The Impact of Low Probability Ground Motions on Canadian Geotechn
The Impact of Low Probability Ground Motions on Canadian Geotechn
Scholars' Mine
Recommended Citation
Finn, W. D. Liam, "The Impact of Low Probability Ground Motions on Canadian Geotechnical Engineering
Practice" (2008). International Conference on Case Histories in Geotechnical Engineering. 1.
https://scholarsmine.mst.edu/icchge/6icchge/session00d/1
This work is licensed under a Creative Commons Attribution-Noncommercial-No Derivative Works 4.0 License.
This Article - Conference proceedings is brought to you for free and open access by Scholars' Mine. It has been
accepted for inclusion in International Conference on Case Histories in Geotechnical Engineering by an authorized
administrator of Scholars' Mine. This work is protected by U. S. Copyright Law. Unauthorized use including
reproduction for redistribution requires the permission of the copyright holder. For more information, please
contact [email protected].
THE IMPACT OF LOW PROBABILITY GROUND MOTIONS ON CANADIAN
GEOTECHNICAL ENGINEERING PRACTICE
W. D. Liam Finn
University of British Columbia
Vancouver, Canada, V6T 1Z4
ABSTRACT
The adoption of design motions with a 2% rate of exceedance in 50 years in the National Building Code of Canada (NBCC 2005) has had a
major impact on geotechnical engineering practice in Canada. The peak ground accelerations were doubled compared with the previous
motions which had an exceedance rate of 10% in 50 years. The increase in accelerations has had a huge effect on assessments of
liquefaction potential and slope stability, because the methods of assessment in common use depend on peak ground acceleration. This
paper describes typical problems encountered in Canadian practice with use of the low probability motions and describes some measures for
alleviating the impact on design, while maintaining the code objective of life safety.
The impact on seismic slope stability makes an interesting case In more conventional practice, the Seed and Idriss (1971)
history. Following the adoption of the NBCC 2005 design simplified method for assessing liquefaction, as updated in Youd
motions by the province of British Columbia (BC) in the BC et al. (2001), is widely used, especially in Eastern Canada. The
Acceleration, a
the peak ground acceleration. The probabilistic ground motions
in NBCC 2005 are the combined contribution to hazard of all 0
Slope H k15 k=0.5(PGA) The observed displacement of the slope of the Austrian Dam was
Location (m) 2% in 50 yrs 10% in 50 yrs 50cm during the 1989 Loma Prieta Earthquake. The results of the
RELAN analysis are shown in Fig. 6 which shows the
Nanaimo 30 0.16 0.11
conditional probabilities of exceedance of prescribed
Duncan 22 0.18 0.15 displacements Dlim. The observed displacement of 50cm is
Victoria 13 0.20 0.18 . predicted to have a probability of exceedance of 38% for the
specified variations in seismicity and slope parameters. Bray and
Travasarou (2007) estimated the 84% displacement to be 70cm.
ANALYSIS WITH UNCERTAINTY IN VARIABLES RELAN estimates that this displacement has a probability of
exceedance of 30% for the specified uncertainties in the
controlling parameters.
Slope displacement D>1cm is given by Bray and Travasarou
(2007) as
Probability
as deterministic by Bray and Travasarou (2007) in their Eq.1 for
evaluating D. The error term, ε, is the uncertainty in the
displacements for deterministic values of the other independent
variables and has a normal distribution with a mean of 0.0 and a
standard deviation of 0.66.
The variations in slope parameters were prescribed as follows. Method 2 is based on pseudo-static (limit equilibrium)
The spectral values in NBCC 2005 have a lognormal distribution seismic slope stability analysis, similar to current
with a standard deviation of 0.7. A standard deviation of 0.3 was practice, but uses a slope displacement-based seismic
assumed for magnitude M. Standard deviations equivalent to coefficient, k15, given by Eq. 3, that is equivalent to a
20% of the deterministic values used by Bray and Travasarou tolerable slope displacement of 15cm, when the slope is
(2007) in their analysis of the dam were assumed for the other subjected to design ground motions.
variables, ky and Ts, reflecting the difficulty in defining shear
strength and slope period accurately. The latter three variables
were assumed to have normal distributions.
The use of k = PGA with a factor of safety FS > 1.0 as a basis for
final judgment on slope stability is considered by the TFSSS as
too conservative and is recommended only as a preliminary
screening tool. The limiting displacement of 15 cm is proposed
as a guideline and is not intended to preclude the engineer of
record from selecting any other value that he judges appropriate.
The engineer should strive for a balance between desirable
locations for a building and the associated seismic displacements.
The effect of the magnitude weighting factor on the CSR for a The weighted magnitude probabilistic analyses reported in this
given magnitude is given by Eq.8. paper were conducted to obtain the magnitude–acceleration pair
for evaluating liquefaction potential. In this context, the weighted
CSR = 0.65 (amax/g) (σvo/σ’vo) (rd) (MWF) (8) hazard curves are called liquefaction hazard curves. The seismic
hazard curve for Vancouver and the liquefaction hazard curve
When dealing with a scenario earthquake of magnitude M which weighted for magnitude M = 7.5 are shown in Fig. 8.
has a direct link to the PGA at the site, the MWF for M can be
Annual Frequency of Exceedance
should be used? In current practice a single magnitude is often 10-2 Liquefaction Hazard
The unweighted and weighted PGA are for firm ground and,
depending on the intensity of shaking, will be amplified or
deamplified at the surface by a site factor C on propagating
through the softer soils often associated with liquefaction. The
site factor C is often estimated from generalized amplification
data such in Idriss (1990), the short period amplification factors
in NBCC 2005 or from ground motion attenuation relations for
different soil types. Site response analysis should not be used to
get PGA for use with the simplified Seed-Idriss method. It would
be more reliable in this case to use the computed cyclic stress Fig.9. Magnitude-distance deaggregation for NBCC 2005
ratios from the analysis directly with Fig. 8 to assess liquefaction PGA in Vancouver
potential. The factors of safety against liquefaction presented in
the following table were calculated by the simplified method for
a range in (N1)60 values using the magnitude-acceleration pair
from the weighted magnitude probabilistic analysis. Generic site
conditions were assumed, consisting of sand, with unit weight
20 kN/m3, a water table at 2 m, and a range of (N1)60 values at
6 m depth. For these analyses the site factor was assumed to be C
= 1.0. The factors of safety are shown in Table 5.
18
16 The deaggregation method is based on site deaggregations given
14 by the Geological Survey of Canada (Halchuk and Adams,
12 2006). The analyses leading to these deaggregations include the
10 effects of epistemic uncertainty through the use of three sets of
8 seismic parameters, the best estimates and upper and lower
6
bounds on these estimates. The results from using these three sets
4
are weighted and summed to give the code values for PGA and
2
the associated deaggregations. The effects of epistemic
0
uncertainty vary with the seismic environment.
4 5 6 7 8
Magnitude
Fig.14. Magnitude Contributions to Toronto NBCC 2005 CONCLUDING COMMENTS ON LIQUEFACTION
PGA Hazard
There are two logical methods for incorporating probabilistic
The resulting factors of safety are given in Table 8. The ground accelerations into the Seed-Idriss simplified method for
magnitude deaggregation method gives factors of safety on evaluating liquefaction potential at a site. The most direct method
average 4% greater than the weighted magnitude analysis. The is a probabilistic seismic hazard analysis using weighted
mean magnitude in combination with the NBCC 2005 PGA gives magnitudes. The weighting factors quantify the contributions of
factors of safety for the Toronto site that are similar to the factors different magnitudes to liquefaction potential for a given ground
given by the deaggregation and weighted magnitude methods. In surface acceleration relative to a normalizing magnitude M. The
the Toronto seismic environment, the modal magnitude also normalizing magnitude is usually taken as M = 7.5. The
gives 15% - 20% less to liquefaction potential. These analyses weighting factors for liquefaction assessment may be any of the
were conducted with an amplification⁄deamplification factor C = sets recommended by Youd et al. (2001) as determined by the
1.0 as in the case of Vancouver. geotechnical engineer. In the analyses conducted for this study,
the weighting factors recommended by Idriss are used. These
Table 8. Factors of safety against liquefaction in Toronto for factors are a lower bound on the factors available in Youd et al.
various triggering options (2001).
Liquefaction Triggering Safety Factors for Toronto The weighted magnitude probabilistic analysis gives a unique
magnitude-acceleration pair for use with the Seed-Idriss
Modal Mean Deaggregation Weighted
simplified method. In this study the normalizing magnitude was
(N1)60 Magnitude Magnitude Method Mag. Analysis
taken to be M = 7.5. Any other normalizing magnitude can be
PGA = 0.20g PGA = 0.11g
selected and a compatible magnitude-acceleration pair can be
mN=5.875 mN=5.67 mN=7.0-4.75 mN=7.5 determined by simple proportion of the relative scaling factors
Mw=5.47 Mw=5.204 Mw=7.0-4.75 Mw=7.78 for the magnitudes. All compatible magnitude-acceleration pairs
10 1.33 1.52 1.59 1.5 determined by the weighted probabilistic analysis will yield the
13 1.67 1.9 1.96 1.89 same factor of safety against liquefaction. The probabilistic
15 1.9 2.16 2.24 2.2 acceleration from the weighted magnitude analysis must be
18 2.27 2.59 2.68 2.58 multiplied by the site amplification/deamplification factor, C, to
20 2.54 2.91 3.01 2.92 give the magnitude-acceleration pair to be used in evaluating
25 3.46 3.94 4.08 3.93
liquefaction potential.
30 4.61 5.05 5.29 4.92
The second logical approach is based on a magnitude-distance
deaggregation of the seismic hazard at a site. Here a 2-D
magnitude deaggregation is developed which gives the
ASSESSMENT OF LIQUEFACTION RESULTS
contribution of each magnitude to the probability of exceeding
the NBCC 2005 PGA. The code PGA is first multiplied by the
The factors of safety given by weighted magnitude analysis and
amplification/deamplification factor C. Then the factor of safety
deaggregation analysis are approximately the same. The minor
against liquefaction for each magnitude bin is calculated for the
differences result primarily from the different approaches to
Anderson, DL, Byrne, PM, DeVall, RH, Naesgaard, E, and Idriss, IM. [1990]. Response of soft soil sites during earthquakes,
Wijewickreme, D. [2007]. Task Force Report: Geotechnical Proceedings H.B. Seed Memorial Symposium, Editor J. Michael
Design Guidelines for buildings on Liquefiable Sites in Duncan, BiTech Publishers Ltd., Vancouver, BC Canada. Vol.2,
Accordance with NBC 2005 for Greater Vancouver Region, see pp 273-290.
http://www.civil.ubc.ca/liquefaction.
Kramer, SL. and Mayfield, RT. [2005]. Performance-based
BCBC (BC Building Code) [2006]. Published by the Office of liquefaction hazard evaluation, Earthquake Engineering and Soil
Housing and Construction Standards, BC Ministry of Forests and Dynamics, Geotechnical Special Publication GSP 133, ASCE.
Range.
Makdisi, F., and Seed, HB. [1978]. Simplified procedure for
Blake, TF, Hollingsworth, N, Bray, JD and Stewart, JP. [2002]. estimating dam and embankment earthquake-induced
Recommended Procedures for Implementing of DMG Special deformations, Journal of Geotechnical and Environmental
Publication 117, Guidelines for Analyzing and Mitigating Engineering, ASCE, Vol. 104, No.4 , pp 381-392.
Landslide Hazards in California, Southern California Earthquake Newmark, NM. (1965). Effects of earthquakes on dams and
Center, University of Southern California, Los Angeles, CA. embankments, Geotechnique, 15(2) p 139-160.
Bray, JD. [2007]. Private communication to TFSSS.
Bray, J.D., Rathje, E.M., Augello, A.J., and Merry, S.M. [1998].
Simplified seismic design procedures for geosynthetic-lined solid
waste landfills. Geosynthetic. Int., 5(1-2),203-235.
Seed, HB., and Idriss, IM. [1982]. Ground motion and soil
liquefaction during earthquakes. Earthquake Engineering
Research Institute Monograph, EERI. Oakland, California.