Schedule - Instalasi Fender Jetty

The document outlines the schedule, manpower, and tools planning for the installation of a fender jetty by PT. Sinar Alam Permai in Palembang, proposed by PT. Sinbar Persada Indonesia. The project is set to last 120 days and includes detailed descriptions of work phases, manpower requirements, and equipment needed. Key roles include site manager, supervisors, safety personnel, and various skilled workers, with a comprehensive breakdown of their weekly manpower allocation and equipment usage throughout the project timeline.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
17 views1 page

Schedule - Instalasi Fender Jetty

The document outlines the schedule, manpower, and tools planning for the installation of a fender jetty by PT. Sinar Alam Permai in Palembang, proposed by PT. Sinbar Persada Indonesia. The project is set to last 120 days and includes detailed descriptions of work phases, manpower requirements, and equipment needed. Key roles include site manager, supervisors, safety personnel, and various skilled workers, with a comprehensive breakdown of their weekly manpower allocation and equipment usage throughout the project timeline.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

SCHEDULE, MANPOWER, & TOOLS PLANNING

INSTALASI FENDER JETTY PT. SINAR ALAM PERMAI PALEMBANG


Project : INSTALASI FENDER JETTY
Owner : PT. SINAR ALAM PERMAI - PALEMBANG
Proposed by : PT. SINBAR PERSADA INDONESIA
Contract Period : 120 Days of Calendar

WEEK
DURASI
No. DESCRIPTION UNIT REMARKS
(WEEK) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

I WORK SCHEDULE COMMENCEMENT COMPLETION

A PRELIMINARY 16.00 ls

B PEKERJAAN FENDER

2.1. Pilling Work 4.00 ls

2.2. Catwalk 5.00 ls

2.3. Fender System 8.00 ls

2.4. Bracing Structure 6.00 ls

WEEK

No. DESCRIPTION UNIT REMARKS


1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

II MANPOWER PLANNING
Site Manager Manweeks 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Supervisor Manweeks 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Safety Man Manweeks 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Surveyor Manweeks 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Security Manweeks 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 2

Operator Mesin Pancang & Crane Manweeks 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Rigger Manweeks 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Foreman Crane Manweeks 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3

Specialist Coating Manweeks 4 4 4 4

Welder Manweeks 1 1 1 2 2 2 2 2 2 2 2 2 2 1 1

Fitter Manweeks 2 2 2 4 4 4 4 4 4 4 2 2 2

Helper Manweeks 3 3 3 3 3 3 3 3 3 3 3 2 2

TOTAL 12 13 17 22 23 23 21 21 21 21 21 21 21 19 15 10

WEEK

No. DESCRIPTION UNIT REMARKS


1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

III TOOLS & EQUIPMENT PLANNING

Service Crane Unit 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Alat Ukur Survey Unit 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Trafo Las Unit 1 1 2 2 2 4 4 4 4 4 4 4 2 2 2

Cutting Torch pc 2 2 2 2 2 2 2 2 2 2 2 1 1

Tabung Gas Oksigen pc 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2

Gerinda pc 1 1 4 4 4 4 4 4 4 4 4 4 2 2 2

PROPOSED BY,
PT. SINBAR PERSADA INDONESIA

TEDI ALFIAN MUSLIM


Project Manager