the pigments may influence the body on a more subtle level to produce cancer
and these are called carcinogens. Toxin is another class of hazardous pigments which the
body does not excrete and can build up to a dangerous dose; e.g. lead. Other pigments are
not toxic but are nevertheless harmful as they may have an irritating action which the
body responds to much more slowly than to a really toxic material.
i. Silica
It is very adsorbent and may have a drying effect on skin and eyes. When the
occupational exposure limit is exceeded, a mechanical burdening of the system is
possible.
7
Process optimization using Design for Environment concept in the input material of the
disperser unit
Acute hazards or symptoms include cough when inhaled and when there is skin
contact, and then skin becomes reddish. Repeated or prolonged contact with skin
may cause dermatitis. Lungs may be affected by repeated or prolonged exposure,
resulting in fibrosis, chronic bronchitis, and pneumoconiosis.
Design for the Environment Program (DfE) is a United States Environmental Protection
Agency (USEPA) program, created in 1992, that works to prevent pollution, and the risk
pollution presents to humans and the environment.
There are three main concepts that fall under the Design for Environment umbrella.
I. Design for environmental packaging: This ensures that the materials used in
packaging are environmentally friendly, which can be achieved through the reuse
of shipping products, elimination of unnecessary paper and packaging products,
efficient use of materials and space, use of recycled and/or recyclable materials.
8
Process optimization using Design for Environment concept in the input material of the
disperser unit
II. Design for disposal or reuse: The end-of-life of a product is very important,
because some products emit dangerous chemicals into the air, ground and water
after they are disposed of in a landfill. Planning for the reuse or refurbishing of a
product will change the types of materials that would be used, how they could
later be disassembled and reused, and the environmental impacts such materials
have.
III. Design for environmental processing and manufacturing: This ensures that
raw material extraction (mining, drilling, etc.), processing (processing reusable
materials, metal melting, etc.) and manufacturing are done using materials and
processes which are not dangerous to the environment or the employees working
on said processes. This includes the minimization of waste and hazardous by-
products, air pollution, energy expenditure and other factors.
DfE employs a variety of design approaches that attempt to reduce the overall human
health and environmental impact of a product, process or service, where impacts are
considered across its life cycle. The common design approaches are;
Barriers:
- Technological (alternative is not technically feasible)
- Ergonomic, Safety (alternative may be a misfit or unsafe)
- Societal (people may not be prepared for the alternative)
9
Process optimization using Design for Environment concept in the input material of the
disperser unit
Many times the only way to approach the redesign (ex. paper, steel)
Rethink what enters the manufacturing (entry materials)
Barriers:
- Technological (alternative is not technically feasible)
- Ergonomic, Safety (alternative may be a misfit or unsafe)
Of these options the order of difficulty and commitment on the part of the company to
implement is illustrated in Fig 1.4 that follows.
10
Process optimization using Design for Environment concept in the input material of the
disperser unit
Since DfE works to prevent pollution, and the risk pollution presents to humans and the
environment, its adoption in the PVA plant will help reduce pollution in the form of
emissions and spills thereby reducing health risks to the operators. Different software
tools have been developed to assist designers in finding optimized products (or
processes/services) thus there will be an increase in plant productivity which results in
gain in competitive advantage.
11
Process optimization using Design for Environment concept in the input material of the
disperser unit
12
Process optimization using Design for Environment concept in the input material of the
disperser unit
1.5 PROPOSITION
The application of DFE technology to the PVA plant will;
reduce the quantities of dust emissions and spills
reduce exposure to hazardous materials and associated risks
improve productivity
The working environment will be cleaner and safe thereby reducing health hazards.
1.8 METHODOLOGY
Both quantitative and qualitative methods will be used. These will include;
13
Process optimization using Design for Environment concept in the input material of the
disperser unit
Data gathering tools such as interviews, questionnaires and field study through
participant observation and experiments
Design for the Environment approach
Cleaner Production Assessment methodology
ISO 14001
Life Cycle Assessment
Design for Experiments
14
Process optimization using Design for Environment concept in the input material of the
disperser unit
15
Process optimization using Design for Environment concept in the input material of the
disperser unit
1.13 CONCLUSION
The Design for Environment technology will be applied to prevent pollution from dust
emissions and spillages in the plant. With the DFE approach, some tools will be used to
identify, quantify and find options to minimize wastes and improve environmental
performance. The identified option for DFE product will be developed with the aid of
finite element analysis softwares so as to come up with optimized products or processes.
The PVA plant will be cleaner and safe thereby reducing potential health hazards.
16
Process optimization using Design for Environment concept in the input material of the
disperser unit
CHAPTER TWO:
LITERATURE REVIEW
2.0 INTRODUCTION
This chapter is on literature of paint manufacturing, the wastes that are generated, the
impacts of these and how they can be eradicated. Further to this technologies to reduce
pollution due to these wastes were explored.
17
Process optimization using Design for Environment concept in the input material of the
disperser unit
Some of the equipment used to accomplish these manufacturing steps include roller mills;
ball and pebble mills; attritors; sand, bead, and shot mills; horizontal media mills; and
high-speed disk dispersers, (U.S. EPA, 1992).
Raw Materials
Paint is composed of pigments, solvents, resins, and various additives. The pigments give
the paint colour; solvents make it easier to apply; resins help it dry; and additives serve as
everything from fillers to anti-fungicidal agents.
Pigments
Pigment is the most obvious part of the paint and is normally a solid material
composed of very fine particles which are insoluble in the vehicle (or binder). Its
presence affects the flow, gloss and durability of the paint and other properties such
as corrosion resistance, fire resistance, antifouling etc. It must remain suspended in
the paint and not settle to form hard sediment (www.apmf.asn.au/index.php).
Hundreds of different pigments, both natural and synthetic, exist. The basic white
pigment is titanium dioxide, selected for its excellent concealing properties, but also
used are zinc oxide, lithopone (a mixture of zinc sulphide and barium sulphate) and
antimony oxide. The black pigment is commonly made from carbon black. Other
pigments used to make paint include iron oxide and cadmium sulphide for reds,
metallic salts for yellows and oranges, and iron blue and chrome yellows for blues
and greens.
Solvents
The solvent or diluent is the material with which the binder and pigment are mixed in
order that the paint may be of the correct consistency when applied to the surface by
brush, roller, spray, dipping and other methods. Solvents are various low viscosities,
volatile liquids. They include petroleum mineral spirits and aromatic solvents such as
18
Process optimization using Design for Environment concept in the input material of the
disperser unit
benzol, alcohols, esters, ketones, and acetone. Water is the main diluent for water-
borne paints, even the co-solvent types.
Resins
These are binders, solid or liquid material, commonly referred to as vehicles that are
used to bind together the pigment particles to form a tough, continuous and adherent
film, (SAPMA 2010). The natural resins most commonly used are lint-seed, coconut,
and soybean oil, while alkyds, acrylics, epoxies, and polyurethanes number among
the most popular synthetic resins.
Additives
Additives are materials which are added to the paint, usually in small quantities to
serve many purposes. Some additives are polymerization modifiers which act as
initiators, catalysts, accelerators and stabilizers, others are viscosity modifiers which
are thickeners or fine particle extenders, whilst there are surface tension modifiers
which can reduce gloss, promote flow, wetting agents, and dispersion stabilizers.
Some, like calcium carbonate and aluminium silicate, are simply fillers that give the
paint body and substance without changing its properties. Other additives produce
certain desired characteristics help it dry more quickly or flow out evenly to remove
brush marks and to stop skinning in the can. One example is silicone; this makes the
surface of the paint film more resistant to marking and scratching.
Production process
A block flow diagram of the steps involved in manufacturing paint is presented in Fig 2.1
that follows.
19
Process optimization using Design for Environment concept in the input material of the
disperser unit
Products
At a typical plant in the paint production industry, there are two main products: solvent-
based paint and water-based paint, (U.S EPA, 1990).
20
Process optimization using Design for Environment concept in the input material of the
disperser unit
a. Solvent-based paint
The production of solvent-based paint (or enamel) begins by mixing some of these:
resins, dry pigment, and pigment extenders, in a high speed mixer. During this operation,
solvents and plasticizers are also added. Following the mixing operation, the batch
frequently is transferred to a mill for additional grinding and mixing. The type of mill is
dependent on the types of pigments being handled, so that no one style is universal. Next,
the paint base or concentrate is transferred to an agitated tank where tints and thinner
(usually a volatile naphtha or blend of solvents) and the balance of the resin are added.
Upon reaching the proper consistency, the paint is filtered to remove any non-dispersed
pigment and transferred to a loading hopper. From the hopper, the paint is poured into
cans, labeled, packed, and moved to storage.
b. Water-based paint
The water-based paint (the polyvinyl acetate paint, PVA) production process is very
similar to that of solvent-based paint. The major difference is the substitution of water for
solvent and the sequencing of material additions. Preparation of water-based paint begins
by mixing together water, ammonia, and a dispersant in a mixer. To this mixture, dry
pigment and pigment extenders are added. After mixing, the material is ground in a mill
and then transferred to an agitated mix tank. Four additions of materials occur in this
tank. First, resin and plasticizers are added to the mixture; second, a preservative and an
antifoaming agent are added; third, a polyvinyl acetate emulsion is added; and fourth,
water is added as a thinner. Following this mixing operation, the handling of the paint is
similar to that for solvent-based paints. At many facilities the grinding and the mixing
and grinding operation may be bypassed with all the dispersion operations occurring in a
single high-speed mixer.
21
Process optimization using Design for Environment concept in the input material of the
disperser unit
22
Process optimization using Design for Environment concept in the input material of the
disperser unit
Silica
This is a synthetic, odourless white powder which is non-toxic. It is an amorphous silica
substance with special treatment and is chemically and biologically inert. Though it is
non-toxic, the product is very adsorbent and may have a drying effect on skin and eyes.
When the Occupational exposure limit is exceeded, a mechanical burdening of the system
is possible, (EC Safety Data Sheet, 1993)
Titanium Dioxide
Titanium dioxide is a white, opaque and naturally- occurring mineral found in two main
forms: rutile and anatase. When used as a pigment, it is called titanium white or Pigment
White 6. Titanium dioxide is regarded as an inert, non-toxic substance by many
regulatory bodies such as the MSDS (Material Safety Data Sheets) and others charged
with the responsibility of safeguarding the health of occupational workers and public
health. The ACGIH states that titanium dioxide is "not classifiable as a human
carcinogen". Titanium dioxide dust, when inhaled, has been classified by the
International Agency for Research on Cancer (IARC) as an IARC Group 2B carcinogen;
possibly carcinogenic to humans. The findings of the IARC are based on the discovery
that high concentrations of pigment-grade (powdered) and ultrafine titanium dioxide dust
caused respiratory tract cancer in rats exposed by inhalation and intracheal instillation.
MSDS states that titanium dioxide can cause some lung fibrosis at fifty times the
nuisance dust, defined by the US Department of Labour as 15 mg/m cubed (OSHA) or 10
mg/m cubed (ACGIH Threshold Limit Value).
23
Process optimization using Design for Environment concept in the input material of the
disperser unit
Chromium Oxide
Chromium Oxide, Cr2O3, is a brown-black powder in appearance. According to National
Institute of Occupational Health and Safety, NIOSH, acute hazards or symptoms include
cough when inhaled and when there is skin contact, and then skin becomes reddish.
Repeated or prolonged contact with skin may cause dermatitis. Lungs may be affected by
repeated or prolonged exposure, resulting in fibrosis. From the MSDS, Potential Acute
Health Effects include hazardous in case of skin contact (irritant), of eye contact
(irritant), of ingestion, of inhalation. Potential chronic health effects involve its
hazardousness in case of inhalation and slightly hazardous in case of skin contact
(sensitizer). For the carcinogenic effects it is coded A4 (Not classifiable for human) by
American Conference of Governmental Industrial Hygienists, (ACGIH), and coded 3
(Not classifiable for human.) by international Agency for Research on Cancer, (IARC).
Mutagenic effects include mutagenic for mammalian somatic cells and mutagenic for
bacteria and/or yeast. The substance may be toxic to upper respiratory tract, skin.
Repeated or prolonged exposure to the substance can produce target organs damage. As
noted by ACGIH, in their publication, "Documentation of Threshold Limit Values"
repeated and prolonged exposures may cause delayed effects involving the respiratory
system such as chronic bronchitis, pneumoconiosis.
Georgia Kaolin
Kaolin is a hydrated aluminium silicate and the name Georgia Kaolin indicates that it is
kaolin from Georgia. Kaolin has traditionally been used internally to control diarrhoea.
Kaolin has also been used topically as an emollient and drying agent. Specifically, it has
been used to dry oozing and weeping poison ivy, poison oak, and poison sumac rashes.
For the side effects of kaolin, inhalation of kaolin through occupational exposure may
24
Process optimization using Design for Environment concept in the input material of the
disperser unit
cause pneumoconiosis whilst for its toxicities inhalation may predispose miners to
pulmonary diseases.
Mica 300
Mica is a colorless, odorless solid that easily flakes into powder. It is typically used in
industrial settings as electrical insulation, and in the production of roofing shingles,
wallpaper, paint and plastics. As a powder, it is pearlescent and satiny- a quality that also
makes it a common ingredient in mineral cosmetics where it provides a glittery effect.
Though mica is harmless as a solid, its powder or dust can cause both short and long term
health problems. In some people, mica can have the immediate effect of irritating the
eyes and skin, causing redness and itching. Inhaling mica can cause wheezing, coughing
and shortness of breath as it irritates the mucous membranes lining the lungs. Repeated
high exposure to mica can cause fibrosis in the lungs, where the constant irritation from
inhaling mica dust causes scarring of the lung tissue. This results in the chronic coughing
and shortness of breath typical of pneumoconiosis, a disease often seen in people who
work in mines where they are exposed to coal dust. The carcinogenic effects of mica are
unclear, but considering other known health effects it is probably best to avoid exposure
as much as possible. (www.ehow.com/info_8551607_harmful-effects-powdered-
mica.html#ixzz1pZa9EJ1z)
25
Process optimization using Design for Environment concept in the input material of the
disperser unit
while small companies (those that produce 20,000 gallons or less per year) send the waste
to an off-site recycler. The fourth option, off-site treatment/ disposal, involve incineration
or land disposal and equipment cleaning wastes. Equipment cleaning wastes are a
dominant waste stream, (EPA, 1990).
There various ways that can be employed to mitigate waste highlighted in the previous
section are described in Table2.2 that follows.
26
Process optimization using Design for Environment concept in the input material of the
disperser unit
27
Process optimization using Design for Environment concept in the input material of the
disperser unit
The two major types of air emissions that occur in the paint manufacturing process are
volatile organic compounds and pigment dusts. Volatile organics may be emitted from
the bulk storage of resins and solvents and from their use in open processing equipment
such as mix tanks. Since most existing equipment is of open design, reducing or
controlling organic emissions from process equipment could require substantial
expenditures in retrofit costs. Additional work on control methods appears to be
warranted in this area, and as a result, the following measures only address bulk storage
and pigment handling.
28
Process optimization using Design for Environment concept in the input material of the
disperser unit
recycled) and therefore would eliminate the waste due to empty bags. While this method
would increase the amount of pigment handling occurring at the supplier’s facility, it can
be argued that the overall number of handling/transfer points for dry powder will be
greatly reduced along with the probability of spills and dust generation.
29
Process optimization using Design for Environment concept in the input material of the
disperser unit
30
Process optimization using Design for Environment concept in the input material of the
disperser unit
Design for the Environment can also provide a method of compliance with increasingly
stringent environmental regulations (both present and future) for products. Market entry
can now be explicitly dictated by the regulation of environmental performance. For New
Zealand manufacturers to export to Europe, they are already faced with this issue due to
explicit regulations concerning packaging, electronics and restricted substances. Non-
compliant products can now be denied access to the valuable European market. As a
result, manufacturers and brand owners can gain commercial advantage by addressing
compliance issues through Design for the Environment.
Promoting green cleaning and recognizing safer consumer and industrial and
institutional products through safer product labeling.
Defining Best Practices in areas ranging from auto refinishing to nail salon safety.
To achieve these goals, there are three main concepts that fall under the DFE umbrella
and they include design for environmental processing and manufacturing, design for
environmental packaging and design for disposal or reuse
31
Process optimization using Design for Environment concept in the input material of the
disperser unit
Design for environmental processing and manufacturing: This ensures that raw material
extraction (mining, drilling, etc.), processing (processing reusable materials, metal
melting, etc.) and manufacturing are done using materials and processes which are not
dangerous to the environment or the employees working on said processes. This includes
the minimization of waste and hazardous by-products, air pollution, energy expenditure
and other factors.
Design for environmental packaging: This ensures that the materials used in packaging
are environmentally friendly, which can be achieved through the reuse of shipping
products, elimination of unnecessary paper and packaging products, efficient use of
materials and space, use of recycled and/or recyclable materials.
Design for disposal or reuse: The end-of-life of a product is very important, because
some products emit dangerous chemicals into the air, ground and water after they are
disposed of in a landfill. Planning for the reuse or refurbishing of a product will change
the types of materials that would be used, how they could later be disassembled and
reused, and the environmental impacts such materials have.
Internal Drivers
(a) Need for increased product quality — a high level of environmental quality may
also raise product quality in terms of functionality, reliability in operation,
durability and/or reparability.
32
Process optimization using Design for Environment concept in the input material of the
disperser unit
(c) Need to stimulate innovation — Design for the Environment can lead to radical
changes at the product system level – the combination of product, market and
technology. Such innovations can provide entry into new markets.
(d) Need to reduce costs — Companies can use DfE strategies to deliver financial
benefits by:
External Drivers
33
Process optimization using Design for Environment concept in the input material of the
disperser unit
• Some companies are systematically reviewing their entire supply chain and
imposing new environmental standards or other measures of environmental
performance.
34
Process optimization using Design for Environment concept in the input material of the
disperser unit
(d) Waste charges — Waste processing charges such as landfill costs are constantly
increasing. The prevention of waste and emissions and re-use and recycling will
consequently become more attractive and make economic sense.
i. The bottom line — Cuts costs of raw materials and waste disposal
35
Process optimization using Design for Environment concept in the input material of the
disperser unit
iii. Environmental marketing — some customers now include Design for the
Environment issues in tender documentation and a ‘greener’ image can increase
market share
vi. Increased staff morale — there is a growing awareness among staff that
businesses play an important role in working towards sustainable development.
This can provide a strong personal incentive to pursue Design for the
Environment.
36
Process optimization using Design for Environment concept in the input material of the
disperser unit
1. Analyse Opportunities
This can be through an investigation of the product development process within the
company, the product market and incentives for adopting DFE by:
identifying drivers behind product design (for example, are product specifications
driven by engineering or by marketing?)
37
Process optimization using Design for Environment concept in the input material of the
disperser unit
38
Process optimization using Design for Environment concept in the input material of the
disperser unit
39
Process optimization using Design for Environment concept in the input material of the
disperser unit
talking with individuals who have an interest in DFE or an incentive to adopt it,
for example, a marketing manager interested in green consumer preferences
finding and supporting a DFE ‘champion’ in the company, and departmental
representatives, who comprise the team to promote DFE and ensure its
consideration within their section;
providing training and education for those involved with DFE.
Having identified potential DFE opportunities and raised awareness within the company,
there is a need to develop goals and strategies for implementing DFE. Organisational
goals and strategies can be set first before working at the level of specific products. These
can help to gain commitment within the company and raise awareness of the scope,
implementation and likely outcomes of a DFE project. It is essential that the DFE
strategies and goals are closely aligned with the organisation’s overall strategic direction.
This could be through:
holding a strategy formulation session for staff at various levels who have been
informed about DFE;
identifying realistic goals and targets for DFE implementation, environmental
improvements and economic performance based on DFE initiatives;
identifying the resources available for implementing DFE and seek additional
resources if necessary;
setting goals for specific products, business units or divisions;
ensuring DFE strategies are aligned with overall company directions or redirect
company where necessary;
developing strategies for achieving the targets;
identifying time-oriented milestones and areas of responsibility.
40
Process optimization using Design for Environment concept in the input material of the
disperser unit
Different tools shall be used in implementing DFE; Cleaner Production; life cycle
assessment programs, simple checklists, guidelines and scoring matrices, and especially
ISO 14001.
explore the available tools, consider the level of sophistication needed, the
resources available to invest in tools, the complexity of the product and the
amount of design time available;
determine which other DFE tools are suitable, both for the tasks and the people
using them;
evaluate tools and select the most appropriate ones;
start with simple DFE tools and work towards more complex ones;
bring in external assistance and/or training if needed.
A preliminary analysis of the life cycle can reveal where the greatest environmental
impacts occur and the opportunities for improvement. This is achieved by:
identifying the inputs, outputs and wastes of each stage of the product’s life cycle;
identifying environmental impacts through an initial simple analysis, for example,
by brainstorming with other staff;
41
Process optimization using Design for Environment concept in the input material of the
disperser unit
Having moved through all or some of the previous stages, the next step is to begin
designing, developing and prototyping the new product.
Much of the ability of the DFE process to add value to the product will eventually come
down to marketing by:
42
Process optimization using Design for Environment concept in the input material of the
disperser unit
finding ways to inform and educate consumers about the environmental benefits
of our product;
considering forming partnerships with retailers, local governments, environment
and consumer groups to help with marketing.
7. Evaluating
With any new process there are risks: we may find unanticipated environmental impacts
or other reasons that an aspect of the DFE project may not be completely successful.
However, implementing DFE is a continuous learning process and knowledge gained
from the experience can improve the next product or process. At this stage there is need
to:
adopt a formal feedback process to improve the learning ability of our company,
any person involved in product development should be able to comment on
successes and problems;
evaluate progress against our initial goals and milestones;
ensure feedback is incorporated into new designs or follow-on products;
regularly audit the level of implementation within each business unit and provide
incentives for adoption.
43
Process optimization using Design for Environment concept in the input material of the
disperser unit
The earlier concepts of "ignore", "dilute" and "treat" pollution changed to "prevent
pollution", "re-utilize wastes or generated by-products" and finally "treat" and "dispose
of" residues in a secured manner. For production processes, cleaner production results
from one or a combination of the following - conserving raw materials and energy,
substituting toxic/hazardous materials by more benign ones and reducing the quantity
and/or toxicity of all emissions and wastes before they leave a production process.
Cleaner Production programs are beneficial because they reduce operating costs.
For example, the costs involved with waste treatment, storage, and disposal are
often reduced through Cleaner Production programs and the savings can be used
to offset the development and implementation costs of the program. Material,
energy, and facility cleanup costs can also be reduced through Cleaner Production
programs. Material, energy, and facility cleanup costs can also be reduced through
Cleaner Production programs.
44
Process optimization using Design for Environment concept in the input material of the
disperser unit
These steps and the related tasks of a typical CPA process are shown in Figure 2.4 that
follows.
45
Process optimization using Design for Environment concept in the input material of the
disperser unit
46
Process optimization using Design for Environment concept in the input material of the
disperser unit
47
Process optimization using Design for Environment concept in the input material of the
disperser unit
ii. Pre-assessment
Checklist of Questions to be asked During the Walkthrough
Work floor or shop floor -
• Is the floor dirty or pounded?
• Can the workers move about easily? Is there unnecessary piling of raw materials and
stocks?
• Is the layout optimum; i.e. can the workflow be improved to minimize movement of
materials and walking time?
Storage areas -
• Is the storage system FIFO (i.e. first in first out; raw material is utilized based on the
date of procurement, giving preference to old stock) or LIFO (last in first out; fresh raw
material is utilized first, while the old stock of raw material remains unutilized)?
• How are the received raw materials checked for quality?
48
Process optimization using Design for Environment concept in the input material of the
disperser unit
• Are there frequent instances of receiving raw materials that do not meet the required
specifications? What happens to the rejects?
Equipment and process -
• Is the process operated as per the Standard Operating Practice laid down by the
equipment/technology provider? What are the reasons if there are any variations?
• Is the equipment upkeep regularly conducted? What are the operating efficiencies of the
equipment? Are machine breakdowns or problems recorded and their causes corrected
regularly?
• Are quality assurance / quality control done for the finished and intermediate products?
How frequently? What are the current results?
Boiler and steam distribution system -
• Are there any leaking joints, glands, valves, safety valves?
• Is the condensate being returned to the maximum extent possible?
• Are the condensate return lines and feed tanks jacketed or lagged?
• Are steam traps of correct types being used for each process?
• What is the fuel used? Is it of a consistent quality and composition?
• What is the source of water? Is the raw water treated before use?
• What is the type of boiler (e.g. single pass / double pass, etc.)? How frequently does the
boiler blow down?
Waste and emissions -
• Is the waste properly collected, segregated and transported?
• Is the waste generation continuous or in spurts?
• Are any measurements made of waste generated or emissions emitted?
• Are any valuable raw materials or products wasted as part of the emissions? Is it
possible to reuse or recycle them if recovered?
49
Process optimization using Design for Environment concept in the input material of the
disperser unit
iii. Assessment
Preparation of detailed material & energy balance
It is probable that the cleaner production team finds substantial discrepancies in the
preliminary M&E balance. This may require re-discussing the assumptions behind the
numbers, conducting measurements, and making whatever revisions are necessary to the
data used for inputs and outputs. Hence, the next task for the team is to prepare detailed
material and energy balances around certain parts of the PFD. Developing a detailed
material balance for each operation is neither practical nor relevant. While assigning a
monetary value to the materials or waste streams, the team should consider the following:
The cost of raw materials / intermediate products / final products lost in the waste
streams (e.g., the costs of unexhausted dye in waste dye liquor);
The cost of energy in waste streams, in terms of the energy consumed to heat or
chills them;
The cost of treatment / handling / disposal of waste streams, including tipping or
discharge fees if any;
The costs incurred, if any, in protecting the workers and maintaining safe working
conditions (e.g., shop floor exhaust systems);
The potential liability costs from a possible accidental spill, discharge, or leakage
50
Process optimization using Design for Environment concept in the input material of the
disperser unit
likely to be involved. Once such a diagram has been prepared, the team can effectively
use it for the generation of cleaner production options
CP option generation
Once the points of action and priorities are understood and listed, the cleaner production
team should move on to the logical next phase; i.e. option generation. Cleaner production
options could fall under one of the following categories:
Housekeeping – Improvements to work practices and methods, proper maintenance of
equipment etc., fall under this category. Efficient housekeeping can provide significant
benefits in terms of saving resources. These options are typically low cost and provide
low to moderate benefits8. A simple example of good housekeeping in a dyeing operation
is to clean the floors and machines of dirt, grease, rust, etc. regularly, which will reduce
the possibility of accidentally soiling the fabric, and thus minimize the need for extra
washing.
Management and personnel practices – Management and personnel practices include
effective supervision, employee training, enhancing operator skills, and the provision of
incentives and bonuses to encourage employees to conscientiously strive to reduce waste
and emissions. These options are typically low cost and can provide moderate to high
benefits.
51
Process optimization using Design for Environment concept in the input material of the
disperser unit
Raw material substitution – Primary / auxiliary raw materials can be substituted if better
options exist in terms of costs, process efficiency, and reduced health and safety related
hazards. Such an approach may be necessary if the materials already in use are difficult to
source, or become expensive, or come under the purview of new environmental or health
and safety regulations. In all cases of material substitution, it is crucial to test the
suitability of the new material in terms of environmental and economic benefits, optimum
concentration, product quality, productivity, and improved working conditions. For
instance, sodium sulphide and acidified dichromate tend to be used as auxiliary agents in
the sulphur black textile dyeing
process9. However, both these agents are toxic and hazardous to handle. Their usage may
leave harmful residues in the finished fabric and generate effluents that are difficult to
treat and damage the environment. Both these agents may be safely substituted without a
decline in fabric quality, thus eliminating adverse health and environmental impacts.
Sodium sulphide may be replaced with glucose or dextrose, whereas acidified dichromate
may be substituted with sodium
perborate or ammonium persulphate. The substitution of chemical dyes with natural dyes
may also be cited as an example of raw material substitution.
New technology – Adopting and transferring new technologies can often reduce resource
consumption, minimize wastes, as well as increase the throughput or the productivity.
These options are often capital intensive, but can lead to potentially high benefits.
Modifications in equipment design can be another option, which tends to be slightly less
52
Process optimization using Design for Environment concept in the input material of the
disperser unit
or equally capital intensive as the option for new technology, and can lead to potentially
high benefits.
New product design – Changing the product design can cause impacts on both the
“upstream” as well as “downstream” side of the product life-cycle. Product re-design for
instance, can reduce the quantity or toxicity of materials in a product, or reduce the use of
energy, water and other materials during use, or reduce packaging requirements, or
increase the “recyclability” of used components. This can lead to benefits such as reduced
consumption of natural resources, increased productivity, and reduced environmental
risks. Often, this helps in both establishing as well as widening the market. Product
redesign is, however, a major business strategy and may require feasibility studies and
market surveys, especially if the supply-chain around the product is already established
and is complex.
Recovery of useful by-products / resources – This cleaner production option entails the
recovery of wastes as by-products / resources, which may have useful applications within
the industry itself or outside it. This type of options essentially leads to the reuse /
recycle, and thus minimization, of waste as well as to cost savings. A common example
of recovery from a waste stream for many industries is heat recovery through the use of
heat exchangers. Such options are typically medium cost and can provide moderate to
high benefits.
Onsite recycling and reuse – Onsite recycling and reuse involves the return of a waste
material either to the originating process or to another process as a substitute for an input
material.
For instance, in the case of a textile dyeing unit, instead of draining off the last cold
washes, they can be collected in an underground tank, adjusted for pH10, and then
filtered prior to reuse in subsequent washing operations. These options are typically low
to medium cost and can provide moderate to high benefits.
53
Process optimization using Design for Environment concept in the input material of the
disperser unit
In reality, many of the options a team will identify result as a combination of the above
categories so as to produce cost-effective and sustainable results. For instance, any option
of new technology should be preceded and followed by improvements in management
and training. In addition, many a time, the option of new technology also requires
substitution of raw materials.
54
Process optimization using Design for Environment concept in the input material of the
disperser unit
very high costs, lack of technology, requiring major changes, etc.). These can be left
pending for later consideration.
Detailed screening of options
The team can now undertake a detailed screening of the options in the category requiring
further analysis in order to determine which of the options are technically feasible, and
ascertain both the economic and the environmental benefits of implementing these
options. Each of these aspects is described below.
Technical evaluation
The technical evaluation should cover the following aspects:
Materials and energy consumption – For each option, it is important to establish material
and energy balances for conditions before and after implementation to quantify the
materials and energy savings that will result.
Product /by-product quality – there is need to assess the product / by-product’s quality
before and after implementation of the option.
Right First Time (RFT) – Provide estimates on the possible improvement of the RFT
corresponding to before and after option implementation. It is also important to examine
the following aspects from the point of view of implementation.
Human resources required – whether the option can be implemented by in-house staff, or
whether external expertise or collaboration with partner organization is required.
Risks in implementing the option - Some options may not be fully proven and may
require laboratory scale experiments or pilot studies to assess the outcomes before a full-
scale implementation is carried out. Some options may affect the key production process
or product features, so the potential impact on the business if the option does not work as
planned is very high.
Ease of implementation – The technical ease with which an option can be implemented
will depend on such things as the layout of the production processes and of the auxiliary
services such as steam lines, water lines, inert gas lines, etc., the physical space available,
55
Process optimization using Design for Environment concept in the input material of the
disperser unit
the maintenance requirements, the training requirements, etc. Also, if options require
working on key production processes, the timing of the options’ implementation becomes
critical. If the option requires major changes in, or interruptions to, production patterns,
any loss in production needs to be factored into the economic analysis of the option.
Time required for implementation – Time required if equipment or material needs to be
procured, installed or commissioned including consideration of shut-down time for
affecting the implementation of the option.
Cross-linkages with other options – Determine whether a particular option is linked to
implementation of other options and/or whether the option is best implemented stand-
alone or in consideration with other options.
Environmental evaluation
The environmental evaluation of an option should ideally take into account its impacts on
the entire lifecycle of a product or a service, wherever practically possible. In practical
situations, however, the evaluation is often restricted to on-site and offsite
(neighbourhood) environmental improvements. The environmental evaluation should
include estimation of following benefits that each option can bring about:
Likely reduction in the quantity of waste/emission released (expressed on a mass
basis);
Likely reduction in the release of hazardous, toxic, or non-biodegradable
wastes/emissions (expressed on a mass basis);
Likely reduction in the consumption of renewable natural resources (expressed on
a mass basis);
Likely reduction in consumption of non-renewable natural resources, e.g. fossil
fuels consumed (expressed on a mass basis);
Likely reduction in noise levels;
Likely reduction in odour nuisance (due to elimination of an odorous compound);
Likely reduction in the on-site risk levels (from the point of process safety);
56
Process optimization using Design for Environment concept in the input material of the
disperser unit
Economic evaluation
The team must now evaluate the economic benefits of all the reductions in waste
generation and resource consumption that each option can bring about. It must estimate
the immediately obvious savings in the purchase costs of materials and fuels, the
treatment and disposal costs avoided as well as the material and waste stream costs
(identified during the M&E balance earlier). However, it must also estimate less obvious
financial benefits such reduced sick days for workers or generally higher worker
productivity, lower personnel costs from reducing the burden of special management and
reporting of hazardous materials, wastes and pollution, reduced worker and
environmental liability, potential profits from sale of waste as by-product, from carbon
dioxide credits, etc. Experience has shown that such an expanded financial assessment
often helps in considerably improving the economic feasibility of an option.
The team must also estimate the economic costs of each option, in the form of
investments in new technology or equipment, but also in terms of training and other costs
ancillary to the implementation of the option.
These benefits and costs are then analyzed and computed using various evaluation criteria
[e.g. Payback Period, Net Present Value (NPV), Internal Rate of Return (IRR), etc.].
A simple Payback Period is evaluated based on a comparison of the annual savings and
the initial investment. It simply indicates the time period to return the initial investment.
It is calculated as,
57
Process optimization using Design for Environment concept in the input material of the
disperser unit
investment decisions can only be made on the basis of payback period alone if the
investment required is low and / or the returns are high so that the payback period is less
than two years.
If these conditions are not met, a better approach is to use the concepts of NPV or IRR.
These concepts consider the time value of cash inflows and outflows during the useful
life of the investment made. This kind of economic evaluation requires information on:
The capital costs associated with any investments required;
Net revenue, which is computed as a difference between total revenue (that could
be higher than the base case) and the operating costs (that are typically lower in
the changed scenario); and
Rates of interest and depreciation to enable computation of the Present Value.
The following are the equations that can be used for computation of NPV:
The I 's are income amounts for each year. The subscripts (which are also the exponents
in the denominators) are the year numbers, starting with 0, which is this year. The
discount rate -- assumed to be constant in the future -- is r. The number of years the
investment lasts is n. For an investment to be financially viable NPV must be greater than
zero.
IRR is essentially that rate of return on an investment that ensures that during the
investment’s lifetime the net cash inflows (i.e. inflows – outflows) are equal to zero, i.e.,
IRR is the value of r that gives zero as the value of NPV thus given the (period, cash
flow) pairs (n, Cn) where n is a positive integer, the total number of periods N, and the net
present value NPV, the internal rate of return is given by r in:
58
Process optimization using Design for Environment concept in the input material of the
disperser unit
This problem is solved by assuming r and then following an interpolation procedure. The
IRR is then compared with the rate of interest of the borrowings that may be needed from
the market. Typically, if the IRR is lower than the market borrowing rate, then the
investment is not considered to be financially viable.
It is useful to carry out a sensitivity analysis to understand the “ruggedness” of an option.
This can be done by varying the expected efficiencies or yields, prices that the by-
products may fetch in the market, or the capital costs of new equipment, and see how
much of an effect these have on the outcome. This can help in building both optimistic
and pessimistic scenarios to test how sensitive the IRR or NPV are to the data assumed in
the economic analysis.
59
Process optimization using Design for Environment concept in the input material of the
disperser unit
may decide to give the highest weightage to environmental performance (say, 50%), less
to technical feasibility (say, 30%) and least to financial viability (the remaining 20%).
This indicates that the enterprise is most keen to reduce pollution load but does not have
high levels of capability to undertake technically involved options.
Once weights are assigned, simple indicators such as “scores” can be developed to assess
the relative performance of each option. For example, economic viability could be
assessed based on the payback period / NPV / IRR. Environmental performance could be
assessed based on percent pollutant load reduction. Technical feasibility could be
assessed based on technical complexity, requirements for new equipment / technology,
requirement of additional technical skills, etc. Each option is then evaluated on a
subjective basis and scores assigned to each of the three aspects. Scores could have a
range such as 0 to 10 where lower scores will imply poor attainment of the performance
etc. For example, two options may have IRR of 15% and 33% respectively and hence
may be assigned scores of 8 and 5 on the aspect of economic viability.
The weighted sum of the scores will give an index for each option, on the basis of which
priorities may be assigned. It should be noted that the intention is not to prioritize each
option individually but to group them into categories such as “top priority”, medium
priority”, and “low priority”. This exercise would then be the basis for preparing the
implementation plan.
60
Process optimization using Design for Environment concept in the input material of the
disperser unit
The cleaner production team should give first priority to implementing options that are
low in cost, easy to implement and / or are a pre-requisite for the implementation of other
options. This should be followed by options that require more investment, laboratory or
pilot trials, or interruption in production schedules. Many a time, options are
implemented during or immediately after the CPAs at enterprises. The very conduct of a
CPA in this form becomes a demonstration for others to follow.
61
Process optimization using Design for Environment concept in the input material of the
disperser unit
An EMS is defined by ISO as: “part of the overall management system, that includes
organizational structure, planning activities, responsibilities, practices, procedures,
processes and resources for developing, implementing, achieving and maintaining the
environmental policy’ (ISO 1996 cited in Federal Facilities Council Report 1999). The
concept of an environmental management system evolved in the early nineties when the
United Nations organized a conference on the Human Environment in Stockholm and the
United Nations Environment Programme (UNEP) was launched. In 1992, the British
Standard International, BSI, group published the world's first environmental management
systems standard, BS 7750 and this supplied the template for the development of the
International Organization for Standardization, (ISO), 14000 series.
62
Process optimization using Design for Environment concept in the input material of the
disperser unit
Environmental Labeling
eco-labels (seals of approval)
14020/23 self-declared environmental claims
quantified environmental information about
products and services
63
Process optimization using Design for Environment concept in the input material of the
disperser unit
Glossary
14050
-Terms and Definitions
Adapted from the Quality Network paper on International Standard ISO 14000
64
Process optimization using Design for Environment concept in the input material of the
disperser unit
The major objective of the ISO 14000 series of norms is "to promote more effective and
efficient environmental management in organizations and to provide useful and usable
tools that are cost effective, system-based, and flexible and reflect the best organizations
and the best objectives and goals and the subsequent monitoring and measurement of
these (IISD 2010).
ISO 14001, as with other ISO 14000 standards, is voluntary (IISD 2010), with its main
aim to assist companies in continually improving their environmental performance,
whilst complying with any applicable legislation. Organizations are responsible for
setting their own targets and performance measures, with the standard serving to assist
them in meeting these.
65
Process optimization using Design for Environment concept in the input material of the
disperser unit
2. Planning
Environmental aspects
Legal and other requirements
Objectives and targets
Environmental management program(s)
66
Process optimization using Design for Environment concept in the input material of the
disperser unit
5. Management review
Step 2: Planning
Plan what the EMS is to address. For the environmental aspects, first make lists of the
environmental aspects (issues) that are relevant to the business. The environmental
review mentioned earlier should provide most of this information and the Annex to ISO
14001 provides guidance on the format for doing this. Consider the inputs, outputs and
processes/activities of the business in relation to;
emissions to air
releases to water
waste management
contamination of land
use of raw materials and natural resources
other local environmental and community issues
67
Process optimization using Design for Environment concept in the input material of the
disperser unit
Consider both site (direct) and offsite (i.e. indirect) aspects that you control or have
influence over (such as suppliers) and in relation to normal operations, shut-down and
start-up conditions and reasonably foreseeable and emergencies situations. A simple
written procedure is then required to determine which of the aspects identified are really
or probably significant (important) and training needs, outline the key stages of the
project and dates that will lead to the target achievement).
Gradually apply environmental management programme thinking to such things as the
introduction of new products, new or improved processes and other key activities of the
business. In particular, ensure existing projects become environmental management
projects
where there is a significant environmental impact involved, so that the EMS becomes
company wide. This is a frequent oversight found during ISO 14001 assessments. The
EMS must cover the whole business – like a net thrown over the whole business and for
example including such things as engineering and maintenance.
68
Process optimization using Design for Environment concept in the input material of the
disperser unit
its share of cynics but even some of these can be won over with time. Training will vary
from a general briefing for the workforce to detailed environmental auditor training.
Communication
Implement procedures to establish a system of internal and external communication to
receive environmental information and respond to it and to circulate new information to
people that need to know. This will include: new legislation, information from suppliers,
customers and neighbours and communications both with employees and for employees
about progress with the EMS. This process can often generate worthwhile ideas from
employees themselves for future environmental improvements.
Environmental management system documentation
The EMS itself needs to be documented with a manual, procedure and work instructions
but keep it brief and simple. The Standard clearly states where procedures are required.
Eleven system procedures are required to maintain the EMS, plus operating work
instructions but if you already have ISO 9000, this will cover most of six of the
procedures required and a quality system can certainly be expanded to cover ISO 14001
as well. Cross reference the EMS manual to other environmental and quality documents
to link the EMS and to integrate it with existing business practices.
Operational control
Implement additional operating procedures (work instructions) to control the identified
significant (important) aspects of production processes and other activities. Some of these
will already exist but may need a ‘bit of polish’. Don’t forget significant aspects that
relate to goods and services from suppliers and contractors.
Emergency preparedness and response
Implement procedures to address reasonably foreseeable emergencies and to minimise
their impact should they occur. (e.g. fire, major spillages of hazardous materials,
explosion risks etc.).
69
Process optimization using Design for Environment concept in the input material of the
disperser unit
70
Process optimization using Design for Environment concept in the input material of the
disperser unit
It involves collecting data on raw materials used, energy consumption and wastes
released to the environment (air, water and land). Data is collected for every stage of the
life cycle, from mining of raw materials through to processing, distribution, use, reuse,
maintenance, and recycling, final disposal and all transportation involved, using literature
studies, interviews, measurements, theoretical calculations, data banks and qualified
guesses.
71
Process optimization using Design for Environment concept in the input material of the
disperser unit
Based on a relevant functional unit for the system under study, this data is then calculated
and modeled into a Life Cycle Inventory (LCI), which in turn is classified, characterized
and evaluated to determine the environmental impacts of the system.
As a last step, the improvement assessment can be performed to identify and evaluate the
options for reducing the environmental and possibly the economical burdens of the
system.
72
Process optimization using Design for Environment concept in the input material of the
disperser unit
73
Process optimization using Design for Environment concept in the input material of the
disperser unit
74
Process optimization using Design for Environment concept in the input material of the
disperser unit
have loved to use one of these processes in the prototyping process but the technological
gap that exists between first and third world countries was the first limitation.
FEA consists of a computer model of a material or design that is stressed and analyzed
for specific results. It is used in new product design, and existing product refinement. A
company is able to verify a proposed design will be able to perform to the client's
specifications prior to manufacturing or construction. Modifying an existing product or
structure is utilized to qualify the product or structure for a new service condition. In case
of structural failure, FEA may be used to help determine the design modifications to meet
the new condition.
FEA uses a complex system of points called nodes which make a grid called a mesh. This
mesh is programmed to contain the material and structural properties which define how
the structure will react to certain loading conditions. Nodes are assigned at a certain
density throughout the material depending on the anticipated stress levels of a particular
area. Regions which will receive large amounts of stress usually have a higher node
density than those which experience little or no stress. Points of interest may consist of:
fracture point of previously tested material, fillets, corners, complex detail, and high
stress areas. The mesh acts like a spider web in that from each node, there extends a mesh
element to each of the adjacent nodes. This web of vectors is what carries the material
properties to the object, creating many elements.
A wide range of objective functions (variables within the system) are available for
minimization or maximization:
75
Process optimization using Design for Environment concept in the input material of the
disperser unit
Structural analysis consists of linear and non-linear models. Linear models use simple
parameters and assume that the material is not plastically deformed. Non-linear models
consist of stressing the material past its elastic capabilities. The stresses in the material
then vary with the amount of deformation.
Vibration analysis is used to test a material against random vibrations, shock, and impact.
Each of these incidences may act on the natural vibration frequency of the material
which, in turn, may cause resonance and subsequent failure.
Fatigue analysis helps designers to predict the life of a material or structure by showing
the effects of cyclic loading on the specimen. Such analysis can show the areas where
crack propagation is most likely to occur. Failure due to fatigue may also show the
damage tolerance of the material.
Heat Transfer analysis models the conductivity or thermal fluid dynamics of the material
or structure. This may consist of a steady-state or transient transfer. Steady-state transfer
refers to constant thermo-properties in the material that yield linear heat diffusion.
76
Process optimization using Design for Environment concept in the input material of the
disperser unit
2.5 CONCLUSION
After studying literature on paint manufacturing, the wastes that are generated such as
dust and spills, and the health effects of the pigment raw materials used, it was
discovered that other techniques such as Design for the Environment can be applied to
help reduce dust emissions.
CHAPTER THREE:
METHODOLOGY
3.0 INTRODUCTION
Research methodology is a collective term for the structured process of conducting
research. There are many different methodologies used in various types of research
which can be quantitative (for example, measuring the number of times someone does
something under certain conditions) or qualitative (for example, asking people how
they feel about a certain situation, http://www.blurtit.com/q462869.html).
77
Process optimization using Design for Environment concept in the input material of the
disperser unit
the Environment concept was used as an approach to prevent pollution, and prevent the
risk pollution presents to humans and the environment.
78
Process optimization using Design for Environment concept in the input material of the
disperser unit
79
Process optimization using Design for Environment concept in the input material of the
disperser unit
ISO 14001 was used as key DFE tool for implementing a system that will help an
organization improve its environmental performance. It was implemented according to
the same Plan-Do-Check-Act (PDCA) cycle as in Fig 3.2.
80
Process optimization using Design for Environment concept in the input material of the
disperser unit
81
Process optimization using Design for Environment concept in the input material of the
disperser unit
Finite Element Analysis, (FEA) could be used as a tool to verify whether the proposed
design was able to perform to the researcher’s specifications prior to manufacturing or
construction as it provides the following functions;
• Structural and motion analysis;
• Design parameter sensitivity analysis;
• Design optimization, (Dong, 2006).
Both qualitative and quantitative methods were employed in data collection, presentation
and analysis.
The function of this research design was to provide for the collection of relevant
information with minimal expenditure of effort, time and money. The data gathering tools
that were used include; field study (personal observation), interviews, questionnaires,
experiments and literature review.
i. Observation method:
Marshall, C., Rossman, G., (1989) define observation as the systematic description of
events, behaviours, and artefacts in the social setting chosen for study. Participant
observation is considered a staple in anthropological studies, especially in ethnographic
studies, and has been used as a data collection method for over a century (Kawulich, B.B,
2005).
The reason why direct observation was used in the research was that it yielded
information which people are normally unwilling or unable to provide (Marshall, C.,
Rossman, G., 1995). DeWalt, K and DeWalt, B (2002) suggested that participant
82
Process optimization using Design for Environment concept in the input material of the
disperser unit
observation be used as a way to increase the validity of the study, as observations may
help the researcher have a better understanding of the context and phenomenon under
study, (see Appendix A). They highlighted that the validity is stronger with the use of
additional strategies used with observation, such as interviewing, document analysis, or
surveys, questionnaires, or other more quantitative methods. More so, the information
collected by observer is not representative of the culture, (Johnson and Sackett, 1998).
ii. Interviews
iii. Survey
A structured survey was carried out where formal lists of questions were asked to all
plant operators. In this research, the questions were open ended and they were used to
83
Process optimization using Design for Environment concept in the input material of the
disperser unit
collect factual information and to collect ‘baseline’ information which can then be
tracked over time to examine changes,
(www.kirklees.gov.uk/community/yoursay/Questionnaires.pdf). The reason why
questionnaires were used in survey includes their ability to collect many different kinds
of information and their quickness and low cost as compared to observation and
experimental method. Nevertheless, some drawbacks were faced which included the
inability of respondents to answer because they couldn’t remember or never gave a
thought to what they do and why, (see Appendix B).
84
Process optimization using Design for Environment concept in the input material of the
disperser unit
3.5 CONCLUSION
The DFE approach was employed to prevent pollution using CP, ISO 14 001 and LCA as
DFE tool. The identified product would be developed with the aid of Finite Element
Analysis.
85
Process optimization using Design for Environment concept in the input material of the
disperser unit
CHAPTER FOUR:
4.0 INTRODUCTION
This chapter is concerned with the audit of the processes that was carried out. The
objectives of the audit were to identify, quantify and find options to minimize wastes. An
initial check was carried out by the researcher to ascertain the applicability of Cleaner
Production in the plant, (see Appendix A). The actual audit was then carried out through
a Cleaner Production Assessment done by the project team.
4.2 ASSESSMENT
86
Process optimization using Design for Environment concept in the input material of the
disperser unit
General
Manger
Branch
Manager
87
Process optimization using Design for Environment concept in the input material of the
disperser unit
88
Process optimization using Design for Environment concept in the input material of the
disperser unit
89
Process optimization using Design for Environment concept in the input material of the
disperser unit
PREMIX
Mill base
Let down
DISPERSION
Fail
Dispersion test
MIX
Pass
Fail
Corrections
decided
Colour tests
Pass
LET-DOWN Yes
Fail
Specification tests
Rework
No
90
Process optimization using Design for Environment concept in the input material of the
disperser unit
The inputs and outputs for each process stage are presented in Fig 4.4.
Fig 4.4: Schematic diagram of paint manufacturing indicating all inputs and outputs
91
Process optimization using Design for Environment concept in the input material of the
disperser unit
92
Process optimization using Design for Environment concept in the input material of the
disperser unit
material balance for the raw material measuring, premixing and dispersion process are
shown in Fig 4.6 that follows.
93
Process optimization using Design for Environment concept in the input material of the
disperser unit
Table 4.3 presents the Total Weighted Average (TWA) limit values of dust
exposure for 8hrs according to ACGIH and Factories Act. Table 4.4 presents the
levels of total dust concentration in different process stages in the PVA plant.
Min Max
Though the minimum values are within limit, there maximum observed values go
94
Process optimization using Design for Environment concept in the input material of the
disperser unit
A further comparison of area dust concentration versus the personal dose was done and
is presented in Table 4.5 and graphically in Fig 4.8.
95
Process optimization using Design for Environment concept in the input material of the
disperser unit
Table 4.5: Comparison of area dust concentration with personal dose concentration
Section/Stage Type of Area dust Personal dose
dust concentration concentration
3 3
(mg/m ) (mg/m )
96
Process optimization using Design for Environment concept in the input material of the
disperser unit
In the storeroom area and during the dispersion process, the dust
concentration is more prone in the environment whilst the person is
more exposed during pigment measurement and disperser loading. Most
of the dust emissions occur during disperser loading and at the same
time, personal dose concentration is more pronounced than the
workplace area dust concentration which means that the employee has a
greater health risk.
97
Process optimization using Design for Environment concept in the input material of the
disperser unit
From surveying the plant, it was found that the various causes of dust generation in the
PVA plant are as follows;
i. Poor process and equipment design
The way of disperser feeding through direct pouring of pigments in the disperser
tank creates a lot of dust.
There was no dust extractor at the disperse unit that could have minimized the
amount of dust that is released into the environment.
The spillage of powders was seen to be as a result of poor feeding technique as
well as poor workmanship.
ii. Poor Housekeeping:
Untidiness was seen in the form of pigment spills on the disperser feeding area
floor
Equipment is not wiped off of dust emissions that would have accumulated on
them
98
Process optimization using Design for Environment concept in the input material of the
disperser unit
The emptied raw material bags were thrown on the pallet after emptying
resulting in dust creation on the floor.
iii. Wrong Raw Material
The pigments that are used are in the form of powders which can easily fly out as
dust
iv. Poor workmanship
The emptied raw material bags were thrown on the pallet after emptying resulting
in dust creation on the floor.
The concentration of dust emission is not monitored neither is it measured.
From the causes of dust generation identified, some cleaner production opportunities
were suggested. The cleaner production opportunities are presented in Table 4.4 that
follows.
Table 4.4: Cleaner Production Opportunities
CLEANER PRODUCTION OPPORTUNITIES PROCESS STAGE
Good housekeeping
3. Load empty bags into a drum to avoid spillage of left over materials. Premixing
99
Process optimization using Design for Environment concept in the input material of the
disperser unit
Poor workmanship
1. Load empty bags into a drum to avoid spillage of left over materials. Premixing, Dispersion
2. Measure and control dust emissions in the plant Premixing, Dispersion, Raw
Material Measurement
100
Process optimization using Design for Environment concept in the input material of the
disperser unit
101
Process optimization using Design for Environment concept in the input material of the
disperser unit
Basing on the rate given cleaner production opportunities was selected. Table 4.6
presents the selecting of 7 cleaner production opportunities of the mill.
102
Process optimization using Design for Environment concept in the input material of the
disperser unit
4.3 CONCLUSION
From the results in the previous table, the priorities of the cleaner production
opportunities were obtained. Option 4 which is the design of a material handling system to
reduce dust emissions and spillages during for disperser feeding was strongly recommended.
103
Process optimization using Design for Environment concept in the input material of the disperser
unit
CHAPTER FIVE:
5.0 INTRODUCTION
The main aim of implementing ISO 14 001 was to assist Astra Paints company in continually
improving their environmental performance, whilst complying with any applicable legislation .
This chapter explores the stages for the successful implementation ISO 14 001 at Astra paints so that
there can be improved environmental performance in its production processes.
104
Process optimization using Design for Environment concept in the input material of the disperser
unit
ASTRA PAINTS
ENVIRONMENTAL POLICY
The management and all who work at Astra Paints are committed to the care of the
environment and the prevention of pollution.
The organisation ensures that all its activities are carried out in conformance with the
relevant environmental legislation.
The organisation seeks to minimize waste arising, promote recycling, reduce energy
consumption, reduce harmful emissions and, where possible, to work with suppliers
who themselves have sound environmental policies.
An essential feature of the environmental management system is a commitment to
improving environmental performance. This is achieved by setting annual
environmental improvement objectives and targets which are regularly monitored and
reviewed. The objectives and targets are publicised throughout the organisation and
all staff are committed to their achievement.
In order to ensure the achievement of the above commitments, the organisation has
implemented an environmental management system which satisfies the requirements
of ISO 14001.
This Policy and the obligations and responsibilities required by the environmental
management s y s t e m have been communicated to all employees . The
pol i c y i s available to the public on request.
General Manager Date
105
Process optimization using Design for Environment concept in the input material of the disperser
unit
Contents
5.1.1. Introduction to Astra Paints
5.1.2. Environmental management system
5.1.3. Environmental policy
5.1.4. Planning
5.1.5. Implementation and operation
5.1.6. Checking and corrective action
5.1.7. Management review
Appendix A. Structure of the Environmental Management System
106
Process optimization using Design for Environment concept in the input material of the disperser
unit
Astra Paints is a manufacturer of domestic, industrial, automotive and wood coatings. Astra
Paints manufactures of polyvinyl acetate (PVA) paint, enamel paint and tints. This company is
located in Harare and it has been trading since 1962.
Astra Paints is committed to protecting the environment, and is ready to implement an
environmental management system which is described in this Environmental Management
Manual.
The organisation is a l r e a d y registered to the quality management Standard ISO 9001,
( I S O 9 0 0 1 : 2 0 0 8 ) therefore, where possible the requirements of ISO 14001 and ISO
9001 will be integrated into a common management system.
As required by Clause 4.1 of the Standard, Astra Paints will create and implement an
environmental management system (EMS) which conforms to the requirements of ISO 14001.
The EMS is structured by means of the following documents:
Environmental Policy.
Environmental Manual.
Registers of Environmental Aspects and Environmental Legislation
Operating procedures
107
Process optimization using Design for Environment concept in the input material of the disperser
unit
5.1.4 Planning
109
Process optimization using Design for Environment concept in the input material of the disperser
unit
As required by Clause 4.4.1 of the Standard, the General Manger sets up a management
structure and allocates responsibilities for environmental activities so that there is
effective management of the EMS. The management structure is shown in Fig 5.1.
The responsibilities of individual jobs which will have an input to environmental performance
are described below. The General Manager ensures that adequate resources in terms of people,
skills and equipment are available to allow the proper exercise of these responsibilities.
General Manager
The General Manager has overall responsibility for the policies and activities of the
organisation. He chairs the environmental management review meetings, has the ultimate
responsibility for setting environmental objectives and targets, and authorizes the Environmental
110
Process optimization using Design for Environment concept in the input material of the disperser
unit
Policy.
Production Manager
He is responsible for the control of the environmental aspects related to all manufacturing
activities and for emergency procedures.
Operator
He is responsible for maintaining work station and equipment so that it performs reliably.
111
Process optimization using Design for Environment concept in the input material of the disperser
unit
As required by Clause 4.4.2 of the Standard, all staff and new recruits receive environmental
awareness t r a i n i n g which includes the Environmental Policy, the major
e n v i r o n m e n t a l impacts of the organization’s activities and an introduction to the EMS. All
staff are trained in the specific environmental impacts and responsibilities of their jobs, in
emergency procedures and in the potential consequences of departing from the specific
procedures. Operating Procedure 15 ‘Environmental training’ applies.
5.1.5.3 Communication
As required by Clause 4.4.3 of the Standard, procedures should be implemented for receiving,
documenting and responding to communications from external sources on environmental
subjects including complaints and requests for information and operating Procedure 16
‘Environmental communications’ applies.
112
Process optimization using Design for Environment concept in the input material of the disperser
unit
Documents which need to be retained for historical or legal purposes are clearly marked
as withdrawn.
Operating Procedure in ISO 9001‘Document control’ refers.
113
Process optimization using Design for Environment concept in the input material of the disperser
unit
5.1.6.3 Records
As required by Clause 4.5.3 of the Standard, all documents and records which form part of the
EMS are defined, identified, collated, indexed, filed and stored securely so that they will not
deteriorate and can be retrieved. Retention times are defined. This refers to Operating Procedure
20 ‘Environmental records’.
114
Process optimization using Design for Environment concept in the input material of the disperser
unit
5.2 CONCLUSION
The implementation of ISO 14 001 will assist the company in continually improving its
environmental performance especially on dust emissions in the PVA plant under study.
115
Process optimization using Design for Environment concept in the input material of the disperser
unit
CHAPTER SIX:
6.0 INTRODUCTION
This chapter explore the assessment of Life Cycle as a Design for Environment tool to assess the
environmental aspects and potential impacts associated with the feeding process. Emphasis was
made on the reduction and recovering options to reduce environmental impact.
.
116
Process optimization using Design for Environment concept in the input material of the disperser
unit
117
Process optimization using Design for Environment concept in the input material of the disperser
unit
Raw materials are measured out as per batch card from the raw materials section and sent to the
factory.
2. Transportation
The measured pigments are ferried to the disperser unit using a forklift.
3. Disperser feeding
Two operators carry a bag and hand it over two others who tear it off and pour pigments into the
disperser tank. The total amount of powders fed for 10 000liters of paint are about 7tonnes.
118
Process optimization using Design for Environment concept in the input material of the disperser
unit
4. Dispersion
This is a physical process where particles of the pigment are ground and dispersed throughout
the mixture. The functions of dispersion are disruption, wetting, mixing and stabilization of the
pigments.
5. Recover
The dust that is emitted during raw material measuring can be collected and be used as input
material for dispersion or other processes/products.
6. Reduce
The dust emissions that are produced during disperser loading can be reduced through
modification of the feeding system.
7. Recover
The dust that is emitted during dispersion can be collected and be segregated and used as input
material for dispersion or other processes/products.
The amount of dust that is emitted to the atmosphere is about 7.8g/m3 on average.
6.1.3 Scenarios
Three different scenarios have been studied, that is, optimistic, realistic and worst-case:
119
Process optimization using Design for Environment concept in the input material of the disperser
unit
The optimistic scenario is what is desired to be the situation in the plant during feeding
operation.
Worst-case scenario is chosen to demonstrate the benefit of reducing and recovering pigment
dust.
120
Process optimization using Design for Environment concept in the input material of the disperser
unit
6.1.4 Results
The results of the LCA for disperser feeding are presented below.
6.1.4.1 Scenario 2
Energy consumption
The total energy consumption for the whole life cycle of the process is not known
Resource consumption
The main raw materials used in disperser feeding to produce 10 000litres: about 6000kg of
pigment and 4000kg of water.
121
Process optimization using Design for Environment concept in the input material of the disperser
unit
About 60% of dust emissions are from disperser feeding as a result of fly out dust and empty
raw material bags, 30% occurs during raw material measuring and 10 % is from the dispersion
process.
122
Process optimization using Design for Environment concept in the input material of the disperser
unit
This dust was not segregated but it mainly constituted titanium oxide, talc, kaolin, dolomite
(whiting), and carbon black. The concentration of each chemical in the dust would depend on the
type of paint being produced since the quantity of chemical fed depends on paint type as shown
in Table 6.1 and Fig 6.3 that follows.
Table 6.1: Raw material usage
SUP 1 DUP1 ACW
Consumption
kg % kg % kg %
Titanium
dioxide 1792 30 3350 62 261 14
Talc 6 0 17 0 12 1
Whiting 48 1 44 1 3 0
Kaolin 6 0 15 0 267 15
Iron
oxide 1734 29 1670 31 1260 70
Carbon
black 2384 40 300 6 0 0
123
Process optimization using Design for Environment concept in the input material of the disperser
unit
124
Process optimization using Design for Environment concept in the input material of the disperser
unit
Fig 6.4: Emissions to air for the feeding operation life cycle - Comparison of scenarios.
6.2 CONCLUSION
In order to reduce dust emissions, and resource consumption, either the reduce option should be
adopted or the recover process is made more efficient.
125
Process optimization using Design for Environment concept in the input material of the disperser
unit
CHAPTER SEVEN:
PRODUCT SYTHESIS
7.0 INTRODUCTION
After applying CPA, ISO 14 001 and LCA as DFE tools, the next step is to begin designing,
developing and prototyping the new product. According to the CPA, the identified option must
be able to reduce dust emissions during disperser feeding. With ISO 14001 implementation,
there should be improved environmental performance as the organisation seeks to minimize
waste arising, and reduce harmful emissions and from L C A , t h e opportunity should achieve
environmental improvements by reducing environmental burden.
This chapter explore the optimal solution generation for the recommended DFE product.
126
Process optimization using Design for Environment concept in the input material of the disperser
unit
Principle of Operation
The vibratory feeder unit is available in multiple different trough designs allowing the best
possible metered flow for dry powders. In a pneumatic feeder system, a compressed gas supply
with minimal flow is required to operate the unit which has the amplitude and frequency
adjustments through the supplied manifold. Fig 7.1 shows an example of a Vibro-feeder.
Design analysis
Functionality
This design has an easy adjustment of feed rate with a capacity of 20g/hr to 5kg/hr. It can allow
the best possible metered flow for dry powders.
127
Process optimization using Design for Environment concept in the input material of the disperser
unit
Safety
The design is designed for the lab and R&D environment where explosion proof area
classification will prevent the use of any other vibratory feeder.
Maintainability
This design is fairly is easy to maintain as it may require highly skilled manpower for the
maintenance operations. It however, has a standard design hence modular components are used
to allow for interchangeability and serviceability.
Easy of manufacture
This design cannot be manufactured easily as specialized skills are required to produce it though
terms of actual production; CAD/CAM/CAE software can be employed to reach the required
design specifications.
Cost
This design is expensive to manufacture since most of the technologies required to manufacture
are not readily available.
Principle of Operation
Screw conveyors are used horizontally or at a slight incline as an efficient way to move semi-
solid materials. A screw thread runs through the centre of a container, which dispenses amounts
of powder as it rotates, thus with each revolution of the screw, a fixed volume of material is
discharged. Screw conveyors are always control fed at the inlet by another conveyor or metering
device. Rotary valves, screw feeders, belt conveyors, grinders, or even other screw conveyors
128
Process optimization using Design for Environment concept in the input material of the disperser
unit
typically are connected to the inlet of a screw conveyor. Fig 7.2 that follows is an example of a
screw conveyor at an inclination.
Design analysis
Functionality
The machine is capable of meeting the required production rate of 1600kg/hr without any
difficulties. They can also reach required height of 3.5m since they can go up to 7.5m in length.
The design is semi-automated to reduce the human interaction.
Safety
This machine can design for safety to both the operator and the environment through the
incorporation of a trough cover which most manufacturers recommend to be put in-place before
an operations can start. Safety guards are also provided for dangerous components.
129
Maintainability
This design has mechanical mechanisms which can be maintained without problems. All
machine components are easily accessible on this machine. The machine is made of standard
components which are interchangeable.
Easy Of Manufacture
Local material is used for all components on this machine. The machine can be reduced to
subassemblies which can be manufactured easier then used to build the machine.
Cost
The cost of this design is fairly low since most of the components required on this machine are
readily available.
Principle of Operation
By using techniques such as the Labman pin feeder, a set volume of powder can be rapidly
dispensed into vials, containers, tubes and dishes. This volume, as the density of the powders is
consistent, results in highly accurate and reproducible dispenses. Powders that differ in density
and consistency are fed in smaller dispenses, with multiple dispenses to achieve the final weight.
An illustration of a pin feeder is given in Fig 7.3 that follows.
130
Process optimization using Design for Environment concept in the input material of the disperser
unit
Design analysis
Functionality
This design is fully automated. Nevertheless, the required production rate of 1600kg/hr is
difficult to meet with this design since the machine is designed for smaller production volumes
which make use of smaller dispenses.
Safety
Chemicals having considerable calorific value can be harmful and this includes aluminium dust
and the dust of other metals. The greatest care should be used in handling them. To minimize the
danger of dust explosion resulting adequate ventilation must be provided. A water wash wet
collector should be used.
Maintainability
This design requires skilled manpower because of the precisions that are required in its
operations which otherwise makes it difficult to maintain.
131
Process optimization using Design for Environment concept in the input material of the disperser
unit
Easy of manufacture
This design is difficult to manufacture as high precision is required so that it can also disperse
powders with greater accuracy.
Cost
This design use compressed air which might not be available at the intended work place. The
extra cost of buying a compressor for this machine will eventually increase the cost of the
machine. This design is only cheap were air lines are already installed.
Selection Criterion
After analysis of each design the three solutions are compared against each other in order to find
the most suitable one for the problem at hand using a decision matrix. The attributes discussed in
the design analysis for each solution were used as the basic factors for the selection process.
Functionality 30 15 25 15
Product Safety 30 25 30 15
Cost 10 5 6 3
Manufacturability. 20 10 15 8
Maintainability. 10 5 6 4
Total 100 60 82 45
132
Process optimization using Design for Environment concept in the input material of the disperser
unit
7.2 CONCLUSION
From the decision matrix solution 2 which is a screw conveyor proves to be the best for the
desired application. The design can reach the desired capacity of conveyance of 1600kg/hr and
has greater safety which reduces risks to the human and the environment. There are no
complicated manufacturing methods required for this design as this design has already find wide
application in powder conveyance such as for stock feeds, grains, cereals and wastes.
The researcher recommends this design for process optimization for disperse feeding as it is
capable of feeding raw materials in the disperser unit with minimum dust emissions. The design
details to be used in the screw conveyor are found in Appendices.
133
Process optimization using Design for Environment concept in the input material of the disperser
unit
CHAPTER EIGHT:
8.0 INTRODUCTION
This chapter presents the research conclusions on objectives achievement. Recommendations are
also made that aid in other beneficial improvements in the PVA paint plant.
8.1 CONCLUSIONS
The application of DFE tools helped to meet the set research objectives as follows;
Objective 1
To come up with a design that will reduce dust emissions by 56%
Results
The assessment carried out through Cleaner Production and Life Cycle resulted in the
identification of a DFE product that reduces dust emissions from a maximum of 7.8g/m 3 to a
threshold value of 5g/m3. Further to this, a DFE product was synthesized and design
specifications are given. This objective was successfully achieved.
Objective 2
To reduce potential health hazards in the plant by 50%
Results
The implementation of ISO 14 001 at Astra Paints improves environmental performance thus
consequently reducing risks and related potential health effects. Also the implementation of CPA
and LCA identify a DFE product that reduces dust emissions and health risks at the same time.
There, this objective was achieved.
Objective 3
134
Process optimization using Design for Environment concept in the input material of the disperser
unit
8.2 RECOMMENDATIONS
Employer has the duty to arrange any appropriate health checks provide for the employees under
Regulation 11 COSHH (2002) which they are exposed to substances hazardous to health. Health
surveillance is important which the work-related ill health of the employees will be detect the
early signs of the ill health so the control measures can be taken to control it.
Employer should provide adequate PPE in the plant. PVC gumboots should be provided to
reduce exposure to chemicals to operators. Other face masks which are more protective should
be provided to reduce inhalation of dust particles since the current ones in use are allowing dust
inhalation witnessed in nose discharge, (see attached questionnaire).
All employers must carry out a risk assessment. Under regulation 6 COSHH (2002) mention that
a COSHH risk assessment of the risk health that involve hazardous in substances should be
carried out. Approve Code of Practice ACOP is required to carry out the risk assessment as
required under the guidance which to reduce the hazard in the workplace. Employer should
ensure that the person who does the risk assessment and the inspection are competent person to
135
Process optimization using Design for Environment concept in the input material of the disperser
unit
the job. Risk assessments are recorded and are circulated to all employees and employer so they
are familiar with those risk and hazard. This reduces potential health hazards in the plant.
8.2.4 Training
Adequate training should be provided to operators so that they become conscious about risks
posed to them by the chemicals they handle. This ensures that they follow operational procedures
when carrying out their duties. They will be substantive reduction in potential health hazards.
8.3 CONCLUSION
The researcher recommends DFE technology for process optimization not only at the company
under study but other manufacturing entities. To prevent potential health risks associated with
pigment dust exposure, the mentioned recommendations should be implemented. It is essential
that the employer provides a safe workplace to prevent and minimize the possibility of ill health
that might be exposed to employees at work. Implementation of the control measures and
recommendations can benefits the company to protect its reputation as well as not to breach any
of the current health and safety legislation to avoid any unnecessary compensation claim.
136
Process optimization using Design for Environment concept in the input material of the disperser
unit
137
Process optimization using Design for Environment concept in the input material of the disperser
unit
REFERENCES
1. Boyce, C, Neale, P, (2006), Conducting In-Depth Interviews: A Guide for Designing and
Conducting In-Depth Interviews for Evaluation Input, Pathfinder International Tool
Series
2. CEMA, 2003, Standard 550, Classification and definition of bulk materials, Approved
November, 14, 2003
3. COWI Consulting Engineers and Planners, Cleaner Production Assessment in Fish
Processing for United Nations Environment Programme Division of Technology,
Industry and Economics And Danish Environmental Programme, AS, Denmark
4. Darozhka, S, 2006, Cleaner Production Assessment, Borki-Molo, BUP EM Course
Teachers Conference, 30 June 2006
5. Dawson, C., 2002, Practical Research Methods, New Delhi, UBS Publishers’ Distributors
6. Dawson, Catherine, 2002, Practical Research Methods, New Delhi, UBS
Publishers’Distributors
7. DeWalt, K, M. & DeWalt, B, R. (2002). Participant observation: a guide for
fieldworkers. Walnut Creek, CA: AltaMira Press.
8. Dong, Z., 2006, Tutorials for Pro/Engineer Wildfire 2.0, Department of Mechanical
Engineering University of Victoria January 15, 2006
9. Groover, M.P, 2007, Automation, Production Systems and Computer-Integrated
Manufacturing, 2nd Edition
10. http://asq.org/learn-about-quality/data-collection-analysis-tools/overview/design-of-
experiments.html Accessed 0n 30 March 2012
138
Process optimization using Design for Environment concept in the input material of the disperser
unit
139
Process optimization using Design for Environment concept in the input material of the disperser
unit
29. Kaolin. Review of Natural Products. Facts & Comparisons 4.0. June 2008. Accessed July
22, 2008.
30. Kawulich, B.B, (2005), Participant Observation as a Data Collection Method, Journal
on: Qualitative social research forum, Volume 6, No. 2, Art. 43 – May 2005
31. Key. J.P., 1997, Research Design in Occupational Education, Oklahoma State University
32. Khandani, S, (2005), Engineering Design Process, Education Transfer Plan
33. Kothari, C.R., 1985, Research Methodology- Methods and Techniques, New Delhi,
Wiley Eastern Limited.
34. Kothari, C.R.,1985, Research Methodology- Methods and Techniques, New Delhi,Wiley
Eastern Limited.
35. Kulwiec, R.A., 1981, Basics of Material Handling, Material Handling Institute,
Pennsylvania
36. Kumar, Ranjit, 2005, Research Methodology-A Step-by-Step Guide for Beginners,
(2nd.ed.), Singapore, Pearson Education.
37. Marshall, C; Rossman, G.B. (1989). Designing qualitative research. Newbury Park, CA:
Sage. (p.79).
38. Marshall, C; Rossman, G.B. (1995). Designing qualitative research. Newbury Park, CA:
Sage.
39. MHIA, 2006, the Material Handling Industry of America Annual Report.
40. National Institute of Occupational Health and Safety, NIOSH
41. P. Elefsiniotis, D. G. Wareham, 2005, ISO 14000 Environmental Management Standards:
Their Relation to Sustainability, Journal of Professional Issues in Engineering Education
and Practice, Vol. 131, No. 3
42. Quality Network, 2005, Paper on International Standard ISO 14000.
43. Roberts, A.W, 2001, Design Considerations And Performance Evaluation Of Screw
Conveyors, paper presented at the Proceedings BELTCON 11
44. SAPMA, 2010, SAPMA Paint Technology course, ‘Basic Technology SC01’
140
Process optimization using Design for Environment concept in the input material of the disperser
unit
45. Schensul, S.L.; Schensul, J.J. and LeCompte, M.D, (1999), Essential ethnographic
methods: observations, interviews, and questionnaires (Book 2 in Ethnographer's
Toolkit). Walnut Creek, CA: AltaMira Press
46. Starkey, R, 1996, “The Standardization of Environmental Management Systems.”
Corporate Environmental Management Systems And Strategies, R. Welford, Ed.,
Earthscan, London, 59-61
47. U.S. Environmental Protection Agency, Control of VOC emissions from Ink and Paint
Manufacturing Processes, April 1992, EPA-450/3-92-013.
48. UN, 2001, Paper on Cleaner Production and Eco-efficiency. Complementary Approaches
to Sustainable Development. United Nations Environment Program and the World
Business Council for Sustainable Development
49. UNEP 1999 Centre for Cleaner Production and The CRC for Waste Minimisation and
Pollution Control, Ltd October 1999 Cleaner Production Self Assessment Guide Metal
Casting Industries
50. United Nations Environment Program, UNEP,1989, International Declaration on Cleaner
Production
51. US EPA, 1990, Guides To Pollution Prevention: The Paint Manufacturing Industry,
Risk Reduction Engineering Laboratory and Center for Environmental Research
Information Office of Research and Development, U.S. Environmental Protection
Agency Cincinnati, Ohio
52. USEPA 1979. U. S. Environmental Protection Agency, Office of Water and Waste
Management. Development document for proposed effluent limitation guidelines, new
source performance standards, and pretreatment standards for the paint formulating point
source category. EPA-440-1-79-049b. Washington, D.C. U.S. Environmental Protection
Agency.
53. Washington State, 1998, Air Toxic Sources and Emission Estimation Methods,
Department of Ecology, Facility/Site on the Web, Accessed 28 February 2012.
141
Process optimization using Design for Environment concept in the input material of the disperser
unit
142