GEELY Updated Timeplan

The Geely Project timeline outlines various activities scheduled from October 2023 to June 2024, detailing tasks such as closing out basements, landscaping, and facade work. Each activity has specific start and finish dates, with varying completion percentages indicating progress. The document serves as a project management tool to track milestones and remaining work for the project's successful execution.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
22 views

GEELY Updated Timeplan

The Geely Project timeline outlines various activities scheduled from October 2023 to June 2024, detailing tasks such as closing out basements, landscaping, and facade work. Each activity has specific start and finish dates, with varying completion percentages indicating progress. The document serves as a project management tool to track milestones and remaining work for the project's successful execution.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 6

Geely Project 21-Feb-24

Activity ID Activity Name Original Start Finish Activity % 2023 2024


Duration Complete
Oct Nov Dec Jan Feb Mar Apr May Jun Jul
206 16-Oct-23 A 20-Jun-24 2...
Project: G04-7 Geely Updated 20-2
206 16-Oct-23 A 20-Jun-24 2...
WBS: G04-7.G04-6 Remaining Project
WBS: G04-7.G04-6.1 Project - Milestone 124 16-Oct-23 A 20-Jun-24 2...
A11070 Close Out Basement 1 0 23-Mar-24 0% C...
A11080 Close Out Basement 2 0 10-May-24 0% C...
A11090 Close Out Landscape 0 17-May-24 0% C...
A11100 Close Out Facade 0 23-Mar-24 0% C...
A11110 Colse Out Roof including AHU 0 20-Jun-24 0% C...
A11120 DownPayment 0 03-Mar-24* 0% D...
A11160 Site Resiving 0 16-Oct-23 A 100% S...
A11170 Close Out Long lead Item (Smoke Fan) 0 19-May-24 0% C...
A11180 Close Out Pump Room 0 31-Mar-24 0% C...
A11270 Varation Approved For Compressed Air 0 25-Feb-24* 0% V...

WBS: G04-7.G04-6.3 Materials Submittle to Approval 6 27-Nov-23 A 24-Feb-24 2...


A11140 FM 200 3 27-Nov-23 A 02-Dec-23 A 100% F...
A11150 Cooper bars for panels 3 20-Dec-23 A 24-Feb-24 0% 2...
A11220 AHU 3 07-Feb-24 A 24-Feb-24 0% 2...
A11240 Smoke Fan 3 09-Jan-24 A 09-Jan-24 A 100% S...
A11250 Water Heater 3 21-Feb-24 24-Feb-24 0% 2...
WBS: G04-7.G04-6.4 Material Approval to Delivery 105 03-Mar-24 15-Jun-24 1...
A11190 FM 200 10 03-Mar-24 12-Mar-24 0% 1...
A11200 Cooper bars for panels 4 03-Mar-24 06-Mar-24 0% 0...
A11210 AHU 105 03-Mar-24 15-Jun-24 0% A...
A11230 Smoke Fan 74 03-Mar-24 15-May-24 0% 1...
A11260 Water Heater 9 03-Mar-24 11-Mar-24 0% 1...
WBS: G04-7.G04-6.5 Execution 91 07-Jan-24 A 01-Apr-24 0...
WBS: G04-7.G04-6.5.2 PUMP ROOM 51 07-Jan-24 A 24-Feb-24 2...
WBS: G04-7.G04-6.5.2.4 Pump Room 51 07-Jan-24 A 24-Feb-24 2...
A10810 Civil work required for pump room 4 15-Feb-24 A 22-Feb-24 60% 2...
A1089 Demolish For Access 3 07-Jan-24 A 21-Feb-24 95% 2...
A10950 Install Metal Door & Stair For Pump room 4 15-Feb-24 A 24-Feb-24 0% 2...
WBS: G04-7.G04-6.5.1 General 37 25-Feb-24 01-Apr-24 0...
WBS: G04-7.G04-6.5.1.2 Concrete 4 06-Mar-24 09-Mar-24 0...
WBS: G04-7.G04-6.5.1.2.1 Screed with fiber mesh 4 06-Mar-24 09-Mar-24 0...
A10760 Cast insite slab on grade on Basement 2 floor 4 06-Mar-24 09-Mar-24 0% 0...
A10770 ‫البياره‬ 4 06-Mar-24 09-Mar-24 0% 0...
WBS: G04-7.G04-6.5.1.4 Elevator 30 03-Mar-24 01-Apr-24 0...
A10900 Install Elevator 30 03-Mar-24 01-Apr-24 0% 0...
WBS: G04-7.G04-6.5.1.5 Comperssed Air 25 25-Feb-24 20-Mar-24 2...
WBS: G04-7.G04-6.5.1.5.1 Compressed Air 25 25-Feb-24 20-Mar-24 2...
A11060 Compressed Air 25 25-Feb-24 20-Mar-24 0% 2...
WBS: G04-7.G04-6.2 Spaces 206 06-Nov-23 A 20-Jun-24 2...
WBS: G04-7.G04-6.2.3 First Basement 177 06-Nov-23 A 19-May-24 1...
WBS: G04-7.G04-6.2.3.9 Arch. 136 06-Nov-23 A 23-Mar-24 2...
WBS: G04-7.G04-6.2.3.9.1 Demolishing 5 06-Nov-23 A 13-Nov-23 A 1...
A8360 Demolish Works 5 06-Nov-23 A 13-Nov-23 A 100% D...
WBS: G04-7.G04-6.2.3.9.2 Masonary 6 15-Nov-23 A 12-Dec-23 A 1...
A8370 Masonary Works 6 15-Nov-23 A 12-Dec-23 A 100% M...
WBS: G04-7.G04-6.2.3.9.3 Metals Works 8 15-Mar-24 23-Mar-24 2...
A8380 Alumimium Sliding windows 8 15-Mar-24 23-Mar-24 0% 2...

Actual Level of Effort Remaining Work summary Page 1 of 6 TASK filter: All Activities
Primary Baseline Critical Remaining Work © Oracle Corporation
Actual Work Milestone
21-Feb-24
Activity ID Activity Name Original Start Finish Activity % 2023 2024
Duration Complete
Oct Nov Dec Jan Feb Mar Apr May Jun Jul
A9340 Install Leader 8 15-Mar-24 23-Mar-24 0% 2...
WBS: G04-7.G04-6.2.3.9.4 Water proofing Works 14 20-Feb-24 A 05-Mar-24 0...
A8390 Install Waterproofing 2 20-Feb-24 A 22-Feb-24 50% 2...
A8440 Testing waterproof 1 23-Feb-24 23-Feb-24 0% 2...
A9200 Repair cement bond on water and fire tank 5 24-Feb-24 28-Feb-24 0% 2...
A9350 Epoxy paont on water and fire tank 5 01-Mar-24 05-Mar-24 0% 0...
WBS: G04-7.G04-6.2.3.9.5 Openings 2 27-Jan-24 A 22-Feb-24 2...
A8400 Install Single wooden door 2 27-Jan-24 A 30-Jan-24 A 100% I...
A8410 Install Double wooden door 2 27-Jan-24 A 30-Jan-24 A 100% I...
A8420 Install Single steel door 2 15-Feb-24 A 22-Feb-24 0% 2...
WBS: G04-7.G04-6.2.3.9.6 Finishes 57 16-Jan-24 A 23-Mar-24 2...
WBS: G04-7.G04-6.2.3.9.6.5 Plaster 2 16-Jan-24 A 18-Jan-24 A 1...
A9310 Plaster 2 16-Jan-24 A 18-Jan-24 A 100% P...
WBS: G04-7.G04-6.2.3.9.6.1 Flooring Finshes 61 20-Jan-24 A 23-Mar-24 2...
A8430 Install Flooring Porceline 5 07-Mar-24 11-Mar-24 0% 1...
A8470 Install Marbel 3 07-Mar-24 10-Mar-24 0% 1...
A8480 Install Floor Carpet Fixed On Ceramic 8 15-Mar-24 23-Mar-24 0% 2...
A8500 Install Marble threshold 4 07-Mar-24 10-Mar-24 0% 1...
A9210 Install Ceramic Tiles 3 07-Mar-24 09-Mar-24 0% 0...
A9220 Install Fiber mesh with epoxy finish and road marker- Fist Coat 3 20-Jan-24 A 22-Feb-24 60% 2...
A9230 Install Fiber mesh with epoxy finish and road marker- Second Coat 3 22-Feb-24 25-Feb-24 0% 2...
A9360 White paint lineation 2 07-Mar-24 08-Mar-24 0% 0...
WBS: G04-7.G04-6.2.3.9.6.2 Wall Finishes 53 18-Jan-24 A 15-Mar-24 1...
A9140 Install Wall Paint Finish 2 18-Jan-24 A 21-Feb-24 80% 2...
A9150 Install Wall Marble 2 12-Mar-24 13-Mar-24 0% 1...
A9300 Install marble skirting 3 12-Mar-24 15-Mar-24 0% 1...
A9370 Epoxy skirting 2 12-Mar-24 13-Mar-24 0% 1...
WBS: G04-7.G04-6.2.3.9.6.3 Ceiling Finishes 15 21-Feb-24 06-Mar-24 0...
A8510 Install Ceiling Paint 10 21-Feb-24 01-Mar-24 0% 0...
A8520 Install Gypsum Board 15 21-Feb-24 06-Mar-24 0% 0...
WBS: G04-7.G04-6.2.3.9.6.4 Partitions 0
WBS: G04-7.G04-6.2.3.9.7 Specialteis 22 10-Feb-24 A 15-Mar-24 1...
A8550 Install Handrail 2 09-Mar-24 10-Mar-24 0% 1...
A8570 Install ToiletAccessories 4 12-Mar-24 15-Mar-24 0% 1...
A8580 Install Interior Sign 1 12-Mar-24 12-Mar-24 0% 1...
A8590 Install Pantry 1 10-Mar-24 11-Mar-24 0% 1...
A9380 Install Reflected Mirrors for ramps 1 12-Mar-24 12-Mar-24 0% 1...
A9390 Instl Floor Drainage 8 10-Feb-24 A 28-Feb-24 10% 2...
WBS: G04-7.G04-6.2.3.8 Mechanical 148 11-Dec-23 A 19-May-24 1...
WBS: G04-7.G04-6.2.3.8.1 HVAC 110 09-Feb-24 A 19-May-24 1...
WBS: G04-7.G04-6.2.3.8.1.3 DX Split Unit 3 09-Feb-24 A 23-Feb-24 2...
A8610 Install DX Units (two types) 3 09-Feb-24 A 23-Feb-24 5% 2...
WBS: G04-7.G04-6.2.3.8.1.4 Fans 78 02-Mar-24 19-May-24 1...
A8620 Install Axial Wall Mounted exhaust Fans 2 02-Mar-24 03-Mar-24 0% 0...
A8630 Install Exhaust axial inline Fan 2 02-Mar-24 03-Mar-24 0% 0...
A8640 Install Inline two speed Fan 2 02-Mar-24 03-Mar-24 0% 0...
A8650 Smoke Fan 3 16-May-24 19-May-24 0% 1...
WBS: G04-7.G04-6.2.3.8.1.6 Duct Works 8 10-Feb-24 A 28-Feb-24 2...
A8660 Install Galvanized Duct 8 10-Feb-24 A 28-Feb-24 10% 2...
WBS: G04-7.G04-6.2.3.8.1.8 Air Distribuation 3 21-Feb-24 24-Feb-24 2...
A8680 Install Air Distribuation 3 21-Feb-24 24-Feb-24 0% 2...

Actual Level of Effort Remaining Work summary Page 2 of 6 TASK filter: All Activities
Primary Baseline Critical Remaining Work © Oracle Corporation
Actual Work Milestone
21-Feb-24
Activity ID Activity Name Original Start Finish Activity % 2023 2024
Duration Complete
Oct Nov Dec Jan Feb Mar Apr May Jun Jul
WBS: G04-7.G04-6.2.3.8.2 Fire fighting 100 11-Dec-23 A 31-Mar-24 3...
WBS: G04-7.G04-6.2.3.8.2.1 Fire Pumps 28 04-Mar-24 31-Mar-24 3...
A9400 Electric Horizontal split case fire pump 14 06-Mar-24 19-Mar-24 0% 1...
A9410 Horizontal Split Unit pump 12 18-Mar-24 29-Mar-24 0% 2...
A9420 Jockey FF Pump 12 06-Mar-24 17-Mar-24 0% 1...
A9430 Fuel Tank 14 04-Mar-24 17-Mar-24 0% 1...
A9440 Electric Fuel Pump 11 06-Mar-24 16-Mar-24 0% 1...
A9450 Ditto for manually operated Pump & submenisble Pump 26 06-Mar-24 31-Mar-24 0% 3...
WBS: G04-7.G04-6.2.3.8.2.2 Fire Piping Network 9 11-Dec-23 A 30-Dec-23 A 3...
A8690 Install Fire piping network 9 11-Dec-23 A 30-Dec-23 A 100% I...
WBS: G04-7.G04-6.2.3.8.2.3 Sprinkles 4 12-Feb-24 A 21-Feb-24 2...
A8780 Install Upright Sprinkler 4 12-Feb-24 A 21-Feb-24 80% 2...
WBS: G04-7.G04-6.2.3.8.2.5 Drainage System 18 10-Feb-24 A 08-Mar-24 0...
A8720 Install Drainage System 18 10-Feb-24 A 08-Mar-24 10% 0...
WBS: G04-7.G04-6.2.3.8.2.6 Fire Extinguishers 14 02-Mar-24 16-Mar-24 1...
A8730 Install Fire extinguishers -CO2-Trolly foam - dry powder-FM200 3 13-Mar-24 16-Mar-24 0% 1...
A8740 Install Fire hose cabinet 3 02-Mar-24 05-Mar-24 0% 0...
WBS: G04-7.G04-6.2.3.8.2.7 Firetrace System For Electric Panel 7 07-Mar-24 13-Mar-24 1...
A8750 Install Firetrace system for electrical panel 7 07-Mar-24 13-Mar-24 0% 1...
WBS: G04-7.G04-6.2.3.8.3 Plumbing 12 21-Feb-24 A 03-Mar-24 0...
WBS: G04-7.G04-6.2.3.8.3.1 Plumbing Fixtures 5 28-Feb-24 03-Mar-24 0...
A8760 Install Plumbing fixture 5 28-Feb-24 03-Mar-24 0% 0...
WBS: G04-7.G04-6.2.3.8.3.2 Plumbing Piping 3 21-Feb-24 A 23-Feb-24 2...
A8770 Install Plumbing pipes 3 21-Feb-24 A 23-Feb-24 20% 2...
WBS: G04-7.G04-6.2.3.1 Electrical 96 10-Dec-23 A 11-Mar-24 1...
WBS: G04-7.G04-6.2.3.1.2 Communication 81 10-Dec-23 A 08-Mar-24 0...
WBS: G04-7.G04-6.2.3.1.2.1 IP Communication System 81 10-Dec-23 A 08-Mar-24 0...
A9000 Install IP communication system (Telephone & Data) Outlet 3 10-Dec-23 A 21-Feb-24 90% 2...
A9010 Install Access point Dvices 2 07-Mar-24 08-Mar-24 0% 0...
A9020 Install M.M fiber cable 3 05-Feb-24 A 10-Feb-24 A 100% I...
A9120 Install WI-FI Boxs 2 07-Mar-24 08-Mar-24 0% 0...
WBS: G04-7.G04-6.2.3.1.2.2 Public Adress 3 10-Dec-23 A 30-Dec-23 A 3...
A9030 Install Public adress system Outlet 3 10-Dec-23 A 30-Dec-23 A 100% I...
WBS: G04-7.G04-6.2.3.1.3 Safty & security 20 21-Feb-24 11-Mar-24 1...
WBS: G04-7.G04-6.2.3.1.3.1 Addressable Alarm System 19 21-Feb-24 10-Mar-24 1...
A9060 Install Fire alarm system sounder 4 07-Mar-24 10-Mar-24 0% 1...
A9070 Install Break glass manual station 3 07-Mar-24 10-Mar-24 0% 1...
A9080 Install Smoke detector 4 07-Mar-24 10-Mar-24 0% 1...
A9090 Install Control & Monitor modules 3 07-Mar-24 10-Mar-24 0% 1...
A9460 Install Fire alarm system control panel 3 21-Feb-24 24-Feb-24 0% 2...
WBS: G04-7.G04-6.2.3.1.3.2 IP Video Surveillance System 5 07-Mar-24 11-Mar-24 1...
A9100 Install CCTV Indoor dome camera 5 07-Mar-24 11-Mar-24 0% 1...
A9110 Install CCTV Indoor and Outdoor bullet camera 3 07-Mar-24 10-Mar-24 0% 1...
A9470 Install Equipment IP CCTV Server 3 07-Mar-24 10-Mar-24 0% 1...
A9480 Workstation with LED screen 5 07-Mar-24 11-Mar-24 0% 1...
WBS: G04-7.G04-6.2.3.1.3.3 Access Control Sysytem 4 07-Mar-24 10-Mar-24 1...
A9490 Access control system 4 07-Mar-24 10-Mar-24 0% 1...
WBS: G04-7.G04-6.2.3.1.1 Electrical 96 10-Dec-23 A 07-Mar-24 0...
WBS: G04-7.G04-6.2.3.1.1.1 Interior Lighting 13 06-Feb-24 A 02-Mar-24 0...
A8790 Install Lighting Fixtures 13 06-Feb-24 A 02-Mar-24 20% 0...
WBS: G04-7.G04-6.2.3.1.1.2 Lighting Switches 3 02-Mar-24 05-Mar-24 0...
A8800 Install Lighting Switches 3 02-Mar-24 05-Mar-24 0% 0...

Actual Level of Effort Remaining Work summary Page 3 of 6 TASK filter: All Activities
Primary Baseline Critical Remaining Work © Oracle Corporation
Actual Work Milestone
21-Feb-24
Activity ID Activity Name Original Start Finish Activity % 2023 2024
Duration Complete
Oct Nov Dec Jan Feb Mar Apr May Jun Jul
WBS: G04-7.G04-6.2.3.1.1.16 Wiring Devices and Accessories 80 10-Dec-23 A 07-Mar-24 0...
A8810 Install Wiring devices- cable trunk 6 13-Feb-24 A 25-Feb-24 20% 2...
A8820 Install Wiring devices- Cable tray 6 13-Feb-24 A 25-Feb-24 20% 2...
A8830 Install Wiring devices- Sockets Outlet 3 10-Dec-23 A 31-Dec-23 A 100% I...
A8840 Install Wiring devices- Power Outlet 4 10-Dec-23 A 31-Dec-23 A 100% I...
A8850 Install Wiring devices- Floor Boxs 6 02-Mar-24 07-Mar-24 0% 0...
A8860 Install Wiring devices- Sockets 3 02-Mar-24 05-Mar-24 0% 0...
WBS: G04-7.G04-6.2.3.1.1.3 Disconnect Switches 4 02-Mar-24 05-Mar-24 0...
A8870 Install Disconnect Switches 4 02-Mar-24 05-Mar-24 0% 0...
WBS: G04-7.G04-6.2.3.1.1.4 Low Voltage Electrical Power Conductors and Cables 5 10-Dec-23 A 31-Dec-23 A 3...
A8880 Install Lighting Outlet 3 10-Dec-23 A 31-Dec-23 A 100% I...
A8890 Install AC Outlet 3 10-Dec-23 A 31-Dec-23 A 100% I...
A8900 Install Other outlets 5 10-Dec-23 A 31-Dec-23 A 100% I...
WBS: G04-7.G04-6.2.3.1.1.5 Power and Lighting Panel Board 15 15-Feb-24 A 06-Mar-24 0...
A8910 Install Panel board 15 15-Feb-24 A 06-Mar-24 70% 0...
WBS: G04-7.G04-6.2.3.1.1.11 Cables and Wires 15 14-Feb-24 A 25-Feb-24 2...
A8980 Install Cable and wires 15 14-Feb-24 A 25-Feb-24 70% 2...
WBS: G04-7.G04-6.2.2 Second Basement 157 13-Nov-23 A 10-May-24 1...
WBS: G04-7.G04-6.2.2.9 Arch. 151 13-Nov-23 A 03-May-24 0...
WBS: G04-7.G04-6.2.2.9.1 Demolishing 6 13-Nov-23 A 20-Nov-23 A 2...
A10020 Demolish Works 6 13-Nov-23 A 20-Nov-23 A 100% D...
WBS: G04-7.G04-6.2.2.9.2 Masonary 7 16-Mar-24 22-Mar-24 2...
A10030 Masonary Works 7 16-Mar-24 22-Mar-24 0% 2...
WBS: G04-7.G04-6.2.2.9.3 Metals Works 4 23-Apr-24 26-Apr-24 2...
A10040 Install Alumimium Sliding doors and windows 4 23-Apr-24 26-Apr-24 0% 2...
WBS: G04-7.G04-6.2.2.9.4 Water proofing Works 3 08-Mar-24 10-Mar-24 1...
A10050 Waterproofing 2 08-Mar-24 10-Mar-24 0% 1...
A10110 Testing waterproof 1 10-Mar-24 10-Mar-24 0% 1...
WBS: G04-7.G04-6.2.2.9.5 Openings 4 23-Apr-24 26-Apr-24 2...
A10060 Install Single wooden door 3 23-Apr-24 25-Apr-24 0% 2...
A10070 Install Double wooden door 4 23-Apr-24 26-Apr-24 0% 2...
A10080 Install Single steel door 4 23-Apr-24 26-Apr-24 0% 2...
WBS: G04-7.G04-6.2.2.9.6 Finishes 16 02-Apr-24 29-Apr-24 2...
WBS: G04-7.G04-6.2.2.9.6.5 Plaster 10 02-Apr-24 11-Apr-24 1...
A10610 Plaster 10 02-Apr-24 11-Apr-24 0% 1...
WBS: G04-7.G04-6.2.2.9.6.1 Flooring Finshes 7 19-Apr-24 26-Apr-24 2...
A10660 Install Porceline 4 19-Apr-24 22-Apr-24 0% 2...
A10670 Install Fiber mesh with epoxy finish- First Coat 4 19-Apr-24 22-Apr-24 0% 2...
A10680 Install Marble 4 19-Apr-24 22-Apr-24 0% 2...
A10690 Install Marble threshold 4 19-Apr-24 22-Apr-24 0% 2...
A10730 Install Fiber mesh with epoxy finish- Second Coat 3 23-Apr-24 26-Apr-24 0% 2...
WBS: G04-7.G04-6.2.2.9.6.2 Wall Finishes 5 23-Apr-24 27-Apr-24 2...
A10010 Install ceramic tiles 3 23-Apr-24 25-Apr-24 0% 2...
A10600 Install marble skirting 3 23-Apr-24 25-Apr-24 0% 2...
A10620 Install Epoxy skirting 3 23-Apr-24 25-Apr-24 0% 2...
A10630 Intall Paint 5 23-Apr-24 27-Apr-24 0% 2...
WBS: G04-7.G04-6.2.2.9.6.3 Ceiling Finishes 18 12-Apr-24 29-Apr-24 2...
A10090 Install Ceiling Paint 7 23-Apr-24 29-Apr-24 0% 2...
A10100 Install Gypsum Board 7 12-Apr-24 18-Apr-24 0% 1...
WBS: G04-7.G04-6.2.2.9.6.4 Partitions 0
WBS: G04-7.G04-6.2.2.9.7 Specialteis 4 30-Apr-24 03-May-24 0...

Actual Level of Effort Remaining Work summary Page 4 of 6 TASK filter: All Activities
Primary Baseline Critical Remaining Work © Oracle Corporation
Actual Work Milestone
21-Feb-24
Activity ID Activity Name Original Start Finish Activity % 2023 2024
Duration Complete
Oct Nov Dec Jan Feb Mar Apr May Jun Jul
A10120 Install Handrail 4 30-Apr-24 03-May-24 0% 0...
A10130 Install ToiletAccessories 4 30-Apr-24 03-May-24 0% 0...
A10140 Install Interior Sign 4 30-Apr-24 03-May-24 0% 0...
A10150 Install Pantry 4 30-Apr-24 03-May-24 0% 0...
A10590 Reflected Mirror 4 30-Apr-24 03-May-24 0% 0...
A10700 Floor drinage 4 30-Apr-24 03-May-24 0% 0...
WBS: G04-7.G04-6.2.2.8 Mechanical 62 10-Mar-24 10-May-24 1...
WBS: G04-7.G04-6.2.2.8.1 HVAC 41 23-Mar-24 02-May-24 0...
WBS: G04-7.G04-6.2.2.8.1.3 DX Split Unit 3 30-Apr-24 02-May-24 0...
A10160 Install DX Units (two types) 3 30-Apr-24 02-May-24 0% 0...
WBS: G04-7.G04-6.2.2.8.1.4 Fans 1 30-Apr-24 30-Apr-24 3...
A10170 Install Axial Wall Mounted exhaust Fans 1 30-Apr-24 30-Apr-24 0% 3...
A10180 Install Exhaust axial inline Fan 1 30-Apr-24 30-Apr-24 0% 3...
A10190 Install Inline two speed Fan 1 30-Apr-24 30-Apr-24 0% 3...
WBS: G04-7.G04-6.2.2.8.1.6 Duct Works 3 23-Mar-24 25-Mar-24 2...
A10200 Install Galvanized Duct 3 23-Mar-24 25-Mar-24 0% 2...
WBS: G04-7.G04-6.2.2.8.1.7 Duct Insulation 2 26-Mar-24 27-Mar-24 2...
A10210 Install Duct Insulation 2 26-Mar-24 27-Mar-24 0% 2...
WBS: G04-7.G04-6.2.2.8.1.8 Air Distribuation 3 26-Mar-24 28-Mar-24 2...
A10220 Install Air Distribuation 3 26-Mar-24 28-Mar-24 0% 2...
WBS: G04-7.G04-6.2.2.8.2 Fire fighting 49 23-Mar-24 10-May-24 1...
WBS: G04-7.G04-6.2.2.8.2.2 Fire Piping Network 3 23-Mar-24 25-Mar-24 2...
A10230 Install Fire piping network 3 23-Mar-24 25-Mar-24 0% 2...
WBS: G04-7.G04-6.2.2.8.2.3 Sprinkles 1 10-May-24 10-May-24 1...
A10240 Install Pendant Sprinkler 1 10-May-24 10-May-24 0% 1...
A10310 Install Upright Sprinkler 1 10-May-24 10-May-24 0% 1...
WBS: G04-7.G04-6.2.2.8.2.5 Drainage System 2 02-Apr-24 03-Apr-24 0...
A10250 Install Drainage System 2 02-Apr-24 03-Apr-24 0% 0...
WBS: G04-7.G04-6.2.2.8.2.6 Fire Extinguishers 11 30-Apr-24 10-May-24 1...
A10260 Install Fire extinguishers -CO2-Trolly foam - dry powder-FM200 1 10-May-24 10-May-24 0% 1...
A10270 Install Fire hose cabinet 1 30-Apr-24 30-Apr-24 0% 3...
WBS: G04-7.G04-6.2.2.8.2.7 Firetrace System For Electric Panel 1 30-Apr-24 30-Apr-24 3...
A10280 Install Firetrace system for electrical panel 1 30-Apr-24 30-Apr-24 0% 3...
WBS: G04-7.G04-6.2.2.8.3 Plumbing 55 10-Mar-24 03-May-24 0...
WBS: G04-7.G04-6.2.2.8.3.1 Plumbing Fixtures 4 30-Apr-24 03-May-24 0...
A10290 Install Plumbing fixture 4 30-Apr-24 03-May-24 0% 0...
WBS: G04-7.G04-6.2.2.8.3.2 Plumbing Piping 6 10-Mar-24 15-Mar-24 1...
A10300 Install Plumbing pipes 6 10-Mar-24 15-Mar-24 0% 1...
WBS: G04-7.G04-6.2.2.1 Electrical 43 23-Mar-24 04-May-24 0...
WBS: G04-7.G04-6.2.2.1.2 Communication 43 23-Mar-24 04-May-24 0...
WBS: G04-7.G04-6.2.2.1.2.1 IP Communication System 43 23-Mar-24 04-May-24 0...
A10460 Install IP communication system (Telephone & Data) Outlet 5 23-Mar-24 27-Mar-24 0% 2...
A10470 Install Access point Dvices 5 30-Apr-24 04-May-24 0% 0...
A10570 Install WI-FI Boxs 5 30-Apr-24 04-May-24 0% 0...
WBS: G04-7.G04-6.2.2.1.3 Safty & security 4 30-Apr-24 03-May-24 0...
WBS: G04-7.G04-6.2.2.1.3.1 Addressable Alarm System 4 30-Apr-24 03-May-24 0...
A10510 Install Fire alarm system sounder 4 30-Apr-24 03-May-24 0% 0...
A10520 Install Break glass manual station 4 30-Apr-24 03-May-24 0% 0...
A10530 Install Smoke detector 4 30-Apr-24 03-May-24 0% 0...
A10540 Install Control & Monitor modules 4 30-Apr-24 03-May-24 0% 0...
WBS: G04-7.G04-6.2.2.1.3.2 IP Video Surveillance System 4 30-Apr-24 03-May-24 0...
A10550 Install CCTV Indoor dome camera 4 30-Apr-24 03-May-24 0% 0...

Actual Level of Effort Remaining Work summary Page 5 of 6 TASK filter: All Activities
Primary Baseline Critical Remaining Work © Oracle Corporation
Actual Work Milestone
21-Feb-24
Activity ID Activity Name Original Start Finish Activity % 2023 2024
Duration Complete
Oct Nov Dec Jan Feb Mar Apr May Jun Jul
A10560 Install CCTV Indoor and Outdoor bullet camera 4 30-Apr-24 03-May-24 0% 0...
WBS: G04-7.G04-6.2.2.1.1 Electrical 42 23-Mar-24 03-May-24 0...
WBS: G04-7.G04-6.2.2.1.1.1 Interior Lighting 6 23-Apr-24 28-Apr-24 2...
A10320 Install Lighting Fixtures 6 23-Apr-24 28-Apr-24 0% 2...
WBS: G04-7.G04-6.2.2.1.1.2 Lighting Switches 3 30-Apr-24 02-May-24 0...
A10330 Install Lighting Switches 3 30-Apr-24 02-May-24 0% 0...
WBS: G04-7.G04-6.2.2.1.1.16 Wiring Devices and Accessories 41 23-Mar-24 02-May-24 0...
A10340 Install Wiring devices- cable trunk 3 23-Mar-24 25-Mar-24 0% 2...
A10350 Install Wiring devices- Cable tray 3 23-Mar-24 25-Mar-24 0% 2...
A10360 Install Wiring devices- Sockets Outlet 3 23-Mar-24 25-Mar-24 0% 2...
A10370 Install Wiring devices- Power Outlet 3 23-Mar-24 25-Mar-24 0% 2...
A10380 Install Wiring devices- Floor Boxs 3 30-Apr-24 02-May-24 0% 0...
A10390 Install Wiring devices- Sockets 3 30-Apr-24 02-May-24 0% 0...
WBS: G04-7.G04-6.2.2.1.1.3 Disconnect Switches 4 23-Mar-24 26-Mar-24 2...
A10400 Install Disconnect Switches 4 23-Mar-24 26-Mar-24 0% 2...
WBS: G04-7.G04-6.2.2.1.1.4 Low Voltage Electrical Power Conductors and Cables 3 23-Mar-24 25-Mar-24 2...
A10410 Install Lighting Outlet 3 23-Mar-24 25-Mar-24 0% 2...
A10420 Install AC Outlet 3 23-Mar-24 25-Mar-24 0% 2...
A10430 Install Other outlets 3 23-Mar-24 25-Mar-24 0% 2...
WBS: G04-7.G04-6.2.2.1.1.5 Power and Lighting Panel Board 10 24-Apr-24 03-May-24 0...
A10440 Install Panel board 10 24-Apr-24 03-May-24 0% 0...
WBS: G04-7.G04-6.2.2.1.1.11 Cables and Wires 10 23-Mar-24 01-Apr-24 0...
A10450 Install Cable and wires 10 23-Mar-24 01-Apr-24 0% 0...
WBS: G04-7.G04-6.2.4 Roof 121 01-Feb-24 A 20-Jun-24 2...
WBS: G04-7.G04-6.2.8 Exteriors Work 92 11-Dec-23 A 23-Mar-24 2...
WBS: G04-7.G04-6.2.8.1 Arch. 92 11-Dec-23 A 23-Mar-24 2...
WBS: G04-7.G04-6.2.8.1.3 Metals Works 86 11-Dec-23 A 17-Mar-24 1...
A9680 Install Aluminium Louvers 15 03-Mar-24 17-Mar-24 0% 1...
A9690 Install Aluminium composite panel & Aluminium plastic panel 15 03-Mar-24 17-Mar-24 0% 1...
A9700 Install External dry mix-Paint 15 24-Jan-24 A 28-Feb-24 50% 2...
A9740 Install Double glazed curtain wall 6 11-Dec-23 A 05-Jan-24 A 100% I...
WBS: G04-7.G04-6.2.8.1.7 Specialties 6 18-Mar-24 23-Mar-24 2...
A9830 Install Logo wall Washer light on Facade 6 18-Mar-24 23-Mar-24 0% 2...
A9870 Install Linear wall washer on elevations 6 18-Mar-24 23-Mar-24 0% 2...
WBS: G04-7.G04-6.2.9 Landscape 78 25-Jan-24 A 17-May-24 1...
WBS: G04-7.G04-6.2.9.1 Arch. 78 25-Jan-24 A 17-May-24 1...
WBS: G04-7.G04-6.2.9.1.1 Finishes 30 25-Jan-24 A 17-May-24 1...
A9880 Install Granite for fence 8 01-Feb-24 A 08-Feb-24 A 100% I...
A9900 Install interlok 30 25-Jan-24 A 17-May-24 40% 1...
WBS: G04-7.G04-6.2.9.1.2 Specialties 64 13-Feb-24 A 05-May-24 0...
A9910 Install Outdoor Totem 10 13-Feb-24 A 14-Feb-24 A 100% I...
A9920 Corner Guard 6 30-Apr-24 05-May-24 0% 0...
A9930 Curb Details 12 03-Mar-24 14-Mar-24 0% 1...
WBS: G04-7.G04-6.2.9.10 Electrical 15 31-Jan-24 A 10-Feb-24 A 1...
A10710 Grouding and bonding for electrical system 15 31-Jan-24 A 05-Feb-24 A 100% G...
A10720 Low current system earthing system 12 05-Feb-24 A 10-Feb-24 A 100% L...

Actual Level of Effort Remaining Work summary Page 6 of 6 TASK filter: All Activities
Primary Baseline Critical Remaining Work © Oracle Corporation
Actual Work Milestone