GEELY Updated Timeplan
GEELY Updated Timeplan
Actual Level of Effort Remaining Work summary Page 1 of 6 TASK filter: All Activities
Primary Baseline Critical Remaining Work © Oracle Corporation
Actual Work Milestone
21-Feb-24
Activity ID Activity Name Original Start Finish Activity % 2023 2024
Duration Complete
Oct Nov Dec Jan Feb Mar Apr May Jun Jul
A9340 Install Leader 8 15-Mar-24 23-Mar-24 0% 2...
WBS: G04-7.G04-6.2.3.9.4 Water proofing Works 14 20-Feb-24 A 05-Mar-24 0...
A8390 Install Waterproofing 2 20-Feb-24 A 22-Feb-24 50% 2...
A8440 Testing waterproof 1 23-Feb-24 23-Feb-24 0% 2...
A9200 Repair cement bond on water and fire tank 5 24-Feb-24 28-Feb-24 0% 2...
A9350 Epoxy paont on water and fire tank 5 01-Mar-24 05-Mar-24 0% 0...
WBS: G04-7.G04-6.2.3.9.5 Openings 2 27-Jan-24 A 22-Feb-24 2...
A8400 Install Single wooden door 2 27-Jan-24 A 30-Jan-24 A 100% I...
A8410 Install Double wooden door 2 27-Jan-24 A 30-Jan-24 A 100% I...
A8420 Install Single steel door 2 15-Feb-24 A 22-Feb-24 0% 2...
WBS: G04-7.G04-6.2.3.9.6 Finishes 57 16-Jan-24 A 23-Mar-24 2...
WBS: G04-7.G04-6.2.3.9.6.5 Plaster 2 16-Jan-24 A 18-Jan-24 A 1...
A9310 Plaster 2 16-Jan-24 A 18-Jan-24 A 100% P...
WBS: G04-7.G04-6.2.3.9.6.1 Flooring Finshes 61 20-Jan-24 A 23-Mar-24 2...
A8430 Install Flooring Porceline 5 07-Mar-24 11-Mar-24 0% 1...
A8470 Install Marbel 3 07-Mar-24 10-Mar-24 0% 1...
A8480 Install Floor Carpet Fixed On Ceramic 8 15-Mar-24 23-Mar-24 0% 2...
A8500 Install Marble threshold 4 07-Mar-24 10-Mar-24 0% 1...
A9210 Install Ceramic Tiles 3 07-Mar-24 09-Mar-24 0% 0...
A9220 Install Fiber mesh with epoxy finish and road marker- Fist Coat 3 20-Jan-24 A 22-Feb-24 60% 2...
A9230 Install Fiber mesh with epoxy finish and road marker- Second Coat 3 22-Feb-24 25-Feb-24 0% 2...
A9360 White paint lineation 2 07-Mar-24 08-Mar-24 0% 0...
WBS: G04-7.G04-6.2.3.9.6.2 Wall Finishes 53 18-Jan-24 A 15-Mar-24 1...
A9140 Install Wall Paint Finish 2 18-Jan-24 A 21-Feb-24 80% 2...
A9150 Install Wall Marble 2 12-Mar-24 13-Mar-24 0% 1...
A9300 Install marble skirting 3 12-Mar-24 15-Mar-24 0% 1...
A9370 Epoxy skirting 2 12-Mar-24 13-Mar-24 0% 1...
WBS: G04-7.G04-6.2.3.9.6.3 Ceiling Finishes 15 21-Feb-24 06-Mar-24 0...
A8510 Install Ceiling Paint 10 21-Feb-24 01-Mar-24 0% 0...
A8520 Install Gypsum Board 15 21-Feb-24 06-Mar-24 0% 0...
WBS: G04-7.G04-6.2.3.9.6.4 Partitions 0
WBS: G04-7.G04-6.2.3.9.7 Specialteis 22 10-Feb-24 A 15-Mar-24 1...
A8550 Install Handrail 2 09-Mar-24 10-Mar-24 0% 1...
A8570 Install ToiletAccessories 4 12-Mar-24 15-Mar-24 0% 1...
A8580 Install Interior Sign 1 12-Mar-24 12-Mar-24 0% 1...
A8590 Install Pantry 1 10-Mar-24 11-Mar-24 0% 1...
A9380 Install Reflected Mirrors for ramps 1 12-Mar-24 12-Mar-24 0% 1...
A9390 Instl Floor Drainage 8 10-Feb-24 A 28-Feb-24 10% 2...
WBS: G04-7.G04-6.2.3.8 Mechanical 148 11-Dec-23 A 19-May-24 1...
WBS: G04-7.G04-6.2.3.8.1 HVAC 110 09-Feb-24 A 19-May-24 1...
WBS: G04-7.G04-6.2.3.8.1.3 DX Split Unit 3 09-Feb-24 A 23-Feb-24 2...
A8610 Install DX Units (two types) 3 09-Feb-24 A 23-Feb-24 5% 2...
WBS: G04-7.G04-6.2.3.8.1.4 Fans 78 02-Mar-24 19-May-24 1...
A8620 Install Axial Wall Mounted exhaust Fans 2 02-Mar-24 03-Mar-24 0% 0...
A8630 Install Exhaust axial inline Fan 2 02-Mar-24 03-Mar-24 0% 0...
A8640 Install Inline two speed Fan 2 02-Mar-24 03-Mar-24 0% 0...
A8650 Smoke Fan 3 16-May-24 19-May-24 0% 1...
WBS: G04-7.G04-6.2.3.8.1.6 Duct Works 8 10-Feb-24 A 28-Feb-24 2...
A8660 Install Galvanized Duct 8 10-Feb-24 A 28-Feb-24 10% 2...
WBS: G04-7.G04-6.2.3.8.1.8 Air Distribuation 3 21-Feb-24 24-Feb-24 2...
A8680 Install Air Distribuation 3 21-Feb-24 24-Feb-24 0% 2...
Actual Level of Effort Remaining Work summary Page 2 of 6 TASK filter: All Activities
Primary Baseline Critical Remaining Work © Oracle Corporation
Actual Work Milestone
21-Feb-24
Activity ID Activity Name Original Start Finish Activity % 2023 2024
Duration Complete
Oct Nov Dec Jan Feb Mar Apr May Jun Jul
WBS: G04-7.G04-6.2.3.8.2 Fire fighting 100 11-Dec-23 A 31-Mar-24 3...
WBS: G04-7.G04-6.2.3.8.2.1 Fire Pumps 28 04-Mar-24 31-Mar-24 3...
A9400 Electric Horizontal split case fire pump 14 06-Mar-24 19-Mar-24 0% 1...
A9410 Horizontal Split Unit pump 12 18-Mar-24 29-Mar-24 0% 2...
A9420 Jockey FF Pump 12 06-Mar-24 17-Mar-24 0% 1...
A9430 Fuel Tank 14 04-Mar-24 17-Mar-24 0% 1...
A9440 Electric Fuel Pump 11 06-Mar-24 16-Mar-24 0% 1...
A9450 Ditto for manually operated Pump & submenisble Pump 26 06-Mar-24 31-Mar-24 0% 3...
WBS: G04-7.G04-6.2.3.8.2.2 Fire Piping Network 9 11-Dec-23 A 30-Dec-23 A 3...
A8690 Install Fire piping network 9 11-Dec-23 A 30-Dec-23 A 100% I...
WBS: G04-7.G04-6.2.3.8.2.3 Sprinkles 4 12-Feb-24 A 21-Feb-24 2...
A8780 Install Upright Sprinkler 4 12-Feb-24 A 21-Feb-24 80% 2...
WBS: G04-7.G04-6.2.3.8.2.5 Drainage System 18 10-Feb-24 A 08-Mar-24 0...
A8720 Install Drainage System 18 10-Feb-24 A 08-Mar-24 10% 0...
WBS: G04-7.G04-6.2.3.8.2.6 Fire Extinguishers 14 02-Mar-24 16-Mar-24 1...
A8730 Install Fire extinguishers -CO2-Trolly foam - dry powder-FM200 3 13-Mar-24 16-Mar-24 0% 1...
A8740 Install Fire hose cabinet 3 02-Mar-24 05-Mar-24 0% 0...
WBS: G04-7.G04-6.2.3.8.2.7 Firetrace System For Electric Panel 7 07-Mar-24 13-Mar-24 1...
A8750 Install Firetrace system for electrical panel 7 07-Mar-24 13-Mar-24 0% 1...
WBS: G04-7.G04-6.2.3.8.3 Plumbing 12 21-Feb-24 A 03-Mar-24 0...
WBS: G04-7.G04-6.2.3.8.3.1 Plumbing Fixtures 5 28-Feb-24 03-Mar-24 0...
A8760 Install Plumbing fixture 5 28-Feb-24 03-Mar-24 0% 0...
WBS: G04-7.G04-6.2.3.8.3.2 Plumbing Piping 3 21-Feb-24 A 23-Feb-24 2...
A8770 Install Plumbing pipes 3 21-Feb-24 A 23-Feb-24 20% 2...
WBS: G04-7.G04-6.2.3.1 Electrical 96 10-Dec-23 A 11-Mar-24 1...
WBS: G04-7.G04-6.2.3.1.2 Communication 81 10-Dec-23 A 08-Mar-24 0...
WBS: G04-7.G04-6.2.3.1.2.1 IP Communication System 81 10-Dec-23 A 08-Mar-24 0...
A9000 Install IP communication system (Telephone & Data) Outlet 3 10-Dec-23 A 21-Feb-24 90% 2...
A9010 Install Access point Dvices 2 07-Mar-24 08-Mar-24 0% 0...
A9020 Install M.M fiber cable 3 05-Feb-24 A 10-Feb-24 A 100% I...
A9120 Install WI-FI Boxs 2 07-Mar-24 08-Mar-24 0% 0...
WBS: G04-7.G04-6.2.3.1.2.2 Public Adress 3 10-Dec-23 A 30-Dec-23 A 3...
A9030 Install Public adress system Outlet 3 10-Dec-23 A 30-Dec-23 A 100% I...
WBS: G04-7.G04-6.2.3.1.3 Safty & security 20 21-Feb-24 11-Mar-24 1...
WBS: G04-7.G04-6.2.3.1.3.1 Addressable Alarm System 19 21-Feb-24 10-Mar-24 1...
A9060 Install Fire alarm system sounder 4 07-Mar-24 10-Mar-24 0% 1...
A9070 Install Break glass manual station 3 07-Mar-24 10-Mar-24 0% 1...
A9080 Install Smoke detector 4 07-Mar-24 10-Mar-24 0% 1...
A9090 Install Control & Monitor modules 3 07-Mar-24 10-Mar-24 0% 1...
A9460 Install Fire alarm system control panel 3 21-Feb-24 24-Feb-24 0% 2...
WBS: G04-7.G04-6.2.3.1.3.2 IP Video Surveillance System 5 07-Mar-24 11-Mar-24 1...
A9100 Install CCTV Indoor dome camera 5 07-Mar-24 11-Mar-24 0% 1...
A9110 Install CCTV Indoor and Outdoor bullet camera 3 07-Mar-24 10-Mar-24 0% 1...
A9470 Install Equipment IP CCTV Server 3 07-Mar-24 10-Mar-24 0% 1...
A9480 Workstation with LED screen 5 07-Mar-24 11-Mar-24 0% 1...
WBS: G04-7.G04-6.2.3.1.3.3 Access Control Sysytem 4 07-Mar-24 10-Mar-24 1...
A9490 Access control system 4 07-Mar-24 10-Mar-24 0% 1...
WBS: G04-7.G04-6.2.3.1.1 Electrical 96 10-Dec-23 A 07-Mar-24 0...
WBS: G04-7.G04-6.2.3.1.1.1 Interior Lighting 13 06-Feb-24 A 02-Mar-24 0...
A8790 Install Lighting Fixtures 13 06-Feb-24 A 02-Mar-24 20% 0...
WBS: G04-7.G04-6.2.3.1.1.2 Lighting Switches 3 02-Mar-24 05-Mar-24 0...
A8800 Install Lighting Switches 3 02-Mar-24 05-Mar-24 0% 0...
Actual Level of Effort Remaining Work summary Page 3 of 6 TASK filter: All Activities
Primary Baseline Critical Remaining Work © Oracle Corporation
Actual Work Milestone
21-Feb-24
Activity ID Activity Name Original Start Finish Activity % 2023 2024
Duration Complete
Oct Nov Dec Jan Feb Mar Apr May Jun Jul
WBS: G04-7.G04-6.2.3.1.1.16 Wiring Devices and Accessories 80 10-Dec-23 A 07-Mar-24 0...
A8810 Install Wiring devices- cable trunk 6 13-Feb-24 A 25-Feb-24 20% 2...
A8820 Install Wiring devices- Cable tray 6 13-Feb-24 A 25-Feb-24 20% 2...
A8830 Install Wiring devices- Sockets Outlet 3 10-Dec-23 A 31-Dec-23 A 100% I...
A8840 Install Wiring devices- Power Outlet 4 10-Dec-23 A 31-Dec-23 A 100% I...
A8850 Install Wiring devices- Floor Boxs 6 02-Mar-24 07-Mar-24 0% 0...
A8860 Install Wiring devices- Sockets 3 02-Mar-24 05-Mar-24 0% 0...
WBS: G04-7.G04-6.2.3.1.1.3 Disconnect Switches 4 02-Mar-24 05-Mar-24 0...
A8870 Install Disconnect Switches 4 02-Mar-24 05-Mar-24 0% 0...
WBS: G04-7.G04-6.2.3.1.1.4 Low Voltage Electrical Power Conductors and Cables 5 10-Dec-23 A 31-Dec-23 A 3...
A8880 Install Lighting Outlet 3 10-Dec-23 A 31-Dec-23 A 100% I...
A8890 Install AC Outlet 3 10-Dec-23 A 31-Dec-23 A 100% I...
A8900 Install Other outlets 5 10-Dec-23 A 31-Dec-23 A 100% I...
WBS: G04-7.G04-6.2.3.1.1.5 Power and Lighting Panel Board 15 15-Feb-24 A 06-Mar-24 0...
A8910 Install Panel board 15 15-Feb-24 A 06-Mar-24 70% 0...
WBS: G04-7.G04-6.2.3.1.1.11 Cables and Wires 15 14-Feb-24 A 25-Feb-24 2...
A8980 Install Cable and wires 15 14-Feb-24 A 25-Feb-24 70% 2...
WBS: G04-7.G04-6.2.2 Second Basement 157 13-Nov-23 A 10-May-24 1...
WBS: G04-7.G04-6.2.2.9 Arch. 151 13-Nov-23 A 03-May-24 0...
WBS: G04-7.G04-6.2.2.9.1 Demolishing 6 13-Nov-23 A 20-Nov-23 A 2...
A10020 Demolish Works 6 13-Nov-23 A 20-Nov-23 A 100% D...
WBS: G04-7.G04-6.2.2.9.2 Masonary 7 16-Mar-24 22-Mar-24 2...
A10030 Masonary Works 7 16-Mar-24 22-Mar-24 0% 2...
WBS: G04-7.G04-6.2.2.9.3 Metals Works 4 23-Apr-24 26-Apr-24 2...
A10040 Install Alumimium Sliding doors and windows 4 23-Apr-24 26-Apr-24 0% 2...
WBS: G04-7.G04-6.2.2.9.4 Water proofing Works 3 08-Mar-24 10-Mar-24 1...
A10050 Waterproofing 2 08-Mar-24 10-Mar-24 0% 1...
A10110 Testing waterproof 1 10-Mar-24 10-Mar-24 0% 1...
WBS: G04-7.G04-6.2.2.9.5 Openings 4 23-Apr-24 26-Apr-24 2...
A10060 Install Single wooden door 3 23-Apr-24 25-Apr-24 0% 2...
A10070 Install Double wooden door 4 23-Apr-24 26-Apr-24 0% 2...
A10080 Install Single steel door 4 23-Apr-24 26-Apr-24 0% 2...
WBS: G04-7.G04-6.2.2.9.6 Finishes 16 02-Apr-24 29-Apr-24 2...
WBS: G04-7.G04-6.2.2.9.6.5 Plaster 10 02-Apr-24 11-Apr-24 1...
A10610 Plaster 10 02-Apr-24 11-Apr-24 0% 1...
WBS: G04-7.G04-6.2.2.9.6.1 Flooring Finshes 7 19-Apr-24 26-Apr-24 2...
A10660 Install Porceline 4 19-Apr-24 22-Apr-24 0% 2...
A10670 Install Fiber mesh with epoxy finish- First Coat 4 19-Apr-24 22-Apr-24 0% 2...
A10680 Install Marble 4 19-Apr-24 22-Apr-24 0% 2...
A10690 Install Marble threshold 4 19-Apr-24 22-Apr-24 0% 2...
A10730 Install Fiber mesh with epoxy finish- Second Coat 3 23-Apr-24 26-Apr-24 0% 2...
WBS: G04-7.G04-6.2.2.9.6.2 Wall Finishes 5 23-Apr-24 27-Apr-24 2...
A10010 Install ceramic tiles 3 23-Apr-24 25-Apr-24 0% 2...
A10600 Install marble skirting 3 23-Apr-24 25-Apr-24 0% 2...
A10620 Install Epoxy skirting 3 23-Apr-24 25-Apr-24 0% 2...
A10630 Intall Paint 5 23-Apr-24 27-Apr-24 0% 2...
WBS: G04-7.G04-6.2.2.9.6.3 Ceiling Finishes 18 12-Apr-24 29-Apr-24 2...
A10090 Install Ceiling Paint 7 23-Apr-24 29-Apr-24 0% 2...
A10100 Install Gypsum Board 7 12-Apr-24 18-Apr-24 0% 1...
WBS: G04-7.G04-6.2.2.9.6.4 Partitions 0
WBS: G04-7.G04-6.2.2.9.7 Specialteis 4 30-Apr-24 03-May-24 0...
Actual Level of Effort Remaining Work summary Page 4 of 6 TASK filter: All Activities
Primary Baseline Critical Remaining Work © Oracle Corporation
Actual Work Milestone
21-Feb-24
Activity ID Activity Name Original Start Finish Activity % 2023 2024
Duration Complete
Oct Nov Dec Jan Feb Mar Apr May Jun Jul
A10120 Install Handrail 4 30-Apr-24 03-May-24 0% 0...
A10130 Install ToiletAccessories 4 30-Apr-24 03-May-24 0% 0...
A10140 Install Interior Sign 4 30-Apr-24 03-May-24 0% 0...
A10150 Install Pantry 4 30-Apr-24 03-May-24 0% 0...
A10590 Reflected Mirror 4 30-Apr-24 03-May-24 0% 0...
A10700 Floor drinage 4 30-Apr-24 03-May-24 0% 0...
WBS: G04-7.G04-6.2.2.8 Mechanical 62 10-Mar-24 10-May-24 1...
WBS: G04-7.G04-6.2.2.8.1 HVAC 41 23-Mar-24 02-May-24 0...
WBS: G04-7.G04-6.2.2.8.1.3 DX Split Unit 3 30-Apr-24 02-May-24 0...
A10160 Install DX Units (two types) 3 30-Apr-24 02-May-24 0% 0...
WBS: G04-7.G04-6.2.2.8.1.4 Fans 1 30-Apr-24 30-Apr-24 3...
A10170 Install Axial Wall Mounted exhaust Fans 1 30-Apr-24 30-Apr-24 0% 3...
A10180 Install Exhaust axial inline Fan 1 30-Apr-24 30-Apr-24 0% 3...
A10190 Install Inline two speed Fan 1 30-Apr-24 30-Apr-24 0% 3...
WBS: G04-7.G04-6.2.2.8.1.6 Duct Works 3 23-Mar-24 25-Mar-24 2...
A10200 Install Galvanized Duct 3 23-Mar-24 25-Mar-24 0% 2...
WBS: G04-7.G04-6.2.2.8.1.7 Duct Insulation 2 26-Mar-24 27-Mar-24 2...
A10210 Install Duct Insulation 2 26-Mar-24 27-Mar-24 0% 2...
WBS: G04-7.G04-6.2.2.8.1.8 Air Distribuation 3 26-Mar-24 28-Mar-24 2...
A10220 Install Air Distribuation 3 26-Mar-24 28-Mar-24 0% 2...
WBS: G04-7.G04-6.2.2.8.2 Fire fighting 49 23-Mar-24 10-May-24 1...
WBS: G04-7.G04-6.2.2.8.2.2 Fire Piping Network 3 23-Mar-24 25-Mar-24 2...
A10230 Install Fire piping network 3 23-Mar-24 25-Mar-24 0% 2...
WBS: G04-7.G04-6.2.2.8.2.3 Sprinkles 1 10-May-24 10-May-24 1...
A10240 Install Pendant Sprinkler 1 10-May-24 10-May-24 0% 1...
A10310 Install Upright Sprinkler 1 10-May-24 10-May-24 0% 1...
WBS: G04-7.G04-6.2.2.8.2.5 Drainage System 2 02-Apr-24 03-Apr-24 0...
A10250 Install Drainage System 2 02-Apr-24 03-Apr-24 0% 0...
WBS: G04-7.G04-6.2.2.8.2.6 Fire Extinguishers 11 30-Apr-24 10-May-24 1...
A10260 Install Fire extinguishers -CO2-Trolly foam - dry powder-FM200 1 10-May-24 10-May-24 0% 1...
A10270 Install Fire hose cabinet 1 30-Apr-24 30-Apr-24 0% 3...
WBS: G04-7.G04-6.2.2.8.2.7 Firetrace System For Electric Panel 1 30-Apr-24 30-Apr-24 3...
A10280 Install Firetrace system for electrical panel 1 30-Apr-24 30-Apr-24 0% 3...
WBS: G04-7.G04-6.2.2.8.3 Plumbing 55 10-Mar-24 03-May-24 0...
WBS: G04-7.G04-6.2.2.8.3.1 Plumbing Fixtures 4 30-Apr-24 03-May-24 0...
A10290 Install Plumbing fixture 4 30-Apr-24 03-May-24 0% 0...
WBS: G04-7.G04-6.2.2.8.3.2 Plumbing Piping 6 10-Mar-24 15-Mar-24 1...
A10300 Install Plumbing pipes 6 10-Mar-24 15-Mar-24 0% 1...
WBS: G04-7.G04-6.2.2.1 Electrical 43 23-Mar-24 04-May-24 0...
WBS: G04-7.G04-6.2.2.1.2 Communication 43 23-Mar-24 04-May-24 0...
WBS: G04-7.G04-6.2.2.1.2.1 IP Communication System 43 23-Mar-24 04-May-24 0...
A10460 Install IP communication system (Telephone & Data) Outlet 5 23-Mar-24 27-Mar-24 0% 2...
A10470 Install Access point Dvices 5 30-Apr-24 04-May-24 0% 0...
A10570 Install WI-FI Boxs 5 30-Apr-24 04-May-24 0% 0...
WBS: G04-7.G04-6.2.2.1.3 Safty & security 4 30-Apr-24 03-May-24 0...
WBS: G04-7.G04-6.2.2.1.3.1 Addressable Alarm System 4 30-Apr-24 03-May-24 0...
A10510 Install Fire alarm system sounder 4 30-Apr-24 03-May-24 0% 0...
A10520 Install Break glass manual station 4 30-Apr-24 03-May-24 0% 0...
A10530 Install Smoke detector 4 30-Apr-24 03-May-24 0% 0...
A10540 Install Control & Monitor modules 4 30-Apr-24 03-May-24 0% 0...
WBS: G04-7.G04-6.2.2.1.3.2 IP Video Surveillance System 4 30-Apr-24 03-May-24 0...
A10550 Install CCTV Indoor dome camera 4 30-Apr-24 03-May-24 0% 0...
Actual Level of Effort Remaining Work summary Page 5 of 6 TASK filter: All Activities
Primary Baseline Critical Remaining Work © Oracle Corporation
Actual Work Milestone
21-Feb-24
Activity ID Activity Name Original Start Finish Activity % 2023 2024
Duration Complete
Oct Nov Dec Jan Feb Mar Apr May Jun Jul
A10560 Install CCTV Indoor and Outdoor bullet camera 4 30-Apr-24 03-May-24 0% 0...
WBS: G04-7.G04-6.2.2.1.1 Electrical 42 23-Mar-24 03-May-24 0...
WBS: G04-7.G04-6.2.2.1.1.1 Interior Lighting 6 23-Apr-24 28-Apr-24 2...
A10320 Install Lighting Fixtures 6 23-Apr-24 28-Apr-24 0% 2...
WBS: G04-7.G04-6.2.2.1.1.2 Lighting Switches 3 30-Apr-24 02-May-24 0...
A10330 Install Lighting Switches 3 30-Apr-24 02-May-24 0% 0...
WBS: G04-7.G04-6.2.2.1.1.16 Wiring Devices and Accessories 41 23-Mar-24 02-May-24 0...
A10340 Install Wiring devices- cable trunk 3 23-Mar-24 25-Mar-24 0% 2...
A10350 Install Wiring devices- Cable tray 3 23-Mar-24 25-Mar-24 0% 2...
A10360 Install Wiring devices- Sockets Outlet 3 23-Mar-24 25-Mar-24 0% 2...
A10370 Install Wiring devices- Power Outlet 3 23-Mar-24 25-Mar-24 0% 2...
A10380 Install Wiring devices- Floor Boxs 3 30-Apr-24 02-May-24 0% 0...
A10390 Install Wiring devices- Sockets 3 30-Apr-24 02-May-24 0% 0...
WBS: G04-7.G04-6.2.2.1.1.3 Disconnect Switches 4 23-Mar-24 26-Mar-24 2...
A10400 Install Disconnect Switches 4 23-Mar-24 26-Mar-24 0% 2...
WBS: G04-7.G04-6.2.2.1.1.4 Low Voltage Electrical Power Conductors and Cables 3 23-Mar-24 25-Mar-24 2...
A10410 Install Lighting Outlet 3 23-Mar-24 25-Mar-24 0% 2...
A10420 Install AC Outlet 3 23-Mar-24 25-Mar-24 0% 2...
A10430 Install Other outlets 3 23-Mar-24 25-Mar-24 0% 2...
WBS: G04-7.G04-6.2.2.1.1.5 Power and Lighting Panel Board 10 24-Apr-24 03-May-24 0...
A10440 Install Panel board 10 24-Apr-24 03-May-24 0% 0...
WBS: G04-7.G04-6.2.2.1.1.11 Cables and Wires 10 23-Mar-24 01-Apr-24 0...
A10450 Install Cable and wires 10 23-Mar-24 01-Apr-24 0% 0...
WBS: G04-7.G04-6.2.4 Roof 121 01-Feb-24 A 20-Jun-24 2...
WBS: G04-7.G04-6.2.8 Exteriors Work 92 11-Dec-23 A 23-Mar-24 2...
WBS: G04-7.G04-6.2.8.1 Arch. 92 11-Dec-23 A 23-Mar-24 2...
WBS: G04-7.G04-6.2.8.1.3 Metals Works 86 11-Dec-23 A 17-Mar-24 1...
A9680 Install Aluminium Louvers 15 03-Mar-24 17-Mar-24 0% 1...
A9690 Install Aluminium composite panel & Aluminium plastic panel 15 03-Mar-24 17-Mar-24 0% 1...
A9700 Install External dry mix-Paint 15 24-Jan-24 A 28-Feb-24 50% 2...
A9740 Install Double glazed curtain wall 6 11-Dec-23 A 05-Jan-24 A 100% I...
WBS: G04-7.G04-6.2.8.1.7 Specialties 6 18-Mar-24 23-Mar-24 2...
A9830 Install Logo wall Washer light on Facade 6 18-Mar-24 23-Mar-24 0% 2...
A9870 Install Linear wall washer on elevations 6 18-Mar-24 23-Mar-24 0% 2...
WBS: G04-7.G04-6.2.9 Landscape 78 25-Jan-24 A 17-May-24 1...
WBS: G04-7.G04-6.2.9.1 Arch. 78 25-Jan-24 A 17-May-24 1...
WBS: G04-7.G04-6.2.9.1.1 Finishes 30 25-Jan-24 A 17-May-24 1...
A9880 Install Granite for fence 8 01-Feb-24 A 08-Feb-24 A 100% I...
A9900 Install interlok 30 25-Jan-24 A 17-May-24 40% 1...
WBS: G04-7.G04-6.2.9.1.2 Specialties 64 13-Feb-24 A 05-May-24 0...
A9910 Install Outdoor Totem 10 13-Feb-24 A 14-Feb-24 A 100% I...
A9920 Corner Guard 6 30-Apr-24 05-May-24 0% 0...
A9930 Curb Details 12 03-Mar-24 14-Mar-24 0% 1...
WBS: G04-7.G04-6.2.9.10 Electrical 15 31-Jan-24 A 10-Feb-24 A 1...
A10710 Grouding and bonding for electrical system 15 31-Jan-24 A 05-Feb-24 A 100% G...
A10720 Low current system earthing system 12 05-Feb-24 A 10-Feb-24 A 100% L...
Actual Level of Effort Remaining Work summary Page 6 of 6 TASK filter: All Activities
Primary Baseline Critical Remaining Work © Oracle Corporation
Actual Work Milestone