BASEMENT 1 - GEELY PROJECT
BASEMENT 1 - GEELY PROJECT
Actual Level of Effort Remaining Work summary Page 1 of 3 TASK filter: All Activities
Primary Baseline Critical Remaining Work © Oracle Corporation
Actual Work Milestone
22-Feb-24
Activity ID Activity Name Original Start Finish Activity % 2024
Duration Complete
Mar Apr
A1730
Sprinkles 5 02-Mar-24 06-Mar-24 0% 06-Mar-24, Sprinkles
Actual Level of Effort Remaining Work summary Page 2 of 3 TASK filter: All Activities
Primary Baseline Critical Remaining Work © Oracle Corporation
Actual Work Milestone
22-Feb-24
Activity ID Activity Name Original Start Finish Activity % 2024
Duration Complete
Mar Apr
WBS: G07B1.4.5.1 Arch. Works 9 18-Jan-24 A 07-Mar-24 07-Mar-24, WBS: G07B1.4.5.1 Arch. Works
A1460
Paints 5 18-Jan-24 A 31-Jan-24 A 100% Paints
A1470
Install Metal Door 5 22-Feb-24 A 07-Mar-24 80% 07-Mar-24, Install Metal Door
A1840
Raised Floor 7 01-Feb-24 A 27-Feb-24 40% 27-Feb-24, Raised Floor
WBS: G07B1.4.5.3 Electrical Works 7 27-Feb-24 06-Mar-24 06-Mar-24, WBS: G07B1.4.5.3 Electrical Works
A1340
Cable and wirring for IT Room 7 27-Feb-24 06-Mar-24 0% 06-Mar-24, Cable and wirring for IT Room
A1760
Access Control System 7 27-Feb-24 06-Mar-24 0% 06-Mar-24,Access Control System
WBS: G07B1.4.6 Pump Room + Tanks 33 07-Jan-24 A 30-Mar-24 30-Mar-24, WBS: G07B1.4.6 Pum
WBS: G07B1.4.6.2 Civil Works 15 07-Jan-24 A 06-Mar-24 06-Mar-24, WBS: G07B1.4.6.2 Civil Works
A1510
Civil work required for pump room 15 15-Feb-24 A 06-Mar-24 20% Civil work required for pump room
A1520
Demolish For Access 4 07-Jan-24 A 22-Feb-24 95% 22-Feb-24, Demolish ForAccess
A1530
Install Metal Doors and Stairs 4 15-Feb-24 A 24-Feb-24 60% 24-Feb-24, Install Metal Doors and Stairs
WBS: G07B1.4.6.1 MEP Works 20 07-Mar-24 30-Mar-24 30-Mar-24, WBS: G07B1.4.6.1 ME
A1540
Electric Horzonal Split Case Fire Pump 14 07-Mar-24 23-Mar-24 0% 23-Mar-24, Electric Horzonal Split Case Fire Pump
A1550
Horizontal Split Units Pump 8 21-Mar-24 30-Mar-24 0% Horizontal Split Units Pump
A1560
Jockey FFPump 12 07-Mar-24 20-Mar-24 0% Jockey FFPump
A1570
Fuel Tank 12 07-Mar-24 20-Mar-24 0% Fuel Tank
A1580
Electric Fuel Pump 11 07-Mar-24 19-Mar-24 0% 19-Mar-24, Electric Fuel Pump
A1590
Dilto for manually operated pump & submenisable pump
20 07-Mar-24 30-Mar-24 0% Dilto for manually operated pump &
WBS: G07B1.4.7 Electrical Room 27 22-Feb-24 A 23-Mar-24 23-Mar-24, WBS: G07B1.4.7 Electrical Room
WBS: G07B1.4.7.1 Arch Works 2 22-Feb-24 A 26-Feb-24 26-Feb-24, WBS: G07B1.4.7.1 Arch Works
A1610
Steel Door 2 22-Feb-24 A 26-Feb-24 0% 26-Feb-24, Steel Door
WBS: G07B1.4.7.3 Mechanical Works 12 10-Mar-24 23-Mar-24 23-Mar-24, WBS: G07B1.4.7.3 Mechanical Works
A1600
MDP 12 10-Mar-24 23-Mar-24 0% 23-Mar-24, MDP
WBS: G07B1.4.8 Drainge System 5 22-Feb-24 27-Feb-24 27-Feb-24, WBS: G07B1.4.8 Drainge System
WBS: G07B1.4.8.2 Plumbing Works 5 22-Feb-24 27-Feb-24 27-Feb-24, WBS: G07B1.4.8.2 Plumbing Works
A1630
Install drainge system 5 22-Feb-24 27-Feb-24 0% 27-Feb-24, Install drainge system
Actual Level of Effort Remaining Work summary Page 3 of 3 TASK filter: All Activities
Primary Baseline Critical Remaining Work © Oracle Corporation
Actual Work Milestone