Introduction to Construction Methods and Project Management
Introduction to Construction Methods and Project Management
PROJECT MANAGEMENT
CHAPTER 1
An Overview to Construction
Methods and Project Management
1. Construction Scheduling
2. Quality Control
3. Contract Management
4. Procurement Management
5. Construction Finance Management
Construction Scheduling
Construction scheduling is done at two
different times. First, it is done after the
plans are ready, but before the work starts
at the site, in order to work out a timeline
and calculate construction costs for the
Secondly, it is done during the execution
of the project, when the actual schedule
may differ from the planned schedule
due to delays, weather, or any number
of reasons. In this case it can also be
called project monitoring.
Quality Control years of training in construction quality
supervision.
Quality control is the most difficult part of
construction management. Construction is
done in difficult weather, in restricted
workspaces like shafts, and on precarious
construction scaffolding by workers that
are tired, hungry, cold or hot, and with
limited bathroom access. It is easy for
them to take shortcuts to finish off a job.
A quality control supervisor must know how
to check for quality for a vast array of
completely different work items, from
excavation in the ground to concrete or
steel fabrication to finishing materials like
marble or paint to services like electrical
and plumbing. Quality control demands
technical knowledge, and is best done
either by engineers, or people who have
She or he will have to know the answer to
questions such as: what is the correct
proportion of water to add to a concrete
mix, how to check whether wooden
formwork is correctly laid and is perfectly
level, how to ensure that the geometry of
the building is not being distorted during
construction, and how to provide
adequate fire protection to vertical
shafts.
Contract Management
Contract Management is dealing with the
standard issues that crop up during a
project. These include checking
contractor's bills and paying them
regularly, and dealing with the numerous
issues that could occur, such as:
the contractor demands additional
payment for the steel he is providing,
because though his contract was signed in
2015, he is forced to buy steel in 2017 at a
much higher rate due to global changes in
the price of steel. The contractor demands
additional payment for dumping of debris
because a municipal dumping ground has
been shut, and the debris now has to be
taken to a new site much further away. The
contractor demands an extension of 4
months because the architects and client
made changes to the design while the
project was underway
Procurement Management negotiations with customs authorities and
clearance agents.
Procurement is a huge component in
building construction. Think of the vast
array of materials that are present in
buildings: light fittings, windows, doors,
locks, toilet fittings, wire, switches, air-
conditioning ducts, waterproofing,
electrical transformers, pumps, plants,
sound systems: the list is endless.
Each and every one of these items has to
be ordered, paid for, checked when it
arrives, unloaded from trucks, placed in
secure storage, and issued to construction
workers. Damaged items and non-
functional items need to be replaced. Many
items are sourced internationally, such as
Italian marble, German door fittings, or
Canadian glulam beams, requiring
In addition, it is imperative that each
item arrive at the site at exactly the right
moment: if it is too early, there is no
space to store it, and money is locked up.
If it is too late, then the project is
delayed.
Construction Finance Management
A large construction project can eat up
tens of millions of money a month.
Planning the finances for a project is a key
activity for both owners and contractors.
This planning demands a detailed
knowledge of the project schedule. Once
the project schedule is understood
properly, calculations can be made of how
much money will be required every week in
order to keep the project running on time.
Contingency planning also must be done
for things that could go wrong.