NHIDCL All-States Feb'2022

As of February 28, 2022, the NHIDCL has completed 37 original works totaling 739 km at a cost of Rs 7278 crore, with 282 civil works in progress covering 5637 km at a cost of Rs 106500 crore. The document provides a detailed breakdown of completed and ongoing projects by state, including project lengths, costs, and contractor details. Specific projects include road rehabilitation and upgrades across various states, with completion percentages and target dates outlined.

Uploaded by

Anish Raj
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
35 views23 pages

NHIDCL All-States Feb'2022

As of February 28, 2022, the NHIDCL has completed 37 original works totaling 739 km at a cost of Rs 7278 crore, with 282 civil works in progress covering 5637 km at a cost of Rs 106500 crore. The document provides a detailed breakdown of completed and ongoing projects by state, including project lengths, costs, and contractor details. Specific projects include road rehabilitation and upgrades across various states, with completion percentages and target dates outlined.

Uploaded by

Anish Raj
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 23

As on 28-02-2022

ORIGINAL WORKS - NHIDCL

Total Completed Works Total Civil works in progress


RO STATE
Length Cost Length Cost
Nos. (in Km ) (Rs in Cr) Nos. (in Km ) (Rs in Cr)

1 Arunachal Pradesh 12 303.4 2984.4 35 750.6 10081.2

2 Assam 4 70.0 491.6 35 672.4 19075.0

3 Manipur 1 44.8 868.8 41 805.3 12722.9

4 Meghalaya 12 281.1 3819.5

5 Mizoram 27 736.4 14944.9

6 Nagaland 35 645.2 10762.0

7 Sikkim 1 10.1 33.2 19 220.6 4812.0

8 West Bengal 1 1.5 158.7 7 79.1 1834.4

9 Tripura 3 123.8 1692.7 22 489.8 6086.2

10 Andaman & Nicobar Island 6 142.8 675.4 11 321.0 2082.8

11 Jammu & Kashmir 2 37.2 24.5 19 300.2 15164.5

12 Ladakh 8 230.0 2287.0

13 Uttarakhand 7 5.5 348.9 11 105.0 2827.6

Grand Total 37 739 7278 282 5637 106500


Status as on 28-02-2022

Date of
NHDP NH No. Sanctioned Awarded Cumulative Cumulative Target date of
SL. Mo Length Date of Start/ Likely Date of
Phase/ Name of Project (Old/ Cost/TPC Cost Physical Financial completion as Name of the Contractor
No. de (Km) Award Appointed completion
Scheme New) Rs. in crore Rs. in crore progress % progress % per contract
Date

Andaman & Nicobar


Rehabilitation and Upgradation of Jarwa
Item area of NH-223 (New NH-4) from Km 59.40 to
1 NH(O) NH-4 64.3 59.56 53.73 05-03-2018 09-04-2018 100.00% 97.38% 09-04-2019 Completed M/s Jandu Construction Company
Rate Km 107.00 and Km 138.30 to Km 155.00 on
Item Rate basis
Construction of Major Bridge over
2 EPC NH(O) Humphrey Strait Creek between Km.129.420 NH-223 /NH-4 1.45 277.17 202.909 15-02-2017 26-04-2017 100.00% 95.00% 25-04-2020 Completed MBZ -RDS (JV)
to Km. 130.600 of NH-223
2-Lane with hard shoulder, Rehabilitation
and up-gradation of Beodnabad- Ferrargunj
3 EPC NH(O) NH-223 /NH-4 25.93 175.127 124.74 01-03-2017 01-11-2017 100.00% 100.00% 02-04-2019 Completed M/s DRA Infracon Pvt. Ltd.
section of NH-223 from Km 12.0 to 45.0
(excluding Km 21.0 to 28.0) (Package-I)
Rehabilitation of Km 0.00 to Km 12.00
section in Andaman Trunk Road of NH-4 to
4 EPC NH(O) NH-4 12 32.54 22.6 14-02-2019 02-04-2019 100.00% 99.19% 30-03-2020 Completed M/s Mohan Mutha Exports Pvt Ltd
Intermediate lane with hard shoulder
(Package-V)
Rehabilitation of section from Km 45.00 to
5 EPC NH(O) Km 59.20 of NH-4 to Intermediate lane with NH-4 14.1 59.08 37.67 14-02-2019 02-04-2019 99.68% 98.80% 30-03-2020 Completed M/s Mohan Mutha Exports Pvt Ltd
hard shoulder (Package-VI)
Rehabilitation of Km 181.00 to Km 206.00
section in Andaman Trunk Road of NH-4 to
6 EPC NH(O) NH-4 25 71.93 53.96 28-11-2018 01-01-2019 100.00% 99.06% 31-12-2019 Completed M/s Garg & Sons Estate Promoters Pvt Ltd
Intermediate lane with hard shoulder
(Package-VII)
Construction of Major Bridge over Middle
Strait Creek between Km. 106.590 to Km.
M/s Mantena Constructions Pvt. Ltd.- Vasishta
7 EPC NH(O) 107.762 of NH-223 (New NH-4) connecting NH-223 /NH-4 1.9 262.97 170.4 18-12-2017 03-01-2019 38.19% 37.39% 01-01-2022 01-01-2022
Constructions Pvt. Ltd. Bridge (JV)
South Andaman and Baratang Islands in UT
of A&N.
2-Lane with hard shoulder, Rehabilitation
M/s Vasishta Constructions Pvt. Ltd. - Mantena Infra
8 EPC NH(O) and up-gradation of section from Km 242.0 233/ NH-4 55.45 409.85 190.7 31-03-2017 05-12-2017 78.53% 77.66% 05-12-2019 31-12-2021
LLP NH (JV)
to 298.0 of NH-223 (New NH-4). (Package-II)

2-Lane with hard shoulder, Rehabilitation


and up-gradation of sect. from Km 107.760-
129.445,(Middle strait to Humphrey),Km M/s Mantena Constructions Pvt. Ltd.- Vasishta
9 EPC NH(O) 233/ NH-4 54.71 391.01 248.277 12-03-2018 04-09-2018 44.46% 37.47% 02-09-2020 31-12-2021
130.600 -138 (After Humphrey-Kadamtala) & Constructions Pvt. Ltd. Strait (JV)
Km155.00 -181.0 (End of Jarwa-Rangat)
(Package-III)

2-Lane with hard shoulder, Rehabilitation


and up-gradation of section from Km 206.00
10 EPC NH(O) 233/ NH-4 33.45 234.27 148.6 27-03-2018 04-09-2018 64.22% 61.77% 2-Sep-20 31-12-2021 M/s Vasishta Construction Pvt.Ltd
to Km 242.00 (Nimbutala to Austin Creek) of
NH-223 (New NH-4) (Package-IV).
Rehabilitation of section from Km 298.00 to
Km 330.662 (Karala to Kalipur) of NH-04 to
11 EPC NH(O) NH-4 32.662 109.33 74.611 13-04-2021 01-07-2021 2.34% 0.45% 01-07-2023 01-07-2023 Kaba Infratech Pvt. Ltd.
Intermediate lane with hard shoulder
(Package-VIII)
Total 320.95 2082.84 1328.20
Status as on 28-02-2022

Target date
NHDP NH No. Sanctioned Awarded Date of Cumulative Cumulative of Likely date
SL. Length
Mode Phase/ Name of Project (Old/ Cost/TPC Cost Date of Award Start/Appointed Physical Financial completion of Name of the Contractor
No. (Km)
Scheme New) Rs. in crore Rs. in crore Date progress % progress % as per completion
contract

Meghalaya

2- laning of Ranikor-Nonghyllam- Maheshkola-


Baghmara (from design Ch. 0.000 to Ch. M/s Dhar Construction Company & Chanchal Paul
1 EPC SARDP SH 04 33.25 306.28 216.33 09-03-2019 30-09-2019 43.29% 41.19% 30-03-2022 30-03-2022
129.385) Package-I: Existing Ch. 0.000 to (JV)
Ch.31.700 (Pkg-1)

lmprovement/widening to 2-laning with


earthen shoulder of Nongjri (Design Ch.
30.00km) to Maheshkola (Design Ch.
2 EPC NH(O)-NE 55.525km )[R-M-B Package 2 on SH-4 section SH 04 25.525 283.5 140.928 07-03-2022 to be given 0.00% 0.00% M/s Dhar Construction Company
of Ranikor- Maheshkhola- Baghmara Project
in the state of Meghalaya under NH (O)-NE
(Pkg-2)

lmprovement/ widening to 2-laning with


earthen shoulder from Maheshkola to kanai
3 EPC SARDP existing chainage from Ch. 59.270 to Ch. SH 04 25 260.21 150.2 27-03-2021 28-06-2021 22.70% 16.62% 28-12-2022 28-12-2022 DMR Builders Pvt. Ltd.
85.970 (Design Ch. 55.525 to Ch. 79.680) on
SH-4 Ranikor-Baghmara Project (Package-3)

Improvement/widening to 2-lane with Earthen


shoulder of Ranikor-Maheshkhola- Baghmara
road section from Kanai to Rongara, existing
4 EPC NH(O)-NE SH 04 14.763 157.86 82.80 30-09-2020 24-10-2020 48.22% 38.23% 26-04-2022 26-04-2022 Narendra Sharma
Ch. From Km 85.970 to Km 102.345 (Design
Ch. From Km 81.100 to Km 96.000) Design
length-14.763 km on EPC (Pkg-4)

Improvement/widening to 2-lane with Earthen


shoulder of Ranikor-Maheshkhola- Baghmara
road section from Rongara to Panda, existing
5 EPC NH(O)-NE SH 04 16.30 146.88 74.41 30-09-2020 24-10-2020 55.95% 46.47% 26-04-2022 26-04-2022 Narendra Sharma
Ch. From Km 102.345 to Km 119.810 (design
Ch. From Km 96.00 to Km 112.300) design
length-16.30 km on EPC (Pkg-5)

lmprovement/ widening to 2-laning with


earthen shoulder of Panda (Design Ch.
112.300 km) to Baghmara (Design Ch. 129.385
6 EPC NH(O)-NE km )[R-M-B Package-Vl] on SH-4 section of SH 04 17.085 144.99 82.336 27-01-2022 to be given 0.00% 0.00% Nidhi Creative Infrastructure Pvt. Ltd.
Ranikor- Maheshkhola- Baghmara Project in
the state of Meghalaya under NH(O)-NE (Pkg-
6)

Rehabititation and up gradation of Nongstoin-


Rambrai-Kyrshai road up to Meghalaya-
7 EPC NH(O)-NE Assam border from Km 0.335 to km 34.039 to - 33.70 359.86 155.54 27-01-2022 to be given 0.00% 0.00% SPICA Projects & Infrastructures Pvt. Ltd.
2-Lane under NH(o) - NE in the State of
Meghalaya (Package-l)

Widening to 2- lane with Geometric


improvement of Tura-Dalu Road from Km
M/s Manaranjan Brahma (MB Constructions)
8 EPC EAP (JICA) 85.000 to Km 95.000 & Km 101.000 to km 51 51.54 553.41 358.65 28-03-2018 15-09-2018 43.30% 42.13% 14-09-2021 30-03-2022
145.000 to 2-lanes with paved shoulder of
Tura- Dalu section
Improvement/Widening to 2-L with Paved
Shoulder from (design Km 0.00 to Km 10.670) M/s SS Infrazone Pvt. Ltd.
9 EPC EAP (JICA) 40 11.60 351.12 91.26 02-11-2020 14-12-2020 6.66% 5.20% 14-12-2022 14-12-2022 (CA Signed on 16.11.2020)
/ 4-Laning from (design Km 0.00 to Km
0.930) between Shillong-Dawki (Pkg-1)

Improvement/Widening to 2-Lane with Paved M/s ARSS Infrastructure Pvt Ltd (CA signed on
10 EPC EAP (JICA) 40 26.55 525.68 210 24-11-2020 26-12-2020 24.02% 16.01% 26-12-2022 26-12-2022
Shoulder from (design Km 10.670 to Km 09.12.2020)
37.550) between Shillong-Dawki (Pkg-2)
Improvement/Widening to 2-Lane with Paved M/s SS Infrazone Pvt. Ltd.
11 EPC EAP (JICA) Shoulder from (design Km 45.760 to Km 40 17.77 445.51 88.2 02-11-2020 14-12-2020 17.92% 12.50% 14-12-2022 14-12-2022 (CA Signed on 16.11.2020)
63.530) between Shillong-Dawki (Pkg-4)
Improvement/Widening to 2-Lane with Paved
Shoulder / 4-Laning from (design Km 63.530 M/s Niraj Cement Structurals Limited.
12 EPC EAP (JICA) 40 7.99 284.21 141.14 23-11-2020 28-12-2020 13.70% 5.18% 28-12-2022 28-12-2022
to Km 71.520) between Shillong-Dawki (Pkg- (CA signed on 09.12.2020)
5)
Total 281.07 3819.51 1791.79
Status as on 28-02-2022
NH Awarded
NHDP Sanctioned Date of Cumulative Cumulative Target date of
SL. No. Length Cost Date of Likely date of
Mode Phase/ Name of Project Cost/TPC Start/Appoin Physical Financial completion as Name of the Contractor
No. (Old/ (Km) Rs. in Award completion
Scheme Rs. in crore ted Date progress % progress % per contract
New) crore
Mizoram
Rehabilitation and Up-gradation to 2 lane with
paved shoulders of Economic Corridor of NH-6
1 EC NH(O)-NE 6 13.51 206.9 134.91 31-03-2020 01-07-2020 31.17% 26.60% 01-07-2022 01-07-2022 M/s GVV Construction Pvt. Ltd.
from Design Chainage Km 00+000 to Km
13+510 (Selling-Dulte - I)

Rehabilitation and Up-gradation to 2-lane with


paved shoulders of Economic Corridor of NH-
2 EC NH(O)-NE 6 13.89 216.49 138.75 31-03-2020 01-07-2020 59.35% 48.86% 01-07-2022 01-07-2022 M/s NG Projects Ltd.
06 from Design Chainage Km 13+510 to km
27+400 (Selling-Dulte - II)

Rehabilitation and Up-gradation to 2- lane with


paved shoulders of Economic Corridor of NH-6
3 EC NH(O)-NE 6 17.64 292.23 197.38 31-03-2020 01-07-2020 39.71% 35.20% 01-07-2022 01-07-2022 M/s NG Projects Ltd.
from Design Chainage km 27+400 to km 45+040
(Selling-Dulte - III)

Rehabilitation and Up-gradation to 2-lane with


pave shoulders of Economic Corridor of NH-6
4 EC NH(O)-NE 6 17.16 281.77 185.49 31-03-2020 01-07-2020 67.02% 60.94% 01-07-2022 01-07-2022 M/s Anusha Projects Pvt. Ltd.
from Design Chainage Km 45+040 to Km
62+200 (Selling-Dulte - IV)

Up-gradation to 2 lane with paved shoulders of


Dulte-Kwalkulh road
5 IC NH(O)-NE 6 17.95 374.39 212.365 31-03-2021 25-06-2021 28.61% 17.77% 25-12-2022 25-12-2022 Dhariwal Buildtech Ltd.
(International Corridor) of NH-6 from Design
Chainage Km 54.400 to Km 72.350 (Package-I)
Rehabilitation and Up-gradation to 2 lane with
paved shoulders of
6 IC NH(O)-NE Kwalkuth-Khawzawl road (lnternational 6 12.45 233.25 121.031 31-03-2021 25-06-2021 14.85% 11.97% 25-12-2022 25-12-2022 Dwarakamai Constructions Pvt. Ltd.
Corridor) of NH-6 from Design Chainage Km
72.350 to Km 84.800 (Package-ll)
Up-gradation to 2 lane with paved shoulders of
Khawzawl-Champhai road (lnternational RKC Infrabuilt Pvt. Ltd. - Shri Balaji Construction
7 IC NH(O)-NE 6 26.78 674.71 370.432 31-03-2021 25-06-2021 23.30% 14.23% 25-06-2023 25-06-2023
Corridor) of NH-6 from Design Chainage Km Company [RKCIPL- SBCC] (JV)
84.800 to Km 111.580 (Package-lll)

4-Laning of Vairengte - Chhimluang section


(Package-3) of NH-306
from Existing Chainage km 43+000 to Km
8 EC NH(O)-NE 59+700 (Design Chainage km 46+000 to km 306/ 6 14.85 491.39 244.69 27-01-2022 to be given 0.00% 0.00% Dhatarwal Construction Company Pvt. Ltd.
60+850) on Silchar - Vairengte- Sairang road in
the State of Mizoram under Bharatmala
Pariyojna under NH(O)-NE

4-Laning of chhimluang-Kolasib from section


(pkg-4) of NH-306 & NH-6 existing chainage km
59+700 to km 86+000 (design chainage km
9 EC NH(O)-NE 61+000 to km 77+500) on Silchar-vairengte- 306/ 6 16.5 561.91 276.728 28-01-2022 to be given 0.00% 0.00% Shiwalay Infra Projects Pvt. Ltd.
sairang road in the state of Mizoram under
Bharatmala Pariyojna on EPC mode
Vairengte - Sairang Pkg-4

4-Laning of Kolasib - Sethawn section (Package-


5) of NH-6 from Existing Chainage km 86+000 to
km 107+850 (Design Chainage km 77+500 to km
10 EC NH(O)-NE 95+500) on silchar - vairengte - sairang road 306/ 6 18.00 720.40 Under bidding 0.00% 0.00%
under Bharatmala Pariyojna on EPC mode
under NH(O)-NE
Vairengte - Sairang Pkg-5

4-Laning of Sethawn - N. Kawnpui section


(Package-6) of NH-6 from Existing Chainage km
107+850 to km 126+315 (Design Chainage km
11 EC NH(O)-NE 95+500 to km 111+850) on Silchar-Vairengte- 306/ 6 16.35 595.65 Under bidding 0.00% 0.00%
Sairang road in the State of Mizoram under
Bharatmala Pariyojna on EPC mode
Vairengte - Sairang Pkg-6
Construction of 2-laning with hard shoulder
configuration of Lunglei to Chhumkhum from
12 IC NH(O)-NE 302 37.42 698.45 404.592 30-03-2021 30-06-2021 0.00% 0.00% 30-12-2022 30-12-2022 SRK Constructions and Projects Pvt. Ltd.
Design Chainage Km 0.000 to Km 37.420 of NH-
302 [Pkg-A]
Construction of 2-laning with hard shoulder
configuration of Chhumkhum to Tlabung from
13 IC NH(O)-NE 302 37.53 740.58 435.392 31-03-2021 10-07-2021 12.00% 2.50% 09-01-2023 09-01-2023 SRK Constructions and Projects Pvt. Ltd.
Design Chainage Km 37.420 to Km 74.950 of NH-
302 [Pkg-B]
Widening and up-gradation to 2-lane with
paved shoulder configuration and geometric
14 ICR EAP (JICA) 54 56.96 1099.95 699.3 25-11-2019 24-01-2020 23.00% 17.04% 25-07-2023 25-07-2023 M/s Gawar-SCCPL (JV)
improvements from km 8.00 to km 65.00
(Package-1) on Aizawl-Tuipang section

Widening and up-gradation to 2-lane with


M/s Gammon Engineers and Contractors Private
paved shoulder configuration and geometric
15 ICR EAP (JICA) 54 53.263 1027.83 512 08-03-2019 23-12-2019 28.49% 24.52% 22-06-2023 22-06-2023 Limited
improvements from km 65.00 to km 125.00
(Package-2) on Aizawl-Tuipang section

Widening and up-gradation to 2-lane with


M/s Bhartia Infra Projects Ltd (BIPL) -ABCI
paved shoulder configuration and geometric
16 ICR EAP (JICA) 54 41 867.09 450.45 13-02-2019 25-10-2019 30.97% 30.82% 24-04-2023 24-04-2023 Infrastructures Private Limited (JV)
improvements from km 125.00 to km 166.00
(Package-3) on Aizawl-Tuipang section

Widening and up-gradation to 2-lane with


paved shoulder configuration and geometric M/s ABCI Infrastructures Private Limited
17 ICR EAP (JICA) 54 42.53 899.45 440.5 13-02-2019 25-10-2019 37.92% 36.37% 24-04-2023 24-04-2023
improvements from km 166.00 to km 208.00
(Package-4) on Aizawl-Tuipang section

Widening and up-gradation to 2-lane with


paved shoulder configuration and geometric M/s ABCI Infrastructures Private Limited
18 ICR EAP (JICA) 54 34.58 752.89 395.37 13-02-2019 25-10-2019 38.46% 37.32% 24-04-2023 24-04-2023
improvements from km 208.00 to km 250.00
(Package-5) on Aizawl-Tuipang section

Widening and up-gradation to 2-lane with


M/s ABCI Infrastructures Private Limited-Bhartia Infra
paved shoulder configuration and geometric
19 ICR EAP (JICA) 54 45.46 811.54 546.05 08-03-2019 16-12-2019 34.17% 30.12% 15-06-2023 15-06-2023 Projects Ltd (BIPL) (JV)
improvements from km 250.00 to km 298.00
(Package-6) on Aizawl-Tuipang section

Widening and up-gradation to 2-lane with


paved shoulder configuration and geometric Power Mech Projects Ltd.- SRC Infra Developers
20 EAP EAP (JICA) 54 40.344 719.57 446.4 21-09-2020 01-10-2020 20.28% 16.93% 01-04-2024 01-04-2024
improvements from km 298.00 to km 339.00 Pvt. Ltd. (JV)
(Package-7) on Aizawl-Tuipang section

Widening and up-gradation to 2-lane with


M/s Bhartia Infra Projects Ltd (BIPL) - ABCI
paved shoulder configuration and geometric
21 EAP EAP (JICA) 54 39.94 713.44 443.94 13-02-2019 16-03-2020 28.78% 27.10% 15-09-2023 15-09-2023 Infrastructures Private Limited (JV)
improvements from km 339.00 to km 380.00
(Package-8) on Aizawl-Tuipang section
Construction of 2-L Chhiathlang -Serchhip
22 ICR EAP (JICA) Bypass (Pkg-1) on Aizawl-Tuipang section of 54 14.4 275.02 153.1 30-09-2020 15-10-2020 20.90% 18.45% 15-10-2022 15-10-2022 Kram Infracon Pvt. Ltd.(KIPL) - VKMCPL (JV)
NH-54
Construction of 2-L Hnathial Bypass (Pkg-2) on
23 ICR EAP (JICA) 54 7 113.58 60.3 31-07-2020 01-10-2020 18.59% 15.13% 03-04-2022 03-04-2022 Mathiyan Construction Pvt. Ltd.
Aizawl-Tuipang section of NH-54
Construction of 2-L Lawngtlai Bypass (Pkg-3)
24 ICR EAP (JICA) 54 2.27 58.85 31.14 29-10-2020 20-11-2020 21.47% 18.42% 23-05-2022 23-05-2022 David Zohmachhuana
on Aizawl-Tuipang section of NH-54

Up-gradation to 2-lane with paved shoulders of


Khawkawn (from Bridge across River Tuivai) -
Ngopa section of NH-102B of Aizawl - Imphal
25 EC NH(O)-NE 102B 31.28 492.94 265.6 02-09-2021 26-11-2021 1.50% 0.00% 20-05-2023 20-05-2023 B R Goyal Infrastructure Ltd.
Economic Corridor from Existing Chainage km
0.000 to km 32.796 [Design Chainage km 0.000
to km 31.280] (Package-1)

Up-gradation to 2-lane with paved shoulders of


Ngopa - Pawlrang section of NH 102B of Aizawl -
Imphal Economic Corridor from Existing
26 EC NH(O)-NE 102B 36.89 523.78 271.74 27-01-2022 to be given 0.00% 0.00% Shri Swami Samarth Engineers Ltd.
Chainage km 32.796 to km 72.030 [Design
Chainage km 31.280 to km 68.170] (Package-2)
Keifang- Tuivai Pkg-2

Up-gradation to 2 lane with paved shoutders of


Pawlrang - Rulchawm section- of NH-102B of
Aizawl - Imphal Economic Corridor from
Existing Chainage km 72.030 to km 104.129
including 2.459 km re-alignment section from
27 EC NH(O)-NE 102B 30.41 500.88 Under bidding Under bidding
Tuivai River to Rulchawm connecting km
48.150 of NH-6 [Design Chainage km 68.170 to
km 98.579] (Package-lll)
under Bharatmata Pariyojna (Keifang- Tuivai
Pkg-3)

Total 736.36 14944.93 7437.65


Status as on 28-02-2022
Cumulativ
Awarded Cumulativ
NHDP NH No. Sanctioned Date of e Target date of
SL. Length Cost Date of e Physical Likely date of
Mode Phase/ Name of Project (Old/ Cost/TPC Start/Appointe Financial completion as Name of the Contractor
No. (Km) Rs. in Award progress completion
Scheme New) Rs. in crore d Date progress per contract
crore %
%
Assam
Improvement and Strenghtening of Road Section from
Strength
1 NH(O) Chand Khera to Kurti Bridge on Assam-Tripura Border in 208A 17.95 66.94 60.21 04-10-2016 28-11-2016 100.00% 99.50% 24-01-2018 Completed M/s Ganesh Ram Dokania
ening
the state of Assam on EPC basis

Construction of Dibrugarh By Pass / realignment of NH-


2 EPC SARDP 37 15.5 379.32 96.84 20-02-2015 02-11-2015 100.00% 99.00% 31-10-2018 Completed M/s ABCI-JKM Pvt. Ltd (JV)
37 from Bogibeel Junction at km. 581.700 to km. 597.147

Strength One time improvement of Moran Town section of NH-37


3 NH(O) NH-37 3.5 14.52 13.5 31-05-2019 19-08-2019 100.00% 98.43% 17-08-2020 Completed M/s BB Enterprises
ening from km 555.000 to km 558.500

One time improvement of Digboi to Ledo Town section


Strength
4 NH(O) (via Powal and Margherita ) of NH-38 from km 20.000 to NH-38 33 30.84 26.92 29-07-2019 25-09-2019 100.00% 99.57% 23-09-2020 Completed M/s Ganpati Builders
ening
km 53.000
4-Laning of NH-37 from Nagaon By-pass to Teliagaon
5 EPC SARDP (km 278.600 to km 288.600) in the state of Assam under 37 10 87.11 23-03-2020 01-07-2020 84.28% 77.90% 23-12-2021 28-02-2022 PRL Projects & Infra Structure Ltd.
SARDP-NE Phase-A on EPC mode-Package-1
225.02
4-Laning of NH-37 from Teliagaon to Rangagara (km
6 EPC SARDP 288.600 to km 297.000) in the state of Assam under 37 8.4 66.25 20-03-2020 01-07-2020 62.35% 59.07% 23-12-2021 28-02-2022 Ganga Sagar Singh
SARDP-NE Phase-A on EPC mode – Package - 2

4-Laning from Rangagara to Kaliabhor Tiniali from km


7 EPC SARDP 37 18.315 289.99 196.24 16-01-2017 23-10-2017 58.95% 55.61% 21-04-2020 30-05-2022 M/s Simplex Infrastructure
297.00 to km 315.315 of NH-37 on EPC basis.

4-Laning from Kaliabor Tinali to Dolabari section from


8 EPC SARDP Km 0.0 to Km 17.3 of NH 37-A including construction of 37A 14.01 811.28 588.95 31-10-2014 29-11-2014 90.96% 89.76% 28-11-2018 30-05-2022 M/s Gammon India- S P Singla[SPSCPL] (JV)
new Brahmaputra bridge

4-Lane highway connecting km 17.3 of NH 37A and km


9 EPC SARDP 182 of NH 52 between Dolabari and Jamuguri on EPC 37A &52 16.862 124.58 05-11-2021 07-02-2022 0.00% 0.00% Sri Babul Nath
basis
1049.51
Construction of Jia Bharali Bridge (1.2Km) along with its
37A/
10 EPC SARDP approaches and River Training Work from km 25.552 to 1.948 448.03 21-12-2020 17-02-2021 22.94% 19.35% 05-08-2023 05-08-2023 MKC Infrastructure Ltd. - RSM Infra Projects (JV)
715
km 27.500 of NH-37A (New NH-715)
4-Laning from Jamuguri to Biswanath Chariali from km
11 EPC SARDP 52 26 520.01 303.49 13-10-2016 19-12-2016 72.41% 68.44% 19-06-2019 30-05-2022 M/s T K Engineering Consortium Pvt. Ltd.(TKECPL)
182 to km 208 of NH-52
4-Laning from Biswanath Chariali by-pass Km 208.00 to
12 EPC SARDP Gohpur Km 265.50 (Total length 57.50) in the state of 52 57.5 1099.35 393.482 18-10-2021 11-12-2021 3.70% 0.00% Dhatarwal Construction Company Pvt. Ltd.
Assam on EPC basis Under SARDP-NE

4-Laning from Gohpur to Holongi section from km 264.10 M/s ECI Engg.Construction Co. Ltd.
13 EPC SARDP 52 10.08 223.3 168.39 30-03-2015 11-12-2015 91.94% 90.39% 10-12-2018 30-09-2021
of NH 52 to km 20.37 of NH 52A

4-Laning of Numaligarh to Jorhat section from Km.


M/s Hindustan Construction Company (HCC)
14 EPC SARDP 402.500 to Km. 453.000 (Design Km 403.200 to Km 37 39.72 814.56 454.89 31-10-2014 23-05-2015- 84.07% 82.01% 23-05-2020 30-05-2022
(8638995214)
454.240) except Dergaon bypass (with Toll Plaza)

4-Laning of Jorhat to Jhanji section from Km. 453.00 to


15 EPC SARDP 37 37.8 738.15 220.4 05-11-2021 09-02-2022 0.00% 0.00% Vijeta Projects - Sweety Infrastructure (JV)
Km. 491.08

4-Laning of Jhanjhi Jn to Demow section from Km.


16 EPC SARDP 491.050 to Km. 535.250(Design Km 490.800 to Km 37 44.075 1369.02 398.06 09-11-2017 20-01-2018 42.66% 41.47% 18-01-2021 04-05-2022 M/s Gannon Dunkerley Company Ltd.[GDCL]
534.800) (with Toll Plaza)
4-Laning of NH-37 Section between Demow to End of
17 EPC SARDP Moran Bypass (From Km. 534.800 to Km. 561.700) on 37 26.9 385.57 294.17 14-01-2016 17-08-2016 77.01% 74.73% 12-02-2019 30-05-2022 M/s Gannon Dunkerley Company Ltd.[GDCL]
EPC Mode.
4-Laning of NH-37 Section between End of Moran Bypass
18 EPC SARDP to Bogibeel junction near Lapetketa ((Km. 561.700-Km. 37 19.17 330.3 223.5 31-01-2019 07-06-2019 63.22% 62.53% 02-12-2021 02-12-2021 M/S Manaranjan Brahma[MB]
580.778) on EPC Mode.
2-laning with paved shoulders from km 6.25 to 10.40 of M/s Shree Gautam Construction Company Ltd.
19 EPC SARDP 53/37 4.15 76.78 53.21 23-03-2015 01-10-2015 96.46% 94.82% 11-12-2017 31-03-2022
Silchar Badarpur section (Shri Binod Singhi )
4-Laning of Balachera-Harangjao section of NH-54 (ext.)
20 EPC NHDP II from km 275.00 to km 244.00 in the state of Assam under 54 Ext. 25.25 887.68 519.3 31-10-2017 26-12-2017 46.33% 43.60% 24-06-2020 30-04-2023 M/s Sushee Infra- M/s JSC PTPS (JV)
east west corridor project.
Construction and up gradation to 4-Lane of existing two
lane with paved shoulder from Hapachara to Tulungia
21 EPC NH(O)-NE road of NH-117 of existing Km 0.00 to km 14.050 and 102B/ 117 14.66 220.2 138.25 26-03-2020 26-06-2020 29.68% 26.64% 26-12-2022 26-12-2022 B.K.Sons Infra Pvt. Ltd.
(Design Km 0.000 to km 14.660), (Design length- 14.660
km) under BMP
Widening/Improvement to 4 -Lane with Paved Shoulder
from Ch. 52.470km to Ch.71.500 km (DesignCh.48.655km
22 EPC NH(O)-NE 17 18.9 636.42 418.49 22-03-2021 09-07-2021 10.06% 3.09% 31-12-2022 31-12-2022 Rajendra Singh Bhamboo Infra Pvt. Ltd.
to Ch.67.556km)of Tulungia Jogighopa Bridge Approach
Section (Package-5) of Bilasipura- Guwahati road (NH 17)
Construction of New 2-Lane Bridge with its approaches
23 EPC NH(O)-NE from km 0+000 to Km 4+385 across River Brahmaputra 17 4.385 746.76 402.75 10-08-2021 12-11-2021 0.00% 0.00% 11-11-2024 11-11-2024 Satpal (S. P.) Singla construction Pvt. Ltd.
on NH-17 at Jogighopa
Widening/Improvement to 4-Lane with paved shoulder
from Ch.75.330Km to Ch.88.00km (Design Ch.71.800 to
24 EPC NH(O)-NE 84.100 km) of Jogighopa Bridge Approach (Near NH-17 12.3 208.84 114.3 25-08-2020 26-10-2020 21.40% 19.94% 19-04-2022 19-04-2022 Mayasheel Construction
Pancharatna)- Agia (near Nichinta) section (Pkg. 6) of
Bilasipura-Guwahati road (NH-17) on EPC under BMP

Widening/Improvement to 4 -Lane with Paved Shoulder


from Ch. 88.000km to Ch.99.930 km (Design Ch.84.100km
25 EPC SARDP-BMP to Ch.96.000 km) of Sagunbashi forest (near Nichinta) to NH-17 11.63 286.72 131.865 31-03-2021 09-07-2021 0.00% 0.00% 08-01-2024 08-01-2024 Ram Chandra Paul
starting of Krishnai Bypass Section (Package-7) of
Bilasipura Guwahati road (NH 17)
Widening/lmprovement to 4-Lane with paved shoulders
from Km. 51+246 to Km. 66+000 (Design Chainage P. D. Agrawal Infrastructure Ltd. -Apex Structure Pvt Ltd.
26 EPC NH(O)-NE 29 15.21 335.88 138.33 26-03-2021 12-07-2021 20.94% 16.48% 11-01-2024 11-01-2024
50+710 Km to 65+923 Km) of Parokhuwa-Dokmoka (JV)
section (Package-2)
Widening/Improvement to 4-Lane with Paved shoulder
27 EPC NH(O)-TSP from km 66.00 to km 81.00 (Design Chainage 65.923 to 29 15.007 278.46 129.14 10-08-2020 30-09-2020 63.64% 51.56% 24-03-2022 24-03-2022 Skylark Infra Engg. Pvt. Ltd.
80.930) of Dokmoka - LoringThepi section- (Package-3)
Widening/Improvement to 4-Lane with Paved Shoulder
from km 81+000 to km 95+400 (Design Chainage 80+930
28 EPC NH(O)-TSP 29 15.47 260.07 141.35 03-02-2021 25-06-2021 47.92% 46.47% 17-12-2022 17-12-2022 S.S Builders
to 96+400) of Loring Thepi - Ganapath Gaur Gaon
Section - (Package-4)
Widening/lmprovement to 4-Lane of Daboka Dimapur
Stretch from Km 95+400 to Km 113+830 (Design
29 EPC NH(O)-NE 29 17.43 288.85 141.464 31-03-2021 12-07-2021 0.00% 0.00% 12-01-2023 12-01-2023 B.K.Sons Infra Pvt. Ltd.
Chainage 96+400 Km to 113+830 Km) of Ganpath Gaur
Gaon- Kwaram Taro Vitlage- (Package-5)
Widening/Improvement to 4-Lane with Paved Shoulder
from KM 113+300 to Km 146+230 (Design Chainage
30 EPC NH(O)-NE 29 31.88 625.64 282.11 10-09-2021 to be given 0.00% 0.00% Ashoka Buildcon Ltd.
113+830 to 145+712) of Kwaram Taro Village - Dillai
Section (Package-6)
Widening/lmprovement to 4-Lane with Paved Shoulder
from Dillai at Km 146+230 to Lahorijan at Km 157+46O
31 EPC NH(O)-NE 29 10.79 204.1 Under Bidding UNDER BIDDING
(Design Chainage 145+712 to 156+502) of Dillai -
Lahorijan (Package - 7)
4-Lane Bridge including approaches over River
(65%) (100%) Larsen & Toubro Ltd. Heavy Civil Infrastructure IC Larsen
32 EPC EAP (JICA) Brahmaputra between Dhubri (on North Bank,Assam) 127B 19.282 4997.04 3165.99 24-11-2020 15-12-2020 6.68% 3.80%
15-03-2025 12-09-2028 & Toubro Ltd.(L&T)
and Phulbari (on south Bank,Meghalaya) on NH-127B
Rehabilitation & upgradation to 4-Lane with Paved
shoulder of Dergaon Town section from Km 426.800 to
33 EPC NH(O) 2/ NH-37 11.0 287.63 122.5 19-03-2020 30-06-2020 67.15% 67.05% 19-06-2022 19-06-2022 M/s Rajinder Infrastructure Pvt.Ltd.
Km 437.800 (Total length-11.00 km) on NH 37 on EPC
basis
Widening/improvement to 4-Lane with paved shoulder
from km. 581+700 to km 606+300 of NH-37 on existing
34 EPC NH(O)-NE 37 24.6 215.27 Under Bidding
Dibrugarh-Lahoal-Chabua Bypass i.e. from Lepetketa to
Kandulibari Grant Gaon section under NH(O) - NE

Widening/improvement to 4-Lane with paved shoulder


from km. 606+300 to km 626+030 of NH-37 on existing
35 EPC NH(O)-NE 37 19.73 170.95 Under Bidding
Lahoal-Chabua Bypass i.e. Kandulibari Grant Gaon to
Nalanihulla section under NH(0) - NE

Total 672.40 19074.97 10064.06


Status as on 28-02-2022
Sanctione
Awarded
NHDP NH No. d Date of Cumulative Cumulative Target date of
SL. Length Cost Date of Likely date of
Mode Phase/ Name of Project (Old/ Cost/TPC Start/Appointed Physical Financial completion as Name of the Contractor
No. (Km) Rs. in Award completion
Scheme New) Rs. in Date progress % progress % per contract
crore
crore
Nagaland
4 Laning of Dimapur Kohima Road
from Design Km 123.840 to Km
1 EPC SARDP 138.775 in the state of Nagaland 39/29 14.935 489.01 387 12-05-2016 16-09-2016 92.83% 91.39% 15-09-2019 28-02-2022 M/s Ramky-ECI (JV) Phone : 7085043096
under SARDP-NE on EPC basis
(Package - I).
4 Laning of Dimapur Kohima Road
from Design Km 138.775 to Km
2 EPC SARDP 152.490 in the state of Nagaland 39/29 13.715 519.72 339.55 12-05-2016 03-08-2016 93.02% 92.10% 02-08-2019 28-02-2022 M/s Ramky-ECI (JV) Phone : 7085043096
under SARDP-NE on EPC basis
(Package - II).
4 Laning of Balance work of
Dimapur Kohima Road from Design
Km 152.490 to Km 166.700 (Existing
3 EPC SARDP 39/29 14.21 562.98 111.20 16-07-2021 01-09-2021 10.86% 10.11% 31-08-2022 31-08-2022 OASIS Technocons Ltd.
Km 156.000 to Km 172.900), in the
state of Nagaland under SARDP-NE
(Package - III).

Construction of 4/6 Laning from Km


132.375 to Km 153.058 (Total New
Alignment length of 20.683 Km ) of Connecting NH- M/s Simplex Infrastructure Limited Phone :
4 EPC SARDP 20.68 819.38 387 12-04-2017 05-09-2017 91.61% 88.22% 04-09-2020 13-02-2022
Daboka Dimapur Section (Dimapur 39 & NH-36 9485050101
Bypass) of NH-36 & 39 in the State
of Nagaland on EPC basis.

Construction of Dimapur Bypass


(Assam Portion) of 4/6 Lane
pavement on EPC basis from
existing Km 159.400 of NH-36 to Connecting NH-
5 EPC SARDP 14.33 583.31 336.49 19-03-2018 26-11-2019 46.95% 46.51% 25-11-2022 25-11-2022 M/s Gawar - Singh (JV) consultants Pvt Ltd
existing Km 102.500 of NH-39 and 39 & NH-36
upto end point of Assam portion
[Design Km 118.050 to design Km
132.375] (length 14.325 Km)
Construction of 2-Lane with Hard
shoulders of Chakabama- M/s Shivalaya Construction Co Pvt Ltd. Ph. No.
6 EPC SARDP - 25 339.57 233.35 23-03-2018 03-07-2019 82.14% 78.27% 02-07-2022 02-07-2022
Zunheboto (C-Z) road Km 0-25 PKG- 01165965915
I
Construction of 2-Lane with Hard
shoulders of Chakabama- M/s Shivalaya Construction Co Pvt Ltd. Ph. No.
7 EPC SARDP 702A 25 239.3 174.7 23-03-2018 20-05-2019 79.35% 73.73% 19-05-2022 19-05-2022
Zunheboto (C-Z) road Km25-50 PKG- 01165965915
II
Construction of 2-Lane with Hard
shoulders of Chakabama- M/s Madhucon Projects Limited Ph. No.
8 EPC SARDP 702A 25 285.68 194.1 23-03-2018 05-09-2019 56.41% 13.27% 03-09-2022 03-09-2022
Zunheboto (C-Z) road on EPC 01242359234
[Design Km 50 -75] PKG-III
Construction of 2-Lane with hard
shoulders of Chakabama- M/s Madhucon Projects Limited Ph. No.
9 EPC SARDP 702A 20 315.03 213.3 28-03-2018 13-12-2018 61.20% 56.72% 11-12-2021 30-03-2023
Zunheboto (C-Z) road Km 75-95 01242359234
PKG-IV
Construction of 2-Lane with Hard
shoulders of Chakabama- M/s Madhucon Projects Limited Ph. No.
10 EPC SARDP 702A 20.53 255.58 188.1 28-03-2018 20-12-2018 71.21% 66.92% 19-12-2021 18-01-2023
Zunheboto (C-Z) road Km 95- 01242359234
115.534 PKG-V
Construction of 2-Lane with hard Kantilal Khimjibhi Bhalala (KKB) Project Pvt.
11 EPC SARDP shoulders of Pfutsero- Phek (PP) - 20 237.72 136.73 22-03-2018 08-11-2018 98.66% 98.66% 08-11-2021 08-11-2021 Ltd.
road from Km 0-20 Ph no.02612491690
Construction of 2-Lane with hard
M/s Madhucon Projects Limited Ph. No.
12 EPC SARDP shoulders of Pfutsero- Phek (PP) - 20 251.97 160.1 22-03-2018 15-11-2018 98.10% 98.10% 14-11-2021 14-11-2021
01242359234
road Km 20-40
Construction of 2-Lane with hard
M/s Madhucon Projects Limited Ph. No.
13 EPC SARDP shoulders of Pfutsero- Phek (PP) - 22.56 282.98 192.6 22-03-2018 15-11-2018 97.23% 95.18% 14-11-2021 28-04-2022
01242359234
road Km 40-62.558
Construction of 2-Lane with hard
14 EPC SARDP shoulders of Merangkong-Tamlu- - 20 215.12 143.65 23-03-2018 18-11-2018 84.44% 82.22% 17-11-2021 31-01-2022 M/s Keystone Infra Pvt. Ltd.
Mon (MTM) Km 0-20 - PKG-I

Construction of 2-Lane with hard


15 EPC SARDP shoulders of Merangkong-Tamlu- - 20 215.79 161.99 28-03-2018 03-12-2018 52.60% 50.11% 01-12-2021 31-01-2022 M/s Manaranjan Brahma Ph. No. 8876055466
Mon (MTM) Road Km 20-40 PKG-II

Construction of 2-Lane with hard


M/s SSR Crest Engineers and Constructions
16 EPC SARDP shoulders of Merangkong-Tamlu- - 19 272.89 187 28-03-2018 24-10-2019 45.95% 40.15% 22-10-2022 22-10-2022
Limited Ph. No. +91 9440057454
Mon (MTM) Road Km 40-59 PKG-III

Construction of 2-Lane with hard


shoulders of Merangkong-Tamlu-
17 EPC SARDP - 23.035 323.98 103.8 09-09-2021 09-12-2021 0.00% 0.00% 12-06-2023 12-06-2023 M D Enterprise
Mon (MTM) Road Km 63.800- 86.835
PKG-IV (Balance work)

Construction of 2-lane with hard


shoulders of Merangkong-Tamlu-
Mon road (Wakching Twon portion)
on EPC basis from existing
18 EPC NH(O)-TSP Chainage Km 59+000 to Km 73+640 - 13.45 161.73 79 16-07-2021 01-09-2021 0.00% 0.00% 27-12-2023 27-12-2023 C Gopal Reddy & Company
[Design Km. 59+000 to Km, 72+450]
(Design length - 13.450 Km)
(package-V)

Construction of 2-lane with hard


shoulder of Changtongya -
19 EPC NH(O)-NE Longleng Road on EPC basis from 702 18.78 278.95 177.1 02-03-2020 01-07-2020 53.40% 48.91% 30-06-2022 30-06-2022 M/s RKIPL-NSC(JV)
existing Km0.00 to Km16.592
[Design Km 0.00 to Km.18.779 ]
(Design Length-18.779km) (Pkg-1)

Construction of 2-lane with hard


shoulder of Changtongya -
Longleng Road on EPC basis from
20 EPC NH(O)-NE existing Km16.592 to Km29.530 702 14.65 206.53 128 11-03-2020 01-07-2020 68.45% 66.34% 30-06-2022 30-06-2022 Ksheeraabd Construction Pvt. Ltd. (KCPL)
[Design Km.18.779 to Km 33.428]
(Design Length-14.649 km) (Pkg-2)
2019-20
Construction of 2-Lane with paved
shoulder of Kohima-Bypass Road
connecting NH-39(New NH-02), NH-
21 EPC NH(O)-NE 150(New NH-02), NH-61(New NH-29) NH 29/ NH-02 10.5 232.29 to be given 0.00% 0.00% Ganesh Ram Dokania
and NH-39(New NH-02) from design
Km 0.00 to Km 10.500 [Design
Length- 10.500 km] (Pkg.- 1)

Construction of 2-Lane with paved


shoulder of Kohima-Bypass Road
connecting NH-39(New NH-02), NH-
150(New NH-02), NH-61(New NH-29)
22 EPC NH(O)-NE NH 29/ NH-02 10.5 277.44 177 25-09-2020 15-10-2020 0.00% 0.00% 15-10-2022 15-10-2022 Ms Bharat Construction Pvt. Ltd
and NH-39(New NH-02) from design
Km10.500 to 21.00Km [Design
Length- 10.500 km] (Pkg.- 2) incl.
(TUNNEL of 0.500 Km)

Construction of 2-lane with Paved


shoulder of Kohima-Bypass Road
39/02, 150/02,
23 EPC NH(O)-NE connecting NH-2, 29 from Design 11 159.85 Under Re-bidding 0.00% 0.00% - - M/s Skylark Infra Engg.Pvt. Ltd.
61/29, 39/02
km21.0 to km32.0 [Design
length=11.0 km] (Pkg.- 3)

Construction of 2-lane with Paved


shoulder of Kohima-Bypass Road
39/02, 150/02,
24 EPC NH(O)-NE connecting NH-2, 29 from Dsign 11.45 202.36 118.56 14-08-2020 15-10-2020 5.87% 5.60% 17-04-2022 23-02-2023 M/s Pele Khezhie
61/29, 39/02
km32.0 to km43.454 [Design
length=11.454] (Pkg.- 4)
Construction of 2- lane with hard
shoulder of Kohima-Jessami
Road on NH-29 (Old NH-150) from
existing Km 7.880 (near chedama
25 EPC NH(O)-TSP 150 / 29 21.72 320.97 193.79 17-03-2020 01-07-2020 37.64% 33.49% 30-06-2022 30-06-2022 M/s RKIPL-NSC(JV)
Junction) to existing km 30.474
(Near Chakahabama) (Design km
7.88 to km 29.60) (Design length -
21.72 km) on EPC Mode (Package -I)

Construction of 2-lane with hard


shoulder of Kohima - Jessami
road on NH-29 (Old NH-150) from
existing Km 30.474 (Near Kidwema
road Chakahabama) to existing Km
26 EPC NH(O)-TSP 150 / 29 21.9 355.79 202 18-03-2020 01-07-2020 42.45% 39.51% 30-06-2022 30-06-2022 Ksheeraabd Construction Pvt. Ltd. (KCPL)
53.220 (Near Kikruma Village)
(Design Km 29.60 to Km 51.50)
(Design length-21.90 Km) on EPC
mode (Package II) under NH(O) 2019-
20

Construction of 2-lane with hard


shoulder of Kohima - Jessami road
on NH-29 (Old NH-150) from
existing Km53.220 (Near Kikruma
27 EPC NH(O)-TSP Village) to existing Km 76.320 (Near 150 / 29 22.7 361.53 206.26 23-03-2020 01-07-2020 22.73% 20.32% 30-06-2022 30-06-2022 M/s SIPL - RMN (JV)
Mesulumi Village) (Design Km51.50
to Km74.20) (Design length-22.70
Km) on EPC mode (Package III)
under NH(O) 2019-20

Construction of 2-lane with hard


shoulder of Kohima - Jessami road
on NH 29 (old NH 150) from existing
28 EPC NH(O)-TSP km 76.320 (near Mesulumi Vill.) to 150 / 29 21.5 330.78 205.26 30-03-2020 01-07-2020 39.03% 35.37% 31-12-2021 24-06-2022 M/s Keystone Infra Pvt. Ltd.
existing Km98.380 (near Chizami
Vill.) [Design Length= 21.50 km] on
EPC (Package IV)

Construction of 2-lane with hard


shoulder of Kohima - Jessami road
on NH 29 (old NH 150) from existing
km 98.380 (near Chizami vill.) to
29 EPC NH(O)-TSP 150 / 29 21.5 330.8 214.37 24-04-2020 01-07-2020 26.98% 25.06% 31-12-2021 10-06-2022 M/s Stroyproekt LLC - OIA (JV)
km120.367 (Nagaland/Manipur
Border) [Design km 95.700 to
design km 117.200] [Design Length=
21.500 km] on EPC (Package V)

Upgradation of existing road to 2-


lane with paved shoulder from
30 EPC NH(O)-TSP Kohima to Mao from km 185.540 to 39/ 02 26.25 315.63 167.23 30-09-2020 20-10-2020 6.70% 6.35% 22-04-2022 22-04-2022 Fortune Group
km 211.709 under Bharatmala-
NH(O)-TSP
Construction of 2-lane with hard
shoulder of Peren-Dimapur section
M/s Mayasheel Construction - JPS Projects Pvt.
31 EPC NH(O)-TSP on NH129A from design Km109.494 129A 17.28 257.15 139.88 10-09-2020 20-10-2020 40.09% 37.21% 22-04-2022 22-04-2022
Ltd. (JV)
to Km126.775 (Length=17.281) (Pkg-
1)

Construction of 2-lane with hard


shoulder of Peren-Dimapur section
32 EPC NH(O)-TSP on NH129A from design Km 126.775 129A 19.43 258.52 117.5 19-07-2021 25-08-2021 28.22% 21.24% 25-02-2023 25-02-2023 C Gopal Reddy & Company
to Km 146.208 under NH(O)-TSP
(Pkg-2)
Construction of 2 laning with Hard
shoulder of Peren-Dimapur section
on NH 129A from Design Km
33 EPC NH(O)-TSP 129A 17.38 177.77 89.54 05-02-2021 to be given 0.00% 0.00% - - Fortune Group
146.208 to Km 163.592 (Length-
17.384 km) under NH(O)-TSP (Pkg -
3)
Construction of 2 Laning with Hard
Shoulder of Peren - Dimapur
section on NH - 129A from Design
34 EPC NH(O)-TSP 129A 10.26 116.54 55.93 16-03-2021 to be given 0.00% 0.00% - - Multi Builders
Km 163.592 to Km 173.850 (Length -
10.258 km) (Pkg - 4) under NH (0) -
TSP
Construction of 2 laning with Hard
shoulder of Peren-Dimapur section
on NH 129A from Design Km
35 EPC NH(O)-TSP 173.850 to Km 190.850 (Length - 129A 17.00 207.33 97.01 04-02-2021 to be given 0.00% 0.00% - - Multi Builders
17.000 Km) in the state of Nagaland
on EPC Mode (Package-5) under
NH(O)-TSP

Total 645.25 10761.97 6019.07


Status as on 28-02-2022
Awarded Cumulativ Cumulativ Target date of
NHDP NH No. Sanctioned Date of
SL. Length Cost Date of e Physical e Financial completion Likely Date of
Mode Phase/ Name of Project (Old/ Cost/TPC Start/Appoi Name of the Contractor
No. (Km) Rs. in Award progress progress as per completion
Scheme New) Rs. in crore nted Date
crore % % contract

Arunachal Pradesh
2 laning from Mahadevpur to Buri Dihing M/s Dineshchandra R. Agarwal Infracon Pvt. Ltd.-
1 EPC SARDP 52B/ 215 25.135 136.6 107.16 31-03-2015 30-05-2015 100.00% 100.00% 30-05-2018 Completed
section of NH-52B Puna Hinda (JV)

2 laning from Bordumsa-Namchik (Buri Dihing-


Jairampur) road on NH52-B (New NH-215) from
2 EPC SARDP 52B 22.23 189.91 143.21 23-07-2015 23-10-2015 100.00% 100.00% 22-10-2018 Completed BIPL-BVEPL (JV)
Km 0.15 km (starting Chainage near Buridihing
Bridge) to km 22.380

2 laning from Pasighat to Pangin section of NH-


3 EPC SARDP 229/13 26.58 299.66 235.08 31-03-2015 27-05-2015 100.00% 100.00% 25-05-2018 Completed M/s Dineshchandra R. Agarwal Infracon Pvt. Ltd.
229 from km 0 to Km 28
2 laning from Pasighat to Pangin section of NH-
T K Engineering & Consortium Pvt. Ltd.(TKECPL)
4 EPC SARDP 229 from km 41.3 to 58.420 (Existing Km 42 to 229/13 17.12 247.44 194.11 05-12-2015 27-05-2015 100.00% 99.95% 25-05-2018 Completed
km 59)
Construction of 2-lane road from existing km.
5 EPC SARDP 37.500 of Hunli-Anini road (Near Ithun Bridge) New NH-313 16 259.52 198 06-05-2016 07-10-2016 100.00% 100.00% 06-10-2019 Completed M/s Madhucon Projects Ltd.
to Km. 53.50 - Pkg.II

6 EPC SARDP 2 laning of Singer river to Sijon nala 513 23.38 238.46 179.82 09-11-2015 15-01-2016 100.00% 100.00% 19-01-2019 Completed M/s ABL-BIPL (JV)

2 laning from Changlang Dist Boundary – 14-06-2019/ M/s MGCPL-HGIEPL (JV)


7 EPC SARDP 52B/215 42.844 438.32 334.22 01-03-2016 15-06-2016 100.00% 100.00% Completed
Khonsa (42.844 km) section of NH-52B 04-03-2019
2 laning from Km 40 to Km 58 of
T K Engineering & Consortium Pvt. Ltd.(TKECPL)
8 EPC SARDP Changlang/Tirap District boundary to 52B/215 18.266 172.75 130.1 31-03-2015 01-06-2015 100.00% 97.31% 31-05-2018 Completed
Changlang of NH-52B
2 laning from Longding to Kanubari of NH-
9 EPC SARDP 52B/ 215 47.21 522.87 394 31-03-2015 02-06-2015 100.00% 96.94% 26-11-2018 Completed M/s Monte Carlo Ltd.
52B from Km0.00 to Km47.213
2 laning with paved shoulders from Pasighat
to Bomjur section from km 583.450 to 605.600
10 EPC SARDP 52 22.15 244.82 163.61 02-03-2016 24-02-2017 100.00% 97.81% 23-02-2020 Completed M/s BIPL-ABL (JV )
including Realignment from km591.900 to
602.600
Construction of 2-lane road from km. 12.00 to
11 EPC SARDP Km. 33.00 of Akajan-Likabali- Bame road (Pkg- State Road 21 210.5 148 11-02-2015 20-01-2016 99.84% 99.34% 18-01-2019 Completed M/s JKM-KCL JV
I)
Rehabilitation/ Restoration (One Time
Strength
12 NH(O) Improvement) of Hunli Anini Road from km New NH-313 21.5 23.56 22.12 22-02-2019 10-10-2019 100.00% 93.64% 09-10-2020 Completed M/s N.M. Enterprises
ening
0.00 to km 21.500

2 langing of Khupa - Hayuliang – Hawai


Road on EPC basis from design Km. 0.000
13 EPC SARDP (Khupa) to Km. 17.000 [Existing Km 95.800 of NH-313 13.8 252.05 143.55 23-03-2017 10-11-2017 88.05% 84.49% 09-11-2020 14-05-2022 M/s Sushee Infra & Mining Limited
(Khupa – Hayuliang Road) to Km 8.970
(Hayuliang – Hawai Road)] - I

2 langing of Hayuliang – Hawai Road on EPC


basis from design Km. 17.000 (Khupa) to Km.
14 EPC SARDP NH-313 17 252.79 168.3 23-03-2017 10-11-2017 74.81% 72.01% 09-11-2020 29-08-2022 M/s Sushee Infra & Mining Limited
34.000 [Existing Km 16.950 to Km 34.310
(Hayuliang – Hawai Road)] - II
2 langing of Hayuliang – Hawai Road on EPC
basis from Design Km. 34.000 to Km. 51.825
15 EPC SARDP NH-313 17.83 263.31 177.3 23-03-2017 10-11-2017 72.60% 69.32% 08-11-2020 27-06-2022 M/s Sushee Infra & Mining Limited
[Existing Km 26.625 to Km 45.050 (Hayuliang –
Hawai Road)]- III
2 laning of Balance work of Hayuliang– Hawai
bypass Road on EPC basis from design Km.
16 EPC SARDP NH-313 11.3 256.66 131.91 31-03-2021 03-05-2021 14.00% 11.58% 02-05-2023 02-05-2023 Poddar Infratech Pvt. Ltd. - GRRB Associates (JV)
51.825 to Km. 63.131 Existing Km 45.050 of
Hayuliang – Hawai road to Hawai Town - IV

Construction of 2-lane road from km. 0.00


(Existing km. 16.00 of Roing -Hunli Road) to
17 EPC SARDP NH-313 74.86 1718.59 1058.24 24-03-2017 05-03-2018 55.16% 50.20% 04-03-2022 23-01-2023 M/s DRAIPL - Iron Triangle (ITL) (JV)
Km. 74.00 (Ithun Bridge near existing km.
21.50 of Anini Road)-Green Field alignment

Construction of 2 Major bridges at Existing


Ch. 23+650 (Design Ch. 23+550) and Ch.
18 EPC SARDP 28+200 (Design Ch. 28+200) of bridge span 160 NH-313 0.32 45.43 60 28-09-2021 17-12-2021 0.00% 0.00% 19-06-2023 19-06-2023 Poddar Infratech Pvt. Ltd.
m along the Existing Hunli-Anini Road (Pkg.1)
from Km 21.500 to Km 37.500
Construction of 2-lane road from existing km.
19 EPC SARDP 21.50 of Hunli-Anini road (Near Ithun Bridge) to NH-313 16 322.15 210.44 06-05-2016 21-12-2016 91.07% 88.70% 20-12-2019 30-05-2022 M/s Madhucon Projects Ltd.
Km. 37.500 - (Pkg.-I)
Construction of 2-lane Hunli-Anini road from
20 EPC SARDP NH-313 39 568.92 434.06 12-09-2016 16-12-2016 78.56% 77.32% 20-08-2019 30-05-2022 M/s PCL-Eagle (JV)
km. 53.500 to km. 92.500 - III
Construction of 2-lane of Hunli-Anini road from
21 EPC SARDP NH-313 13.7 191.3 145.8 14-12-2016 19-01-2017 92.02% 88.55% 18-01-2020 30-05-2022 M/s Sushee Infra & Mining Limited
km 92.50 to Km 106.20 - IV
Construction of 2-lane of Hunli-Anini road from
22 EPC SARDP NH-313 13.8 200.44 154.8 14-12-2016 19-01-2017 87.85% 83.12% 18-01-2020 30-05-2022 M/s Sushee Infra & Mining Limited
km. 106.20 to Km. 120.00 (Package V )
Construction of 2-lane of Hunli-Anini road from
23 EPC SARDP NH-313 10.3 145.17 105 31-03-2018 15-06-2018 96.90% 94.70% 22-10-2021 31-03-2022 M/s TTC Infra
km. 120.0 to Km. 130.30 - VI

Construction of Balance work of 2 - Laning


of existing Akajan-Likabali-Bame Road on EPC
24 EPC SARDP basis from design Km 33.00 to Km 65.810 State Road 32.81 118 93 30-06-2021 01-09-2021 18.36% 15.74% 03-03-2023 MVV Satyanaryana
(Existing km 36.00 to km 71.00) in the state of
Arunachal Pradesh under SARDP-NE (Pkg-2)

Construction of 2-lane road from Km. 65.810 to


25 EPC SARDP Km. 99.00 (Design Length=26.118 km) of State Road 26.118 374.73 220.17 31-03-2017 21-03-2018 87.51% 74.98% 19-03-2021 30-05-2022 M/s SCIW-Shivam (JV)
Akajan-Likabali-Bame road (Pkg-3)
T K Engineering & Consortium Pvt. Ltd.-Brand
2-Laning of Joram – Koloriang Road (NH-713)
Eagles
26 EPC SARDP from design Km. 20+000 to Km. 32+050 NH-713 12.05 175.65 102.63 24-03-2017 22-04-2019 97.58% 90.43% 20-04-2022 20-04-2022
(TKECPL - BE)
(Existing Km 20.000 to Km 35.150) (Pkg-I)
T K Engineering & Consortium Pvt. Ltd.-Brand
2-Laning of Joram – Koloriang Road (NH-713)
Eagles
27 EPC SARDP from design Km. 32+050 to Km. 44+000 NH-713 11.95 176.22 103.48 24-03-2017 22-04-2019 83.62% 80.13% 20-04-2022 20-04-2022
(TKECPL - BE)
[Existing Km 35.150 to Km 50.050] (Pkg-II)

Construction of Balance work of 2-Lane with


P S of Joram – Koloriang Road (NH-713) from
28 EPC SARDP NH-713 16.558 228.71 100.21 10-08-2020 01-10-2020 48.14% 47.59% 03-04-2022 03-04-2022 Valecha Engg. Ltd.
existing Km 50.050 to Km 70.00 [Design Km.
44+989 to Km. 61.547 (Pkg-III)

Construction of Balance work of 2-Lane with


P S of Joram – Koloriang Road (NH-713) from
29 EPC SARDP NH-713 17.177 294.04 147.13 11-08-2020 01-10-2020 61.84% 60.33% 03-04-2022 03-04-2022 Bhimji Velji Sorathia Construction Pvt. Ltd.
existing Km 70.00 to Km 88.700 [Design
Km61.547 to Km78.724] (Pkg-IV)

Construction of Balance work of 2-Lane with


P S of Joram – Koloriang Road from existing
30 EPC SARDP NH-713 15 229.7 121.58 14-08-2020 01-10-2020 56.05% 52.49% 03-04-2022 03-04-2022 Bhimji Velji Sorathia Construction Pvt. Ltd.
Km88.700 to Km 104.850 [Design km 78.724 to
Km 93.724] (Pkg-V)

Construction of Balance work of 2-Lane with


P S of Joram – Koloriang Road (NH-713) from
31 EPC SARDP NH-713 15 199.03 102.86 17-08-2020 01-10-2020 57.49% 56.25% 03-04-2022 03-04-2022 Jainco Enterprises Pvt. Ltd.
existing Km104.850 to km 122.600 [Design
km92.724 to km108.724] ((Pkg-VI)

Construction of Balance work of 2-Lane with


P S of Joram – Koloriang Road from existing
32 EPC SARDP NH-713 15 184.88 101.95 07-08-2020 01-10-2020 47.69% 44.80% 03-04-2022 03-04-2022 Jainco Enterprises Pvt. Ltd.
Km122.600 to km138.00 [Design Km108.724 to
Km123.714] (Design length= 14.99km) (Pkg-VII)

Construction of Balance Work of 2 lane with


Paved shoulder of Joram-Koloriang Road (NH-
713) on EPC basis from existing Km 138.000 to
33 EPC SARDP NH-713 16.036 244.1 Under Re-bidding Under Re-bidding
Km 158.00 [Design Km 122+353 to Km
138+389] (Package 8) [design length - 16.035
km] under SARDP-NE
Construction of 2-Laning with hard shoulders
of Arrowa-Khupa-Hayuliang section of NH-113
34 EPC NH(O)-NE 113 23.083 301.06 156.7 31-08-2020 25-10-2020 5.60% 4.97% 26-04-2022 26-04-2022 M.P. Agarwalla
from Ch.68.550 to Ch.91.633 under SARDP-NE
NH(O)-NE
Construction of 2-Laning with hard shoulders
of Demwe-Brahmakund section of NH-13 from
35 EPC NH(O)-NE 13 18.464 353.9 205.56 29-09-2020 05-11-2020 15.79% 12.03% 08-05-2022 08-05-2022 Valecha Engg. Ltd.
Ch.0.00 km to 18.464km on EPC under SARDP-
NE NH(O)-NE
Total 750.57 10081.24 6494.10
Status as on 28-02-2022

NHDP NH No. Sanctioned Awarded Date of Cumulative Cumulative Target date of


SL. Length Likely date of
Mode Phase/ Name of Project (Old/ Cost/TPC Cost Date of Award Start/Appointe Physical Financial completion as Name of the Contractor
No. (Km) completion
Scheme New) Rs. in crore Rs. in crore d Date progress % progress % per contract

Sikkim
Improvement & Rehabilitation of
existing Indira Bye Pass road form
Item
1 NH(O) Km 0.000 to km 10.117 on NH-10 in NH-10 10.12 33.24 17.57 28-03-2018 04-05-2018 100.00% 100.00% 15-08-2019 Completed M/s Pasang Lama & Sons
Rate
the State of Sikkim on Item Rate
Basis
2-lane Chisopani Traffic Tunnel
of length 250 m including
2 EPC NH(O) NH-10 0.42 35.69 29.00 05-03-2019 10-09-2019 80.89% 78.19% 08-09-2021 31-12-2021 M/s Nagyan Constrcution Pvt. Ltd
approaches from Km 67+080 to
Km 67+500
Construction of 48m Bridge over
3 EPC NH(O) Chuba Khola at Km 75+300 to Km NH-10 0.48 8.93 7.45 21-05-2019 16-09-2019 71.01% 59.17% 15-09-2021 30-05-2022 Mohan Bajaj
75+800 on NH-10
M/s Dinesh ChandraAgarwal Infracon Pvt.Ltd.Jagdish Agarwal Ph
Construction of Rangpo-Viaduct
No.09824089999
4 EPC SARDP at Rangpo town Km 51.100 to 10 1.12 133.49 55.79 16-12-2016 20-02-2017 74.50% 68.76% 20-02-2020 10-04-2022
Deepak Sinha
53.800 NH-10
ph.no-8373091911
Construction / Upgrade existing
road to 2 lane with paved shoulder
5 EPC SARDP 510 16.00 375.8 163 26-02-2019 05-10-2019 53.69% 50.19% 05-04-2022 05-04-2023 M/s. VKJ-NSPR (JV) .
from Km 0.000 to 16.000 Singtam -
Tarku NH-510

Construction / Upgrade existing


road to 2 lane with paved shoulder
6 EPC SARDP 510 16.50 290.05 171.53 31-03-2017 01-11-2017 83.64% 80.34% 30-10-2020 30-05-2022 M/s S&P Infrastructures Developers Pvt.ltd
from Km 16.000 to 32.500 Tarku -
Ravangla NH-510 .
M/s Dinesh ChandraAgarwal Infracon Pvt.Ltd.Jagdish Agarwal Ph
Construction of Alternate Highway No.09824089999
7 EPC SARDP 717A 26.70 447.37 318.42 31-03-2017 01-11-2017 96.88% 95.22% 31-10-2020 28-02-2022
from Rhenock-Pakyong NH-717A. Deepak Sinha
ph.no-8373091911
Construction/Upgradation of
Existing road to 2 lane with paved
shoulder including Geometric
8 EPC SARDP Improvement from Ranipool to 717A 14.17 275.26 77.57 07-07-2021 01-09-2021 0.00% 0.00% 04-03-2023 04-03-2023 Garg & Sons Estate Promoters Ltd.
Pakyong from km 2.000 to km
16.167 (Balance Work) under
SARDP-NE 'A'”
Realignment of NH717A from
Design CH: 0.00 (Km 77.800 of NH-
10) to Design CH:2.00 (Km 3.100 of
9 EPC SARDP 717A 2.00 76.67 50 04-02-2021 10-04-2021 2.98% 1.64% 10-04-2023 10-04-2023 Suryodaya Infra Project (I) Pvt. Ltd
NH-717A) with 2-lane paved
shoulder including Major Bridge
of 680 m
Construction and upgradation of
existing road to 2-lane with Paved
shoulder from km. 20.340 (Rongli
Bazzar) to km. 26.588 (Rongli
Bypass End) and upgradation of L. G. Chaudhary (LGC)- Yogi Construction (YCC) (JV)
10 EPC NH(O)-NE 717 B 7.3 332.28 162.74 15-01-2021 10-03-2021 6.99% 3.96% 09-09-2023 09-09-2023
existing road at km 20.600 & km Mr. Akhil Ph no-9800002278
26.400 for length of 0.520 km &
0.554 km of Rhenok - Menla spur
(NH-717B) Package-IIA under
SARDP-NE {Under NH(O)-NE}

Construction & Upgradation of


existing road to 2-lane with paved
shoulder from km27.200 (End of J.K. Associates - A.K. Builders (JV)
11 EPC NH(O)-NE 717 B 10.40 230.45 100.95 31-08-2020 15-10-2020 16.40% 12.28% 15-04-2023 15-04-2023
Rongli bypass) to km37.600(New Mr Rajesh Kumar ph no-954725922
Rolep Bridge) of Rhenok-Menla
spur ( II B)

Construction & Upgradation of


existing road to 2-lane with paved
shoulder from New Rolep Bridge Nalanda Engicon Pvt. Ltd.- Ujjain Engicon Pvt. Ltd. (JV)
12 EPC NH(O)-NE at km 37.600 to Chochenpheri at 717 B 14.40 493.42 236.12 16-03-2021 25-05-2021 4.35% 0.00% 24-05-2024 24-05-2024 Mr Rama
km 52.00 in the section of Rongli Ph No.: 9493910259
to Chochenpheri of NH 717B (Pkg-
II C)
Construction of 2-lane with paved
shoulder of new green field
U.P. State Bridge Corporation Ltd.
alignment from Chochenpheri at
13 EPC NH(O)-NE 717 B 30.00 816.79 532.52 28-10-2020 10-12-2020 1.15% 0.49% 10-12-2023 10-12-2023 Mr Rajeshkar
km 52.000 to Helipad near Menla at
Ph No.9182375476
km82.00 of Rhenok-Menla spur of
NH-717B (Pkg-III A)
Construction of 2-lane with paved
shoulder of new green field A. G. Construction
alignment from Helipad at Menla Mr Chandan
14 EPC NH(O)-NE 717 B 12.03 410.6 260.52 28-12-2020 25-02-2021 5.20% 3.50% 25-02-2024 25-02-2024
at km 82.00 to Menla at Km 94.030 Ph no- 7566709763
of Rhenok-Menla spur of NH-717B
(Pkg-III B)
Construction of 2-lane
specification road with paved
shoulder including Tunnel
15 EPC NH(O)-NE (300m) at Rabangla (Singtam- 510 1.10 79.21 50.60 22-09-2020 15-10-2020 4.98% 3.26% 15-10-2022 15-10-2022 Nagyan Construction Pvt. Ltd.
Tarku-Rabangla-Legship-
Gyalshing) Pkg-III (Design Ch.:
32.500 km to 33.600 km) under
SARDP-NE (Pkg- III)

Rehabilitation & Upgradation of


existing road to 2-lane with paved
shoulder including geometric
16 EPC NH(O)-NE 510 25.24 292.8 144.9 31-08-2020 31-10-2020 11.49% 9.71% 01-05-2022 01-05-2022 Shivam Condev Pvt. Ltd.
improvement of section from start
of Rabangla km33.600 to km58.540
(Pkg- IV)
Construction of 2-lane
specification road with paved
shoulder as realignment
17 EPC NH(O)-NE (Greenfield alignment) of existing 510 16.16 262.84 132.30 14-09-2020 10-11-2020 8.91% 7.13% 09-05-2023 09-05-2023 JRA Infrastructure Ltd. (JRAIPL)
stretch between Legship -
Gyalshing from km58.840 to
km75.00 (Pkg- V)
Construction of 2-lane road with
paved shoulder (Greenfield
alignment) of existing stretch
18 EPC NH(O)-NE 510 15.21 183.31 89.57 14-09-2020 10-11-2020 7.51% 3.71% 10-05-2022 10-05-2022 JRA Infrastructure Ltd. (JRAIPL)
between Legship - Gyalshing
from km75.00 to km 90.210 (Pkg-
VI)
Special protection work on
rehabilitation and restoration of
sliding/sinking zone from Km
70+900to Km 71+100 and Km
Item 71+550 to Km 71+850 with JICA
19 NH(O) NH-10 1.25 33.84 33.84 28-02-2020 11-06-2020 52.00% 42.00% 10-06-2022 31-12-2022 KCC Buildcon Pvt. Ltd.
Rate Technical Assistance including
widening of narrow zone from Km
53+775 to Km 54+100 and fom Km
63+045 to Km 63+470 on NH-10
(Rangpo to Ranipool section)

Total 220.61 4812.04 2634.39


Status as on 28-02-2022

NHDP NH No. Sanctioned Awarded Date of Cumulative Cumulative Target date of Likely date
SL. Length Date of
Mode Phase/ Name of Project (Old/ Cost/TPC Cost Start/Appoin Physical Financial completion as of Name of the Contractor
No. (Km) Award
Scheme New) Rs. in crore Rs. in crore ted Date progress % progress % per contract completion

Tripura
2-laning with Paved shoulder of Udaipur-
44 (New
1 ICR SARDP Sabroom Section of NH-44 from Km 55.00 to 73.712 915 497.89 02-05-2014 31-10-2015 100.00% 100.00% 30-04-2018 Completed M/s Oriental Structural Engineers Pvt. Ltd
NH-08)
128.712
Construction of Extra-dosed RCC Bridge
including viaduct and approaches over river 44 (New
2 BW NH(O) 1.888 128.69 82.57 22-03-2017 27-10-2017 99.50% 99.13% 26-04-2020 Completed M/S DRA Infracon Pvt. Ltd.
Feni at Sabroom on Indo-Bangladesh Border NH-08)
on NH-8 (old NH-44)
2-laning with Paved shoulder of Agartala-
44 (New
3 ICR SARDP Udaipur Section of NH-44 from Km 6.800 to km 48.2 649 369 31-10-2014 15-09-2015 99.21% 97.23% 14-03-2018 Completed M/s KMC Construction
NH-08)
55.00
Strengthening of Churabari - Agartala section
4 EPC NH(O)-NE 8 74.9 257.96 202 03-06-2020 24-07-2020 100.00% 99.65% 15-01-2022 Completed M/s Shiv Build India Pvt. Ltd.
of NH-08 (74.876 Km) on EPC basis

Rehabilitation & Upgradation of Road from Km


0.00 to Km 18.600 (Total length-18.600 km) of
5 EPC NH(O)-NE 208A 18.6 277.5 127.68 03-06-2020 15-07-2020 23.30% 20.97% 13-01-2022 30-05-2022 M/s Satish Prasad
Kumarghat-Kailashahar section on NH-208 to
2-lane with Paved shoulder on EPC bais

Improvement/strengthening to 2-lane with


hard shoulder of Khayerpur-Amtali (Agartala)
6 EPC NH(O)-NE 8 13 147.06 97.07 20-03-2020 01-07-2020 78.05% 67.86% 01-07-2022 01-07-2022 M/s CIVTECT (INDIA) Pvt.
section from Ch. 0.00 Km to 12.900 Km of NH-
8 on EPC basis [Tripura Bypass]

Improvement and Widening to 2 lanes with


7 EPC NH(O)-NE paved shoulders of Jolaibari - Belonia (from 108A 21.412 272.11 141.44 03-06-2020 15-07-2020 25.18% 18.96% 06-01-2022 30-05-2022 M/s Satish Prasad
km 0.000 to km 21.412) section of NH-108A
Rehabilitation & Upgradation of Road from
design Km 0.00 to Km 11.800 (Total length-
8 EPC NH(O)-NE 11.800 km) of Kailashahar-Kurti Bridge 208A 11.8 154.51 84.9 20-03-2020 15-07-2020 23.60% 19.67% 14-07-2022 15-07-2022 M/s ASC Infra Pvt. Ltd.
section on NH-208A to 2-lane with Paved
shoulder on EPC bais(PKG- I )
Rehabilitation and up-gradation of road from
design km 11.800 to km 25.250 (Total length:
9 EPC NH(O)-NE 13.450km) of Kailashahar-Kurti Bridge section 208A 13.45 178.43 88.9 30-03-2020 15-07-2020 22.97% 18.15% 14-07-2022 15-07-2022 M/s ASC Infra Pvt. Ltd.
on NH-208A to 2- lane with paved shoulder on
EPC basis (Package-II)
Rehabilitation and up-gradation of road from
design km 25.250 to km 36.460 (Total lengh:
10 EPC NH(O)-NE 11.210 km) of Kailashahar-Kurti Bridge 208A 11.21 140.55 73.21 03-06-2020 03-08-2020 9.50% 7.74% 25-01-2022 30-05-2022 A K Construction Co.
section on NH-208A to 2-lane with paved
shoulder (Package-III)
Rehabilitation and up-gradation of road from
design km 6.500 to km 19.300 (Total lengh:
208A/ NH-
11 BR NH(O)-NE 12.800 Km) of Agartala - Khowai section on 12.8 165.55 86.47 30-03-2020 15-07-2020 26.10% 20.53% 15-07-2022 15-07-2022 M/s Shiva Buildtech Pvt. Ltd.
108B
NH-108B to 2- lane with paved shoulder
(Package-I)
Rehabilitation and up-gradation of road from
km 19.300 to km 31.300 (Total length:
208A/ NH-
12 BR NH(O)-NE 12.000km) of Agartala-Khowai section on NH- 12 141.48 67.01 08-02-2021 08-06-2021 2.80% 0.00% 17-12-2022 17-12-2022 KLD Creation Infrastructure Pvt. Ltd.
108B
108B to 2- lane with paved shoulder on EPC
basis (Package-II)

Rehabilitation and up-gradation of raod from


design km 31.300 to km 45.300 (Total length:
208A/ NH-
13 BR NH(O)-NE 14.000km) of Agartala-Khowai section on NH- 14 173.17 96 21-09-2020 22-10-2020 18.90% 12.58% 15-04-2022 15-04-2022 A K Construction Co.
108B
108B to 2- lane with paved shoulder on EPC
basis (Package-III)

Rehabilitation and up-gradation of road from


km 0.000 to km 16.29 (Total Length: 16.29 km)
14 EC NH(O)-NE of Manu-Lalchara Section on Nh-44A to 2- lane 108 / 44A 16.29 247.76 166.94 30-03-2020 15-07-2020 29.00% 19.91% 14-01-2022 14-01-2022 Engineering Projects (INDIA) Ltd. (EPIL)
with paved shoulder-on EPC Mode (Manu-
Simlung -I)
Rehabilitation and up-gradation of road from
km 16.077 to km 43.935 (total length 27.858
15 EC NH(O)-NE km) of Lalchara-Kanchanpur section on NH- 108 / 44A 27.858 456.88 Under Bidding Under bidding
44A to 2 lane with paved shoulder (Manu-
Simlung -II)
Rehabilitation & Upgradation of Road from Km
46.597 to Km 66.845 (Total length= 20.248 km)
16 EC NH(O)-NE of Kanchanpur-Vaghmun section(PKG- III) on 108 / 44A 20.25 347.36 225.09 03-06-2020 20-07-2020 54.61% 46.98% 19-01-2022 30-05-2022 Rajendra Singh Bamboo Infra Pvt. Ltd.
NH-44A to 2 -lane with Paved shoulder (Manu-
Simlung-III)

Rehabilitation and up-gradation of road from


Km 66.845 to 85.125
JSR Constructions Pvt Ltd - PRN Infratech, Engineers &
17 EC NH(O)-NE (Total length: 18.280 Km) of Vaghmun- 108 / 44A 18.28 354.79 220.87 27-03-2021 25-06-2021 8.61% 6.70% 25-12-2022 25-12-2022
Contractors (JV)
simlung section on NH-44A (Package-lV) to 2-
lane with paved shoulder (Manu-Simlung-IV)

Improvement & widening to 2-lane with paved


18 EAP EAP (JICA) shoulder of road Kailashahar - Fultali section 208 8.1 99.48 62.25 24-11-2020 29-12-2020 21.64% 15.82% 30-06-2022 30-06-2022 Sahu Construction
from Km 21.100 to Km 29.200 (Pkg-1)

Improvement & widening to 2-lane with paved


19 EAP EAP (JICA) shoulder of road Fultali - Jurichhara section 208 20 206.78 121 24-11-2020 31-12-2020 42.11% 37.93% 01-07-2022 01-07-2022 Narendra Builders - Jeet Construction Co. (JV)
from Km 29.200 to Km 49.200 (Pkg-2)

Improvement & widening to 2-lane with paved


20 EAP EAP (JICA) shoulder of road Jurichhara - Bamanchara 208 14.5 280.91 199.49 24-11-2020 01-01-2021 55.13% 50.11% 02-07-2022 02-07-2022 Jandu Construction India Pvt. Ltd.- Maan Builders (JV)
section from Km 49.200 to Km 63.700 (Pkg-3)

Improvement & widening to 2-lane with paved


21 EAP EAP (JICA) shoulder of road Bamanchara - Srirampur 208 12 159.13 84.48 24-11-2020 29-12-2020 21.55% 14.24% 30-06-2022 30-06-2022 Sahu Construction
section from Km 63.700 to Km 75.700 (Pkg-4)

Improvement & widening to 2-lane with paved


22 EAP EAP (JICA) shoulder of road Srirampur - Khowai section 208 25.6 332.14 149.92 24-11-2020 30-12-2020 22.23% 14.56% 01-07-2022 01-07-2022 CIVTECT (INDIA) Pvt. Ltd.
from Km 75.700 to Km 101.300 (Pkg-5)

Total 489.82 6086.24 3244.17


Status as on 28-02-2022

NHDP NH No. Sanctioned Awarded Date of Cumulative Cumulative Target date of


SL. Length Date of Likely date of
Mode Phase/ Name of Project (Old/ Cost/TPC Cost Start/Appoint Physical Financial completion as per Name of the Contractor
No. (Km) Award completion
Scheme New) Rs. in crore Rs. in crore ed Date progress % progress % contract

Manipur
2- Laning of Imphal – Moreh Section of NH
EAP M/s GR Infra Projects ltd
1 EPC 39 from Km 350.000 to Km 395.680 39 44.78 868.75 457.77 01-06-2018 16-10-2018 100.00% 96.66% 15-10-2021 Completed
(ADB)
(Package II)
Construction of :(i) 154m span steel
superstructure Bridge at km 145.090 over
river Barak & (ii) 122m span steel
2 BW NH(O) 53 2 141.14 109 02-12-2016 27-04-2017 88.25% 80.38% 24-04-2020 30-05-2022 M/s Bhartia Infra (BIPL)
superstructure Bridge at km 189.800 over
river Makru and Approaches of both the
Bridges to be constructed is 1595m.
Construction of 4-Lane Bridge over Irang
3 BW NH(O) River on Imphal-Jiribam road section (95.50 53/ 37 0.377 49.31 41.88 27-11-2020 04-01-2021 28.57% 20.25% 16-10-2022 16-10-2022 Paratech Constructions Pvt. Ltd.
Km)
Widening to 2 -Lane with Paved shoulder
of Imphal to Jiribam section of NH-37 from
4 EPC NH(O)-NE 53/ 37 12.67 139.38 78.99 30-03-2021 01-07-2021 2.50% 0.00% 31-12-2022 31-12-2022 Avantika Contractor (I) Ltd.
Design Chainage 3.275 km to 15.940 Km
(Total length=12.665 Km) (PKG-1)

Widening to 2 -Lane with Paved shoulder


of Imphal to Jiribam section of NH-37 from
5 EPC NH(O)-NE Design Chainage 15.940 km to 33.120 Km 53/ 37 17.18 195.14 120.742 26-03-2021 11-06-2021 2.08% 0.00% 14-12-2022 14-12-2022 CMM Infraprojects Ltd.
(Existing Chainage Km 15.946 to Km
33.395) (Total length=17.180 Km) (PKG-2)

Widening to 2 -Lane with Paved shoulder


of Imphal to Jiribam section of NH-37 from
Mehta Construction Company - Ganpati Builders
6 EPC NH(O)-NE Design Chainage 33.000 km to 66.390 Km 53/ 37 33.16 467 253.84 15-07-2021 15-09-2021 2.70% 0.00% 19-03-2023 19-03-2023
(JV)
(Existing Chainage from km 33.395 to km
67.496) (PKG-3)

Widening to 2 -Lane with Paved shoulder


of Imphal to Jiribam section of NH-37 from
BLA Projects Private Limited - G P Projects Ltd.
7 EPC NH(O)-TSP Design Chainage 66.110 km to 101.280 Km 53/ 37 35.17 579.63 268.335 23-08-2021 to be given 0.00% 0.00%
(JV)
(Existing Chainage km 67.496 to km
103.557) (PKG-4)

Widening to 2 Lane with Paved shoulder of


lmphal to Jiribam section of NH-37 from
8 EPC NH(O)-TSP Design Ch. from Km 101+280 Near 53/ 37 30 410.68 Under Bidding 0.00% 0.00%
Khongsang Village to Km 131+280 near
Puilon (Kambiron) Village ( PKG-5 )
Widening to 2 Lane with Paved shoulder of
lmphal to Jiribam section of NH-37 from
9 EPC NH(O)-TSP 53/ 37 38.29 504.76 Under Bidding 0.00% 0.00%
Design Ch. from km 131.280 to km 169.570
(PKG-6)
Improvement/widening to 2 laning of
10 EPC SARDP stretch from Khongsang to Tamenglong of 137 37.97 424.62 296.25 08-03-2019 01-08-2019 65.57% 56.69% 31-07-2022 31-07-2022 M/s Shivalaya Construction Pvt. Limited
NH-137
Construction of 2 -Lane with paved
shoulders road from Tamenglong to Mahur
Roadridge Developers Pvt. Ltd.
11 EPC NH(O)-TSP in the state of Manipur from km 0.000 at 137 10 185.8 111.8 19-07-2021 15-09-2021 7.43% 5.58% 16-03-2023 16-03-2023
- Sunshine Overseas Pvt. Ltd. (JV)
Tamenglong to km 10.000 near Dialong
(Package-1)
Construction of of 2 -Lane with paved
shoulders road from Tamenglong-Tousem-
Jandu Construction India Limited - Niraj Cement
12 EPC NH(O)-TSP Lisang-Mahur Road (NH-137) starting near 137 21.43 483.87 292.448 20-07-2021 15-09-2021 14.21% 7.79% 16-03-2023 16-03-2023
Structurals Limited (JV)
Dialong Village at km 10.000 and ending
near Barak River at km 31.430 (Package-2)
Construction of 2 -Lane with paved
shoulders road from Tamenglong to Mahur
13 EPC NH(O)-TSP in the state of Manipur from Km 20.500 at 137 12.05 234.08 150.06 26-03-2021 21-06-2021 13.37% 10.06% 20-12-2022 20-12-2022 Kalyan Toll Infrastructure Ltd.
old Tamenglong to Km 30.800 near
Phelong (Package-3)
Construction of 2 -Lane with paved
shoulders road from Tamenglong to Mahur
Roadridge Developers Pvt. Ltd.
14 EPC NH(O)-NE in the state of Manipur from km 34+000 at 137 10.7 198.77 119.744 19-07-2021 15-09-2021 6.38% 5.51% 16-03-2023 16-03-2023
- Sunshine Overseas Pvt. Ltd. (JV)
Phelong to km 44+700 near Azuram
(Package-4)
Construction of 2 -Lane with paved
shoulders road from Tamenglong to Mahur
15 EPC NH(O)-TSP (NH-137) in Manipur starting from km 137 26.45 477.86 286.712 23-08-2021 18-11-2021 1.05% 0.00% 19-05-2023 19-05-2023 Shri Swami Samarth Engineers Ltd.
54.180 near Azuram to km 80.630 near
Mandeu (Package 5)
Construction of 2 -Lane with paved
shoulders road from Tamenglong to Mahur
16 EPC NH(O)-TSP (NH-137) starting from km 80.630 near 137 16.24 311.18 191.08 10-09-2021 19-11-2021 5.94% 0.00% 20-05-2023 20-05-2023 B R Goyal Infrastructure Ltd.
Mandeu to km 96.870 near Jiri River
(Package-6)
Improvement/Strengtening to 2-lane with
hard shoulder of Pallel-Chandel section
17 EPC NH(O)-NE 102C 18 107.72 71.01 27-03-2020 01-07-2020 89.90% 81.11% 30-06-2022 30-06-2022 Krishna Construction Co.
of NH-102C (Km 0.000 to Km 18.292) on
EPC basis
Widening/Improvement to 2-lane with
Paved shoulder of Yaingangpokpi - Finch
18 EPC NH(O)-NE corner road section of NH-202 from Km 202 16.9 124.81 28-03-2020 01-07-2020 27.18% 25.21% 30-06-2022 30-06-2022 M/s Varaha Infra Limited
0.000 to Km 16.900 (part of contract
Package -I) on EPC 478.81
Widening/Improvement to 2-lane with
Paved shoulder of Yaingangpokpi - Finch
19 EPC NH(O)-NE corner road section of NH-202 from Km 202 14.07 135.63 28-03-2020 01-07-2020 30.30% 21.76% 30-06-2022 30-06-2022 M/s Varaha Infra Limited
16.900 to Km 30.970 (part of contract
Package -II) on EPC basis
Construction of 2-laning with Hard
shoulder road of Ukhrul - Toloi - Tadubi L. G. Chaudhary (LGC)- Yogi Construction
20 EPC NH(O)-TSP 102A 31.02 315.56 181.256 22-10-2021 to be given 0.00% 0.00%
section of NH-102A from Design Chainage (YCC) (JV)
50.850 km to 81.870 km (Package -3)

Construction of 2-laning with Hard


shoulder road of Ukhrul - Toloi - Tadubi
21 EPC NH(O)-TSP 102A 23.96 310.76 150.14 27-08-2021 to be given 0.00% 0.00% A K Shivhare Infrastructure Pvt Ltd
section of NH-102A from Design Chainage
81.870 km to 105.825 km (Package -4)
Widening to 2-lane with Hard shoulder of
22 EPC NH(O)-TSP Churachandpur to Tuivai Section from 102B 13.75 167.95 92.71 31-03-2020 01-07-2020 56.05% 54.47% 30-06-2022 30-06-2022 Krishna Construction Co.
km0.00 to km13.747 (Pkg- I A)
Widening to 2-lane with Hard shoulder of
23 EPC NH(O)-TSP Churachandpur to Tuivai Section from 102B 19.09 241.52 139.8 31-03-2020 01-07-2020 34.59% 33.22% 30-06-2022 30-06-2022 RSM Infra Projects
km13.747 to km32.835 (Pkg- I B)
Widening to 2-lane with Hard shoulder of
24 EPC NH(O)-TSP Churachandpur to Tuivai Section from 102B 15.76 232.99 139.19 31-03-2020 01-07-2020 43.50% 42.89% 30-06-2022 30-06-2022 Bharat Vanijya Eastern Pvt. Ltd
km32.835 to km48.587 (Pkg- IIA)
Widening to 2-lane with Hard shoulder of
25 EPC NH(O)-TSP Churachandpur to Tuivai Section from Km 102B 21.88 365.53 206.41 30-06-2020 05-08-2020 45.75% 44.54% 05-08-2022 04-08-2022 Bharat Vanijya Eastern Pvt. Ltd
48.587 to Km 69.875 (Package-II B)
Widening to 2-lane with Hard shoulder of
Churachandpur to Tuivai Section of NH-
26 EPC NH(O)-NE 102B 51.89 673.27 404.48 14-07-2021 25-08-2021 4.64% 2.75% 25-02-2023 25-02-2023 M & S Co.
102B from Design Chainage 69.875 Km to
121.769 Km (Pkg-3)
Widening to 2-lane with Hard shoulder of
27 EPC NH(O)-TSP Churachandpur to Tuivai Section from 102B 11.15 204.12 114.68 31-03-2020 01-07-2020 40.59% 37.35% 30-06-2022 30-06-2022 M/s GPT Infraprojects Ltd.
Km118.850 to km130.00 (Pkg- IVA)

Widening to 2-lane with Hard shoulder of


28 EPC NH(O)-TSP Churachandpur to Tuivai Section from 102B 11.03 177.76 102.80 01-07-2020 05-08-2020 38.32% 35.02% 05-08-2022 04-08-2022 M/s GPT Infraprojects Ltd.
Km130.00 to km 141.029 (Pkg- IVB)
Improvement of existing road to 2 laning
with Hard Shoulders of Maram -Peren
CSR Infratech India Pvt. Ltd.- Raam Infratech
29 EPC NH(O)-TSP section (Package-1A, length- 22.340Km) 129A 22.34 226.32 151.15 05-02-2021 21-06-2021 10.40% 4.44% 22-12-2022 22-12-2022
India Pvt. Ltd. (JV)
from Design Chainage 0.000 km to 22.340
km on NH-129A
Improvement of existing road to 2 laning
with Hard Shoulders of Maram-Peren
CSR Infratech India Pvt. Ltd.- Raam Infratech
30 EPC NH(O)-TSP section (Package-1B, length- 17.660 km) 129A 17.66 188.36 128.55 05-02-2021 21-06-2021 14.81% 7.93% 22-12-2022 22-12-2022
India Pvt. Ltd. (JV)
from Design Chainage 22.340 km to 40.000
km
Improvement of existing road to 2 laning
with Hard Shoulders of Maram-Peren
31 EPC NH(O)-TSP section (Package-2A, length- 16.840 Km) 129A 16.84 204.58 121.00 07-07-2021 15-09-2021 13.20% 7.26% 19-03-2023 19-03-2023 Heera Ram Godara - Dudi & Company (JV)
from Design Chainage 40.000 km to 56.840
km on NH-129A
Improvement of existing road to 2 laning
with Hard Shoulders of Maram-Peren
32 EPC NH(O)-TSP section (Package-2B, length- 18.160 Km) 129A 18.16 232.26 145.87 12-02-2021 21-06-2021 11.94% 4.02% 22-12-2022 22-12-2022 Satya Builders
from Design Chainage 56.840 km to km
75.000 on NH-129A
Improvement of existing road to 2 lanning
with Hard Shoulders of Maram Peren
New India Contractors & Developers Pvt. Ltd. -
33 EPC NH(O)-TSP section (Package-III, length - 34.494 km) 129A 34.49 467.41 269.42 27-08-2021 26-11-2021 0.00% 0.00%
Bharat Construction Co. (JV)
from Design Chainage km 75+000 to
109+494 km on NH-129A
Improvement/Upgradation of existing 2-
lane to 4-Lane Divided Highway from
Lekcon Infrastructure Pvt. Ltd. - R.S.V.
34 EPC NH(O)-NE Taphou Kuki to Daili section of Imphal- 39 12.44 379.39 212.54 31-08-2020 15-10-2020 7.66% 4.08% 17-04-2022 17-04-2022
constructions Pvt. Ltd. (JV)
Kohima Road (Design Ch.: km 262.175 to
274.610) (Pkg-4A)
Improvement/Upgradation of existing 2-
lane to 4-Lane Divided Highway from Daili Project has been Foreclosed due to Non-
To be
35 EPC NH(O)-NE to Kuraopokpi section of Imphal-Kohima 39 12.39 268.98 0.00% 0.00% 15-04-2022 Project Foreclosed availability of land.
Re-awarded
Road (Design Ch.: km 274.610 to 287.00 ) Project to be Re-awarded
(Pkg-4B)
Improvement/Upgradation of existing 2-
lane to 4-Lane Divided Highway from Project has been Foreclosed due to Non-
To be
36 EPC NH(O)-NE Kuraopokpi to Sekmai section of Imphal- 39 10.7 228.97 1.30% 0.00% 15-04-2022 Project Foreclosed availability of land.
Re-awarded
Kohima Road (Design Ch.: km 287.00 to Project to be Re-awarded
297.700) (Pkg-5A)

Improvement/ Up-gradation of existing 2-


Lane road to 4-Lane Divided Highway from
37 EPC NH(O)-NE Sekmai to Nilkhuthi section of Imphal- 39 11.029 211.7 126.58 27-03-2021 28-07-2021 1.35% 0.00% 21-01-2023 21-01-2023 NSC Projects Pvt. Ltd
Kohima Road (Design Chainage from Km
297+700 to Km 308+729) of NH-39 (Pkg-5B)

4- Laning of Imphal – Moreh Section of NH


EAP M/s GR Infra Projects ltd
38 EPC 39 from Km 330.000 to Km 350.000 39 20 761.54 397 05-09-2019 01-06-2020 51.67% 40.49% 31-05-2023 31-05-2023
(ADB)
(Contract Package I)
Widening and Improvement to 2-Lane with
paved shoulders of Imphal-Moreh section
39 EPC NH(O)-NE 39 10.32 259.31 150.11 22-03-2021 21-06-2021 36.80% 31.04% 20-12-2022 20-12-2022 Dwarakamai Constructions Pvt. Ltd.
of NH-39 from Km 395.680 to Km 406.000
(Package-III)
Widening and Improvement to 2-Lane with
paved shoulders of Imphal-Moreh section SKV Infratech Pvt. Ltd. - SPG Infraprojects Pvt.
40 EPC NH(O)-NE 39 19.411 277.99 140 22-03-2021 20-07-2021 12.95% 3.98% 19-01-2023 19-01-2023
of NH-39 from km 406.000 to Km 425.411 Ltd (JV)
(Package-IV)

Construction of Moreh Bypass to 2-lane


with Paved shoulder from km421.950 to
41 EPC NH(O)-NE 39 2.52 68.14 21.51 27-03-2020 01-07-2020 29.95% 16.22% 31-12-2021 31-12-2021 M/s L.K. & Sons
425.411 of NH-39 (Length= 2.52 km) near
Indo-Myanmar border on EPC

Total 805.27 12722.91 6505.29


Rehabilitation (COMPLETED)

Short term routine maintenance and


% improvement of Imphal-Jiribam road from M/s HVS Construction Materials
1 NH (O) 53 51.67 46.76 26-04-2017 01-04-2017 100.00% 100.00% 30-06-2018 Completed
rate Km 3.00 to Km 75.00 on percentage rate Pvt. Limited
basis

Short term routine maintenance and


% improvement of Imphal-Jiribam road from 83.00 M/s Nidhi Creative Infrastructure
2 NH (O) 53 43.05 38.44 17-04-2017 10-03-2017 100.00% 100.00% 11-03-2018 Completed
rate Km 75.00 to Km 145.00 on percentage Limited
rate basis

Short term routine maintenance and


% improvement of Imphal-Jiribam road from
3 NH (O) 53 66.86 60.36 08-05-2017 01-04-2017 100.00% 100.00% 30-06-2018 Completed M/s Bhartia Infra Projects Limited
rate Km 145.00 to Km 220.00 on percentage
rate basis

Restoration/Reconstruction of Ukhrul-
% Toloi-Tadubi road section from Km 0.00
4 NH (O) 102A 28.00 3.78 2.98 26-10-2016 27-10-2016 100.00% 100.00% 26-01-2018 Completed M/s Bhartia Infra Projects Limited
rate to Km 28.00 covering 28 Km length on
NH-102A in the state of Manipur.

Restoration/Reconstruction of Ukhrul-
% Toloi-Tadubi road section from Km 28.00
5 NH (O) 102A 22.00 14.91 11.12 26-10-2016 07-11-2016 100.00% 100.00% 06-02-2018 Completed M/s Shingvah Thanami
rate to Km 50.00 covering 22 Km length on
NH-102A in the state of Manipur.

Restoration/Reconstruction of Ukhrul-
% Toloi-Tadubi road section from Km 50.00
6 NH (O) 102A 20.00 11.40 11.35 26-10-2016 11-01-2016 100.00% 100.00% 31-01-2018 Completed M/s Bhartia Infra Projects Limited
rate to Km 70.00 covering 20 Km length on
NH-102A in the state of Manipur.

Restoration/Reconstruction of Ukhrul-
% Toloi-Tadubi road section from Km 70.00
7 NH (O) 102A 20.00 15.64 13.07 29-03-2017 24-05-2017 100.00% 100.00% 23-05-2018 Completed M/s Haokhotinlen Vaiphei
rate to Km 90.00 covering 20 Km length on
NH-102A in the state of Manipur.

Restoration/Reconstruction of Ukhrul-
% Toloi-Tadubi road section from Km 90.00
8 NH (O) 102A 25.00 15.37 12.91 29-03-2017 24-05-2017 100.00% 100.00% 23-05-2018 Completed M/s Haokhotinlen Vaiphei
rate to Km 115.00 covering 25 Km length on
NH-102A in the state of Manipur.

Rehabilitation/Strengthening of existing
%
9 NH (O) road Churachandpur- Singhat-Sinzawl- 102B 34.5 47.82 37.69 28-11-2017 12-12-2017 100.00% 100.00% 23-09-2019 Completed M/s Satya Builders
rate
Tuivai sector from Km 0.00 to Km 34.500

Rehabilitation/Strengthening of existing
%
10 NH (O) road Churachandpur- Singhat-Sinzawl- 102B 68.6 69.31 54.08 08-06-2016 01-08-2016 100.00% 100.00% 01-08-2019 Completed M/s Bhartia Infra Projects Limited
rate
Tuivai sector from Km 34.00 to Km 103.1

Rehabilitation/Strengthening of existing
% road Churachandpur- Singhat-Sinzawl-
11 NH (O) 102B 58.38 59.4 45.12 04-01-2018 18-01-2018 100.00% 100.00% 30-10-2019 Completed M/s Garg & Sons
rate Tuivai sector from Km 103.1 to Km
161.48

item Temporary restoration of Khongsang-


12 NH (O) 137 40 19.1 17.48 30-01-2017 06-02-2017 100.00% 100.00% 05-02-2018 Completed M/s K. Morung and sons
rate Tamenglong on item rate basis

Total 399.48 418.31 351.36