BASEMENT 1 - GEELY PROJECT

The document outlines the project schedule for the G07B1 Basement 1 project, detailing various activities, their start and finish dates, and completion percentages. Key activities include down payments, material submissions, and various construction tasks across different work breakdown structures (WBS). The project is set to be completed by March 30, 2024, with several tasks currently at 0% completion.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
2 views

BASEMENT 1 - GEELY PROJECT

The document outlines the project schedule for the G07B1 Basement 1 project, detailing various activities, their start and finish dates, and completion percentages. Key activities include down payments, material submissions, and various construction tasks across different work breakdown structures (WBS). The project is set to be completed by March 30, 2024, with several tasks currently at 0% completion.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

22-Feb-24

Activity ID Activity Name Original Start Finish Activity % 2024


Duration Complete
Mar Apr
33 16-Oct-23 A 30-Mar-24 30-Mar-24, Project: G07B1 Basem
Project: G07B1 Basement 1
33 16-Oct-23 A 30-Mar-24 30-Mar-24, WBS: G07B1.1 Mile St
WBS: G07B1.1 Mile Stones
A1000 Down Payment 0 03-Mar-24* 0% Down Payment, 03-Mar-24*
A1010 Variation Approve for Compressed Air 0 25-Feb-24* 0% Variation Approve for Compressed Air, 25-Feb-24*
A1020 ‫الفرن‬ 0 26-Feb-24* 0% 26 ,‫الفرن‬-Feb-24*
A1030 Close Out Offices 0 14-Mar-24 0% Close Out Offices,
A1040 Close Out Storage 0 04-Mar-24 0% Close Out Storage,
A1050 Close Out Toilets 0 16-Mar-24 0% Close Out Toilets,
A1060 Close Out IT Room 0 07-Mar-24 0% Close Out IT Room,
A1070 Close Out Pump Room 0 30-Mar-24 0% Close Out Pump Room,
A1080 Close Out Electrical Room 0 23-Mar-24 0% Close Out Electrical Room,
A1090 Close Out Basement 1 0 30-Mar-24 0% Close Out Basement 1,
A1130 Close Out Service Area 0 06-Mar-24 0% Close Out Service Area,
A1680 Site Receving 0 16-Oct-23 A 100%
6 27-Nov-23 A 27-Feb-24 27-Feb-24, WBS: G07B1.2 Material Submittle -Approval
WBS: G07B1.2 Material Submittle - Approval
A1640 FM 200 5 27-Nov-23 A 02-Dec-23 A 100% FM 200
A1650 Waterheater 5 22-Feb-24 27-Feb-24 0% 27-Feb-24, Waterheater
A1770 Interior Signs 5 04-Feb-24 A 27-Feb-24 0% 27-Feb-24, Interior Signs
A1830 MDP 5 22-Feb-24 27-Feb-24 0% 27-Feb-24, MDP
A1900 Air Distribuation 5 29-Nov-23 A 27-Feb-24 0% 27-Feb-24,Air Distribuation
13 28-Feb-24 13-Mar-24 13-Mar-24, WBS: G07B1.3 Material Approval - Delivey
WBS: G07B1.3 Material Approval - Delivey
A1660 FM 200 10 03-Mar-24 13-Mar-24 0% 13-Mar-24, FM 200
A1670 Waterheater 9 03-Mar-24 12-Mar-24 0% 12-Mar-24, Waterheater
A1780 Interir Signs 9 03-Mar-24 12-Mar-24 0% 12-Mar-24, Interir Signs
A1820 MDP 9 28-Feb-24 09-Mar-24 0% 09-Mar-24, MDP
A1910 Air Distribution 7 03-Mar-24 10-Mar-24 0% 10-Mar-24,Air Distribution
33 06-Nov-23 A 30-Mar-24 30-Mar-24, WBS: G07B1.4 Works
WBS: G07B1.4 Works - Spaces
WBS: G07B1.4.4 General Works 26 06-Nov-23 A 21-Mar-24 21-Mar-24, WBS: G07B1.4.4 General Works
A1100 Demolishing 5 06-Nov-23 A 13-Nov-23 A 100% Demolishing
A1110 Masonary 15 15-Nov-23 A 12-Dec-23 A 100% Masonary
A1120 Compressed Air 23 25-Feb-24 21-Mar-24 0% 21-Mar-24, Compressed Air
A1250 Plaster 5 16-Jan-24 A 20-Jan-24 A 100% Plaster
A1380 Cable Tray 5 13-Feb-24 A 25-Feb-24 40% 25-Feb-24, Cable Tray
A1390 Cable Trunk 5 13-Feb-24 A 25-Feb-24 40% 25-Feb-24, Cable Trunk
A1890 M.M Fiber Cables 5 05-Feb-24 A 10-Feb-24 A 100%
A1920 Concrete Casting 6 26-Feb-24 03-Mar-24 0% 03-Mar-24, Concrete Casting
A1930 Install Fire extinguishers -FM200 5 14-Mar-24 19-Mar-24 0% 19-Mar-24, Install Fire extinguishers -FM200
A1940 Intall Fire Piping Network 5 11-Dec-23 A 30-Dec-23 A 100%
WBS: G07B1.4.9 Service Area 13 10-Dec-23 A 06-Mar-24 06-Mar-24, WBS: G07B1.4.9 Service Area
WBS: G07B1.4.9.1 Arch. Works 5 18-Jan-24 A 29-Feb-24 29-Feb-24, WBS: G07B1.4.9.1 Arch. Works
A1690
Install Fiber mesh with epoxy finish and road marker- Fist
5 Coat
20-Jan-24 A 24-Feb-24 60% 24-Feb-24, Install Fiber mesh with epoxy finish and road marker- Fist Coat
A1700
Paints 5 18-Jan-24 A 29-Feb-24 0% 29-Feb-24, Paints
WBS: G07B1.4.9.2 Electrical Works 13 10-Dec-23 A 06-Mar-24 06-Mar-24, WBS: G07B1.4.9.2 Electrical Works
A1710
Lighting Fixture 5 02-Mar-24 06-Mar-24 0% 06-Mar-24, Lighting Fixture
A1740
IP Outlets 5 10-Dec-23 A 31-Dec-23 A 100%
A1750
IP devices 5 10-Dec-23 A 31-Dec-23 A 100%
A1790
Lighting Outlet 5 10-Dec-23 A 31-Dec-23 A 100%
WBS: G07B1.4.9.3 Mechanical Works 13 10-Feb-24 A 06-Mar-24 06-Mar-24, WBS: G07B1.4.9.3 Mechanical Works
A1720
Install Galvanized Duct 5 10-Feb-24 A 27-Feb-24 0% 27-Feb-24, Install Galvanized Duct

Actual Level of Effort Remaining Work summary Page 1 of 3 TASK filter: All Activities
Primary Baseline Critical Remaining Work © Oracle Corporation
Actual Work Milestone
22-Feb-24
Activity ID Activity Name Original Start Finish Activity % 2024
Duration Complete
Mar Apr
A1730
Sprinkles 5 02-Mar-24 06-Mar-24 0% 06-Mar-24, Sprinkles

WBS: G07B1.4.1 Offices 20 10-Dec-23 A 14-Mar-24 14-Mar-24, WBS: G07B1.4.1 Offices


WBS: G07B1.4.1.1 Arch. Works 20 01-Feb-24 A 14-Mar-24 14-Mar-24, WBS: G07B1.4.1.1 Arch. Works
A1140
Ceramic Tiles Flooring 5 25-Feb-24 02-Mar-24 0% 02-Mar-24, Ceramic Tiles Flooring
A1150
Wall Painting 5 01-Feb-24 A 22-Feb-24 90% 22-Feb-24, Wall Painting
A1160
Gypsum board 5 20-Feb-24 A 27-Feb-24 10% 27-Feb-24, Gypsum board
A1170
Ceilling Paint 5 27-Feb-24 04-Mar-24 0% 04-Mar-24, Ceilling Paint
A1180
Interior Signs 2 13-Mar-24 14-Mar-24 0% 14-Mar-24, Interior Signs
A1280
Aluminium Sliding Windows 3 02-Mar-24 05-Mar-24 0% 05-Mar-24,Aluminium Sliding Windows
A1290
Wooden Doors 2 02-Mar-24 04-Mar-24 0% 04-Mar-24, Wooden Doors
WBS: G07B1.4.1.4 Electrical Works 10 10-Dec-23 A 04-Mar-24 04-Mar-24, WBS: G07B1.4.1.4 Electrical Works
A1350
Lighting Outlets 5 10-Dec-23 A 31-Dec-23 A 100% Lighting Outlets
A1360
Lighting Fixture 5 27-Feb-24 04-Mar-24 0% 04-Mar-24, Lighting Fixture
A1370
AC Outlets 5 01-Jan-24 A 08-Jan-24 A 100% AC Outlets
A1400
Lighting Swithes 5 22-Feb-24 27-Feb-24 0% 27-Feb-24, Lighting Swithes
A1410
IP Communication System Outlet 5 10-Dec-23 A 31-Dec-23 A 100% IP Communication System Outlet
A1420
Sockets & Power Outlets 5 10-Dec-23 A 31-Dec-23 A 100% Sockets & Power Outlets
A1430
Floor Boxes Outlets 5 10-Dec-23 A 31-Dec-23 A 100% Floor Boxes Outlets
A1440
Intsall Floor boxes 5 27-Feb-24 04-Mar-24 0% 04-Mar-24, Intsall Floor boxes
A1450
Install IP devicese 5 27-Feb-24 04-Mar-24 0% 04-Mar-24, Install IP devicese
WBS: G07B1.4.1.3 Mechanical Works 10 12-Feb-24 A 13-Mar-24 13-Mar-24, WBS: G07B1.4.1.3 Mechanical Works
A1200
Air Distribuation 3 11-Mar-24 13-Mar-24 0% 13-Mar-24,Air Distribuation
A1210
Split Units 5 04-Mar-24 10-Mar-24 0% 10-Mar-24, Split Units
A1220
Sprinkles 5 12-Feb-24 A 05-Mar-24 80% 05-Mar-24, Sprinkles
A1230
Fire Extinguishers 5 04-Mar-24 10-Mar-24 0% 10-Mar-24, Fire Extinguishers
WBS: G07B1.4.2 Storage 11 18-Jan-24 A 04-Mar-24 04-Mar-24, WBS: G07B1.4.2 Storage
WBS: G07B1.4.2.1 Arch. Works 6 18-Jan-24 A 27-Feb-24 27-Feb-24, WBS: G07B1.4.2.1 Arch. Works
A1800
Paints 5 18-Jan-24 A 20-Jan-24 A 100%
A1870
Flooring 5 20-Jan-24 A 25-Jan-24 A 100%
A1880
Install Door 5 22-Feb-24 27-Feb-24 0% 27-Feb-24, Install Door
WBS: G07B1.4.2.4 Mechanical Works 5 28-Feb-24 04-Mar-24 04-Mar-24, WBS: G07B1.4.2.4 Mechanical Works
A1810
Pipe Install 5 28-Feb-24 04-Mar-24 0% 04-Mar-24, Pipe Install
WBS: G07B1.4.2.3 Electrical Works 5 06-Feb-24 A 09-Feb-24 A
A1850
Lighting Fixture 5 06-Feb-24 A 09-Feb-24 A 100%
A1860
Switches 5 06-Feb-24 A 09-Feb-24 A 100%
WBS: G07B1.4.3 Toilets 21 10-Dec-23 A 16-Mar-24 16-Mar-24, WBS: G07B1.4.3 Toilets
WBS: G07B1.4.3.1 Arch. Works 20 20-Feb-24 A 14-Mar-24 14-Mar-24, WBS: G07B1.4.3.1 Arch. Works
A1240
Ceramic Tiles (Flooring ) 4 22-Feb-24 26-Feb-24 0% 26-Feb-24, Ceramic Tiles (Flooring )
A1260
Ceramic Tiles (Walls) 5 22-Feb-24 27-Feb-24 0% 27-Feb-24, Ceramic Tiles (Walls)
A1270
ToiletAccessories 2 13-Mar-24 14-Mar-24 0% 14-Mar-24, ToiletAccessories
A1300
Wooden Door 2 28-Feb-24 29-Feb-24 0% 29-Feb-24, Wooden Door
A1310
Ceilling Paint 5 22-Feb-24 27-Feb-24 0% 27-Feb-24, Ceilling Paint
A1320
Waterproofing + Test 5 20-Feb-24 A 22-Feb-24 A 100% Waterproofing + Test
WBS: G07B1.4.3.3 Electrical Works 21 10-Dec-23 A 16-Mar-24 16-Mar-24, WBS: G07B1.4.3.3 Electrical Works
A1480
Lighting Fixture 3 13-Mar-24 16-Mar-24 0% 16-Mar-24, Lighting Fixture
A1490
Lighting Outlet 5 10-Dec-23 A 31-Dec-23 A 100% Lighting Outlet
A1500
Lighting Switches 5 22-Feb-24 27-Feb-24 0% 27-Feb-24, Lighting Switches
WBS: G07B1.4.3.5 Plumbing Works 5 17-Feb-24 A 20-Feb-24 A 20-Feb-24 A, WBS: G07B1.4.3.5 Plumbing Works
A1330
Install Plumbing Pipes 5 17-Feb-24 A 20-Feb-24 A 100% Install Plumbing Pipes
WBS: G07B1.4.5 IT Room 12 18-Jan-24 A 07-Mar-24 07-Mar-24, WBS: G07B1.4.5 IT Room

Actual Level of Effort Remaining Work summary Page 2 of 3 TASK filter: All Activities
Primary Baseline Critical Remaining Work © Oracle Corporation
Actual Work Milestone
22-Feb-24
Activity ID Activity Name Original Start Finish Activity % 2024
Duration Complete
Mar Apr
WBS: G07B1.4.5.1 Arch. Works 9 18-Jan-24 A 07-Mar-24 07-Mar-24, WBS: G07B1.4.5.1 Arch. Works
A1460
Paints 5 18-Jan-24 A 31-Jan-24 A 100% Paints
A1470
Install Metal Door 5 22-Feb-24 A 07-Mar-24 80% 07-Mar-24, Install Metal Door
A1840
Raised Floor 7 01-Feb-24 A 27-Feb-24 40% 27-Feb-24, Raised Floor
WBS: G07B1.4.5.3 Electrical Works 7 27-Feb-24 06-Mar-24 06-Mar-24, WBS: G07B1.4.5.3 Electrical Works
A1340
Cable and wirring for IT Room 7 27-Feb-24 06-Mar-24 0% 06-Mar-24, Cable and wirring for IT Room
A1760
Access Control System 7 27-Feb-24 06-Mar-24 0% 06-Mar-24,Access Control System

WBS: G07B1.4.6 Pump Room + Tanks 33 07-Jan-24 A 30-Mar-24 30-Mar-24, WBS: G07B1.4.6 Pum
WBS: G07B1.4.6.2 Civil Works 15 07-Jan-24 A 06-Mar-24 06-Mar-24, WBS: G07B1.4.6.2 Civil Works
A1510
Civil work required for pump room 15 15-Feb-24 A 06-Mar-24 20% Civil work required for pump room
A1520
Demolish For Access 4 07-Jan-24 A 22-Feb-24 95% 22-Feb-24, Demolish ForAccess
A1530
Install Metal Doors and Stairs 4 15-Feb-24 A 24-Feb-24 60% 24-Feb-24, Install Metal Doors and Stairs
WBS: G07B1.4.6.1 MEP Works 20 07-Mar-24 30-Mar-24 30-Mar-24, WBS: G07B1.4.6.1 ME
A1540
Electric Horzonal Split Case Fire Pump 14 07-Mar-24 23-Mar-24 0% 23-Mar-24, Electric Horzonal Split Case Fire Pump
A1550
Horizontal Split Units Pump 8 21-Mar-24 30-Mar-24 0% Horizontal Split Units Pump
A1560
Jockey FFPump 12 07-Mar-24 20-Mar-24 0% Jockey FFPump
A1570
Fuel Tank 12 07-Mar-24 20-Mar-24 0% Fuel Tank
A1580
Electric Fuel Pump 11 07-Mar-24 19-Mar-24 0% 19-Mar-24, Electric Fuel Pump
A1590
Dilto for manually operated pump & submenisable pump
20 07-Mar-24 30-Mar-24 0% Dilto for manually operated pump &
WBS: G07B1.4.7 Electrical Room 27 22-Feb-24 A 23-Mar-24 23-Mar-24, WBS: G07B1.4.7 Electrical Room
WBS: G07B1.4.7.1 Arch Works 2 22-Feb-24 A 26-Feb-24 26-Feb-24, WBS: G07B1.4.7.1 Arch Works
A1610
Steel Door 2 22-Feb-24 A 26-Feb-24 0% 26-Feb-24, Steel Door
WBS: G07B1.4.7.3 Mechanical Works 12 10-Mar-24 23-Mar-24 23-Mar-24, WBS: G07B1.4.7.3 Mechanical Works
A1600
MDP 12 10-Mar-24 23-Mar-24 0% 23-Mar-24, MDP
WBS: G07B1.4.8 Drainge System 5 22-Feb-24 27-Feb-24 27-Feb-24, WBS: G07B1.4.8 Drainge System
WBS: G07B1.4.8.2 Plumbing Works 5 22-Feb-24 27-Feb-24 27-Feb-24, WBS: G07B1.4.8.2 Plumbing Works
A1630
Install drainge system 5 22-Feb-24 27-Feb-24 0% 27-Feb-24, Install drainge system

Actual Level of Effort Remaining Work summary Page 3 of 3 TASK filter: All Activities
Primary Baseline Critical Remaining Work © Oracle Corporation
Actual Work Milestone