Investigate an Innovative Connection between RC Beam and Steel Column
Investigate an Innovative Connection between RC Beam and Steel Column
TABLE II :
ULTIMATE LOAD, COLUMN CORRESPONDING DEFLECTION AND STRAIN
Upper Chord Lower Chord
Ultimate
Maximum Maximum Maximum Maximum
Load
Name Deflection Strain Deflection Strain
(kN)
(mm) (mm)
δ1 mm
SP1 39.67 3.06 0.000063 3.84 0.0000345
SP2 109.5 6.74 0.000435 1.256 0.0021470
θ3 rad P3u
δ mm Beam Length in mm P2u
θ3
Fig. 8 Relation between the Beams Rotation Angles and the Column
angle
𝐶=𝑇
0.85𝑓𝑐 ′ 𝑎 𝑏 = 𝐴𝑠 𝐹𝑦
𝐴𝑠 𝐹𝑦
𝑎= = 39.05𝑚𝑚
0.85𝑓𝑐 ′ 𝑏
′
𝑓𝑐 = 0.8 ∗ 50 = 40𝑁/𝑚𝑚2
𝑏 = 160𝑚𝑚 𝑑 = 286𝑚𝑚 Fig.10 Beams RC Section
𝑎
𝑓𝑐′
𝑀𝑛 = 0.85 ∗ ∗ 𝑏 ∗ 𝑎 ∗ (𝑑 − ) = 56.60𝑘𝑁. 𝑚
2
A chance of slipping between
Fig.10 Cracks in SP1 Beam and Splitting of the Steel Bars.
steel bars and steel section is
not being considered in this The existing of the transfer part by 30% of the whole span as
scenario of fully encased steel in SP2 arise the capacity of the reinforced concrete section,
section and that is why balanced that the ultimate moment of the used concrete section is
equation 𝐶 = 𝑇 is provided to 56.60kN.m whiled the applied one before failure was
calculate the nominal moment, 82.12kN.m and no failure is occurred at the RC section or the
see Fig.11. Fig.11 Beams composite Section composite section which appeared a moment by a value of
𝐶 = 0.85𝑓𝑐 ′ 𝑎 𝑏 131.40kN.m without failure.
𝑇 = 𝐴𝑠 𝐹𝑦𝑠 + 𝐴𝑓 𝐹𝑦𝑎 + 𝐴𝑤 𝐹𝑦𝑎
𝐴𝑠 𝐹𝑦𝑠 = 452 ∗ 470
𝐴𝑓 𝐹𝑦𝑎 = 120 ∗ 9.8 ∗ 370
𝐴𝑤 𝐹𝑦𝑎 = (270 − 𝑎)𝑡𝑤 ∗ 370
From the equilibrium equation 𝐶 = 𝑇 → 𝑎 = 163.8𝑚𝑚
𝑎 270−𝑎
𝑀𝑛 = 0.85 ∗ 𝑓𝑐 ′ ∗ 𝑏 ∗ 𝑎 ∗ (𝑑 − ) − 𝐴𝑤 . 𝐹𝑦 ( + 𝑡𝑤 +
2 2
𝑅𝑓𝑡 𝑆𝑡𝑒𝑒𝑙 𝐷𝑖𝑎 𝑡𝑤 𝑅𝑓𝑡 𝑆𝑡𝑒𝑒𝑙 𝐷𝑖𝑎
) − 𝐴𝑓 . 𝐹𝑦 ( + ) = 162kN.m
2 2 2
As shown above the nominal moment of the reinforced
concrete section is less than the nominal moment of the
composite section by more than 50%.
Fig.11 SP2; Beam flexural cracks and column deformed shape.
Elastic and plastic moment of the bare steel column is
calculated below where the Elastic Modulus (Zx) equal to The ability of the column to rotate under the effect of
312cm3 and the Plastic Modulus (Sx) equal to 354 cm3. increasing applied load prevented formation of a plastic hinge
𝑀𝑦 = 𝐹𝑦 . 𝑍𝑥 = 370 ∗ 312000 ∗ 10−6 = 115.44 𝑘𝑁. 𝑚 at the transfer area between reinforced concrete and composite
𝑀𝑝 = 𝐹𝑦 . 𝑆𝑥 = 370 ∗ 354000 ∗ 10−6 = 130.980 𝑘𝑁. 𝑚 beam. If the column did not have an ability to rotate, failure
As per calculation; the highest ability to carry moment is for would have occurred at the transfer joint. It is distinctly shown
the composite section while bare steel column is not able to that the composition of beam succeeded in transferring the
carry the same amount of moment without going through load to the column. In other words, the over lapping length of
plastic deformation. Table III shows moment and transfer steel reinforcement along the steel beam and confinement it by
moment values for all tested specimens. stirrups enabled the two parts of the beam to work as a one
unit; see Fig. 11 for beam flexural cracks and column plastic
TABLE III :
MAXIMUM MOMENT AT THE END AND AT THE TRANSFER POINT deformed. Same behavior of SP2 is repeated at SP3 that the
Name Mend (kN.m) MTr (kN.m) plastic deformation of the SP3 column was the major defect.
SP1 47.60 -------- Flexural cracks which appeared along the beam were minor as
SP2 131.40 82.125 although the column strain value is recorded 3900microstrain
SP3 145.53 30.32
SP4 100.12 62.57 at the maximum applied load, see Fig 12.
It has to be mentioned that the extra loading on specimens steel column prevented the failure of the column and kept it
SP2 and SP3 did not show mentionable response. The far from joint. It must be mentioned that although exaggerated
maximum applied moment at the SP3 specimen was increase of the transfer part could increase the failure load but
145.53kN.m which was less than the ultimate capacity of the by doing that, the failure mode may change to shear failure or
composite section but higher than the plastic moment of the the failure may shift at the column side.
column.
V. CONCLUSION
The main conclusions of this investigation can be
summarized as follows:
1. Use of the transfer beam (Tr.P) is considered a new
promising technique to decrease the beam required
depth and modifies the beam behavior.
2. Use of of Tr.P increases the beam capacity with
Strain Value = 3900 minimum steel requirement.
at the Failure Load
3. The existence of Tr.P helps to avoid the sudden
collapse of the structure.
4. Replacing bare steel column by a composite column
give the advantage of shifting the collapse from the
Fig.12 SP3; Beam flexural cracks and column deformed shape. column.
Column is deformed at both SP2 and SP3 in a way which 5. Increasing the stiffness of the column either as a
shows that the stresses on column exceeded the elastic limit composite or bare steel is recommended for avoiding
and it is running at the plastic stage. Once the load was column buckling.
released, column didn’t back to its original shape. As
mentioned before, Mp of column is equal to 130.98kN.m while REFERENCES
the applied moment at the columns of SP2 and SP3 is 131.40 [1] A. H. El-Masry, “Connection between Composite
and 145.53kN.m respectively. Undoubtedly, failure of both Columns and RC Beams in Multi-Story Building,”
samples happened because the applied moments on their Ph.D. thesis under preparation.
columns was higher than their capacity in elastic stage. [2] G. J. Parra-Montesions, P. Dasgupta, S. C. Goel
“Development of Connections between Hybrid steel
truss–FRC Beams and RC Columns for Precast
Earthquake-Resistant Framed Construction,”
Transfer Area
Engineering Structures, June 2005.
[3] A.- Elremaily, A. Azizinamini “Experimental Behavior of
Steel beam to CFT Column Connections,” Journal of
Constructional Steel Research, June 2001.
[4] A. Elremaily, A. Azizinamini “Design Provisions for
Connections between Steel Beams and Concrete Filled
Tube Columns,” Journal of Constructional Steel
Research, April 2001.
[5] Eurocode 3.,‘‘Design of Steel Structures’’part 1.8 Design
of joints CEN.2005.
[6] HG. Park, HJ. Hwang, CH. Lee, CH. Park and CN. Lee,
Fig.13 Cracks at the failure of SP4.
“Cyclic loading test for concrete-filled U-shaped steel
beam–RC column connections,” Journal of Engineering
SP4 failure, being “flexural failure”, is the ideal one where the
Structures, January 2012.
failure occurred at the beam side in the transfer area as shown
[7] M. A. Dabaon, M. H. El-Boghdadi, E. A. El-Kasaby and
in Fig. 13. Moment at failure was 62.57kN.m at the transfer
N. N. Gerges, “Early Prediction of Intimal Stiffness of
area which was higher than the nominal moment of the beam
Composite Joints,” ASCE-EGS, III Regional Conference
reinforcement at this point “56.60kN.m” by 9.4%. It is worth
on Civil Engineering Technology, April 2002.
mentioning that the use of composite column section has
[8] M. A. Dabaon, “Behavior and Strength of Partially
decreased the ability of column to rotate which can be
Encased Beams With Built-up Sections Having Thin Steel
considered the main reason for the failure at the beam side. As
Webs,” Ain-Shams University, Faculty of Engineering
shown in Fig. 13, the major crack which started from top to
Scientific Bulletin, Vol.37, No.3, September 2002.
bottom of the beam is occurred at the end of steel beam and all
[9] C. Cheng-Chih, L. Chun-Chou and T. Chia-Liang,
other cracks were minor until the appearance of the major
“Evaluation of reinforced connections between steel
crack. All other cracks were a natural result of increasing
beams and box columns,” Journal of Engineering
tension force on the top reinforcement of the beam. Changing
Structures, June 2004.
the column type to a partially encased column instead of bare