NHIDCL All-States Feb'2022
NHIDCL All-States Feb'2022
Date of
NHDP NH No. Sanctioned Awarded Cumulative Cumulative Target date of
SL. Mo Length Date of Start/ Likely Date of
Phase/ Name of Project (Old/ Cost/TPC Cost Physical Financial completion as Name of the Contractor
No. de (Km) Award Appointed completion
Scheme New) Rs. in crore Rs. in crore progress % progress % per contract
Date
Target date
NHDP NH No. Sanctioned Awarded Date of Cumulative Cumulative of Likely date
SL. Length
Mode Phase/ Name of Project (Old/ Cost/TPC Cost Date of Award Start/Appointed Physical Financial completion of Name of the Contractor
No. (Km)
Scheme New) Rs. in crore Rs. in crore Date progress % progress % as per completion
contract
Meghalaya
Improvement/Widening to 2-Lane with Paved M/s ARSS Infrastructure Pvt Ltd (CA signed on
10 EPC EAP (JICA) 40 26.55 525.68 210 24-11-2020 26-12-2020 24.02% 16.01% 26-12-2022 26-12-2022
Shoulder from (design Km 10.670 to Km 09.12.2020)
37.550) between Shillong-Dawki (Pkg-2)
Improvement/Widening to 2-Lane with Paved M/s SS Infrazone Pvt. Ltd.
11 EPC EAP (JICA) Shoulder from (design Km 45.760 to Km 40 17.77 445.51 88.2 02-11-2020 14-12-2020 17.92% 12.50% 14-12-2022 14-12-2022 (CA Signed on 16.11.2020)
63.530) between Shillong-Dawki (Pkg-4)
Improvement/Widening to 2-Lane with Paved
Shoulder / 4-Laning from (design Km 63.530 M/s Niraj Cement Structurals Limited.
12 EPC EAP (JICA) 40 7.99 284.21 141.14 23-11-2020 28-12-2020 13.70% 5.18% 28-12-2022 28-12-2022
to Km 71.520) between Shillong-Dawki (Pkg- (CA signed on 09.12.2020)
5)
Total 281.07 3819.51 1791.79
Status as on 28-02-2022
NH Awarded
NHDP Sanctioned Date of Cumulative Cumulative Target date of
SL. No. Length Cost Date of Likely date of
Mode Phase/ Name of Project Cost/TPC Start/Appoin Physical Financial completion as Name of the Contractor
No. (Old/ (Km) Rs. in Award completion
Scheme Rs. in crore ted Date progress % progress % per contract
New) crore
Mizoram
Rehabilitation and Up-gradation to 2 lane with
paved shoulders of Economic Corridor of NH-6
1 EC NH(O)-NE 6 13.51 206.9 134.91 31-03-2020 01-07-2020 31.17% 26.60% 01-07-2022 01-07-2022 M/s GVV Construction Pvt. Ltd.
from Design Chainage Km 00+000 to Km
13+510 (Selling-Dulte - I)
4-Laning from Gohpur to Holongi section from km 264.10 M/s ECI Engg.Construction Co. Ltd.
13 EPC SARDP 52 10.08 223.3 168.39 30-03-2015 11-12-2015 91.94% 90.39% 10-12-2018 30-09-2021
of NH 52 to km 20.37 of NH 52A
Arunachal Pradesh
2 laning from Mahadevpur to Buri Dihing M/s Dineshchandra R. Agarwal Infracon Pvt. Ltd.-
1 EPC SARDP 52B/ 215 25.135 136.6 107.16 31-03-2015 30-05-2015 100.00% 100.00% 30-05-2018 Completed
section of NH-52B Puna Hinda (JV)
6 EPC SARDP 2 laning of Singer river to Sijon nala 513 23.38 238.46 179.82 09-11-2015 15-01-2016 100.00% 100.00% 19-01-2019 Completed M/s ABL-BIPL (JV)
Sikkim
Improvement & Rehabilitation of
existing Indira Bye Pass road form
Item
1 NH(O) Km 0.000 to km 10.117 on NH-10 in NH-10 10.12 33.24 17.57 28-03-2018 04-05-2018 100.00% 100.00% 15-08-2019 Completed M/s Pasang Lama & Sons
Rate
the State of Sikkim on Item Rate
Basis
2-lane Chisopani Traffic Tunnel
of length 250 m including
2 EPC NH(O) NH-10 0.42 35.69 29.00 05-03-2019 10-09-2019 80.89% 78.19% 08-09-2021 31-12-2021 M/s Nagyan Constrcution Pvt. Ltd
approaches from Km 67+080 to
Km 67+500
Construction of 48m Bridge over
3 EPC NH(O) Chuba Khola at Km 75+300 to Km NH-10 0.48 8.93 7.45 21-05-2019 16-09-2019 71.01% 59.17% 15-09-2021 30-05-2022 Mohan Bajaj
75+800 on NH-10
M/s Dinesh ChandraAgarwal Infracon Pvt.Ltd.Jagdish Agarwal Ph
Construction of Rangpo-Viaduct
No.09824089999
4 EPC SARDP at Rangpo town Km 51.100 to 10 1.12 133.49 55.79 16-12-2016 20-02-2017 74.50% 68.76% 20-02-2020 10-04-2022
Deepak Sinha
53.800 NH-10
ph.no-8373091911
Construction / Upgrade existing
road to 2 lane with paved shoulder
5 EPC SARDP 510 16.00 375.8 163 26-02-2019 05-10-2019 53.69% 50.19% 05-04-2022 05-04-2023 M/s. VKJ-NSPR (JV) .
from Km 0.000 to 16.000 Singtam -
Tarku NH-510
NHDP NH No. Sanctioned Awarded Date of Cumulative Cumulative Target date of Likely date
SL. Length Date of
Mode Phase/ Name of Project (Old/ Cost/TPC Cost Start/Appoin Physical Financial completion as of Name of the Contractor
No. (Km) Award
Scheme New) Rs. in crore Rs. in crore ted Date progress % progress % per contract completion
Tripura
2-laning with Paved shoulder of Udaipur-
44 (New
1 ICR SARDP Sabroom Section of NH-44 from Km 55.00 to 73.712 915 497.89 02-05-2014 31-10-2015 100.00% 100.00% 30-04-2018 Completed M/s Oriental Structural Engineers Pvt. Ltd
NH-08)
128.712
Construction of Extra-dosed RCC Bridge
including viaduct and approaches over river 44 (New
2 BW NH(O) 1.888 128.69 82.57 22-03-2017 27-10-2017 99.50% 99.13% 26-04-2020 Completed M/S DRA Infracon Pvt. Ltd.
Feni at Sabroom on Indo-Bangladesh Border NH-08)
on NH-8 (old NH-44)
2-laning with Paved shoulder of Agartala-
44 (New
3 ICR SARDP Udaipur Section of NH-44 from Km 6.800 to km 48.2 649 369 31-10-2014 15-09-2015 99.21% 97.23% 14-03-2018 Completed M/s KMC Construction
NH-08)
55.00
Strengthening of Churabari - Agartala section
4 EPC NH(O)-NE 8 74.9 257.96 202 03-06-2020 24-07-2020 100.00% 99.65% 15-01-2022 Completed M/s Shiv Build India Pvt. Ltd.
of NH-08 (74.876 Km) on EPC basis
Manipur
2- Laning of Imphal – Moreh Section of NH
EAP M/s GR Infra Projects ltd
1 EPC 39 from Km 350.000 to Km 395.680 39 44.78 868.75 457.77 01-06-2018 16-10-2018 100.00% 96.66% 15-10-2021 Completed
(ADB)
(Package II)
Construction of :(i) 154m span steel
superstructure Bridge at km 145.090 over
river Barak & (ii) 122m span steel
2 BW NH(O) 53 2 141.14 109 02-12-2016 27-04-2017 88.25% 80.38% 24-04-2020 30-05-2022 M/s Bhartia Infra (BIPL)
superstructure Bridge at km 189.800 over
river Makru and Approaches of both the
Bridges to be constructed is 1595m.
Construction of 4-Lane Bridge over Irang
3 BW NH(O) River on Imphal-Jiribam road section (95.50 53/ 37 0.377 49.31 41.88 27-11-2020 04-01-2021 28.57% 20.25% 16-10-2022 16-10-2022 Paratech Constructions Pvt. Ltd.
Km)
Widening to 2 -Lane with Paved shoulder
of Imphal to Jiribam section of NH-37 from
4 EPC NH(O)-NE 53/ 37 12.67 139.38 78.99 30-03-2021 01-07-2021 2.50% 0.00% 31-12-2022 31-12-2022 Avantika Contractor (I) Ltd.
Design Chainage 3.275 km to 15.940 Km
(Total length=12.665 Km) (PKG-1)
Restoration/Reconstruction of Ukhrul-
% Toloi-Tadubi road section from Km 0.00
4 NH (O) 102A 28.00 3.78 2.98 26-10-2016 27-10-2016 100.00% 100.00% 26-01-2018 Completed M/s Bhartia Infra Projects Limited
rate to Km 28.00 covering 28 Km length on
NH-102A in the state of Manipur.
Restoration/Reconstruction of Ukhrul-
% Toloi-Tadubi road section from Km 28.00
5 NH (O) 102A 22.00 14.91 11.12 26-10-2016 07-11-2016 100.00% 100.00% 06-02-2018 Completed M/s Shingvah Thanami
rate to Km 50.00 covering 22 Km length on
NH-102A in the state of Manipur.
Restoration/Reconstruction of Ukhrul-
% Toloi-Tadubi road section from Km 50.00
6 NH (O) 102A 20.00 11.40 11.35 26-10-2016 11-01-2016 100.00% 100.00% 31-01-2018 Completed M/s Bhartia Infra Projects Limited
rate to Km 70.00 covering 20 Km length on
NH-102A in the state of Manipur.
Restoration/Reconstruction of Ukhrul-
% Toloi-Tadubi road section from Km 70.00
7 NH (O) 102A 20.00 15.64 13.07 29-03-2017 24-05-2017 100.00% 100.00% 23-05-2018 Completed M/s Haokhotinlen Vaiphei
rate to Km 90.00 covering 20 Km length on
NH-102A in the state of Manipur.
Restoration/Reconstruction of Ukhrul-
% Toloi-Tadubi road section from Km 90.00
8 NH (O) 102A 25.00 15.37 12.91 29-03-2017 24-05-2017 100.00% 100.00% 23-05-2018 Completed M/s Haokhotinlen Vaiphei
rate to Km 115.00 covering 25 Km length on
NH-102A in the state of Manipur.
Rehabilitation/Strengthening of existing
%
9 NH (O) road Churachandpur- Singhat-Sinzawl- 102B 34.5 47.82 37.69 28-11-2017 12-12-2017 100.00% 100.00% 23-09-2019 Completed M/s Satya Builders
rate
Tuivai sector from Km 0.00 to Km 34.500
Rehabilitation/Strengthening of existing
%
10 NH (O) road Churachandpur- Singhat-Sinzawl- 102B 68.6 69.31 54.08 08-06-2016 01-08-2016 100.00% 100.00% 01-08-2019 Completed M/s Bhartia Infra Projects Limited
rate
Tuivai sector from Km 34.00 to Km 103.1
Rehabilitation/Strengthening of existing
% road Churachandpur- Singhat-Sinzawl-
11 NH (O) 102B 58.38 59.4 45.12 04-01-2018 18-01-2018 100.00% 100.00% 30-10-2019 Completed M/s Garg & Sons
rate Tuivai sector from Km 103.1 to Km
161.48