0% found this document useful (0 votes)
9 views

Failure Analysis and Risk Concepts

The document discusses the fundamental concepts of risk management, emphasizing that risk is inherent in all projects and should be managed rather than feared. It outlines the benefits of effective risk management, including proactive control and improved performance, while detailing various analytical methods such as Failure Mode and Effects Analysis (FMEA) and Monte Carlo simulations. Additionally, it addresses the components of a risk register and the common root causes of project failures.

Uploaded by

rutteralyssa3
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
9 views

Failure Analysis and Risk Concepts

The document discusses the fundamental concepts of risk management, emphasizing that risk is inherent in all projects and should be managed rather than feared. It outlines the benefits of effective risk management, including proactive control and improved performance, while detailing various analytical methods such as Failure Mode and Effects Analysis (FMEA) and Monte Carlo simulations. Additionally, it addresses the components of a risk register and the common root causes of project failures.

Uploaded by

rutteralyssa3
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 23

Basic Concepts of Risk

Management as
Demonstrated by Post-
Mortem Failure Analysis
What is Risk?

• Risk is the possibility, or uncertainty of an


event occurring that will have an impact
(positive or negative) on the achievement of
project objectives.
 Risk is inherent in every project,
regardless of size and complexity
 Risk intrinsically is neither good nor
bad
 Risk is not something to fear, but
something to manage
 Risk is a fundamental element of
opportunity
Benefits of Good Risk Management

• Proactive, not reactive


• Reduces surprises and negative consequences
• Take advantage of opportunistic risks
• Control of the project future
• Improves performance chances

3
The “Normal” Risk Event Graph

4
The Risk
Management
Process

5
The Risk Breakdown Structure (RBS)

6
Risk Severity Matrix
Failure Mode and Effects Analysis (FMEA)
Impact × Probability × Detection = Risk Value

User Interface
4 Backlash problems
Likelihood

Red zone (major risk)


3 Yellow zone (moderate risk)
Green zone (minor risk)

System
2
freezing

Hardware
1 malfunc-
tioning

1 2 3 4 5
Impact
7
Quantitative Analysis of Risk
• Uncertainties measured by standard statistical functions
These are:
• Mean Values (Expectation)

• Variance / Standard Deviation

• Probability of Exceedance

8
Mean Value (Expectation)

• Mean Value or expected value of a random variable X:



o E(X) = ∫−∞ 𝑥𝑥 𝑑𝑑𝑑𝑑(𝑥𝑥) where F(X) is the cumulative distribution function of X
• In Excel, Mean Value is calculated with formula “average()”

9
Graph of mean value
• For symmetric distributions

• For asymmetric distributions

10
Variance
• For a discrete random variable:
o Var(X) = ∑∞
𝑖𝑖=1 𝑝𝑝𝑖𝑖 [𝑥𝑥𝑖𝑖 −𝐸𝐸(𝑋𝑋)] 2

• In Excel, Variance is calculated with function “var.s()”.

11
Standard deviation
• Standard deviation 𝜎𝜎 of random variable X :
o 𝜎𝜎(X) = 𝑉𝑉𝑉𝑉𝑉𝑉 𝑋𝑋

• Standard deviation measures the “spread” around the mean


• 𝜎𝜎].
For normal random variable
approximately 95% of realizations fall
in that interval.

• In Excel formula “stdev.s()”


calculates the standard deviation.

12
Probability of Exceedance (POE)
• Probability of exceeding threshold value y .
• The shaded area on the graph is the
probability of exceedance.

13
POE Insurance Loss Calculation

14
• Activity duration follows a beta distribution.

• Three time estimates for each activity: optimistic,


pessimistic, and most likely.

PERT—Program
Evaluation Review
Technique

15
Activity Time Calculations

The weighted average activity time is computed by


the following formula:

16
Monte Carlo method

• Monte Carlo simulation

• Estimates various quantitative characteristics

• Random numbers replace uncertain values.

17
For Active, Ongoing Projects: Key Risk Register Components

• Many variations and templates exist. . .here are the key


components of a standard tool:
– Risk identification
– Condition
– Consequence
– Qualitative analysis
• Probability
• Impact
• Exposure
– Mitigation
– Contingency
– Triggers
– Assignee

Completion of each is done in a step-wise fashion for all identified risks

18
Failure Analysis Register
– Failure identification: describe the failure point

– Condition: capture the likely cause of the failure

– Consequence: the result of the failure

– Mitigation: document the team’s plans to lower the probability or to reduce the impact ahead of
time (preventative steps)

– Contingency: what countermeasures or contingencies did the team take to avoid the risk or failure

– Triggers: what event or circumstance happened that cause the team to invoke the contingency
plan

– Assignee: who had assigned responsibility within the project team to address, manage or
otherwise monitor this risk and to raise alarms at the appropriate time
19
Troubled Project General Facts
• Doomed to fail
• Political savvy and courage
• Failure > success
• Failure in many places, but success in only one
• No failures overnight
• Companies and troubled projects
• PMs and skills to manage troubled projects
• Stakeholder and client input

20
Troubled Project Turnaround – Some Observations

• Very high project success rates


• Followers, not leaders
• Demonstrated turnaround skills
• Warning sign recognition
• Recovery costs
• Recovery goals can be different than original
• For some, little or no recovery

21
Failure Root Causes

• Three general categories of failures:

– Management mistakes

– Planning mistakes

– External influences

corrosionpedia

22
• Two different concepts and
approaches

• Recovery

Project Recovery • Rescue


and Rescue

eCameron Inc

23

You might also like