Bills of Quantities for CAK
Bills of Quantities for CAK
VOLUME I
EMPLOYER
MARCH 2022
TRADE PREAMBLES
TRADE PREAMBLES
PREAMBLES AND PRICING NOTES
A. GENERALLY
All work to be carried out in accordance with the Ministry of Public Works General
Specifications for Building Works issued in 1976 or as qualified or amended below.
B. MANUFACTURERS’ NAMES
Manufacturers’ names and catalogue references are given for guidance to quality and
standard only. Alternative manufacturer of equal quality will be accepted at the
discretion of the Project Manager.
C. WALLING
All precast concrete blocks shall be manufactured by the methods and to the sizes
specified in the Ministry of Public Works “Specification for Metric Sized Concrete
Blocks for Building (1972)”
Walling of 100 mm thickness or under shall be reinforced with hoop iron every
alternate course.
Prices for walling must allow for all costs in preparing, packing and sending sample
blocks for testing as and when required by the Project Manager.
D. CARPENTRY
The grading rules for cypress shall be the same for Podocarpus and all timber used for
structural work shall be select (second grade).
All structural timber must conform to the minimum requirements for moisture content
and preservative treatment and timber prices must allow for preparing, packing and
sending samples for testing when required.
PN/1
A. JOINERY
Cypress for joinery shall be second grade in accordance with the latest grading rules
of the Kenya Government
Where Mahogany is specified, this refers to prime grade only. The Contractor may
with the approval of the Project Manager; use either Msharagi or Mvuli in lieu of
Mahogany but such approval will be given only in the case of shortages of the
hardwoods specified.
Plugging shall be carried out by drilling walling or concrete with masonry drill and
filling with propriety plugs of the correct sizes. Cutting with hammer and chisel will
not be allowed.
Prices for joinery must include for pencil rounded arises, protection against damage,
nails, screws, framing and bedding in cement mortar as required.
Sizes given for joinery items are nominal sizes and exact dimensions of doors, etc.,
must be ascertained on site.
B. IRONMONGERY
Ironmongery shall be specified in the Bills of Quantities or equal and approved
Prices must include for removing and re-fixing during and after painting, labeling all
keys, and for fixing to hardwood, softwood, concrete or blockwork.
Catalogue references given for ironmongery are for purposes of indicating quality and
size of item(s). Should the Contractor wish to substitute the specified item(s) with
others of equal manufacture, he must inform the Project Manager and obtain approval
in writing. No Ironmongery shall be fitted/installed without sample approvals.
C. STRUCTURAL STEELWORK
All structural steelwork shall comply with the Ministry of Public Works “Structural Steelwork
Specification (1973) and shall be executed by an approved Sub-contractor
PN/2
A. PLASTERWORK AND OTHER FINISHES
All finishing shall be as described in these Bills of Quantities.
Prices for paving are to include for brushing concrete clean, wetting and coating with
cement and sand grout 1:1.
Rates for glazed wall tiling are to include for a 12 mm cement and sand (1:4) backing
screed unless otherwise specified in these Bills of Quantities.
B. GLAZING
Where polished plate glass is specified, this refers to general glazing quality
Prices for glazing shall include for priming of rebates before placing putty.
The Contractor will be responsible for replacing any broken or scratched glass and
handing over in perfect condition.
C. PAINTING
Painting shall be applied in accordance with the manufacturers’ instructions.
Prices for painting are to include for scaffolding, preparatory work, priming coats,
protection of other works and for cleaning up on completion. Prices for painting on
galvanized metal are to include for mordant solution as necessary.
The bidder shall be deemed to have priced the best materials for this esteemed
office. No curtains & covers shall be fitted/installed without sample approvals.
No claim shall be allowed on the grounds that the bidder priced an inferior quality.
PN/3
PARTICULAR PRELIMINARIES
ITEM DESCRIPTION AMOUNT
PARTICULAR PRELIMINARIES
EMPLOYER
A The "Employer" is COUNTY ASSEMBLY OF KILIFI - P.O BOX 332 - 80200 MALINDI
The term "Employer" and "Government" wherever used in the contract document shall be
synonymous
PROJECT MANAGER
B The term 'Engineer' shall mean the "PM" wherever used in these Bills of Quantities and shall be
deemed to imply the project Manager as defined in Condition 1 of the Conditions of Contract or
such person or persons as may be duly authorised to represent him on behalf of the Government .
ARCHITECT
C The term "Architect" shall be deemed to mean "The P.M " as defined above whose address unless
otherwise notified shall be appointed by the Employer
QUANTITY SURVEYOR
D The term "Quantity Surveyor" shall be deemed to mean "The P.M " as defined above whose
address unless otherwise notified shall be appointed by the Employer
E ELECTRICAL ENGINEER
The term "Electrical Engineer" shall be deemed to mean "The P.M " as defined above whose
address unless otherwise notified shall be appointed by the Employer
MECHANICAL ENGINEER
F The term "Mechanical Engineer" shall be deemed to mean "The P.M " as defined above whose
address unless otherwise notifiedshall be appointed by the Employer
STRUCTURAL ENGINEER
G The term "Structural Engineer" shall be deemed to mean "The P.M " as defined above whose
address unless otherwise notifiedshall be appointed by the Employer
Carried to collection
A Prices SHALL BE INSERTED against items of “preliminaries” in the tenderer’s priced Bills of
Quantities. The contractor is advised to read and understand all preliminary items.
B The works to be carried out under this contract comprises the completion of the office block of
the County Assembly of Kilifi and support buildings, civil works, lift installations and
associated mechanical and electrical works to be carried out by nominated and domestic
subcontractors
SCOPE OF WORKS
C The works to be carried out under this contract comprise of: the completion of the office block of
the County Assembly of Kilifi and support buildings, civil works, lift installations and associated
mechanical and electrical works to be carried out by nominated and domestic subcontractors
MEASUREMENTS
D In the event of any discrepancies arising between the Bills of Quantities and the actual works, the
site measurements shall generally take precedence. However, such discrepancies between any
contract documents shall immediately be referred to the PROJECT MANAGER in accordance
with Clause 22 of the Conditions of Contract. The discrepancies shall then be treated as a
variation and be dealt with in accordance with Clause 22 of the said Conditions.
LOCATION OF SITE
E The site is located at the County Assembly of Kilifi, Malindi Town, Kilifi County. The
Contractor is advised to visit the site, to familiarize with the location of the project. No claims
arising from the Contractor’s failure to do so will be entertained.
Carried to collection
A The bidder shall append his / her signature and / or company ‘s rubberstamp on each and every
page of tender document.
B The Contractor is to allow for all temporary protection required during the works including
ordinary and special dust screens, hoardings, barriers, warning signs, etc as directed by the Project
Manager and as necessary for the adequate propping and protection of existing property, finishes,
workmen employed on the site, employer's agents and the public. Any damage or loss incurred
due to the insufficiency of such protection must be made good by the Contractor. All protective
devices are to be removed on completion of the works and any necessary making good consequent
upon this is to be excecuted to the satisfaction of the Project Manager
The works shall be propped, strutted and supported as necessary before any alteration or
demolition work commences. Prices shall include for all cleaning and preparatory work to
structure and finishes and for making good to all finishes on completion whether or not
specifically described.
Unless described as set aside for re-use all arising debris and surplus materials shall be carefully
removed from building and carterd away from site.
The Contractor shall be entirely responsible for any breakage or damage which may occur to
materials required for re-use during their removal unless it is certified by the Project Manager that
such damage or breakage was inevitable as a result of the condition of the item concerned
CLEARING AWAY
C The Contractor shall remove all temporary works, rubbish, debris and surplus materials from the
site as they accumulate and upon completion of the works, remove and clear away all plant,
equipment, rubbish, unused materials and stains and leave in a clean and tidy state to the
reasonable satisfaction of the Project Manager.
D The whole of the works shall be delivered up clean, complete and in perfect condition in every
respect to the satisfaction of the Project Manager.
Carried to collection
A It shall be a condition of this contract that upon it becoming reasonably apparent to the Contractor
that he has incurred losses and / or expenses due to any of the contract conditions, or by any other
reason whatsoever, he shall present such a claim or intent to claim notice to the PROJECT
MANAGER within the contract period. No claim shall be entertained upon the expiry of the said
contact period.
PAYMENTS
B The Procuring Entity shall make an advance payment, as an interest-free loan for mobilization and
cashflow support, when the Contractor submits a guarantee in accordance with this Clause. The
total advance payment, the number and timing of instalments (if more than one), and the
applicable currencies and proportions, shall be as stated in the Special Conditions of Contract all
in accordance with Clause 14.2 of the Conditions of Contract Agreement. In order to facilitate
this, a list of the general component elements for the works is given at the summary page of these
specifications and the tenderer is requested to break down his tender sum commensurate to the
said elements
C The Contractor is notified that these works are to be carried out on a restricted site where the
client is going on with other nomal activities. The Contractor is thus instructed to take reasonable
care in the execution of the works as to prevent accidents, damage or loss and disruoption of
activities beeing carried out by the Client. The Contractor shall allow in his rates any expense he
deemed necessary by taking such care within the site.
WORKING CONDITIONS
D The Contractor shall allow in his rates for any interferance that he may encounter in the course of
the works for the Client may in some cases ask the Contractor not to proceed with the works until
some activities within the site are completed, as the facility will be operating as usual during the
course of the contract.
SIGNBOARD
E Allow for providing, erecting, maintaining throughout the course of the Contract and afterwards
clearing away a signboard as designed, specified and approved by the Project Manager.
Carried to collection
A The Contractor shall not be allowed to house labour on site. Allow for transporting workers to
and from the site during the tenure of the contract.
B Any materials arising from demolitions and not re-used shall become the property of the client.
The Contractor shall allow in his rates the cost of disposing the demolished materials as directed.
PRICING RATES
C The tenderer shall include for all costs in executing the whole of the works, including transport,
replacing damaged items, fixing, all to comply with the said Conditions of Contract.
D The Contractor is notified that these “works are urgent” and should be completed within the
period stated in these Particular Preliminaries.
The Contractor shall allow in his rates for any costs he/ she deems that he/she may incur by having
to complete these works within the stipulated contract period.
E All materials for incorporation in the works must be stored on site before payment is effected,
unless specifically exempted by the Project Manager. This is to include materials of the
Contractor, nominated sub-Contractors and nominated suppliers.
Carried to collection
EXISTING SERVICES
A Prior to the commencement of any work, the Contractor is to ascertain from the relevant authority
the exact position, depth and level of all existing services in the area and he/she shall make
whatever provisions may be required by the authorities concerned for the support, maintenance
and protection of such services.
The ‘PROJECT MANAGER’ shall strictly monitor the Contractors progress in relation to the
progress chart and should it be found necessary the ‘PROJECT MANAGER’ shall inform the
Contractor in writing that his actual performance on site is not satisfactory .In all such cases the
Contractor shall accelerate his rate of performance production and progress by all means such as
additional labour,plant, e.t.c and working overtime all at his cost.
PERFORMANCE BOND
C A bond of 5% of the contract sum will be required in accordance with clause 6.00 (as amended)
on award of contract of the Instructions to Tenderer’s. No payment on account for the works
executed will be made to the contractor until he has submitted the Performance Bond to the
Project Manager duly signed, sealed and stamped from an approved Bank or Insurance Company
approved by the Public Procurement Oversight Authority (PPOA).
TENDER DOCUMENTS
D Tender documents are as listed in Clause 2.1 of the Instruction to Tenderer’s Page STD/9
DELIVERY OF TENDER
E Tenders and all documents in connection therewith, as specified above must be delivered in the
addressed envelope which should be properly sealed and deposited at the offices as specified in
the letter accompanying these documents or as indicated in the advertisement.
Tenders will be opened at the time specified in the letter accompanying these Tender Documents
or as indicated in the advertisement. Tenders delivered/received later than the above time will not
be opened.
Carried to collection
A The Contractor’s attention is drawn to the Legal Notice in the Finance Act part 3 Section 21(b)
operative from 1st September, 1993 which requires payment of VAT on all contracts. The
Contractor should therefore include allowance in his rates and prices for prices for VAT and any
other Government taxes currently in force.
The tenderer is advised that in accordance with the Finance Act 2019 withholding VAT tax was
reintroduced at a rate of 2% with effect from 7th November, 2019
B NOTE: Any materials found usable for the works shall be given to the contractor on creidit with
the approval of the client
FORM OF CONTRACT
C The Form of Contract shall be as stipulated in the Republic of Kenya's Standard Tender Document
for Procurement of Building Works(2021 Edition) and its regulations included herein The
Conditions of Contract are also included herein Particulars of insertions to be made in the
Appendix to the Contract Agreement will be found in the Particular Preliminaries part of these
Bills of Quantities
Carried to collection
SPECIAL PRELIMINARIES
PROJECT MANAGEMENT EXPENSES
A Allow a sum of Two Million, Five Hundred Thousand (Ksh. 2,500,00.00) Kenya Shillings only
for subsistence allowances for the project team for the whole of the project period 2,500,000.00
C Provide a sum of Eight Hundred and Fifty Thousand (Kshs 850,000.00) Kenya Shillings only for 850,000.00
Project manager's stationery and documentation
Transport
The contractor shall provide for site trips only a vehicle of type Toyota or Nissan Van to
comfortably seat Nine persons including maintaining licences and insurances, competent driver:
all to the satisfaction of the Project Manager.
The vehicle shall be provided specificaly for and during site visits by the Project Management
Technical team. The vehicle shall be in perfect conditions for the entire duration of the trip i.e.
from the Project Managers Office to Kilifi County Assembly and back tothe Project Managers
Office including Local running.
The driver shall be at the sole direction of the Project Manager for the entire duration of the trip,
until released by him /her
Reimbursement to the contactor for providing the transport services will be based per trip to the
site and back during the currency of the contract at a rate as herebelow (Contractor to insert rate
- Item E) inserted. Reimbursement to the contractor for providing driver, servicing, fuels, oils,
Lubricants and tyres will similarly be based per trip at a rate herebelow (Contractor to insert rate
- Item F) inserted.
E Allow for providing a vehicle as above described including maintaining licences and
compresensive insurance (……………….. X 15 TRIPS)
F Alow for providing driver, maintenance, fuels, lubricants spares and tyres (……………….. X15
TRIPS)
G Allow a sum of Six Hundred Thousand (Ksh. 600,00.00) Kenya Shillings only for subsistence
allowances for the clerk of works for the whole of the project period
Carried to Collection
The following are the insertions to be made in the appendix to the Contract Agreement: -
Liquidated and Ascertained At the rate of Kshs.. 20,000/= per day or part thereof:
Carried to Collection
COLLECTION
GENERAL PRELIMINARIES
A The Contractor shall be deemed to have included in his prices or rates for the various items
in the Bills of Quantities or Specification for all costs involved in complying with all the
requirements for the proper execution of the whole of the works in the Contract.
ABBREVIATIONS
B Throughout these Bills, units of measurement and terms are abbreviated and shall be
interpreted as follows:-
Carried to collection
A Attendance ; Clause B19(a) of the Standard Method of Measurement is deleted and the
following clause is substituted:-
Fix Only:-
"Fix Only" shall mean take delivery at nearest railway station (Unless otherwise stated),pay
all demurrage charges, load and transport to site where necessary, unload, store, unpack,
assemble as necessary, distribute to position, hoist and fix only.
FORM OF CONTRACT
B The Form of Contract shall be as stipulated in the Republic of Kenya's Standard Tender
Document for Procurement of Building Works (2021 Edition) included herein
Conditions of Contract
These are numbered from 1 to 20 as set out in pages 69 to 132 of these tender documents.
Carried to collection
A Allow for providing all scaffolding, plant, tools and vehicles required for the works except in
so far as may be stated otherwise herein and except for such items specifically and only
required for the use of nominated Sub-Contractors as described herein. No timber used for
scaffolding, formwork or temporary works of any kind shall be used afterwards in the
permanent work.
TRANSPORT.
B Allow for transport of workmen, materials, etc., to and from the site at such hours and by
such routes as may be permitted by the competent authorities.
C All materials and workmanship used in the execution of the work shall be of the best quality
and description unless otherwise stated. The Contractor shall order all materials to be
obtained from overseas immediately after the Contract is signed and shall also order
materials to be obtained from local sources as early as necessary to ensure that they are
onsite when required for use in the works. The Bills of Quantities shall not be used for the
purpose of ordering materials.
D The Contractor will be required to sign a receipt for all articles and materials supplied by the
PROJECT MANAGER at the time of taking deliver thereof, as having received them in
good order and condition, and will thereafter be responsible for any loss or damage and for
replacements of any such loss or damage with articles and/or materials which will be
supplied by the PROJECT MANAGER at the current market prices including Customs Duty
and V.A.T., all at the Contractor's own cost and expense, to the satisfaction of the
PROJECT MANAGER
STORAGE OF MATERIALS
E The Contractor shall provide at his own risk and cost where directed on the site weather
proof lock-up sheds and make good damaged or disturbed surfaces upon completion to the
satisfaction of the PROJECT MANAGER Nominated Sub-Contractors are to be made liable
for the cost of any storage accommodation provided especially for their use.
Carried to collection
A The Contractor shall furnish at his own cost any samples of materials or workmanship
including concrete test cubes required for the works that may be called for by the PROJECT
MANAGER for his approval until such samples are approved by the PROJECT MANAGER
and the PROJECT MANAGER, may reject any materials or workmanship not in his opinion
to be up to approved samples. The PROJECT MANAGER shall arrange for the testing of
such materials as he may at his discretion deem desirable, but the testing shall be made at
the expense of the Contractor and not at the expense of the PROJECT MANAGER. The
Contractor shall pay for the testing in accordance with the current scale of testing charges
laid down by the Ministry of Lands, Housing and Urban Development (State Department of
Public Works).
The procedure for submitting samples of materials for testing and the method of marking for
identification shall be as laid down by the PROJECT MANAGER The Contractor shall
allow in his tender for such samples and tests except those in connection with nominated sub-
contractors' work.
B Allow for complying with all Government Acts, Orders and Regulations in connection with
the employment of Labour and other matters related to the execution of the works. In
particular the Contractor's attention is drawn to the provisions of the Factory Act 1950 and
his tender must include for all costs arising or resulting from compliance with any Act,
Order or Regulation relating to Insurances, pensions and holidays for workpeople or so the
safety, health and welfare of the workpeople.
The Contractor must make himself fully acquainted with current Acts including Police
Regulations regarding the movement, housing, security and control of and Regulations,
labour, labour camps , passes for transport, etc. It is most important that the Contractor,
before tendering, shall obtain from the relevant Authority the fullest information regarding
all such regulations and/or restrictions which may affect the organisation of the works,
supply and control of labour, etc., and allow accordingly in his tender. No claim in respect of
want of knowledge in this connection will be entertained.
Carried to collection
B Maintain as required throughout the execution of the works and make good any damage to
public or private roads arising from or consequent upon the execution of the works to the
satisfaction of the local and other competent authority and the PROJECT MANAGER
EXISTING PROPERTY.
C The Contractor shall take every precaution to avoid damage to all existing property including
roads, cables, drains and other services and he will be held responsible for and shall make
good all such damage arising from the execution of this contract at his own expense to the
satisfaction of the PROJECT MANAGER
D The Contractor is recommended to examine the drawings and visit the site the location of
which is described in the Particular Preliminaries hereof. He shall be deemed to have
acquainted himself therewith as to its nature, position, means of access or any other matter
which, may affect his tender. No claim arising from his failure to comply with this
recommendation will be considered.
E Means of access to the Site shall be agreed with the PROJECT MANAGER prior to
commencement of the work and Contractor must allow for building any necessary temporary
access roads (approximately 70 metres long) for the transport of the materials, plant and
workmen as may be required for the complete execution of the works including the provision
of temporary culverts, crossings, bridges, or any other means of gaining access to the Site.
Upon completion of the works, the Contractor shall remove such temporary access roads;
temporary culverts, bridges, etc., and make good and reinstate all works and surfaces
disturbed to the satisfaction of the PROJECT MANAGER
Carried to collection
The area of the site which may be occupied by the Contractor for use of storage and for the
purpose of erecting workshops, etc., shall be defined on site by the PROJECT MANAGER
The contractor shall allow for beverages, snacks, soft drinks and water to be provided for
attendees of site inspections and site meetings on site.
WATER AND ELECTRICITY SUPPLY FOR THE WORKS
B The Contractor shall provide at his own risk and cost all necessary water, electric light and
power required for use in the works. The Contractor must make his own arrangements for
connection to the nearest suitable water main and for metering the water used. He must also
provide temporary tanks and meters as required at his own cost and clear away when no
longer required and make good on completion to the entire satisfaction of the PROJECT
MANAGER . The Contractor shall pay all charges in connection herewith. No guarantee is
given or implied that sufficient water will be available from mains and the Contractor must
make his own arrangements for augmenting this supply at his own cost. Nominated Sub--
contractors are to be made liable for the cost of any water or electric current used and for any
installation provided especially for their own use.
Carried to collection
A The Sanitation of the works shall be arranged and maintained by the Contractor to the
satisfaction of the Government and/or Local Authorities, Labour Department and the
PROJECT MANAGER
B The works shall be executed under the direction and to the entire satisfaction in all respects
of the PROJECT MANAGER who shall at all times during normal working hours have
access to the works and to the yards and workshops of the Contractor and sub-Contractors or
other places where work is being prepared for the contract.
PROVISIONAL SUMS.
C The term "Provisional Sum" wherever used in these Bills of Quantities shall have the
meaning stated in Section A item A7(i) of the Standard Method of Measurement mentioned
in Condition No. 12 of the conditions of Contract. Such sums are net and no addition shall
be made to them for profit.
D The term "Prime Cost Sum" or "P.C. Sum" wherever used in these Bills of Quantities shall
have the meaning stated in Section A item A7 (ii) of the Standard Method of Measurement
mentioned in Condition of Contract. Persons or firms nominated by the PROJECT
MANAGER to execute work or to provide and fix materials or goods as stated in the
Conditions of Contract are described herein as Nominated Sub-Contractors.
PROTECTIVE CLOTHING
E The Contractor shall provide all protective or any other special clothing or equipment for his
employees that may be necessary.This shall include, inter-alia, safety helmets, gloves,
goggles, earmuffs, gumboots, overalls, etc., according to the type of work. The Contractor
shall ensure that safety helmets are worn by all staff at all times.
Carried to collection
PROGRESS CHART.
A The Contractor shall provide within two weeks of Possession of Site and in agreement with
the PROJECT MANAGER a Progress Chart for the whole of the works including the works
of Nominated Sub-Contractors ; one copy to be handed to the PROJECT MANAGER and a
further copy to be retained on Site. Progress to be recorded and chart to be amended as
necessary as the work proceeds.
B In the final account all P.C. Sums shall be deducted and the amount properly expended upon
the PROJECT MANAGER'S order in respect of each of them added to the Contract sum.
The Contractor shall produce to the PROJECT MANAGER such quotations, invoices or
bills, properly receipted, as may be necessary to show the actual details of the sums paid by
the Contractor. Items of profit upon P.C. Sums shall be adjusted in the final account pro-rata
to the amount paid. Items of "attendance" (as previously described) following P.C. Sums
shall be adjusted pro-rata to the physical extent of the work executed (not pro-rata to the
amount paid) and this shall apply even though the Contractor's priced Bill shows a
percentage in the rate column in respect of them. Should the Contractor be permitted to
tender and his tender be accepted of any work for which a P.C. Sum is included in these Bill
of Quantities profit and attendance will be allowed at the same rate as it would be if the
work were executed by a Nominated Sub-Contractor.
Carried to collection
NOMINATED SUB-CONTRACTORS
B When any work is ordered by the PROJECT MANAGER to be executed by nominated sub-
contractors, the Contractor shall enter into sub-contracts as described in the Conditions of
Contract and shall thereafter be responsible for such sub-contractors in every respect. Unless
otherwise described the Contractor is to provide for such Sub-Contractors any or all of the
facilities described in these Preliminaries. The Contractor should price for these with the
nominated Sub-contract Contractor's work concerned in the P.C. Sums under the description
"add for Attendance".
DIRECT CONTRACTS
C Notwithstanding the foregoing conditions, the Government reserves the right to place a
"Direct Contract" for any goods or services required in the works which are covered by a
P.C. Sum in the Bills of Quantities and to pay for the same direct. In any such instances,
profit relative to the P.C. Sum the priced Bills of Quantities will be adjusted as described for
P.C. Sums and allowed.
D The Contractor shall allow for the attendance of trade upon trade and shall afford any
tradesmen or other persons employed for the execution of any work not included in this
Contract every facility for carrying out their work and also for use of his ordinary
scaffolding. The Contractor, however, shall not be required to erect any special scaffolding
for them. The Contractor shall perform such cutting away for and making good after the
work of such tradesmen or persons as may be ordered by the PROJECT MANAGER and the
work will be measured and paid for to the extent executed at rates provided in these Bills.
Carried to collection
PROVISIONAL WORK
C Any unauthorised alteration or qualification made to the text of the Bills of Quantities may
cause the Tender to be disqualified and will in any case be ignored. The Contractor shall be
deemed to have made allowance in his prices generally to cover any items against which no
price has been inserted in the priced Bills of Quantities.
All items of measured work shall be priced in detail and the Tenders Sums to cover trades
or groups of work must be broken down to show the price of containing Lump each item
before they will be accepted.
Carried to collection
BLASTING OPERATIONS
A Blasting will only be allowed with the express permission of the PROJECT MANAGER in
writing. All blasting operations shall be carried out at the Contractor's sole risk and cost in
accordance with any Government regulations in force for the time being, and any special
regulations laid down by the PROJECT MANAGER governing the use and storage of
explosives.
B Materials of any kind obtained from the excavations shall be the property of the
Government. Unless the PROJECT MANAGER directs otherwise such materials shall be
dealt with as provided in the Contract. Such materials shall only be used in the works, in
substitution of materials which the Contractor would otherwise have had to supply with the
written permission of the PROJECT MANAGER Should such permission be given, the
Contractor shall make due allowance for the value of the materials so used at a price to be
agreed.
C Provide protection of the whole of the works contained in the Bills of Quantities, including
casing , casing up, covering or such other means as may be necessary to avoid damage to the
satisfaction of the PROJECT MANAGER and remove such protection when no longer
required and make good any damage which may nevertheless have been done at completion
free of cost to the Government.
D Clean and flush all gutters, rainwater and waste pipes, manholes and drains, wash (except
where such treatment might cause damage) and clean all floors, sanitary fittings, glass inside
and outside and any other parts of the works and remove all marks, blemishes, stains and
defects from joinery, fittings and decorated surfaces generally, polish door furniture and
bright parts of metalwork and leave the whole of the buildings watertight, clean, perfect and
fit for occupation to the approval of the PROJECT MANAGER
Carried to collection
A For the full description of materials and workmanship, method of execution of the work and
notes for pricing, the Contractor is referred to the Ministry of Roads and Public Works and
Housing General Specification dated 1976 or any subsequent revision thereof which is
issued as a separate document, and which shall be allowed in all respects unless it conflicts
with the General Preliminaries, Trade Preambles or other items in these Bills of Quantities.
TRAINING LEVY
B The Contractor's attention is drawn to the legal notice which requires payment by the
Contractor of a Training Levy at the rate of 1/4 % of the Contract sum on all contracts of
more than KShs. 1,000,000.00 in value.
MATERIALS ON SITE
C All materials for incorporation in the works must be stored on or adjacent to the site before
payment is effected unless specifically exempted by the PROJECT MANAGER. This
includes the materials of the Main Contractor, Nominated Sub-Contractors and Nominated
Suppliers.
HOARDING
D The Contractor shall enclose all the site or part of the works under construction with a
hoarding 2400 mm high consisting of iron sheets on 100 x 50 mm timber posts firmly
secured at 1800 mm centres with two 75 x 50 mm timber rails. The Contractor is in addition
required to take all precautions necessary for the safe custody of the works, materials, plant,
public and Employer's property on the site.
Approximately …......metres at ……………… per metre
E The Contractor shall constantly keep on the works a literate English speaking Agent or
Representative, competent and experienced in the kind of work involved who shall give his
whole experience in the kind of work involved and shall give his whole time to the
superintendence of the works. Such Agent or Representative shall receive on behalf of the
Contractor all directions and instructions from the Project Manager and such directions shall
be deemed to have been given to the Contractor in accordance with the Conditions of
Contract.
Carried to Collection
COLLECTION
DEMOLITIONS
Walling
Demolish existing copings; 300 mm x 100 mm extreme thick;
dispose as directed by the project manager; and prepare
A ITEM
surfaces to receive new walling; Approx. 160metres
Concrete
Allow for demolitions to reveal starter bars in concrete; and
prepare surfaces to receive fresh concrete in;
Roofing
Carefully bring down existing shingle tiles and store for
E ITEM
reuse; Approx. 325 square metres
50mm Thick mass concrete 1:4:8: class 7.5/20 in: blinding to:
A Steps 58 SM
Formwork
Sawn formwork to:
F Floor bed: (measured nett; allow for laps): allow for joining
17 SM
new BRC to existing
Filling
Anti-termite treatment
Sundries
K wall ties; 25 x 450 mm 2,380 NO
Element No. 3
SUPERSTRUCTURE
Formwork to:
Sundries
R wall ties; 25 x 450 mm 2,890 NO
Element No. 4
STAIRCASE
Sawn formwork : to
J Sides of beams 69 SM
K Sides of columns 8 SM
Finishes.
34mm Thick cement and sand 1:4 cement and sand 1:4
screed finished to receive 6mm thick epoxy floor finish
(measured separately) in:
P Landings 95 SM
A Landings 95 SM
Prepare and apply three coats 1st grade silk vinyl emulsion
paint : to
H Textured ceiling surfaces; internally 211 SM
BALUSTRADES
75 x 75mm mvule handrail: on 75mm moulded mvule
balusters at regular spacing plugged to wall/concrete:
profiled as required by Architect to detail and subsequent
approval
Element No. 5
C 25 mm -12 mm 9,540 KG
D 10 mm 3,180 KG
Marineply formwork : to
E soffits of slab 11 SM
FINISHES
Metal Work
H Lift hooks; 12 mm diameter x 1000 mm long 2 No.
Floor Finishes
1:3 cement/sand backing screed: on floors
J Cement screeds with integral hardener; 50 mm thick 11 SM
Wall Finishes
15mm Cement/sand (1:4) render: finished to approval &
satisfaction of the Architect: on
K Plaster; 15 mm thick; to walls to receive cladding 70 SM
Ceiling Finishes
15mm thick Neeru plaster: on ceilings; prepared to receive
new coats of paint
M Ceilings 11 SM
EXPOSED FINISHES
8mm thick 200 x 400mm Italian ceramic wall tiles; Allow for
fixing with 'sealmaster 101' or equal and approved tile
adhesive: jointed and pointed in 'sealmaster 201' grout: clean
with approved detergent and apply 'Johnson wax' polish:
allow for tile spacers: in
A Fix only wall tiles 70 SM
Element No. 6
WALLING
External walls
Internal walls
Coping
Insitu coping; 300 x 100mm extereme thick; twice throated
F 103 LM
Sunshading
Insitu concrete : class 25/20 : vibrated : reinforced
G 75mm thick window hood 15 CM
Formwork
J Horizontal soffits of window hoods 80 SM
Lintols
Precast concrete units : class 25/12mm : vibrated : reinforced:
weathered: Throated: including hoisting into position:
(provisional)
Window cill
275mm Wide clay brick window cill from Kenya Clay
C Products or other equal and approved : grooved water bar : 127 LM
cement wash finished in all exposed surfaces.
Element No. 7
Roof Cover
Zinc coated galvanised shingle aluminium roofing sheets : 26
gauge sheets (Provide at least 15years guarantee); fixed on
timber trusses; at least 3m above existing ground level; Slope
not exceeding 45 degrees
Rainwater Goods
Sheet metal : 26 gauge Aluminium sheets (Provide at least
15years guarantee)
Roof Structure
The following in 3mm thick steel frames; 6fw continuous
fillet welding to BS5135; open ends blanked off in 3mm thick
mild steel plates; primed with 2coats of zinc chromate and
painted with 3 coats gloss oil paint to structural engineers
approval.
Coping
Insitu coping; 300 x 100mm extereme thick; twice throated
36 LM
Waterproofing
H SBS to flat areas 1770 SM
Element No. 8
FINISHES
F Floors 8366 SM
F External walls 12 SM
G External walls 72 SM
8mm thick 200 x 400mm Italian ceramic wall tiles; Allow for
fixing with 'sealmaster 101' or equal and approved tile
adhesive: jointed and pointed in 'sealmaster 201' grout: clean
with approved detergent and apply 'Johnson wax' polish:
allow for tile spacers: in
C External walls 72 SM
D External walls 22 SM
E Disabled WC 70 LM
Gypsum board
Acoustic ceiling
Panelling
25mm thick solid mahogany panels with grooves; fixed to
masonry/ concrete surfaces fixed on and including 50 x 25
mm wrot celcure grounds: 150mm x 50mm thick moulded
podo beading to edges of panels : 100 x 25mm architrave:
polished
Carpet tiles
F Floors 376 SM
Division strips
40 x 3 mm polished brass strips set between different floor
H 23 LM
finishes (Provisional)
Element No. 10
Kitchen Cupboards;
Low level kitchen cabinet: comprising; Plastified sheet metal
frame with open undercarriage; 20mm stainless steel
worktop and 100mm high backsplash; Laminated hardwood
sides and doors: 100mm high stainless steel fascia bonded to
concrete base with approved adhesive: opening for a
commercial kitchen sink: 75mm thick concrete (1:3:6)
reinforced in BRC Mesh type A142 : 100mm concrete (1:3:6)
plinth finished in cement screed: piano hinges, brass door
and drawer knobs: to detail as described
Bar Counters;
Ditto but; bar counter with curved bulge at the middle,
(overall) size 3000 x 940 x 1200mm : comprising steel frame
supports covered with and including 25mm polished solid
mahogany panels to front and sides; provision for fixing
artwork to the front : 25mm thick polished black marble top
and fascia, fixed with approvedadhesive to and including
25mm thick blackboard base fixed on RHS framing
provision for downlighter below the fascias : 150 mm high
moulded skirting : (Architects detail no. --)
Vanity Tops
75mm Thick concrete class 25/20 vanity tops and fascia :
fabric mesh reinforcement A142 : allow for 100mm high
splash back : 150mm high fascia : form opening for wash
basins : rounded edges; allow for all formwork and chasing
in blockwalls or concrete
Reception Counter
Storage cabinets
SUMMARY Page
C SUPERSTRUCTURE OB/3
D STAIRCASE OB/6
F WALLING OB/10
H FINISHES OB/17
Element No. 1
Excavations
Bulk excavation to remove vegetable soil : commencing at
A existing ground level : not exceeding 1500mm deep 13 CM
Filling
J 50mm Thick stone dust blinding to hardcore surfaces. 5 CM
Anti-termite treatment
Chemical anti-termite treatment to subsoil or filling: Dragnet
38% E.C. or equal approved: applied strictly to
L manufacturers written specification: provide a ten year 60 SM
guarantee
OUT-BUILDING PB/1
ITEM DESCRIPTION QTY UNIT RATE AMOUNT
Concrete
B Mass concrete; Mix 1:4:8-20; blinding; 50 mm thick 2 CM
Reinforcement
High yield ribbed and/or round reinforcement bars to BS
4461 & 4449 respectively: allow for cutting, bending, tying
and hoisting (Provisional)
J Bars; 8 mm 201 KG
Floor bed: (measured nett; allow for laps): allow for joining
K new BRC to existing 40 SM
Formwork to:
L sides of columns 7 SM
OUT-BUILDING PB/2
ITEM DESCRIPTION QTY UNIT RATE AMOUNT
Sundries
A Wall ties 25 x 450 mm 64 NO
Waterproofing
1000g Polythene damp proof membrane laid under floor bed
C with 300mm side and end laps (measured nett allow for 60 SM
laps)
Reinforcement
High yield ribbed and/or round reinforcement bars to BS
4461 & 4449 respectively: allow for cutting, bending, tying
and hoisting (Provisional)
H Bars; 8 mm 1100 KG
Formwork to:
J soffits of slab 46 SM
L sides of columns 16 SM
Sundries
N Wall ties 25 x 450 mm 128 No.
OUT-BUILDING PB/3
ITEM DESCRIPTION QTY UNIT RATE AMOUNT
Waterproofing
E 150mm Wide bituminous felt damp proof course 49 LM
Coping
Insitu coping; 300 x 100mm extereme thick; twice throated
G 37 LM
Roofing
COVERING AND LININGS
H SBS to flat surfaces 70 SM
OUT-BUILDING PB/4
ITEM DESCRIPTION QTY UNIT RATE AMOUNT
Lintols
Precast concrete units : class 25/12mm : vibrated :
reinforced: weathered: Throated: including hoisting into
position: (provisional)
C Lintels; 200 x 200 mm; reinforced 11 LM
Window cill
275mm Wide clay brick window cill from Kenya Clay
D Products or other equal and approved : grooved water bar : 4 LM
cement wash finished in all exposed surfaces.
FINISHES
Floor Finishes
1:3 cement/sand backing screed: on floors
E Floors screeds; 30 mm thick; finished to receive tiles 38 SM
F Floors 38 SM
Wall Finishes
20mm Cement/sand (1:4) render: finished to approval &
satisfaction of the Architect: on
H Plastered wall surfaces; externally 34 SM
OUT-BUILDING PB/5
ITEM DESCRIPTION QTY UNIT RATE AMOUNT
8mm thick 200 x 400mm Italian ceramic wall tiles; Allow for
fixing with 'sealmaster 101' or equal and approved tile
adhesive: jointed and pointed in 'sealmaster 201' grout:
clean with approved detergent and apply 'Johnson wax'
polish: allow for tile spacers: in
OUT-BUILDING PB/6
ITEM DESCRIPTION QTY UNIT RATE AMOUNT
OUT-BUILDING PB/7
ITEM DESCRIPTION QTY UNIT RATE AMOUNT
Element No. 2
Roofing
A SBS to flat surfaces 79 SM
Lintols
Precast concrete units : class 25/12mm : vibrated :
reinforced: weathered: Throated: including hoisting into
position: (provisional)
M Lintels; 200 x 200 mm; reinforced 15 LM
Window cill
275mm Wide clay brick window cill from Kenya Clay
N Products or other equal and approved : grooved water bar : 11 LM
cement wash finished in all exposed surfaces.
OUT-BUILDING PB/8
ITEM DESCRIPTION QTY UNIT RATE AMOUNT
FINISHES
Floor finishes
1:3 cement/sand backing screed: on floors
A 30mm thick finished to receive ceramic floor tiles 46 SM
Wall finishes
28mm thick Cement/sand (1:4) render: finished to approval
& satisfaction of the Architect: on
E Decorative double plaster; Externally 71 SM
8mm thick 200 x 400mm Italian ceramic wall tiles; Allow for
fixing with 'sealmaster 101' or equal and approved tile
adhesive: jointed and pointed in 'sealmaster 201' grout:
clean with approved detergent and apply 'Johnson wax'
polish: allow for tile spacers: in
H Wall tiles 98 SM
OUT-BUILDING PB/9
ITEM DESCRIPTION QTY UNIT RATE AMOUNT
OUT-BUILDING PB/10
ITEM DESCRIPTION QTY UNIT RATE AMOUNT
Element No. 3
GYM BUILDING
Roofing
B SBS to flat surfaces 153 SM
FINISHES
Floor Finishes
1:3 cement/sand backing screed: on floors
G 30mm thick finished to receive quarry tiles 70 SM
OUT-BUILDING PB/11
ITEM DESCRIPTION QTY UNIT RATE AMOUNT
Wall Finishes
Prepare and apply one undercoat and two coats of exterior
quality paint as 'Duracoat Duraplast' or other equal and
approved; on
E Paint walls; Ext 70 SM
OUT-BUILDING PB/12
ITEM DESCRIPTION QTY UNIT RATE AMOUNT
8mm thick 200 x 400mm Italian ceramic wall tiles; Allow for
fixing with 'sealmaster 101' or equal and approved tile
adhesive: jointed and pointed in 'sealmaster 201' grout:
clean with approved detergent and apply 'Johnson wax'
polish: allow for tile spacers: in
A Fix only wall tiles; Int 128 SM
Accessories
B toilet roll holders; size 150 x 150 mm 1 No.
OUT-BUILDING PB/13
ITEM DESCRIPTION QTY UNIT RATE AMOUNT
OUT-BUILDING PB/14
ITEM DESCRIPTION QTY UNIT RATE AMOUNT
Element No. 4
WORKSHOP BLOCK
Roofing
A SBS to flat surfaces 77 SM
D outlets 1 No.
FINISHES
Wall Finishes
15mm Cement/sand (1:4) render: finished to approval &
satisfaction of the Architect: on
J Render; 15 mm to walls 16 SM
OUT-BUILDING PB/15
ITEM DESCRIPTION QTY UNIT RATE AMOUNT
C Paint; ceiling 65 SM
Floor Finishes
1:3 cement/sand backing screed: on floors
D 50 mm thick; integral hardener; steel trowelled 47 SM
OUT-BUILDING PB/16
ITEM DESCRIPTION QTY UNIT RATE AMOUNT
Element No. 5
GENERATOR HOUSE
Reinforcement
High yield ribbed and/or round reinforcement bars to BS
4461 & 4449 respectively: allow for cutting, bending, tying
and hoisting (Provisional)
E Bars; 32mm -12 mm 503 KG
F Bars; 8 mm 335 KG
Formwork to:
G soffits of slab 33 SM
J sides of columns 10 SM
Coping
Insitu coping; 300 x 100mm extereme thick; twice throated
L 22 LM
OUT-BUILDING PB/17
ITEM DESCRIPTION QTY UNIT RATE AMOUNT
Parapet walling
Machine cut natural coral stone wall : load bearing
(7N/mm²) block walling : bedded, jointed and pointed : in
cement and sand (1:4) mortar: 25 x 3mm hoop iron every
alternate course
A Parapet walls; 200 mm thick 11 SM
Floor Finishes
1:3 cement/sand backing screed: on floors; steel trowelled
smooth:
L Cement screeds; 50 mm thick floors 20 SM
Wall Finishes
15mm Cement/sand (1:4) render: finished to approval &
satisfaction of the Architect: on
N Render; 15 mm thick to walls 12 SM
OUT-BUILDING PB/18
ITEM DESCRIPTION QTY UNIT RATE AMOUNT
OUT-BUILDING PB/19
ITEM DESCRIPTION QTY UNIT RATE AMOUNT
Element No. 6
GUARD HOUSE
Paving & Surfacing
Concrete block paving: heavy duty: minimum load bearing
40N/mm2: laid to falls to manufacturers specifications.
Floor Finishes
1:3 cement/sand backing screed: on floors
L Cement screeds with integral hardener; 50 mm thick 3 SM
OUT-BUILDING PB/20
ITEM DESCRIPTION QTY UNIT RATE AMOUNT
Wall Finishes
15mm Cement/sand (1:4) render: finished to approval &
satisfaction of the Architect: on
A Render 15 mm thick to walls; Ext 12 SM
OUT-BUILDING PB/21
ITEM DESCRIPTION QTY UNIT RATE AMOUNT
SUMMARY Page
OUT-BUILDING PB/22
FIT-OUT WORKS
ITEM DESCRIPTION QTY UNIT RATE AMOUNT
Element No. 1
OPENINGS
G 800 x 1950 mm high as door type D7; with no top frame; 36 No.
Out - Buildings
Panel doors, single doors, flush doors to be in accordance
with Architect's drawing No. H.B.2014.08.21 (Rates for the
doors to include for supply and fix complete including
frames and all necessary door furniture, ironmongery and
the like)
Office Block
Windows etc. to be in accordance with Architect's drawing
No. H.B.2014.08.22 (Rates for windows to include for supply
and fix complete including glazing and all necessary
furniture as required.)
Out - Buildings
V 1800 x 1500 mm as window type W1 10 No.
Element No. 2
PARTITIONS
White Aluminium powder coated partition on 900 mm high
gypsum partition with 100 x 25 mm Mvule skirting; on all
gypsum partitioning walls allow 150 x 25 mm Timber coping
and 100 x 25 mm skirting
Partitions to be in accordance with Architect's drawing No.
H.B.2014.08.40
(Rates for the partitions to include for supply and fix)
Element No. 3
Flag Masts
Allow for supply and fixing on ground, flag posts 6m in
height above ground level made from 200 mm diameter
galvanized pipe at the bottom 4 m and 2 m of 75 mm
D 4 No.
diameter. Top to be completed in a ball shaped diameter of
100 mm. Allow for flag hoisting gears to each unit to
approval. Allow for adequate concrete foundation.
Element No. 4
Entrance to Store.(D6)
Overall opening size of 3000mm ht and 900 width. Frame
size RHS 25mm x 50mm depend 1mm thick cut and welded
D 1 No.
to suitable size. Total length of frame fixed to wall 8 r meters.
Ditto but frame for shutters 7 r meters
Internal sections of 25x3mm thick flats welded and shaped
to approval. Total length 44 running m. All above painted
with rustic paint to approval.
To Large Opening
75mm diameter and 2mm thick approved quality stainless
G steel railing fixed on top of M/S railing. Length of railing to 14 No.
be 4 Running meters.
SUMMARY Page
A OPENINGS FW/1
B PARTITIONS FW/10
Page
B OUT-BUILDINGS PB/22
Element No. 1
SOFT LANDSCAPING
Grassing
Excavate to remove top vegetable soil 200mm deep
A average and store in temporary heaps on site for reuse 3125 SM
Shrubs
Prepare a Shrub Pit (size 450mm x 450mm x 450mm.) by
excavation; Apply anti-termite treatment in form of 15 ml
of Chlorpyriphos per plant on the walls & base of the pit;
Fill the pit with compost (ratio 1 manure : 3 good earth : 1
sand by volume); Supply, transport and mix soil
improvement nutrients as required in all pits including
DAP, Urea, Neem Cake, and Mustard Cake etc. as per
good horticultural practices; Flood with water at least 15
litre. Per plant , dressing including removal of rubbish &
surplus earth if any with all leads & lifts, planting in full
and final location including all locations specified; Supply
& planting of the shrub/climbers as per botanical name &
specification mentioned hereunder:
G Bamboo 422 NO
Planters
1500 x 600 x 500mm overall; 50mm thick concrete
H planters; allow for 5mm 5No seeping holes; to Architects 78 NO
detail and approval
Maintenance
Allow for maintenance of plants for a period of 30
months, replacement of any dead & sickly plants in this
J 1 ITEM
period, supply & spraying of insecticides as required.
Element No. 2
Excavation
Oversite excavation to remove vegetable soil :
A commencing at existing ground level : not exceeding 301 CM
250mm deep
Surface treatment
Treat surface of the formation with approved persistent
C herbicide 2,000 SM
Filling
Imported fill as murram or equal approved material to
D make up levels; well watered, rolled and compacted in 301 CM
layers not exceeding 150mm thick
Element No. 3
COVERED WALKWAY
Excavations
Oversite excavation to remove vegetable soil :
A commencing at existing ground level : not exceeding 14 CM
250mm deep
Filling
Imported fill as murram or equal approved material to
J make up levels; well watered, rolled and compacted in 15 CM
layers not exceeding 150mm thick
K
50mm Thick stone dust blinding to hardcore surfaces. 99 SM
Antitermite treatment
Chemical anti-termite treatment to subsoil or filling:
Dragnet 38% E.C. or equal approved: applied strictly to
L manufacturers written specification: provide a ten year 99 SM
guarantee
Total Carried to Collection
Concrete work
50mm Thick mass concrete 1:4:8: class 7.5/20 in: blinding
to:
A mix 1:4:8-20; blinding; 50 mm thick 2 CM
H Bars 8 mm 400 KG
Formwork
K sides of columns 22 SM
Sundries
M wall ties; 25 x 450 mm 144 No.
F Bars; 8 mm 1200 KG
Formwork
G soffits of slab 104 SM
J sides of columns 63 SM
L 200 mm thick 35 SM
WALL FINISHES
20mm Cement/sand (1:4) render: finished to approval &
satisfaction of the Architect: on
E Render; 20 mm thick to walls 63 SM
CEILING FINISHES
BOUNDARY WALL
Prepare and apply one undercoat and two coats of
interior quality paint as 'Duracoat Royale Soft Satin
Emulsion' or other equal and approved; on
J Paint walls 158 SM
Element No. 4
SOIL DRAINAGE
Manholes
D 450 mm x 600 mm x 1000 to 1500 mm deep 31 No.
Page
Materials KG
a Cement Bags
b River sand tons
c Ballast tons
d Reinforcement bars
y25 Pcs.
y20 Pcs.
y16 Pcs.
y12 Pcs.
y10 Pcs.
y8 Pcs.
y8 - cuts Kg.
e Steel mesh reinforcement
A142 Rolls
A252 Rolls
f Binding wires Rolls
g Fixing nails Kg
h Hoop iron No.
i Concrete blocks No.
j Boriti poles No.
k Marine ply boards No.
l Structural glass SM
Hafele Ironmongery (Contractor to attach priced schedule)
K. Shs.
SECTION C
SUB-CONTRACT PRELIMINARIES
AND
GENERAL CONDITIONS
SUB- CONTRACT PRELIMINARIES AND GENERAL CONDITIONS
(i)
1.24 Contractor’s Office in Kenya C-6
(ii)
1.49 Clear Away on Completion C-14
(iii)
SECTION C
SUB-CONTRACT PRELIMINARIES AND GENERAL CONDITIONS
1.01 Examination of Tender Documents
The tenderer is required to check the number of pages of this document and should he find
any missing or indistinct, he must inform the Engineer at once and have the same rectified.
b) The Republic of Kenya Document “General Conditions of Contract for Electrical and
Mechanical Works”.
He shall also be deemed to have included for any expenditure which may be incurred in
conforming with the above items (a), (b), (c) and observe this expense as being attached to
the contract placed for the whole or any part of the work.
The tenderer shall ensure that all ambiguities, doubts or obscure points of detail, are
clarified with the Engineer before submission of his tender, as no claims for alleged
deficiencies in the information given shall be considered after this date.
1.02 Discrepancies
The Sub-contractor shall include all work either shown on the Contract Drawings or detailed
in the specification. No claim or extra cost shall be considered for works which has been
shown on the drawings or in the specification alone.
Should the drawing and the specification appear to conflict, the Sub-contractor shall query
the points at the time of tendering and satisfy himself that he has included for the work
intended, as no claim for extra payment on this account shall be considered after the
contract is awarded.
The Sub-contractor shall be required to enter into a Sub-contract with the Main Contractor.
The Conditions of the Contract between the Main Contractor and the Sub-contractor as
hereinafter defined shall be the latest edition of the Agreement and Schedule of Conditions
of Kenya Association of Building and Civil Engineering Contractors as particularly modified
and amended hereinafter.
For the purpose of this contract the Agreement and Schedule of Conditions and any such
modifications and amendments shall read and construed together. In any event of
discrepancy the modifications and amendments shall prevail.
1.04 Payment
Payment will be made through certificates to the Main Contractor, unless he specifically
agrees to forego this right, in which case direct payment can be made to the Sub-contractor.
All payments will be less retention as specified in the Main Contract. No payment will
become due until materials are delivered to site.
C-1
1.05 Definition of Terms
Throughout these contract documents units of measurements, terms and expressions are
abbreviated and wherever used hereinafter and in all other documents they shall be
interpreted as follows:
i) Employer: The term “Employer” shall mean The Clerk,County Assembly of Kilifi-
P.O BOX 332,MALINDI
ii) Architect: The term “Architect” shall mean the Architect appointed by the
Employer
iii) Quantity Surveyor: The term “Quantity Surveyor” shall mean the Quantity
Surveyor appointed by the Employer
v) Engineer: The term “Engineer” shall mean the Mechanical &/OR Electrical
Engineer appointed by the Employer.
vi) Main Contractor: The term “Main Contractor” shall mean the firm or company
appointed to carry out the Building Works and shall include his or their heir, executors,
assigns, administrators, successors, and duly appointed representatives.
viii) Sub-contract Works: The term “Sub-contract Works” shall mean all or any
portion of the work, materials and articles, whether the same are being manufactured
or prepared, which are to be used in the execution of this Sub-contract and whether
the same may be on site or not.
ix) Contract Drawings: The term “Contract Drawings” shall mean those drawings
required or referred to herein and forming part of the Bills of Quantities.
x) Working Drawings: The term “Working Drawings” shall mean those drawings
required to be prepared by the Sub-contractor as hereinafter described.
xi) Record Drawings: The term “Record Drawings” shall mean those drawings
required to be prepared by the Sub-contractor showing “as installed” and other
records for the Sub-contract Works.
xii) Abbreviations:
CM shall mean Cubic Metre
SM shall mean Square Metre
LM shall mean Linear Metre
LS shall mean Lump Sum
mm shall mean Millimetres
No. shall mean Number
Kg. shall mean Kilogramme
KEBS shall meanKenya Bureau of Standards
BS shall mean. Current standard British Standard Specification published
by the British Standard Institution, 2 Park Street, London W1, England
C-2
“Ditto” shall mean the whole of the preceding description in which it occurs.
Where it occurs in description of succeeding item it shall mean the same as in the
first description of the series in which it occurs except as qualified in the description
concerned. Where it occurs in brackets it shall mean the whole of the preceding
description which is contained within the appropriate brackets.
The sub-contractor shall supply all accessories, whether of items or equipment supplied by
the Main Contractor but to be fixed and commissioned under this Sub-contract.
Materials supplied by others for installation and/or connection by the Subcontractor shall be
carefully examined in the presence of the supplier before installation and connection. Any
defects noted shall immediately be
reported to the Engineer.
The Sub-contractor shall be responsible for verifying all dimensions relative to his work by
actual measurements taken on site.
The Sub-contractor shall mark accurately on one set of drawings and indicate all alterations
and/or modifications carried out to the designed system during the construction period.
This information must be
made available on site for inspection by the Engineer.
C-3
All relevant British Standard Specifications and Codes of Practice
(hereinafter referred to as B.S. and C.P. respectively).
This Specification.
1.13 Variation
No alteration to the Sub-contract Works shall be carried out until receipt by the Sub-
contractor of written instructions from the Project Manager.
Any variation from the contract price in respect of any extra work, alteration or omission
requested or sanctioned by the Architect or Engineer shall be agreed and confirmed in
writing at the same time such variations are decided and shall not affect the validity of the
Contract. Schedule of Unit Rates shall be used to assess the value of such variations. No
allowance shall be made for loss of profit on omitted works.
If the Sub-contractor fails to give such notice he will be deemed responsible for the claims
arising from the delay occasioned by reason of such extension of time.
The work covered by Prime Cost and Provisional Sums may or may not be carried out at the
discretion of the Architect.
The whole or any part of these sums utilised by the Sub-contractor shall be deducted from
the value of the Sub-contract price when calculating the final account.
C-4
1.15 Bond
The tenderer must submit with his tender the name of one Surety who must be an
established Bank only who will be willing to be bound to the Main Contractor for an amount
equal to 7½ % of the Sub-contract amount as Clause 31 of the Main Contract.
The Sub-contractor must also make himself acquainted with current legislation and any
Government regulations regarding the movement, housing, security and control of labour,
labour camps, passes for transport, etc.
The Sub-contractor shall allow for providing holidays and transport for work people, and for
complying with Legislation, Regulations and Union Agreements.
No allowance shall be made to the Sub-contractor with respect to fees should these have
been omitted by the tenderer due to his negligence in this respect.
a) Attendance on the Sub-contractor and the carrying out of all work affecting the
structure of the building which may be necessary, including all chasing, cutting away
and making good brickwork, etc., except that all plugging for fixing, fittings,
machinery, fan ducting, etc., and all drilling and tapping of steel work shall be the
responsibility of the Sub-contractor. Any purpose made fixing brackets shall not
constitute Builder’s Work and shall be provided and installed by the Sub-contractor
unless stated hereinafter otherwise.
b) The provision of temporary water, lighting and power: All these services utilised shall
be paid for by the Main Contractor. The Sub-contractor shall, however, allow for
additional connections/extensions required for his purposes.
c) Fixing of anchorage and pipe supports in the shuttering, except that all anchorage
shall be
supplied by the Sub-contractor who shall also supply the Main Contractor with fully
dimensioned drawings detailing the exact locations.
C-5
ii) Any specialist scaffolding, cranes, etc. by the Sub-contractor for his own
exclusive use shall be paid for by the Sub-contractor.
1.20 Suppliers
The Sub-contractor shall submit names of any supplier for the materials to be incorporated,
to the Engineer for approval. The information regarding the names of the suppliers may be
submitted at different times, as may be convenient, but no sources of supply will be
changed without prior approval.
Each supplier must be willing to admit the Engineer or his representative to his premises
during working hours for the purpose of examining or obtaining samples of the materials in
question.
All work liable to adjustment under this Sub-contract shall be left uncovered for a reasonable
time to allow measurements needed for such adjustment to be taken by the Quantity
Surveyor or Engineer. Immediately the work is ready for measuring the Sub-contractor shall
give notice to the Quantity Surveyor or Engineer to carry out measurements before covering
up. If the Sub-contractor shall make default in these respects he shall, if the Architect so
directs, uncover the work to enable the necessary measurements to be taken and
afterwards reinstate at his own expense.
The Sub-contractor shall drill and plug holes in floors, walls, ceiling and roof for securing
services and equipment requiring screw or bolt fixings.
Any purpose made fixing brackets shall not constitute builder’s work and shall be provided
and installed by the Sub-contractor unless stated hereinafter to the contrary.
The preliminary major structural provision made will be deemed as adequate unless the
Sub-contractor stated otherwise when submitting his tender.
Any major structural provision or alteration to major structural provisions required by the
Sub-contractor shall be shown on Working Drawings to be submitted to the Engineer within
30 days of being appointed.
No requests for alterations to preliminary major structural provisions will be approved except
where they are considered unavoidable by the Engineer. In no case will they be approved if
building work is so far advanced as to cause additional costs or delays in the work of the
Main Contractor.
The routes of services and positions of apparatus shall be determined by the approved
dimensions detailed in the Working Drawings or on site by the Engineer in consultation with
the Sub-contractor or the Main Contractor.
Services throughout the ducts shall be arranged to allow maximum access along the ducts
and the services shall be readily accessible for maintenance. Any work which has to be re-
done due to negligence in this respect shall be the Sub-contractor’s responsibility.
The Sub-contractor shall be deemed to have allowed in his Sub-contract Sum for locating
terminal points of services (e.g. lighting, switches, socket outlets, lighting points, control
switches, thermostats and other initiating devices, taps, stop cocks) in positions plus or
minus 1.2m horizontally and vertically from the locations shown on Contract Drawings.
Within these limits no variations in the Sub-contract Sum will be made unless the work has
already been executed in accordance with previously approved Working Drawings and with
the approval of the Engineer.
C-7
1.29 Setting to Work and Regulating System
The Sub-contractor shall carry out such tests of the Sub-contract Works as required by
British Standard Specifications, or equal and approved codes as specified hereinafter and as
customary.
It will be deemed that the Sub-contractor has included in the Sub-contract Sum for the costs
of all fuel, power, water and the like, for testing and commissioning as required as part of
the Sub-contract Works. He shall submit for approval to the Engineer a suitable programme
for testing and commissioning. The Engineer and Employer shall be given ample warning in
writing, as to the date on which testing and commissioning will take place.
The Sub-contractor shall commission the Sub-contract Works and provide attendance during
the commissioning of all services, plant and apparatus connected under the Sub-contract
Agreement or other Sub-contract Agreements, related to the project.
Each system shall be properly balanced, graded and regulated to ensure that correct
distribution is achieved and where existing installations are affected, the Sub-contractor shall
also regulate these systems to ensure that their performance is maintained.
The proving of any system of plant or equipment as to compliance with the Specification
shall not be approved by the Engineer, except at his discretion, until tests have been carried
out under operating conditions pertaining to the most onerous conditions specified except
where the time taken to obtain such conditions is unreasonable or exceeds 12 months after
practical completion of the Sub-contract Works.
1.32 WorkingDrawings
The Sub-contractor shall prepare such Working Drawings as may be necessary. The
Working Drawings shall be complete in such detail not only that the Sub-contract Works can
be executed on site but also that the Engineer can approve the Sub-contractor’s proposals,
detailed designs and intentions in the execution of the Sub-contract Works.
If the Sub-contractor submits his Working Drawings to the Engineer without first liaising and
obtaining clearance for his installations from the Main Contractor and other Sub-contractors
whose installations and works might be affected, then he shall be liable to pay for any
alterations or modification to his own, the Main Contractor’s or other Sub-contractor’s
installations and works, which are incurred, notwithstanding any technical or other approval
received from the Engineer.
Working Drawings to be prepared by the Sub-contractor shall include but not be restricted
to the following:
a) Any drawings required by the Main Contractor, or Engineer to enable structural
provisions
to be made including Builder’s Working Drawings or Schedules and those for the
detailing of holes, fixings, foundations, cables and paperwork ducting below or above
ground or in or outside or below buildings.
b) General Arrangement Drawings of all plant, control boards, fittings and apparatus or
any part thereof and of installation layout arrangement of such plant and apparatus.
d) Layout Drawings of all embedded and non-embedded paperwork, ducts and electrical
conduits.
f) Such other drawings as are called for in the text of the Specification or Schedules or
as the Engineer may reasonably require.
Three copies of all Working Drawings shall be submitted to the Engineer for approval. One
copy of the Working Drawings submitted to the Engineer for approval shall be returned to
the Sub-contractor indicating approval or amendment therein.
Six copies of the approved Working Drawings shall be given to the Main Contractor by the
Sub-contractor for information and distribution to other Sub-contractors carrying out work
associated with or in close proximity to or which might be affected by the Sub-contract
Works.
Approved Working Drawings shall not be departed from except as may be approved or
directed by the Engineer.
Approval by the Engineer of Working Drawings shall neither relieve the Sub-contractor of
any of his obligations under the Sub-contract nor relieve him from correcting any errors
found subsequently in the Approved Working Drawings or other Working Drawings and in
the Sub-contract Works on site or elsewhere associated therewith.
The Sub-contractor shall ensure that the Working Drawings are submitted to the Architect
for approval at a time not unreasonably close to the date when such approval is required.
Late submission of his Working Drawings will not relieve the Sub-contractor of his obligation
to complete the Sub-contract Works within the agreed Contract Period and in a manner that
would receive the approval of the Architect.
C-9
1.33 Record Drawings (As Installed) and Instructions
During the execution of the Sub-contract Works the Sub-contractor shall, in a manner
approved by the Engineer record on Working or other Drawings at site all information
necessary for preparing Record Drawings of the installed Sub-contract Works. Marked-up
Working or other Drawings and other documents shall be made available to the Engineer as
he may require for inspection and checking.
Record Drawings, may, subject to the approval of the Engineer, include approved Working
Drawings adjusted as necessary and certified by the Sub-contractor as a correct record of
the installation of the Sub-contract Works.
They shall include but not restricted to the following drawings or information:
a) Working Drawings amended as necessary but titled “Record Drawings” and certified
as a true record of the “As Installed” Sub-contract Works. Subject to the approval of
the Engineer such Working Drawings as may be inappropriate may be omitted.
d) Routes, types, sizes and arrangement of all pipework and ductwork including dates
of installation of underground pipework.
f) Routes, types, sizes and arrangement of all electric cables, conduits, ducts and
wiring including the dates of installation of buried works.
g) System schematic and trunking diagrams showing all salient information relating to
control and instrumentation.
h) Grading Charts.
k) Schematic diagrams of individual plant, apparatus and switch and control boards.
These diagrams to include those peculiar to individual plant or apparatus and also
those applicable to system operation as a whole.
l) Operating Instruction
Schematic and wiring diagrams shall not be manufacturer’s multipurpose general issue
drawings. They shall be prepared specially for the Sub-contract Works and shall contain no
spurious or irrelevant information.
Marked-up drawings of the installation of the Sub-contract Works shall be kept to date and
completed by the date of practical or section completion. Two copies of the Record
Drawings of Sub-contract Works and two sets of the relay adjustment and grading charts
and schematic diagrams on stiff backing shall be provided not later than one month later.
C-10
The Sub-contractor shall supply for fixing in sub-stations, switch-rooms, boiler houses, plant
rooms, pump houses, the office of the Maintenance Engineer and other places, suitable
valve and instructions charts, schematic diagrams of instrumentation and of the electrical
reticulation as may be requested by the Engineer providing that the charts, diagrams, etc.,
relate to installations forming part of the Sub-contract Works. All such charts and diagrams
shall be of suitable plastic material on a stiff backing and must be approved by the Engineer
before final printing.
The Engineer shall have these drawings produced by others. The cost of obtaining the
necessary information and preparing such drawings, etc., will be recovered from the Sub-
contractor.
The manual shall be loose-leaf type, International A4 size with stiff covers and cloth bound.
It may be in several volumes and shall be sub-divided into sections, each section covering
one Engineering service system. It shall have a ready means of reference and a detailed
index.
There shall be a separate volume dealing with Air Conditioning and Mechanical Ventilation
installation where such installations are included in the Sub-contract Works.
The manual shall contain full operating and maintenance instructions for each item of
equipment, plant and apparatus set out in a form dealing systematically with each system. It
shall include as may be applicable to the Sub-contract Works the following and any other
items listed in the text of the Specifications:
a) System Description.
b) Plant
c) Valve Operation
d) Switch Operation
f) Emergency Procedures
g) Lubrication Requirements
1.35 Hand-over
The Sub-contract Works shall be considered complete and the Maintenance and Defects
Liability Period shall commence only when the Sub-contract Works and supporting services
have been tested, commissioned and operated to the satisfaction of the Engineer and
officially approved and accepted by the Employer, provided always that the handing over of
the Sub-contract Works shall be coincident with the handing over of the Main Contract
Works.
c) The Sub-contractor shall arrange with the Engineer and Employer for a complete
demonstration of each and every service to be carried out and for instruction to be
given to the relevant operation staff and other representatives of the Employer.
d) In the presence of the Employer and the Engineer, Hand-over will take place, subject
to Agreement of the Hand-over Certificates and associated check lists.
1.36 Painting
It will be deemed that the Sub-contractor allowed for all protective and finish painting in the
Sub-contract Sum for the Sub-contract Works, including colour coding of service pipework to
the approval of the Engineer. Any special requirements are described in the text of the
Specifications.
1.37 Spares
The Sub-contractor shall supply and deliver such spares suitably protected and boxed to the
Engineer’s approval as are called for in the Specifications or in the Price Schedules.
The foregoing provisions relate to tests at manufacturer’s works and as appropriate to those
carried out at site.
C-12
1.39 Testing and Inspection -Installation
Allow for testing each section of the Sub-contract Works installation as described hereinafter
to the satisfaction of the Engineer.
The work people employed by the Sub-contractor shall occupy or be about only that part of
the site necessary for the performance of the work and the Sub-contractor shall instruct his
employees accordingly.
If practicable, W.C. accommodation shall be allocated for the sole use of the Sub-
contractor’s workmen and the Sub-contractor will be required to keep the same clean and
disinfected, to make good any damage thereto and leave in good condition.
Nominated Sub-contractors are to be made liable for the cost of any storage accommodation
provided specially for their use. No materials shall be stored or stacked on suspended slabs
without the prior approval of the Project manager.
The sub-contractor shall also provide a 24 -hour break-down service to attend to faults on or
malfunctioning of the installation between the routine visits of inspection.
The sub-contractor shall allow in the sub-contract Sum of the initial maintenance, inspection
and break-down service and shall provide for all tools, instruments, plant and scaffolding
and the transportation thereof, as required for the correct and full execution of these
obligations and the provision, use or installation of all materials as oils, greases, sandpaper,
etc., or parts which are periodically renewed such as brake linings etc., or parts which are
faulty for any reason whatsoever excepting always Acts of God such as storm, tempest,
flood, earthquake and civil revolt, acts of war and vandalism.
The terms of any such agreement shall not be less beneficial to the employer than the terms
of Agreements for either similar installation.
The sub-contractor shall submit with his tender for the works, where called upon a firm
quotation for the maintenance and service of the installation as specified herein, which shall
be based upon the present day costs and may be varied only to take into account increases
in material and labour unit rate costs between the time of tendering and the signing of the
formal maintenance
C-13
and service agreement and which shall remain valid and open for acceptance by the
Employer to and including the last day of the fifth complete calendar month following the
end of the liability for Defects Period.
1.46 Protection
The sub-contractor shall adequately cover up and protect his own work to prevent injury
and also to cover up and protect from damage all parts of the building or premises where
work is performed by him under the Contract.
The sub-contractor shall, upon completion of the works, at his own expense, remove and
clear away all plant, equipment, rubbish and unused materials, and shall leave the whole of
the works in a clean and tidy state, to the satisfaction of the Engineer. On completion, the
whole of the works shall be delivered up clean, complete and perfect in every respect to the
satisfaction of the Engineer.
On completion of the works the sub-contractor shall agree with the Engineer the value of
any variations outstanding and as soon as possible thereafter submit to the Engineer his
final statement of account showing the total sum claimed sub-divided as follows:
Statement A - detailing the tender amounts less the Prime Cost and Provisional
Sums, included therein.
Statement C - Summarizing statement A and B giving the net grand total due to the
Contractor for the execution of the Contract.
C-14
a) The sub-contractor shall pay rates of the wages and observe hours and conditions of
labour not less favorable than those established for the trade or industry in the
district where work is carried out.
1.52 Supervision
During the progress of the works, the Sub-contractor shall provide and keep constantly
available for consultation on site an experienced English - speaking Supervisor and shall
provide reasonable office facilities, attendance, etc., for the Supervisor.
In addition, during the whole of the time the works are under construction, the sub-
contractor shall maintain on site one experienced foreman or charge-hand and an adequate
number of fitters, etc., for the work covered by the Specification. The number of this staff
shall not be reduced without the prior written approval of the Project manager or Engineer.
One copy of this Specification and one copy of each of the Contract Drawings (latest issue)
must be retained on site at all times, and available for reference by the Engineer or sub-
contractor.
1.54 Labour
The Sub-contractor shall provide skilled and unskilled labour as may be necessary for
completion of the contract.
1.56 Guarantee
The whole of the work will be guaranteed for a period of 12 months from the date of the
Engineer’s certification of completion and under such guarantee the Sub-contractor shall
remedy at his expense all defects in materials and apparatus due to faulty design,
construction or workmanship which may develop in that period.
The Contractor shall allow for the attendance of trade upon trade and shall afford any
tradesmen or other persons employed for the execution of any work not included in this
contract every facility for carrying out their work and also for the use of ordinary scaffolding.
The contractor however, shall not be required to erect any special scaffolding for them.
The contractor shall recognize the freedom of his work people to be members of trade
unions.
C-15
1.59 Local and other Authorities notices and fees
The contractor shall comply with and give all notices required by any Regulations, Act or by
Law of any Local Authority or of any Public Service, Company or Authority who have any
jurisdiction with regard to the works or with those systems the same are or will be
connected and he shall pay and indemnify the Government against any fees or charges
legally demandable under any regulation or by-law in respect of the works; provided that
the said fees and charges if not expressly included in the contract sum or stated by way of
provisional sum shall be added to the contract sum.
The contractor before making any variation from the contract drawings or specification
necessitated by such compliance shall give the Project Manager written notice specifying
and giving the reason for such variation and applying for instructions in reference thereto.
If the contractor within seven days of having applied for the same does not receive such
instructions, he shall proceed with the works in conforming to the provision regulation or by-
law in question and any variation thereby necessitated shall be deemed to be a variation in
accordance to the conditions of contract.
The contractor shall make good any defects or other faults in the relevant part that had
been deemed complete.
The contractor shall reduce the value of insurance by the full value of the relevant part
The contractor shall be paid for the part of works taken possession by the Government
The contractor shall include for the cost of and make necessary arrangements with the
Project Manager for such temporary works. For temporary lighting, electricity shall be
metered and paid for by the contract
Percentage of extended preliminaries shall be inserted in Bill No.1 page H/5 section
H. However, this amount of the extended preliminaries SHALL NOT exceed the
Liquidated and Ascertained Damages indicated on page B-9 of Section B of this
tender document
C-18
SECTION D
GENERAL SPECIFICATIONS
OF
2.1 General
2.3 Workmanship
This specification is to be read in conjunction with any other information herein issued with
it. Bills of quantities and schedule of unit rates shall be the basis of all additions and
omissions during the progress of the works.
Where the material and equipment are specifically describedand named in the Specification
followed by approved equal, they are so named or described for the purpose of
establishing a standard to which the contractor shall adhere.
Should the contractor install any material not specified herein before receiving approval
from the proper authorities, the Engineer shall direct the contractor to remove the material
in question immediately. The fact that this material has been installed shall have no
bearing or influence on the decision by the Engineer.
All materials condemned by the Engineer as not approved for use, are to be removed from
the premises and suitable materials delivered and installed in their place at the expense of
the Contractor. All materials required for the works shall be from branded manufacturers,
and shall be new and the best of the respective kind and shall be of a uniform pattern.
2.3 WORKMANSHIP
The workmanship and method of installation shall conform to the best standard practice.
All work shall be performed by a skilled tradesman and to the satisfaction of the Engineer.
Helpers shall have qualified supervision.
Any work that does not in the opinion of the Engineer conform to the best standard
practice will be removed and reinstated at the contractor’s expense.
Permits, Certificates or Licences must be held by all tradesmen for the type of work; in
which they are involved where such permits, certificates or licences exist under
Government legislation.
The contractor is advised that no assistance can be given in the procurement or allotment of
any materials or products to be used in and necessary for the construction and completion
of the work.
Contractors are warned that they must make their own arrangements for the supply of
materials and/or products specified or required. Where necessary, advance payment shall be
granted as stipulated in the Appendix to Instruction to Tenderers clause 9 page A/17
D-2
2.5 RECORD DRAWINGS
These diagrams and drawings shall show the completed installation including sizes, runs
and arrangements of the installation. The drawings shall be to scale not less than 1:50
and shall include plan views and section.
The drawings shall include all the details which may be useful in the operation,
maintenance or subsequent modifications or extensions to the installation.
Three sets of diagrams and drawings shall be provided, all to the approval of the Engineer.
One coloured set of line diagrams relating to operating and maintenance instructions shall
be framed and, mounted in a suitable location.
All work executed by the contractor shall comply with the current edition of the
“Regulations” for the Electrical Equipment of Buildings, issued by the Institution of
Electrical Engineers, Electric Power Act, Kenya Bureau of Standards (KBS), Institution of
Electrical Engineers (I.E.E) Wiring Regulations, Current recommendation of CCITT and
CCIR, and with the Regulations of the Local Electricity Authority and the Communications
Commission of Kenya (CCK)
Where the sets of regulations appear to conflict, they shall be clarified with the Engineer.
The contractor, at his own expenses, is to set out works and take all measurements and
dimensions required for the erection of his materials on site; making any modifications in
details as may be found necessary during the progress of the works, submitting any such
modifications or alterations in detail to the Engineer before proceeding and must allow in
his tender for all such modifications and for the provision of any such sketches or drawings
related thereto.
The contractor shall conduct during and at the completion of the installation and, if
required, again at the expiration of the maintenance period, tests in accordance with the
relevant section of the current edition of the Regulations for the electrical equipment of
buildings issued by the I.E.E of Great Britain, the Government Electrical Specifications No. 1
and No.2, Electric Supply Company’s By-Laws, Communications Commission of Kenya
(CCK) requirements or any other supplementary Regulations as may be produced by the
engineer.
D-3
SECTION E
1.0 Bidders shall be required to view the electrical drawings to ascertain dimensions of
the lift pit, headroom and shaft, cable routes and cable lengths before pricing the
Bills of Quantities of this tender document.
E/1
SECTION F
FOR
LIFT INSTALLATIONS
GENENERAL SPECIFICATIONS FOR LIFTS INSTALLATION WORKS
1. REGULATIONS
All Apparatus and materials supplied and work carried out shall comply with the
provisions of the following documents:-
(c) The Electric Power Act and the Rules made there under.
(e) The requirements of the Chief Inspector of Factories for the Kenya Government,
Factories Act Chapter 514 SECTION 30. The contractor shall avail all the
certificates.
A. Lifts Shaft
(ii)The lifts Contractor shall provide cut-outs for hall buttons, hall position indicators,
hall lanterns, shaft ventilations and fire man’s switch
(iii) The lifts Contractor shall provide the necessary scaffolding for erection of
equipment and hoarding to secure the work area from general public and
maintain safety of the people and other installations in the building.
(iv) The lifts Contractor shall provide temporary electricity supply for erection and
shaft lighting, and thereafter a permanent supply from an appropriate
isolator.
B. Lifts Pit
The lifts contractor shall provide and fix ladders where such facility may be required
as stipulated in BS 5655, and terminal and over travel limit switches.
F-1
C. Lift Motor Room
The lifts Contractor shall provide the following in the lifts motor room:
(i) Cut-outs for roping, safety gear ropes, selector tapes (where provided)
cabling etc. in the lifts motor room floor.
(iii) General lighting cable ducts and conduits and power and ventilation
equipment.
D. Access
The lifts Contractor shall provide stairway access with lockable doors to the lifts
motor room. On the outer side of the door shall be written in red letters:
E. Builder’s Work
(ii) All drilling and plugging of holes in floors, walls, ceiling and roofs for security
services, and for equipment requiring screw or bolt fixing.
A fireman’s control switch shall be provided in the down terminal floor, main entrance lobby.
The Fireman‘s switch shall be of the type approved by the Engineer.
Operation of the Fireman’s switch shall stop the lift car on the next landing but without
opening the car and landing doors and immediately return the lift to the ground floor
irrespective of any other calls and park lift with doors open. The car will then become in-
operative with the exception of the ‘Fireman’s Lift’ which shall operate in answer to the car
buttons until only the fireman s switch is reset.
An emergency alarm system in the form of an intercom shall be installed between the car,
the motor room, and the reception desk on the ground floor.
F-2
The alarm system shall be clearly labeled “Emergency Alarm”. On pushing an alarm button,
the system should ring simultaneously in the car, motor room and the reception desk.
The lifts Contractor shall carry out the wiring in the lift car and between machine and the
reception desk. The power supply for the alarm system shall be derived from a self-
recharging unit.
It shall be possible to open every lift-landing door by the use of a release key whether or
not the lift car is in the landing zone. The key hole shall be unobtrusive and located at high
level.
The call station, distributed between the lifts on each landing, and operating panel buttons
shall be micro-motion push button.
7. INTERFERENCE SUPPRESSION
The lift motor and auxiliary controls shall be suppressed so as not to interfere with local
radio and television reception and closed circuit television or Electro mechanical equipment
within the building. The suppression shall be carried out in accordance with B.S. 800 and all
suppression devices incorporated shall comply with B.S. 5655.
8. PROTECTION PADS
The lifts Contractor shall supply one set of protective quilted cover pads to
approval for passenger lift cars.
The lift cars shall be provided with an emergency light fitting operating from a
self-recharging battery unit. The emergency light will be built in the car-operatingpanel.
10. TEST
Both on completion of his work on the lifts and at the end of the guarantee period, the lifts
Contractor shall carry out all the tests as required and in accordance with B.S 5655part 7 in
the presence of the Engineer and shall provide all the necessary instruments, labour and
materials to do so at his cost.
Damage occurring, as a result of these tests will be made good by the Lifts Contractor to the
Engineer’s satisfaction at his expense.
4No. (Four) copies of the test certificates for each lift should be forwarded to
the Engineer within 4 days of completion of the last test.
F-3
11. TRAINING
The tenderer shall provide in his tender for the training of 2No.technicians on site in
the maintenance of the lifts during the dismantling, installation, testing and commissioning
period.
12.1 The lift equipment and all its controls shall be protected against power/ voltage fluctuations,
surges and transient currents. The contractor shall provide for and install all the necessary
equipment for this protection. The protective switchgear shall be verified by the Engineer
during the overseas factory inspection.
13.1 The tenderer shall allow in his tender for the initial statutory inspection of the lift by an
Approved Government Lift Inspector during the commissioning of the new lift, and
thereafter for inspection at intervals of six (6) months periodic time during the 12 months
defects liability period. One of the inspections shall be done after the expiry of the defects
liability period on confirming that all the defects (if any) have been corrected by the lift
contractor.
13.2 The employer and the contractor shall, at each inspection, each retain a copy of
the lift inspection certificates while the original will be submitted to the Ministry of Labour
and Human Resources Development.
14.1 The tenderer shall allow in his tender for the initial routine service maintenance of the new
lift once a month during the 12 months defects liability period and shall carry out all
necessary adjustments and repairs, cleaning, greasing and oiling of moving parts.
14.2 During the initial maintenance of the new lift, the tenderer shall also allow in his tender for
all tools, instruments, plant and scaffolding and the transportation thereof, as required for
the correct and full execution of these obligations and the provision, use or installation of all
materials or parts which are periodically renewed such as brake linings etc., or parts which
are faulty for any reason whatsoever excepting always acts of God such as storm, tempest,
flood, earthquake and civil revolt, acts of war and vandalism.
14.3 The contractor shall also provide a 24 -hour break-down service to attend to faults on or
malfunctioning of the installation between the routine visits of the defects liability period.
14.4 A monthly report of any works done upon the installation shall be supplied to the Engineer.
15.1 The tenderer shall allow in his tender for the registration of the new lifts with the Ministry of
Labour including payments of any fees that may be required. It is the responsibility of the
Contractor to avail the registration certificate to the client once the registration has been
done.
F-4
16.0 INTERIOR LIFT CAR FINISHES
16.1 The interior lift car finishes including ceiling, floor, cabin panels, car door, landing door and
architraves shall be to the Engineers approval in liaison with the Client. The approval will be
within the range of the manufacturers’ range of finishes in their brochures. The tenderer
must therefore allow for this in their bid.
17.1 The employer shall be entitled to have the quantity and quality of the imported lifts
materials inspected by two number (2No.) engineers appointed by the Project Manager, and
one (1No.) representative for the employer.
17.2 The said inspection shall be carried out at the factory of manufacture of the lifts materials
during normal working hours and the successful tenderer shall give written notice to the
Project Manager at the latest thirty (30) calendar days in advance of the date that the lifts
materials are ready for inspection.
17.3 Travel (including ground, air travel and airport passage taxes) and full board accommodation
expenses in at least a three (3) star hotel incurred by the engineers appointed by the Project
Manager, and the employer’s representative shall (see clause 12.1) be borne by the
contractor. The contractor shall also meet out of pocket expenses for the officers at
Government of Kenya rates for the duration of the factory inspection. The costs incurred
shall be re-imbursed to the contractor from the provisional sum allowed in page (G/8) of the
Bills of Quantities.
17.4 The inspection period shall be five (5) working days excluding travelling time.
17.5 If as a result of the inspection any of the lift materials are found to be defective, the
successful tenderer shall replace the defective materials and determine a new date as when
a new inspection shall be performed at the expense of the contractor.
17.6 The successful tenderer shall only ship the lift materials after the said factory inspection.
18.1 This is to be a software based system with a 20” colour monitor and a key board to monitor
and control security functions at all times. It shall be located at the reception/security desk.
F-5
PARTICULAR SPECIFICATIONS
The site of the proposed works is at The County Assembly of Kilifi-Malini Town.
The project comprises the supply, installation, testing and commissioning of 3No.modern
microprocessor control based lifts.
The following climatic conditions apply at the site of the contract work and the equipment,
materials and the installations shall be suitable for these conditions.
Extremely heavy rainfall is experienced at certain periods of the year and the contractor
shall be deemed to have taken account of this factor both in his prices and his planning of
the execution of the contract works.
The lift Contractor shall supply, deliver unload, hoist, fix and erect, test and commission all
the equipment, plant and materials in accordance with all specifications contained in this
document including the Building plans to provide a complete and operable installation.
The lifts Contractor shall become liable for defects and be responsible for the initial
maintenance of the lifts installed all as specified here in.
F-6
PASSENGER LIFTS
F-7
: Cabin ventilation shall be tropicalised high
Capacity cylinder type operation.
: Car extract fan should be powerful, quiet, drought
free and multi-directional complete with a maintained back-up
power supply
: Shall incorporate an Audio Visual car overload
divice.
: Shall have forced ventilation key switch.
Code compliance : The lifts shall comply with BS 5655 or European
Specifiadction equivalent code EN 81 and KS 2169 -1
Structural Openings : The lift Contractor shall set the landing doors at
10mm from the finished floor levels so as to get a
fall away from the landing to prevent water from
flowing down the lift shafts when washing up.
Entrances : The lifts car shall have automatic high speed power
operated 2 panel centre openings of 900mm wide
by 2100mm high
Landing door : Stainless steel to Engineer’s approval.
Car door : Stainless steel to Engineer’s approval.
Landing door architraves: Architraves to be granitotilesof a client approved colourwith an
aluminium strip at the edge, all to the Engineer’s approval.
Wall switches : All operating switches in the lifts shaft shall be of
the totally enclosed drip proof type.
Lighting : Indirect Lighting shall be fitted in the car to a level
of 150 lux.
Cabin walls : Hairline Stainless steel to Engineer’s approval
Car interior fronts : Hairline Stainless steel to Engineer’s approval.
Mirror : Three quarter full height at the rear car panel.
Door Operation : Heavy duty variable frequency driven door
operators on a frame above the lift car.
: Fully adjustable door open and close speeds -
micro-processor controlled. The goods lift has no
mirror and/or hand rail.
: Intelligent speed adjustments to cope with traffic requirements
: Full curtain electronic infrared 3 dimensional
detectors.
: An electro- mechanical type tested interlock shall be provided,
fitted on the landing door and operated by the door lock cam
on the lift car to prevent movement of the lift car until the
landing door is both mechanically and electronically locked.
Hand rails : Round sectioned stainless steel on the 3 panels of
the lift car.
Emergency light : Emergency light in the lift cars shall be 6 watts
complete with a maintained back-up power supply
Signal Hall Lanterns : LCD displays and different tones for up and down
motions.
Signal fixtures : Wide angle view car position indicator unit with
high relieable ELD technology.
Floor buttons : Micromotion with ring illumination
: Brushed stainless steel plate with Braille
indication.
Floor : Rubber knobbed tiles, not less than 6mm thick
Intercom : 5-Way
F-8
Car position indicators: Car position indicators shall be digital LCD type.
Car direction indicators : Car direction indicators shall have polycarbonate
covers and 160o angle view.
Manual operation : Provision shall be made for manual raising and
lowering by means of spokeless wheel. This wheel
shall be mounted on the drive motor. This facility should be
availed at the control panel.
Announcer : Floor Voice Announcer
ARD : Automatic Rescue Device
Painting : All parts of the control equipment, switchgear
trunking bed plates and closed sections of metal parts which
will not be accessible for painting after erection shall be given
three coats of paint at the manufacture’s works.
All bright surfaces shall be coated with lacquer or other
protective coating before leaving the manufacturer’s works.
Metal works in the lift shaft shall be painted on site with three
coats of best quality oil paint. The lifts machine and other
machinery located in the lifts motor room shall be painted with
three coats of best quality oil paint one coat being applied
after erection.
Motor Room Head : 4.2M
Guarantee of Spare parts : The tenderer must confrim in writing and provide
written commitment from manufacturer, the availability of
parts for the make of lift proposed for installation, for a
continous period of at least 10 (ten) years.
Construction : In general, the lift car shall be constructed from
pressed steel.The method of construction and strenth of lift
cars ,doors and panels shall complywith B.S. 5655. Part 1
1970 and the amendments and in accordance with European
code EN 81.
Base frame : The complete hoisting equipment shall be mounted
on base frame of fablicated steel which when
installed shall be insulataed from the building
structure by means of rubber or other approved
sound and viration isolated material provided and
fixed in an approved manner between frame and
the supporting beams.
Power factor : The powerfactor for the drive shall not be less than
0.9 lagging
F-9
7.0 INFROMATION TO BE SUPPLIED BY THE TENDERER
7.1 The tenderer shall fill in the following information pertaining to the passenger lifts being offered at
the time of tendering:-
F-10
8.0 TECHNICAL SPECIFICATIOS FOR COMPUTER AND ACCESSORIES
8.1 SPECIFICATIONS FOR DESKTOP COMPUTERS
ITEM DESCRIPTION MINIMUM REQUIREMENTS BIDDER’S
SPECIFICATIONS
A GENERAL
SPECIFICATIONS
1 Make BRANDED
2 Model
3 Country of Origin
4 Manufacturer’s brochure Must be supplied
and specifications
B TECHNICAL
SPECIFICATIONS
5 Processor Intel Pentium IV or above - 3.0 GHZ
F-11
8.2 MEDIUM DUTY LASER PRINTER SPECIFICATIONS
4 Country of Origin
5 Manufacturer’s brochure Must be supplied
and specification
B TECHNICAL
SPECIFICATIONS
6 Resolution 1200x1200 dpi
8 Memory 72 MB
9 Languages Enhanced HP PCL,
postscript
10 Maximum Media size A4 paper
F-12
8.3 MEDIUM DUTY UPS SPECIFICATIONS
2
Model
3
Country of Origin
4 Manufacturer’s brochure Must be supplied
and specification
B TECHNICAL
SPECIFICATIONS
5
Rating 650VA
6 220 – 270V ac
Input voltage swing
7 220-240V ac
Output voltage
8
Output frequency 50-60HZ auto-sensing
9 Protection Output overload
Input/output short
circuit
10 Communication Interface Serial port communication
support
11 Design Automatic voltage
regulation
Mains isolation
User replaceable
batteries
Static-automatic
bypass
Maintenance bypass
12 Battery Module 25 minute backup time
3 year lifetime
Sealed lead acid type
preferred
Automatic periodic
battery tests
Short recharge time
(maximum 5 hours for
100% run time)
Protection against
excessive discharge
F-13
Statement of Compliance
b) I confirm I have not made and will not make any payment to any person, who can
be perceived as an inducement to win this tender.
Date: ……………………..
F-14
SECTION G
BILLS OF QUANTITIES
BILLS OF QUANTITIES
Prices will be inserted against item of preliminaries in the Contractor’s Bills of Quantities and
specification. These Bills are designated as Bill No.1 in this Section. Where the Contractor
fails to insert his price in any item he shall be deemed to have made adequate provision
for this on various items in the Bills of Quantities. The preliminaries form part of this
contract and together with other Bills of Quantities covers for the costs involved in
complying with all the requirements for the proper execution of the whole of the
works in the contract.
The brief description of the items in these Bills of Quantities should in no way modify or
supersede the detailed descriptions in the contract Drawings, conditions of contract and
specifications.
The unit of measurements and observations are as per those described in clause 1.0 5 of the
section C.
Summary
The summary contains tabulation of the separate parts of the Bills of Quantities carried
forward with provisional sum, contingencies and any prime cost sums included. The
Contract shall insert his totals and enter his grand total tender sum in the space provided
below the summary.
This grand total tender sum shall be entered in the Form of Tenderprovided
elsewhere in this document.
G-1
SPECIAL NOTES TO BILLS OF QUANTITIES
1. The Bills of Quantities form part of the contract documents and are to be read in
conjunction with the contract drawings and general specifications of materials and works.
2. The prices quoted shall be deemed to include for all obligations under the Contract including
but not limited to supply of materials, labour, delivery to site, storage on site, installation,
testing, commissioning and all taxes (including 16% VAT and 3% withholding tax).
In accordance with Government policy, the 16% VAT and 3% Withholding Tax shall be
deducted from all payments made to the Tenderer, and the same shall be forwarded to the
Kenya Revenue Authority (KRA).
3 All prices omitted from any item, section or part of the Bills of Quantities shall be deemed to
have been included to another item, section or part there of.
4. The brief description of the items given in the Bills of Quantities are for the purpose of
establishing a standard to which the Contractor shall adhere. Otherwise alternative brands
of equal and approved quality will be accepted.
Should the Contractor install any material not specified here in before receiving
writtenapproval from the Project Manager, the Contractor shall remove the material in
question and, at his own cost, install the proper material.
5. The grand total of prices in the price summary page must be carried forward to the Form of
Tender for the tender to be deemed valid.
6. Tenderers must enclose, together with their submitted tenders, manufacturer’s brochures
detailing technical literature and specifications of the generator set that they intend to offer.
Where the brochure contains different models and sizes of generators, the bidders MUST
clearly mark out the model and size of generator they intend to offer by using a ‘mark pen’.
The brochures are to be used to ascertain the suitability of the lift being offered
by the bidders, and bidders not complying with this requirement may be
considered non-responsive and may be disqualified from technical evaluation.
G-2
SCHEDULE 1.0 - CONTRACT PRELIMINARIES (Refer to Section C of thisTender
Document)
Bidders MUST either insert percentage or indicate as NIL for the following
clauses:
(1). Attendance Upon Tradesmen, etc. (Insert percentage only) clause 1.58
of section C
...............................%
G-5
PRICE SCHEDULE 2.0 – PRICE FOR 2NO. PASSENGER LIFTS
3.5 Price for full service maintenance of the 2No.New lifts during the 12
months defects liability period for whole period as described on
page F/5 clause 17.0 @ Kshs. ………….........………per month
3.8 Price for the travelling cable for interfacing fire alarm system,
C.C.T.V and Audio system to be installed by others.
3.9 Price for high quality speakers connected to the cable and installed
in the lift car to engineer’s approval.
3.10 Allow for statutory inspection of the 2No. New lift on commissioning
and thereafter two times during the 12months defects liability
period for the period as described on page F/5 clause 16.0
G-6
PRICE SCHEDULE 3.0 – PROVISIONAL SUMS AND PROJECT MANAGER’S EXPENSES
G-7
PRICE SUMMARY
5.0 Cost for the lift monitoring system complete with the software
for the 2No. Passenger lifts to be installed at the reception
desk as per the particular specifications Item 18.1
.................................................................................................................................
Date …………………………………………………………………………………………
G-8
Name of Witness …………………………………………………………………………..
Address ……………………………………………………………………………………
Signed by Witness.......................................................................
Date ……………………………………………………………
G-9
APPENDIX TO BILLS OF QUANTITIES
APPENDIX ‘A’
…………………………………………………………………………………………………
Date ………………………………………………………………………………………
G-10
APPENDIX TO BILLS OF QUANTITIES
APPENDIX ‘B’
…………………………………………………………………………………………………
Date ………………………………………………………………………………………
G-11
SECTION-H
SPECIAL NOTES
1. The tenderer is advised to note that their price shall be used in the evaluation of the
tenders.
2. The tenderer shall price for both labour and consumables( materials) during the 36 months
full service period in appenix A of this section. The price shall be for supply, installation,
testing and commissioning including all taxes applicable at the time of tender.
3. The tenderer shall list and price the consumable/ spare parts/ materials to be used during
the 36 months full service period in appenix B of this section. The price shall be for supply,
installation, testing and commissioning including all taxes applicable at the time of tender.
4. The tenderer shall list and price the consumable/ spare parts/ materials to be used during
the 36 months full service period. This list is to be comprehensive as possible and shall
inculde major spares as cards, fan motors etc. The price shall be for supply, installation,
testing and commissioning including all taxes applicable at the time of tender. These are
the spare parts that are not required during the normal routine maintenance. These spare
parts shall only be paid for as and when repalced. The tenderer shall give the details of
these spare parts in in appenix C of this section.
5. The price quoted for the above lifts shall be as per the Standard Maintanance Tender
Document which can be examined at the offices of the Project Manager.
6. The tenderer shall be required to the sign the 36 Months after Defects Liability Maintanance
Contract based on the price quoted and the Standard Maintanance Tender Document
refered to in item 5 above.
7. The tenderer MUST fill all the prices and rates in the Appendices A, B and C of this section.
Failure to do so shall lead to disqualification.
H-1
APPENDIX ‘A’
Date................................................................................................................................
H-2
APPENDIX ‘B’
SCHEDULE OF UNIT RATES OF SPARE PARTS THAT MAY BE REQUIRED DURING 36
MONTHS AFTER DEFECTS LIABILITY MAINTENANCE PERIOD (ATTACHMENTS ARE
ALLOWED IF THE LIST IS LONG)
…………………………………………………………………………………………………
Date ………………………………………………………………………………………
H-3
APPENDIX ‘C’
NOTE: The Price Total in this Appendix C SHOULD tally with the Grand Price Total
in Appenix A of this section.
…………………………………………………………………………………………………
Date ………………………………………………………………………………………
H-4
SECTION I
TECHNICAL SCHEDULE
OF
ITEMS TO BE SUPPLIED
TECHNICAL SCHEDULE
1.0 The technical schedule shall be submitted by tenderers to facilitate and enable the Project
Manager to evaluate the tenders
2.0 The filling of this schedule forms part of Technical Evaluation of the tenders, and bidders
shall therefore be required to indicate the type/make and country of origin of all the
materials and equipments they intend to offer to the employer as they shall listed in the
technical schedule.
3.0 Any bid returned with unfilled Technical Schedule shall be considered technically non-
responsive, and the bidder may be disqualified.
I-1
TECHNICAL SCHEDULE OF ITEMS TO BE SUPPLIED
(To be Completed by the Tenderer)
I-2
J/15
Code: E/CG/03
COMMISSIONING GUIDE
FOR
ELECTRIC LIFTS
Issued by:
1. Owner’s manual
2. Specifications/Bills of Quantities
3. As Built (approved) drawings
B. SPECIAL NOTES
Item Details/Remarks
1. Confirm that the main switch is in accordance with the
specified
4. Confirm that the safety signs are inside the MAC and SCP.
10. Confirm that the safety chain has been tested to ensure that
an earth fault will cause disconnection.
Item Details/Remarks
1. Confirm that the above dimensions are within the specified
tolerance
2. Confirm that the car buffers are in accordance with what was
specified by the manufacturer
7. Confirm that the well lighting level above the car roof and the pit is
about 50 lux
8. Confirm that the lighting level in front of the machine is about 200
lux
9. confirm that the terminal light fittings are less than 0.5m from the
pit floor and ceiling
10. Confirm that the lights can be switched from both the pit and
controller
11. Confirm that an electrical outlet has been provided in the pit
13. Confirm that the maximum pitch of the rail fixings does not exceed
the value indicated on the lay out drawing.
J. THE CAR
Item Details/Remarks
3. confirm that where glass panels are used a hand rail is not fixed
on the panels
5. Confirm that the emergency alarm device allows two way verbal
communication with a rescue service
10. Confirm that the ventilation has been provided in the car.
K. CAR TOP
Item Details/Remarks
1. Confirm that the top has been fitted with controls, stopping
devices and socket outlets.
Movement
Stopping
Travel limits
Interaction with emergency recall drive
3. Confirm that the alarm device on the car roof top operates
correctly
4. Confirm that the car roof has one clear area for standing
5. Confirm that the parking device on the car roof operates correctly
mechanically and electronically
6. Confirm that the stopping devices on the car top have been
positioned correctly and provided so that when operated they
stop and prevent movement of the car confirm double presence
incase of double entrance.
L.CAR ENTRANCE CLEARANCE
Item Details/Remarks
1. Confirm that the running clearance between the door
panels and between the panels and uprights, lintels, or
sills is less than or equal to 6mm.
Item Details/Remark
1. Confirm that the over speed governor has been CE
marked.
S. DOCUMENTATION
ELEMENT NO.1:
Extra over (G.I) tubing for Pump manifolds and above desrcribed
pipework:-
ELEMENT NO.2:
Excavations
A Excavate trench in soil/murram for Water Mains supply pipe not 156 LM
exceeding 1200mm deep ,lay pipe,part return in,fill ram and surplus
cart away
Pipe Work
B 25mm diameter (PN-20) PPR Riser in wall chase and distribution 60 LM
pipework to overhead and roof terrace water tanks
C 32mm ditto 32 LM
D 40mm ditto 24 LM
E 50mm ditto 24 LM
F 32mm diameter (PN-20) PPR Pipe laid and jointed in trench 48 LM
G 40mm ditto 60 LM
H 50mm ditto 48 LM
Bends
M 25mm diameter bend/Elbow 10 No.
N 32mm ditto 2 No.
O 40mm ditto 4 No
P 50mm ditto 3 No.
Tees;
Q 25mm diameter equal tee 2 No.
R 32mm ditto 2 No.
S 40mm ditto 4 No
T 50mm ditto 3 No.
Valves;
A 75mm diameter supply mains full way gate valve as PEGLAR or equal 1 No.
and approved
Stand Pipe
I 15mm diameter bib tap suitable for connecting to a hose pipe complete 5 ITEM
with threaded adaptors.The tap to be complete with 5-metre long 20mm
diameter pipe,bends,e.t.c.The chrome plated bib tap to be as 'cobra'
Ref.107EC taps or other approved equivalent
Hydrant Chamber
K Construct Hydrant Chamber approx. size 1200x1200x750mm deep 5 ITEM
with100mm concrete block wall rendered all round in cement nd sand
(1;4) including supply and fixing of 600x450mm mild steel iron cover
and frame in grease
A 100mm diameter G.I. Medium grade supply pipe to the above Hydrants 96 LM
Painting
Allow for priming with suitable anti rust oil paint and to approval on
F the general surfaces of the above described (G.I) pipework before 1 ITEM
laying in trenches
Testing
Allow for connecting the above earlier described Booster pumps to the
pump delivery and suction lines, including Test Pumping and testing
G the whole of the water Reticulation system both during progress and at 3 ITEM
commissioning to leave in sound working condition and to the
Engineer's satisfaction
ELEMENT NO.3:
PROVISIONAL SUMS:
A Provide a Provisional Sum of Kenya Shillings One Hundred and 1 ITEM 150000 150,000.00
Fifty Thousand (Kshs. 150,000.00) only for Engineers Supervision
and Contract Administration Expenses
B Provide a Provisional Sum of Kenya Shillings Five Hundred 1 ITEM 500000 500,000.00
Thousand (Kshs.500,000.00) only for Contigencies
SUBTOTALS…………………………………………………….
GRAND TOTAL……………………………………………………
……………………………………………………………………….
……………………………………………………………………….
……………………………………………………………………….
DATE:…………………………SIGNATURE:…………………….
……………………………………………………………………….
DATE:…………………………SIGNATURE:…………………….
Kichen Hood,Mechanical Ventilation,L.P.Gas Storage Tank and Distribution Services For The
Proposed County Assembly Block
ELEMENT NO.1:
Extract System:
ELEMENT NO.2:
L.P.GAS INSTALLATION:
Tees
E 10mm diameter heavy duty brass equal tee 4 No.
F 15mm ditto 2 No.
G 10x10x8mm diameter brass reducing tee 3 No.
H 25x25x20mm ditto 1 No. -
Stop Cocks
I 10mm diameter Stop Cock 1 No.
J 15mm ditto 1 No.
K 20mm ditto 1 No.
L 25mm ditto 1 No.
Testing
M Allow for Testing the whole L.P.Gas Installation both during progress 1 ITEM
and at Commissioning to the Engineer's satisfaction and to leave the it
in sound and good working condition
ELEMENT NO.3:
PROVISIONAL SUMS
A Provide a Provisional Sum of Kenya Shillings Fifty Thousand (Kshs. 1 ITEM 50,000.00 50,000.00
50,000.00) only for Engineers Supervision and Contract Administration
Expenses.
B Provide a Provisional Sum of Kenya Shillings Two Hundred 1 ITEM 200,000.00 200,000.00
Thousand (Kshs.200,00.00) only for Contingencies
SUBTOTALS…………………………………………………….
GRAND TOTAL…………………………………………………….
SHILLINGS……………………………………………………………
…………………………………………………………….
……………………………………………………………………….
……………………………………………………………………….
……………………………………………………………………….
DATE…………………………….SIGNATURE……………………
……………………………………………………………………….
……………………………………………………………………….
DATE…………………………….SIGNATURE……………………
PROVISIONAL SUMS
ITEM DESCRIPTION UNIT AMOUNT
PROVISIONAL SUMS
PC PC/1
MAIN SUMMARY
ITEM DESCRIPTION SHS SHS
PROPOSED COMPLETION OF THE FOR OFFICIAL FOR
ASSEMBLY OFFICE BLOCK FOR THE USE CONTRACTORS
COUNTY ASSEMBLY OF KILIFI USE
………………………………………………………………………………………………………………….
ADDRESS ,………………………………………………………………………………
,……………………………………………………………………………..
DATE ,……………………………………………………………………………………
SIGNATURE ,…………………………………………………………………………...
ADDRESS ,……………………………………………………………………………...
,……………………………………………………………………………..
DATE ,……………………………………………………………………………………
SIGNATURE,…………………………………………………………………………....
MS/1