MEGA user manual
MEGA user manual
User Manual
CONTENTS
1
6.1 Cable Requirements .....................................................................................................23
6.2 Connection Terminal ....................................................................................................24
6.3 Wiring Specification .....................................................................................................24
6.4 Fixation and Protection of Connecting Cables .............................................................25
6.5 Remove Switch Baffle And Lower Panel ......................................................................25
6.6 Internal Terminal ..........................................................................................................26
6.7 DC Side Wiring ..............................................................................................................27
6.8 AC Side Wiring ..............................................................................................................28
6.9 System Grounding ........................................................................................................28
6.10 Installation Is Complete .............................................................................................28
7 Test Run ........................................................................................................................... 29
7.1 Pre-Boot Check .............................................................................................................29
7.2 Start-Up Operation Flow ..............................................................................................30
7.3 Shutdown Operation Flow ...........................................................................................31
8 Touch Screen Operational Guidelines ............................................................................. 33
8.1 Introduction of Touch Screen ......................................................................................33
8.2 Alarm Buzzer ................................................................................................................34
8.3 Communication Settings ..............................................................................................34
8.4 Software Introduction ..................................................................................................34
9 Maintenance and troubleshooting .................................................................................. 41
9.1 Explain ..........................................................................................................................41
9.2 Matters Needing Attention ..........................................................................................41
9.3 Fault Handling ..............................................................................................................43
Appendix 1:Technical Parameter ......................................................................................... 48
Appendix II: Quality Assurance ................................................................................................ 51
2
1 About This Manual
1.1Preface
Dear Customer,
Thank you for using the energy storage inverter . We sincerely hope that our product can
meet your needs. We also invite you to put forward more valuable suggestions on the
product performance and function.
1.2Applicable products
This manual is applicable to the product types as follows:
Model power isolation Off-grid model With on-grid and off-Grid
automatically switch internal
transformer
MEGA0030T 30KW √ √
MEGA0050T 50KW √ √
MEGA0100T 100KW √ √
MEGA0150T 150KW √ √
MEGA0250T 250KW √ √
MEGA0500T 500KW √ √
MEGA0100 100KW √
MEGA0500 500KW √
MEGA0630 630KW √
MEGA0030TS 30KW √ √
MEGA0050TS 50KW √ √
MEGA0100TS 100KW √ √
MEGA0150TS 150KW √ √
MEGA0250TS 250KW √ √
MEGA0500TS 500KW √ √
※Unless specified otherwise, any "inverter" and "energy storage inverter" mentioned
in this manual refers to this series of products.
3
1.4 Symbols
In order to ensure the safety of the user's personal and property when using the product, and
to better use the product, the manual provides relevant information and highlights it with
appropriate symbols.
The following list of symbolic hints may be used in this manual, please read them carefully.
DANGER
"Danger" indicates that there is a high potential hazard which, if not avoided, will result
in death or serious injury.
DANGER
WARNING
"Warning" indicates that there is a moderate potential hazard which, if not avoided, may
result in death or serious injury.
CAUTION
"Caution" indicates that there is a low potential hazard which, if not avoided, may result
in moderate or minor injury.
NOTE
"Note" indicates that there is a potential risk which, if not avoided, may result in
abnormal operation of the equipment or property damage.
Please pay attention to the warning labels on the product, which include:
Label Meaning
This label indicates there is high voltage within the product, and touch may cause an
electric shock.
This symbol indicates that the temperature here is higher than the acceptable range
of the human body, and do not contact in order to avoid personal injury.
This symbol indicates here is the protective grounding (PE) terminal, and solid
grounding is needed to ensure operators’ safety.
4
2 Safety Instructions
2.1 Personnel Requirements
◆ Only professional electricians or qualified personnel can operate the product.
◆ Operators should be fully familiar with the structure and working principle of the whole
energy storage system.
◆ Operators should be fully familiar with this manual "MEGA Series Energy Storage
Inverter User Manual"
◆ Operators should be fully familiar with the relevant standards in the country/area where
the project is located.
⚫ Make sure the device logo is clear and readable at all times.
⚫ Once the device logo is damaged or blurred, it must be replaced immediately.
CAUTION
5
2.4 Electricity Safety Matters
2.4.1 Electrical safety
There is a lethal high voltage inside the product!!
⚫ There is a fatal high voltage between the positive and negative electrodes of the energy
storage battery pack connected with the energy storage inverter.
⚫ When maintaining the equipment, ensure that the connection between the energy
storage inverter and the energy storage battery pack is completely disconnected.
DANGER
6
2.6 On-line test specification
2.6.1 On-line Test
There is a high voltage in the equipment. Accidental contact may lead to fatal shock hazard.
Therefore, in live measurement, it should::
⚫ Ensure adequate levels of protection (such as wearing insulating gloves, insulating
shoes, etc.).
DANGER ⚫ At least two persons must be ensured to be on site to ensure personal safety.
⚫ Using inappropriate parameter settings may affect the normal function and capabilities
of energy the storage inverter.
⚫ Only authorized professionals can set the parameters of energy storage inverters.
WARNING
7
2.9 Product Scrapping
◆ When the energy storage inverter needs to be discarded, it can not be treated as
conventional waste, we will accept this product as per W and there may be a handling fee.
◆ Alternatively contact the local authorized professional recycling agency.
All operations of energy storage inverters must meet the relevant national/regional standards.
CAUTION
All descriptions in this manual are for energy storage inverters with standard configurations. If you have
special needs, please give instructions to us. when ordering. Specifically, please refer to the actual
products you receive.
This manual cannot cover all possible situations during operation, maintenance and overhaul. In case of
any situation that cannot be explained in the manual, please contact Shenzhen McGuinness Technology
Co., Ltd.
8
3 Product introduction
3.1 Product Appearance
The appearance and external components of the energy storage inverter are described as follows:
The emergency shutdown button can be used to turn off the energy storage inverter only in a
fault scenario!
If the emergency shutdown button is not properly used, it can cause damage to the energy
storage inverter.
If the emergency shutdown button is pressed in the case of load, the related parts of the
WARNING energy storage inverter will encounter greater stresses and may fail.
9
3.2Main Power Topology
The inverter achieves the rectification and inversion through a three-phase full-bridge
inverter, and the rectified output is injected into the energy storage battery. The inverter
output is turned into sine wave voltage via the LC filter, then goes through the isolated boost
of three-phase transformer and then is incorporated into the grid power generation or
becomes off-grid power supply to the load.
Main circuit schematic inside the energy storage inverter is as shown in the figure below.
Grid
Figure3.5 MEGA Series Main Power Topology for Grid Connection and Off-grid
10
3.3Communication Solutions
3.3.1Communication Scheme of Upper Computer
The energy storage inverter communicates with the host computer through RS485/RS232
inverter. Several energy storage inverters are connected through 485 bus, and finally
connected to the upper terminal.
PC
RS485/RS232 PCS
11
4 Inverter Mode and Function
12
◼ Charge and Discharge Control of Energy Storage Batteries
All MEGA series energy storage inverters can charge and discharge in grid-connected mode.
Charge and discharge depth can be set by user.
For grid-connected charging mode, please refer to point 1 of 4.1.1 "grid-connected mode".
For grid-connected discharge mode, please refer to Point 2 of 4.1.1 "grid-connected mode".
※Independent inverters are connected in parallel as additional functions. If necessary, please contact
the technical staff of our company.
4.2.2 Low Voltage Ride Through (LVRT)
When the voltage of the grid connection point of the power station drops to 0, the power
station should stay operational and will not be disconnected from the grid for 0.15s.
13
4.3 Introduction of Inverter Status
There are six states of energy storage inverter, as shown in Table 4-1 below.
Table 4-1 Status and Description
Status Description
When the inverter receives standby instructions from the LCD screen
or the host computer, it turns to standby state in shutdown or
operation mode. When the AC and DC contactors of the inverter are
Standby
closed in standby state, the system is in hot standby state. When the
LCD screen or the host computer carries out relevant control, the
inverter can respond quickly.
When the energy storage system fails, the inverter will stop working,
automatically disconnect the contactor on the AC and DC side, and
the main circuit will be disconnected from the battery, power grid or
fault load. In the fault state, the system always monitors whether the fault
is eliminated or not. If the fault is not eliminated, the system
maintains the fault state. If the fault is eliminated, it will enter
standby state after the default of 30 seconds.
If the energy storage inverter is in the normal "running" state, the user
can stop the energy storage inverter by issuing the stop instruction
Shutdown
from the host computer, or Turn off the key through the LCD screen
switch page.
When the energy storage inverter fails or the power module fails, it is forbidden to start again
through the touch screen.
It should be checked by power off to confirm that there is no problem, and then power on
WARNING again, otherwise it may damage the inverter.
14
5 Mechanical Installation Guidance
Start
Pre-installation preparation
Mechanical installation
Electrical installation
End
15
5.3 Installation Preparation
5.3.1 Packaging Inspection
Before installation, it is necessary to check whether the equipment is damaged. If any
transportation damage is found, please contact the transportation company. and provide
photos of the damage.
5.3.2 Delivery Checklist
According to the packing list in the packing box, check whether all the parts delivered are
complete or not: transportation
Table 5-1 Delivery list
project Number
Inverter 1PCS
Key 2PCS
Certificate 1 PCS
Warranty card 1 PCS
Product User Manual 1 PCS
Exit Inspection Report 1 PCS
16
Table 5-4 Description of Packing Parameters
Name Explain
Sign Describe
17
Figure 5-2 Packaged Handling
18
5.5 Location and Fixation
5.5.1 Space Requirement
◆ Installed indoors with good ventilation. Not in high humidity and high ambient
temperature, no corrosive gasse.
◆ Avoid direct sunlight or rain.
◆ Ensure that the grounding resistance of the grounding wire in the distribution room is
less than 4 in dry environment.
◆ Inverter can only be installed on concrete base or other non-flammable mounting
surface, and sufficient load bearing should be guaranteed.
◆ Avoid placing together with inflammable and explosive materials, meeting fire
protection requirements.
The volumetric space reserved size is shown in the following figure:
Model Size(W×D×H)
MEGA0030T/MEGA0030TS 800×800×2050(mm)
MEGA0050T/MEGA0050TS 800×800×2050(mm)
MEGA0100T/MEGA0100TS 800×800×2050(mm)
MEGA0150T/MEGA0150TS 800×800×2050(mm)
MEGA0250T/MEGA0250TS 1200×800×2050(mm)
MEGA0500/MEGA0630 1200×800×2050(mm)
MEGA0500T/MEGA0500TS 1600×1050×2050(mm)
19
5.5.3 Base Mounting
The bottom of this series inverters should be connected with the base reliably. The bottom of
the inverter has a fixed hole for fixing the inverter on the bottom support channel steel or on
the ground. As shown in the following figure:
Floor installation.
≥1000mm
Cover
plate
Remove the outlet position baffle.
Figure 5-6 30kW/50kW/100kW/150kW Bottom Size Figure 5-7 250kW Bottom Size
AC inlet2
Ground wire inlet .
N line inlet
DC inlet.
AC inlet1
Cabinet
fixing hole
Figure 5-8 500kW/630kW Bottom Size Figure 5-8 500kW-TS Bottom Size
20
5.6.2 Ventilation Environment
In order to meet the ventilation requirements of this series inverters, the installation
environment should meet the following requirements:
◆ Inverter should avoid installing in the situation of poor ventilation condition and low air
flow. It can get more ventilation by increasing construction measures such as air supply
grille or fan.
◆ Air quality must be guaranteed. If the content of suspended solids such as sand and dust
in the air is too high, the air quality can meet the requirements through construction
measures (such as installing filters at the air supply grille of the building).
◆ The interface between air duct and inverter cabinet is well sealed.
◆ Protection should be added to the outlet of the air duct (rodent and bird control, etc.)
21
The air required by the inverter is inhaled through the bottom vent and the dust net of the front
door. Hot air is discharged through the top vent of the inverter, and there is an outlet at the top.
The sketch maps of the top section outlets of each type of this inverter are shown in the
following figures (mm).
22
6 Electrical Installation Guidance
Before wiring operation, confirm that both the municipal power input and BAT input switches
are disconnected, and affix warning signs to prevent others from operating the switches.
WARNING
The cable dimensions provided in this table are for reference only. The actual selection should be based
on the working environment temperature, laying method, heat dissipation conditions and so on.
23
The equipment does not have external cables. The above cable recommendation table is not
provided by inverters. Users are requested to provide their own cables according to relevant
needs.
CAUTION
All external cables are connected to the corresponding position after entering the equipment
through the bottom entry and exit holes.
The terminals and fixing screw used in power cable wiring of this series inverters have been
CAUTION installed at the corresponding wiring terminals when the equipment is delivered.
※The data line should be as close as possible to the supporting line of the surface ring, such as
supporting beams, steel troughs, metal guideways, etc.
24
6.4 Fixation and Protection of Connecting Cables
6.4.1 Cable Fixation
In order to prevent loosening of the copper nose, causing poor contact, or increasing contact
resistance leading to fever or even fire, it is necessary to ensure that the screw fastening the
terminal meets the torque requirements listed in Table 6-4:
Table 6-4 Screw dimensions and required torques
Torque (N.
2 3.2 7 16 34 46 58 68
m)
25
6.5.2 Installation Of Lower Fender
MEGA series inverters have lower fencing boards at the bottom of front, back, left and right.
They are packaged and placed at the bottom of the packaging box. Before installation, all
lower fencing boards of the inverter must be removed and put out. After the inverter is
positioned and the screw is locked, the lower fencing boards shall be installed. Dust-proof
cotton is installed in the lower fencing board, which can not be lost during installation.
Left lower
panel Dash
Panel
M5 * 12 screws
26
6.7 DC Side Wiring
6.7.1 Battery Connection
The DC-side connection of batteries connected to this series inverters is shown in Table 6-5
below.
For a single MEGA series inverter, the power should not exceed 1.05 times the rated power.
When connecting, users need to access at least 50mm²input lines per channel. The energy
storage inverter has left many terminals for users. Refer to Section 6.6 for the access location
of copper bars.
GND Earthing
In order to avoid personal and equipment injury, wiring must be carried out without
electricity.
⚫ DC switch is off.
⚫ Multimeter is used to measure that the DC side wiring row is not live.
DANGER
DC input voltage limit. Confirm that the DC input voltage should not exceed 850VDC!
⚫ Any DC input voltage exceeding this limit may cause damage to the inverter.
⚫ Damage and loss of equipment caused in this case do not fall within the scope of
quality assurance.
WARNING
Fixed screw and other parts used for wiring have been installed at the corresponding wiring terminals
when the equipment is delivered.
Need to check the material of the external terminal connection point. If copper and aluminium materials
are interconnected, special copper and aluminium connectors should be used. Do not connect directly!
27
6.8 AC Side Wiring
6.8.1AC Connection
All models of this series energy storage inverters have grid connection. Only those with
bypass need to consider bypass connection. Their corresponding relations are shown in the
table below. Refer to Section 6.5 for the access location of copper bars.
28
7 Test Run
7.1 Pre-Boot Check
Before commissioning, a thorough inspection of the installation of the equipment should be
carried out, especially to check whether the DC and AC voltages meet the requirements of
the inverter, as well as whether the polarity and phase sequence are correct.
Check that all connections have met the requirements of the relevant standards and
specifications. And whether the system is well grounded. Grounding resistance is of great
importance to the safety of the whole system. It must be determined that the grounding
resistance meets the requirements before the first trial operation.
Before commissioning, it is necessary to ensure that all switches on the AC side are open.
CAUTION
◆ Check whether the phase voltage and line voltage are within the predetermined
range and record the voltage value.
◆ If possible, measure the total harmonic distortion (THD) and view the curve. If the
distortion is serious, the inverter may not work.
WARNING
29
Step 4: Check other content
After completing the above check before starting, the following items need to be carefully
checked to ensure that they are correct.
◆ All links are made in accordance with Chapter 6 of this manual.
◆ The protective shield inside the equipment has been firmly installed.
◆ The AC side and DC side circuit breakers have been disconnected, i.e. they are in
the "OFF" position.
◆ The multimeter is used to detect whether the AC and DC side voltages meet the
starting conditions of the inverter, and there is no danger of overvoltage.
◆ The door of the cabinet has been closed and the key of the cabinet door has been
pulled out and handed over to a special person for safekeeping.
For the long downtime energy storage inverter, before starting, the equipment must be
thoroughly and meticulously checked to ensure that all indicators meet the requirements
before starting.
WARNING
30
Figure 7-1 Touch Screen Inverter Open Button Interface
When you need to boot through the DC side, you need to press the "cold start" button (red).
When the machine is working normally, it is strictly forbidden to disconnect the circuit
breaker directly, so as to avoid dangerous arc damage to the circuit breaker.
In severe cases, it may also lead to damage of energy storage inverter.
WARNING
31
7.3.2 Turn off at a time of failure or emergency
In case of emergency or failure, follow the following procedure:
Step 1: Press the emergency shutdown button "EPO";
Step 2: Disconnect the machine DC side circuit breaker or load switch, AC side circuit
breaker;
Step 3: Reset the EPO button after confirming that the danger or fault has been removed and
needs to be operated.
32
8 Touch Screen Operational Guidelines
33
Table 8-2 Indicator status
Indicator
Function State Significance
light
Green always Abnormal monitoring
System Operating shines/fades system
Indicator 1
Indicator
Green scintillation Normal monitoring system
※ndicator lamp 1, indicator lamp 2, indicator lamp 3, refers to the working status indicator lamp, the
order is from top to bottom.
Short-lived single-beep alert When pressing any function operation key, issue this alarm sound
Whisper every 1 second When an alarm occurs in the inverters, the alarm sounds are emitted
The main interface mainly displays machine model, network address, time, menu bar, battery
information, inverter information, communication information, operation status, alarm
34
information, switch status information. As shown in Figure 8-2 below:
1. Click on the "Battery" icon on the main page to view battery properties.
3. Click on the triangular "Warning" sign in the lower right corner of the screen to view all alerts.
4. Click on the status button in the lower right corner of the screen to view the status of each
switch.
35
Table 8-4 Menu expansion items
Serial Menu
Menu item Parameter function
number name
2 State PCS State Display of Inverter Operation State and Switching State
36
8.4.2 Introduction to Status Menu
Click on the status button to enter the status menu interface. In this interface, users can click
on the three buttons of "real-time data", "real-time status" and "real-time alarm".
Users can monitor the inverter by observing the feedback of these three real-time quantities.
The state interface is shown in Figure 8-4.
37
1. 1. In the record menu, click the "Export Data" button.
After entering the interface, you need to access the U disk.
You can select in the interface whether you need to export "History" or "Operation
Log".
After the guide is finished, click "Eject U disk".
38
Click "General Settings" in the system menu and enter the password to enter the operation
interface.
If the inverter restarts or does not click the touch screen for a long time (10 minutes) and
then clicks the general setting or "system parameters" setting button again, the input
password interface will pop up.
The password is 123.
The interface can select general settings such as inverter working mode and battery
charging and discharging mode.
39
Select "Running Time" from the system menu and enter the setting of charging and discharging
time for peak shaving and valley filling.
Users can set it according to the local electricity price difference or the actual peak-valley
power consumption time.
40
9 Maintenance and troubleshooting
9.1 Explain
Due to the influence of ambient temperature, humidity, dust and vibration, the internal
devices of energy storage inverter will be aging, which will affect the performance of
inverter and can even lead to failure. Therefore, it is necessary to carry out routine and
regular maintenance of energy storage inverter to ensure its normal operation and service
life. All measures and methods to help the energy storage inverter in good working condition
belong to the scope of maintenance work. If there is a malfunction, with the help of this
manual, you still can't solve the problem. Please contact us. At the same time, provide some
information in order to provide you with better service:
◆ Photographs of Fault Site
◆ Type and serial number of energy storage inverter.
◆ Information on components connected to energy storage inverters, configuration of
energy storage batteries and network parameters.
◆ Communication connection scheme of energy storage inverter.
◆ Fault information and brief description.
Only qualified and authorized personnel can maintain the energy storage inverter and other
operations.
In the maintenance work, do not leave screw, washer and other metal parts in the energy
storage inverter to avoid damage to the inverter!
WARNING
41
If only the circuit breaker is disconnected, the cable connection terminals in the AC/DC
cabinet of the energy storage inverter are still live!
Before opening the cabinet door and starting the formal maintenance work, it is necessary to
disconnect not only the circuit breaker, but also the front and back stage circuit breakers of
WARNING the energy storage inverter.
After the energy storage inverter is out of operation, please wait at least 15 minutes before
operating it.
WARNING
Due to the capacitance of DC bus, it will take at least 15 minutes to wait until the energy
storage inverter is completely cut off. Before removing the dust, please use the multimeter
measurement to confirm that there is no electricity in the machine, so as to avoid electric
WARNING shock.
42
The overwhelming majority of maintenance work can only be carried out by removing the
protective net cover inside the machine. At the end of all maintenance work, it is necessary to
restore all dismantled maintenance covers to their original state. Make sure all screws are
tightened in place
WARNING
Only the recommended product routine maintenance cycle is included in the table. The actual
maintenance cycle should be determined according to the specific installation environment of the product.
The maintenance cycle of the product will be affected by factors such as the scale of the power plant, the
location of the plant and the on-site environment. It is necessary to shorten the maintenance cycle and
increase the maintenance frequency if the wind and sand in the operation environment are larger or the
dust is thicker.。
Under the condition of failure, there may still be fatal high voltage inside the energy storage
inverter! Only technicians who meet the requirements can perform the operations described
in this chapter. "Compliance with requirements" means that operators have participated in
professional training on equipment troubleshooting operations in the early stage. Please
perform only the troubleshooting operations described in this manual. When operating, please
WARNING observe all safety operation specifications.
When the energy storage inverter can't output as expected or the charge and discharge
quantity changes abnormally, please pay attention to the following items:
◆ Open-circuit voltage of energy storage battery
◆ Whether the machine is in a state of failure
◆ Whether the power grid is connected correctly and powered on
◆ Check whether the communication of measuring equipment is normal
43
9.3.2 Non-Alarm Inducing Failure
Machine working noise is high
◆ Check whether the power is in the normal range; Measure whether the grid-connected
current and voltage waveforms are normal; Check the replacement of cooling fans.
Network communication mode:
◆ Please check whether the IP address, subnet mask and gateway are set correctly.
◆ Check whether the communication line is through and whether it is well connected.
◆ If all the above tests are normal and correct, try to replace the LCD monitoring board.
Serial communication mode:
◆ Check the wiring, check all wiring is good, A/B has no connection.
◆ Communication adapter does not match. Replace communication adapter and try again.
◆ Check whether the local address and baud rate are consistent with the host computer.
LCD screen cannot be switched on and off
◆ Check the communication connection between LCD screen and DSP board
9.3.3 Alarm Failure List
LCD can display 32 alarms, and the corresponding solutions are shown in Table 9-2 below.
Table 9-2 Alarm Fault Handling Method
Battery Voltage Low Disconnect DC load switch and check DC side voltage and battery
Bus Short Circuit Fault Turn off and check DC bus connection
Overvoltage of power
Check the voltage of grid connection point by shutdown
network
Low grid voltage Check the voltage of grid connection point by shutdown
Inverse Voltage Sequence of Disconnect the power supply switch and Turn off to check the three-
Abnormal Frequency of
Turn off and check grid voltage
Power Grid
44
DC Contactor Fault Turn off and check whether the DC contactor is damaged.
Output contactor open circuit Turn off and check if AC contactor is damaged
AC auxiliary power failure Turn off and check the AC auxiliary power supply board
15V power failure Turn off , check AC and DC auxiliary power supply board
Turn off , check whether the input and output of the inverter are short
Inverter overcurrent
circuit or whether the inverter is overloaded.
Wave by Wave Current Turn off , check whether the input and output of the inverter are short
Turn off , check whether the inverter fan is out of order and whether the
Inverter overheating
air duct is unobstructed.
Inverter Phase Shortage Fault Turn off and check AC side line
Lightning protection failure Turn off and check the lightning protection of the inverter
Turn off and check if the communication cable between inverter and
BMS Communication Fault
battery system is loose
Drive Line Fault Turn off,Check whether the internal drive line is loose
Insulation impedance
Turn off,Check inverter grounding and cable aging
anomaly
45
9.3.4 Safety Protection Functions
Energy storage inverter has perfect protection function and warning function. When the
input voltage or abnormal situation of power grid occurs, it can operate effectively to
protect the safe operation of energy storage inverter and continue to operate the set mode
until the abnormal situation disappears.
When the DC voltage of the energy storage battery exceeds the allowable voltage
DC over/under voltage range, the energy storage inverter will stop working and send out warning signals,
protection and display the fault type on the LCD screen.
Energy storage inverter can detect abnormal voltage quickly and react.
When the energy storage inverter detects that the grid voltage exceeds the
Overvoltage/undervoltage allowable voltage range, the energy storage inverter will stop working and send
protection of power grid out warning signals, and display the fault type on the LCD screen. Energy storage
inverter can detect abnormal voltage quickly and react.
When the energy storage inverter detects that the frequency fluctuation of the
power grid exceeds the allowable range, the energy storage inverter will stop
Over/Under Frequency
working and send out warning signals. The fault type is displayed on the LCD
Protection of Power Grid
screen. Energy storage inverter can detect abnormal frequency quickly and
respond to it.
When the energy storage inverter detects that the grid voltage is 0, the energy
storage inverter will stop working and send out warning signals, and display the
Isolated island protection
fault type on the LCD screen. Energy storage inverter can detect abnormal
voltage quickly and react.
When the output power of the energy storage battery exceeds the maximum DC
input power allowed by the energy storage inverter, the energy storage inverter
AC Overcurrent will work at the allowable maximum AC output power. When the AC current is
Protection detected to be greater than 1.2 times the rated current, the energy storage inverter
will stop working. After restoring to normal, the energy storage inverter should be
able to work normally.
The energy storage inverter has the function of grounding protection. A leakage
AC leakage current current sensor is installed in the grounding cable. When the leakage current
protection exceeds 2A, the machine will stop immediately. When the current is less than
1.5A, the protection can be eliminated. The fault is displayed on the LCD screen.
IGBT module of energy storage inverter uses high precision temperature sensor,
IGBT Overtemperature which can monitor module temperature in real time. When the temperature is too
Protection high, the DSP will issue instructions to stop the operation of energy storage
inverter to protect the stable operation of equipment.
The IGBT module of the energy storage inverter has self-protection function.
When the module detects that the module has over-current, it can send fault
IGBT Fault Protection information to the DSP quickly. The DSP will issue instructions to stop the
energy storage inverter running, and send warning signals, and display the fault
type on the LCD.
Polarity Reverse When the energy storage inverter detects that the DC voltage is negative, the
Connection Fault energy storage inverter will send a warning signal and display the fault type on
Protection the liquid crystal.
46
Function Function Description
High precision temperature sensor is used in the energy storage inverter, which
Environmental
can monitor the temperature inside the machine in real time. When the
Overtemperature
temperature is too high, the DSP will issue instructions to stop the operation of
Protection
the energy storage inverter to protect the stable operation of the equipment.
When the energy storage inverter detects that the DC current is greater than 1.2
DC Overcurrent times the rated current, the energy storage inverter will stop working and send out
Protection warning signals, and display the fault type on the LCD. After restoring to normal,
the energy storage inverter should be able to work normally.
When the energy storage inverter operates in the independent inverting mode and
Independent Inverter detects that the three-phase output voltage exceeds the allowable voltage range,
Overvoltage Protection the energy storage inverter will stop working and send out warning signals, and
display the fault type on the liquid crystal.
When the energy storage inverter self-checks and finds that the three-phase
voltage phase of the connected power grid is wrong, the inverter will send out
Phase Sequence Reverse
warning signals and display the fault type on the LCD. After returning to normal,
Connection Protection
the energy storage inverter should be re-energized and self-checked to work
normally.
When the energy storage inverter detects that the difference of three-phase AC
AC voltage unbalance voltage exceeds the allowable range, the energy storage inverter will stop working
protection and send out warning signals, and display the fault type on the LCD. Energy
storage inverter can detect abnormal voltage quickly and react.
When the energy storage inverter detects that the difference of three-phase AC
AC current unbalance voltage exceeds the allowable range, the energy storage inverter will stop working
protection and send out warning signals, and display the fault type on the LCD. Energy
storage inverter can detect abnormal voltage quickly and react.
The fan of the energy storage inverter has the function of automatic detection.
When the fan is not turned, it can send fault information to the DSP quickly. The
Fan Fault Protection
DSP will issue instructions to stop the energy storage inverter, and send warning
signals, and display the fault type on the LCD.
When the operating state of the energy storage inverter is standby, grid-connected
Fault Protection of or off-grid, the AC/DC main contactor is detected to be disconnected, the energy
AC/DC Contactors storage inverter will stop working, and send out warning signals, and display the
fault type on the LCD.
47
Appendix 1:Technical Parameter
Table 1
MEGA0030TS MEGA0050TS MEGA0100TS
TYPE
MEGA030T MEGA0050T MEGA0100T
DC(battery)
AC
grid-connected
PF >0.99(rated power)
PF range -1~+1
Off-grid
Voltage regulation 1%
THDU <3%(linear)
System Parameter
noise <65dB
Mechanical parameters
48
Table 2
MEGA0150TS MEGA0250TS MEGA0500TS
TYPE
MEGA0150T MEGA0250T MEGA0500T
DC(battery)
AC
grid-connected
PF >0.99(Rated power)
PF range -1~+1
Off-grid
Voltage regulation 1%
THDU <3%(linear)
system parameter
noise <75dB
Mechanical parameters
49
Table 3
DC(battery)
AC
grid-connected
PF >0.99(Rated power)
PF range -1~+1
Off-grid
Voltage regulation 1%
THDU <3%(linear)
system parameter
noise <75dB
Mechanical parameters
Dimension(W*D*Hmm) 1200*800*2050
50
Appendix II: Quality Assurance
In order to continuously improve customer satisfaction, the company's products and product manuals are
in the process of continuous improvement and upgrading. If there is a difference between the manuals and
the products in your hand, it may be the reason for the edition, please refer to the specific products. If you
still have questions, please contact us.
51
Shenzhen Megarevo Technology Co., Ltd.
Web: www.megarevo.com
e-mail: [email protected]
Fax : 0755-86312930
Address : 4th floor, block B, Invt Guangming Technology Building, Kejie Four Road, Matian
Street, Guangming, Shenzhen, China
※ Any changes in product size and parameters are subject to our latest information without prior notice
52