Lab No. 2
Lab No. 2
BLDG 2045
Lab 2 - Individual
Instructions,
Answer the following questions, using Yorkland Structural Specifications for Drilled
Caissons 31 63 26 and Drawing S1-01.
The liner is used to prevent unwanted soil or water into the excavation and to allow
removal of any loose materials from the bottom and to allow inspection and testing
companies to be able to inspect the excavation. As per section 3.4.1 “Liner Installation”
on the Yorkland Structural specifications for drilled caissons.
1
by earths pressure or any other reasons. As per 3.5.1-3.5.2 “Liner Removal” on the
Yorkdland Structural specifications.
As per 1.5.3 Allow ten (10) working days for the review of shop drawings and supply as
many copies for review and distribution as directed. Shop drawings shall be checked in
detail by the General Contractor before submission. Drawings which fail to meet this
requirement shall be returned marked NOT REVIEWED.
As per 3.3.4 Test Cassions, information of the nature of the soil and the amount6 of
water encountered at various levels.
As per 3.6.3 Concrete placement, the concrete must be poured so that the discharge
can be controlled to evenly spread in a uniform mixture over the whole area without
striking shaft sides, and to prevent segregation or voids or honeycombing.