WGM
WGM
B super structure
Contractor Suervisor
Vat15% 40,689.47 10,058.96
Total After Vat 311,952.62 77,118.68
Contractor Suervisor
MEASUREMENT
Quantity Amount
No Description Unit RATE
Contract Executed Contract Executed
Bulk excavation in
1.2 ordinary soil to a depth m3 733.95 1,420.00 25.00 18,348.75 35,500.00
not exceeding 1000mm
contractor suervisor
2. CONCRETE WORK
50mm lean concrete
quality C-5 with minimum
2.1
cement content of
150kg /m3 of concrete
a/ Under stone masonry wal m2 144.00 30.00
B/ Under drainage bed slab m2 90.00 30.00
Reinforced concrete
2.2
quality C-20,
a/ In 100mm thick drainage m2 162.00 100.00
b/ In masonry topping m3 144.00 100.00
Provide,cut and fix in
2.3 position sawn structural
wood or steel formwork
a/ To masonry topping m2 72.00 100.00
2.4 Mild steel reinforcement
a/ Dia 8mm deformed bar kg 526.14 30.00
2.5 MANHOLES
Size:- 600mm(Av.Depth
pcs 13.00 3,000.00
800mm)
TOTAL CARRIED TO SUMMARY -------
3. MASONRY WORK
500mm thick hard
3.1 m3 129.60 400.00
trachytic (N.G.L)
3.2 Ditto but above ground leve m3 14.40 400.00
Total CARRIED TO SUMMARY -------
contractor suervisor
Take Off Sheet
Project :-Weliya Sidist School Expansion
Client :-SACFDO
Consultant :- Siltie Zone Admni. Office Design Construction Office
Conntractor :-Getachew Erdapo B.C
Timesing Dimension Result Description Timesing Dimension Result
A. Substructure
1.1.Site clearing to a depth of
19.60 L= 16.60+2(1.5)=19.6m 75.00
11.40 w=8.40 +2(1.5)=11.40m 0.30
223.44 m2 0.20 4.50
16.60 1.2.Bulk Excavation
8.40 13.00 3.00
0.70 97.61 m 3
0.20
1.3.Trench excavation 0.20 1.56
T.L.= 3x16.60+3x8.40=75ml
75.00 L=75m 13.00 3.00
1.50 4.00 0.30 46.80
0.80 90.00 m3
\ 1.4.Cart away excavated mtrl
44.60
97.61 3.00 75.00
90.00 232.21 m 3
0.30 67.50
1.5.Back fill selected material
75.00 around masonary
1.50 3.00 16.60
0.30 33.75 m 3
3.00 149.40
16.60 under hard core 2.00 7.00
8.40 3.00 42.00
0.4 55.78 m 3
2.00 2.80
89.53 m Total
3
0.90 -5.04
1.6.Hard basaltic hard core 8.00 1.80
16.60 1.70 -24.48
8.40 139.44 m 2
12.00 0.85
2.Concrete work 0.61 -6.22
75.00 2.1. 5cm thick lean concete 2.00 8.40
0.50 A) Under massonary 1.50 25.20
37.50 m 2
180.86
139.44 m2 as item no 1.6 under floor slab
2.2.C-25 concrete to:- 7.00
A) Grade beam 3.00
75.00 21.00
0.40
0.20 6.00 m3
2.3. Form work to:-
2.00 75.00 A) Grade beam
0.40 60.00 m2
2.5.10cm thick ground floor slab
139.44 m2 as to item no.1.6
3.Massonary work
3.1. 50cm thick stone massonary
75.00 fondation BNGL
1.50
0.60 67.50 m3
3.2.Ditto but ANGL
75.00
0.70
0.60 31.50 m3
B. dia 8cm-10cm vertical & diagonal
43.00 12.00 avg= 2x.5=.75 12 pcs
516 ml
4.2 5x7cm roof purlin
43.20 13.40 2x6=12pc
578.88 ml
4.3 Fascia board
115.20 ml
B.5 Internal wall
plastering,column & beam
2.00 42.00
1.00 block wall
84.00
4.00 12.00
1.00
48.00
column
24.00 3.50
4.00 0.25
84.00
3.00 150.00 tt.beam
0.25
112.50
108.00 grade beam
0.30
32.40
360.90 m2
5.3 cement sand screed
139.44 m2 as item 1.6
112.00 ml
5.6 Concrete pavement
112.00
1.00
112.00 m2
Description
B) Super Structure
2.Concrete Work
2.1.C-25 concrete to:-
a) top tie beam
m3
b)elevation column
m3
2.3.Form work to
a)Elevation column
m2
deduction
door
w1
W2
gable side
m2
2.2.15cm thick block
MEASUREMENT
Project:-dry latrine
Client:- Melik Silte Farmers' Co-operative Unions.
Contractor:- Kemal Aman B.C
Quantity Amount
No Description Unit Unit
Contract Executed Contract Executed
A) Substructure
1.2 Pit excavtion to a depth of 150 cm. m3 26.00 21.04 30.00 780.00 631.12
1.3 Pit excavtion to a depth of 450 cm. m3 51.00 42.07 40.00 2,040.00 1,683.00
Back fill around massonry foundation
1.4 m3 18.00 8.42 100.00 1,800.00 841.50
and under hard core
1.5 Cart away Excavated material m3 84.00 70.51 100.00 8,400.00 7,051.25
2.Concrete Work
2.1 5 cm thick lean concrete m2 8.40 12.88 50.00 420.00 644.00
2.2 Concrete grade beam m3 1.40 1.59 1,600.00 2,240.00 2,540.80
3.Massonry Work
3.1 masonry below NGL &above NGL m3 80.00 50.70 600.00 48,000.00 30,420.00
b)in all beam & lintels m3 1.50 1.68 1,660.00 2,490.00 2,788.80
1.2 form work 0.00 0.00
b)in all beam & lintels m2 26.00 25.20 60.00 1,560.00 1,512.00
1.3 steel reinforcment bar 0.00 0.00
contractor suervisor
TAKEOFF SHEET
Project:-,Road & Parking
Client:- Melik Silte Farmers' Co-operative Unions.
Contractor:- Kemal Aman B.C Page: 01
T D S Description T D S Description
320.00 A6
A.SUB STRUCTURE 1.00
1. EXCAVATION & EARTH WORK 320.00
1.1. Site clearing 84.00 A7
0.00 A1 1.00
0.00 84.00
0.00 A2
0.00 ### m3 Total bulk excavation
450.00 A3
1.4.Fill with sellected
450.00 material access road
168.00 A4 0.00 A1
168.00 1.00
328.00 A5 0.00
328.00 0.00 A2
320.00 A6 1.00
320.00 0.00
84.00 A7 450.00 A3
84.00 1.00
450.00
### m Total site clearing
2
168.00 A4
1.2 Bulk Excavation 1.00
0.00 A1 168.00
1.00 328.00 A5
0.00 1.00
0.00 A2 328.00
1.00
0.00 946.00 m3 Total selected fill
450.00 A3 1.6 cart away
1.00 0.00 A1
450.00 0.00 A2
168.00 A4 450.00 A3
1.00 168.00 A4
168.00 328.00 A5
328.00 A5 320.00 A6
1.00 84.00 A7
328.00 270.00 site clear
### m2
4.uprooting tree
340.00
340.00 pcs
contractor supervisor
4 1.70 F-1
1.70
0.35 4.046
4.05
4.05 m3 total in footing pad
B.in foundation columns
34 3.00
0.40
0.40 16.32
16.32 m3 total
C.in grade beams
m3 total
D.20cm floor slab
m2
2.4 Stee
895.15 kg Dia 8mm plain bar
0.00 kg Dia 14mm plain bar
0.00 kg Dia 16mm plain bar
0.00 kg Dia 20mm plain bar
contractor supervisor
worabe agricultural reaearch center cow witting class mintainance work BoQ
Unit
No DESCRIPTION Unit QTY
Rate/birr
1. Demolishing and chesilling existed concrete
chesilling floor concrete to approprete works as M2 195.0 60.0
1 need teady to for nexte work
Total carried to summary….
2. MASONARY WORK
stone for cow feeding bowl /bedded with 1:3 mix
ratio cement mortar price include all nescssory M3 0.0 4,000.0
2 goods and accessories to complete it.
Total carried to summary….
3. Concrete Work
Reinforced concrete C-253 360kg cement/m3 filled
into formwork and vibrated around rod
reinforcement steel and formwork measured
separetly the work shoul be done using man power
3.1 or mixer and vibrator for any concrete mixing
d) round tubolari metal with cuting wellding and fixing ls 1.0 110,000.0
with existed metal guard
Total carried to summary….
Grand total summary….
15% VAT
Total with Vat 15%
ss mintainance work BoQ
total amount/birr
11,700.0
11,700.0
0.0
0.0
210,000.0
6,500.0
0.0
115,600.0
0.0
110,000.0
442,100.0
453,800.0
68,070.0
521,870.0