Sourcing and Facilities Management Final Audit Report 2015
Sourcing and Facilities Management Final Audit Report 2015
Distribution list
For action Follow up For information
ABBREVIATIONS…………………………………………………………………………………
2
INTRODUCTION………………………………………………………………………………...
3
Summary of key internal audit
findings……………………………………………………...3
Issue and report
ratings……………………………………………………………………….. 3
Follow up tracking…………………………………………………………………………….
4
CONCLUSION……………………………………………………………………………………
4
Overall report rating………………………………………………………………………….
4
Appreciation………………………………………………………………………………………
5
DETAILED FINDINGS…………………………………….….
…………………………………..6
ABBREVIATIONS
The key abbreviations used in this report are:
EXECUTIVE SUMMARY
The full list of the findings identified and the recommendations made during this
review is included in the ‘detailed internal audit findings’ section of this report.
The management action plans will be included in the tracking of internal audit
recommendations maintained by the internal audit function.
Issue rating
The following stratification has been used to rate the significance of each issue /
finding that has been raised.
High Issues classified as high risk are significant control issues that
expose the bank considerably. They should be addressed
immediately.
Follow up tracking
CONCLUSION
Overall report rating
Fair
Satisfacto The department had an overall rating of Fair (60%)
ry
Good
Appreciation
Internal audit would like to thank the department’s management and staff for
their support during the audit.
PROCUREMENT
As per the Expenditure Management Committee (EMC) The head Response: There was no
meeting held on 28th January 2015, they recommended the procurement should purchase at Kes.7.08 and
approval of payments for PIN mailers to the Group ensure that no Kes.8.82 in January 2015
Managing Director & CEO as listed below; tender award is since tests for the new PIN
issued without the Mailers had not been
Coop Cash VISA PIN Mailers appropriate approval done.
The approval to procure 200,000 Co-op Cash VISA PIN to incur costs in
Mailers and 50,000 Sacco Link PIN Mailers from Bewa place. Case one is a re-order at
Wholesalers Ltd at Kshs. 9.50 each (totalling Kshs. 1.9M) Kes.9.50 for both the Co-
was granted by ICTPC on 23/01/2015. The EMC should op cash and sacco link pin
ensure that they do mailers whereas case two
In the same ICTPC meeting, they approved the purchase of not give is the analysis of quotes
Co-op Cash VISA Mailers at Kshs. 7.08 and Sacco Link PIN contradicting received from suppliers.
Mailers at Kshs. 8.82 thus causing the bank to incur an approval The pin mailers from the
unnecessary loss Kshs. 518,000.00 recommendations on lowest bidder in that
the items. analysis had not been
From our review, the tenders were opened on 14th January tested and hence the need
2015 and the analysis done thereafter for presentation to to have safety stock
ICTPC on 23/01/2015. through placing a re-order
The head Sourcing and Facilities Management department to avoid stock out.
who is the secretary to the EMC should have noted this.
Way Forward:
However, from our observations, the LPO 617 for the All tender awards to have
approvals in place.
Risk:
Loss of funds by the bank due to overvalued costs.
LPOs should be sent out to suppliers within the shortest Suppliers should be Response: Suppliers are
time possible upon authorization. Quotations received from informed about engaged to collect the POs
suppliers usually have a time limit within which the bank is awarded tenders to but request for scanned
supposed to engage the supplier through an LPO upon make supplies and ones.
whose expiry the supplier can fail to accept the LPO. Our picking of the
review of the LPO books noted instances where LPOs had prepared LPO. Most suppliers prefer e-
been prepared but were not picked by suppliers. We could Follow up should be POs and in most of the
not ascertain whether the suppliers were the ones delaying made with suppliers mentioned occasions the
in picking the LPOs or they had not been informed by the to pick the LPOs on PO’s were scanned to
unit to pick them. The LPO acts as a contractual document timely basis. them for them to
which details the items to be supplied, at what quantities acknowledge.
and the prices to be supplied at. Delays in picking the LPOs
may lead to stock outs. In the case of LPO no.
62 Victoria Furniture
Internal Audit Department
Page 7 of 67
Sourcing and Facilities Management Audit 2015
Private & Confidential
SOURCING AND FACILITIES MANAGEMENT AUDIT 2015
INTERNAL AUDIT REPORT AS AT July 2015
Finding and Risk (Implication) Recommendation Agreed management
action
Further, the LPO is valid for 90 days after which could not pick the LPO
cancellation is done. on time since there was
a historical pending
Cases noted include; payment.
LPO no. 81 dated 23/03/2015 for the supply of 2 laptop LPO no. 263 for the
chargers for Kshs. 4,990.00 by MackPhilisa was picked supply of 4 drawer
on 23/05/2015 i.e. after 2 months. cabinets by orbit
LPO no. 617 dated 07/01/2015 for the supply of 50,000 Engineering, the LPO
Sacco Link PIN Mailer for Kshs. 475,000.00 by Bewa has since been
Wholesalers Ltd was collected on 13/03/2015 i.e. after 2 cancelled.
months. On the issue of the LPO
LPO no. 34 dated 06/02/2015 for the supply of 3 metres no. 271 for fast choice
CAT 6 patch Siemen Cables for Kshs. 22,500.00 by ltd the seats were for
Applewood Tech was collected on 10/05/2015 i.e. 93 the first wave of
days. Transformation
LPO no. 62 dated 04/03/2015 for the supply of cashier branches and the LPO
tools at Kshs. 49,500.00 by Victoria Furniture Ltd was was scanned to the
collected on 19/05/2015 i.e. 76 days. supplier to fast track
delivery as they were
There were some LPOs that had been issued but were yet urgently needed and
to be collected. Examples were; promised to pick the
More than three months;- LPO later.
Responsibil Head
ity: Procuremen
t
Target Continuous
date:
3. Inappropriate tender awards Rating of internal audit
finding: High
The procurement function involves the acquisition of goods, The head Response:
services and works from an external source, that are Procurement should
appropriate and procured at the best possible cost to meet ensure that The manual does not
the business needs in terms of quality, quantity, time and responses for bids state 50% but states “A
location. As per the procurement manual section 5.1, page are received from at tender that has more
14; a minimum number of 10 suppliers should be invited for least 50% of the than half the response
any bid. Where a category has less than 10 suppliers, all suppliers invited, (5 responses) should be
the suppliers should be invited and where responses are telephone follow ups considered successful
and should be
Risk:
The minimum number of suppliers that can be invited for The head Response: The two items
any bid is 10 as per the procurement manual, section 5.1 procurement should relate to specialised items
page 14. However, there were occasions in which tenders ensure that at least whereby;
were sent out to a very low number of vendors/ suppliers a minimum number
whereas there are others in the same category that could of 10 suppliers are The Bank currently uses
have been invited to bid as well. Examples are:- invited for bids a system procured from
Only two suppliers were invited to bid for the supply where the numbers AUA for access control
and the system is
Internal Audit Department
Page 13 of 67
Sourcing and Facilities Management Audit 2015
Private & Confidential
SOURCING AND FACILITIES MANAGEMENT AUDIT 2015
INTERNAL AUDIT REPORT AS AT July 2015
Finding and Risk (Implication) Recommendation Agreed management
action
of "Proximity card access control system for CIC plaza of suppliers in a locked meaning it is not
6 doors complete with control accessories and category are more compatible with devices
software" even though there are 47 pre-qualified than the minimum. from other providers.
suppliers for the category under "Supply and The quotation from Top
installation of CCTV systems". The lowest bidder was Security was for price
Top Security at an amount of Kshs. 1,204,984.80 but discovery.
the tender was awarded to AUA Industria at an
amount of Kshs. 1,399,987.61 with the presenter to Security Department
the evaluation committee that sat on 12/05/2015 have been engaged to
stating that preference was given to AUA, the current review how the Bank
service provider, since they have the structure and can benefit from
bringing in a new contractor may cause compatibility multiple vendors for
issues and breach of contract if the new contractor different buildings
uses AUA's platform. instead of one vendor
for all buildings and this
The tender invitations for the procurement will be handled in 2016.
of ThinkPad Lenovo laptops at an amount of USD
43,290 (Exclusive of VAT) were only sent to three The Laptop
vendors namely; HP, Lenovo and ASUS. However, manufacturers
other manufactures such as Toshiba, Acer and Dell contacted were three
could have been invited as well. as indicated as we were
Risk: unable to obtain
The Bank may procure goods and/ or services at costs that contacts for Dell. The
are high as a result of a few number of suppliers invited to manufacturers
bid without the benefits of analysing a larger number of contacted were the
leaders as per
attached.
suppliers.
Way Forward:
We will endeavour to
reach out to more
suppliers / manufacturers
for specialised items.
Responsibil Head
ity: Procuremen
t
Target Continuous
date:
5. Documentation of the procurement process. Rating of internal audit
finding: High
Procurement is the purchase of goods and services at the The management Response:
best possible price to meet a purchaser's demand in terms should come up with Recommendations noted.
quantity, quality, dimensions and site. Procurement an efficient way of
requirements are initiated via a purchase requisition filing procurement Way Forward: During
template which includes all the necessary information documents or filing, we will ensure all
pertaining to the procurement or through a business case consider investing in purchases are
for projects. After analysing the requests, obtaining and a system that will accompanied by user
evaluating bids from request for quotations (RFQs)/request collate related requisitions for ease of
for information (RFIs) or request for proposals (RFPs), the documents for ease matching and retrievals.
procurement unit obtains necessary approvals from the of retrieval or Responsibil Head
evaluation & expenditure management committees (EMC) review. ity: Procuremen
of the bank. A local purchase order (LPO) or a tender award t
letter is then issued to the selected supplier/ vendor who in
turn delivers the requested goods or renders the requested Target Continuous
services, a delivery note is then issued by the supplier and date:
later an invoice is presented for payment. However these
documents are not matched and filed together and as a
result it is difficult to establish whether the items procured
were the ones requested for, delivered and paid for. For
example; from the following items procured, the requisition,
invitation for bids and delivery documents were not availed.
The requisition form for the procurement of 40,000
pieces of 930G POS receipt rolls and 25,000 pieces of
IWL POS receipt rolls supplied by BEWA Wholesalers
worth Kshs 2,314,000 was not held.
Risk:
Poor management of procurement records makes it difficult
to trace and/ or retrieve documents, lack of audit trail for
reconstructing processing.
6. Failure to conduct regular and comprehensive market surveys. Rating of internal audit
finding: High
The procurement manual on page 14, section 5.1 ‘Operationalization of the Bank’s suppliers list’ part (b) states
that;- “The procurement manager should at all times undertake market surveys on the going average prices of
items being tendered for comparison with the tender process”. Also on page 6 of the same manual, section
2.3.2 ‘Responsibility’ states that “Purchase of recurrent items – Note: The committee approves prices only
once, for the prices to hold for the next six months". However, the last comprehensive market survey was done
Internal Audit Department
Page 18 of 67
Sourcing and Facilities Management Audit 2015
Private & Confidential
SOURCING AND FACILITIES MANAGEMENT AUDIT 2015
INTERNAL AUDIT REPORT AS AT July 2015
Finding and Risk (Implication) Recommendation Agreed management
action
in May 2014, the head procurement stated that a survey was done in March 2015 but the report (attached) held
only had a few items, some of which had the price for only one supplier and others did not have any price on
them, thus not comprehensively researched and cannot be relied upon. This in effect means that the Bank
could be procuring items at prices that are higher than the market.
within a period of 6
months for and the other items like furniture,
report signed by the some electronic items and
head sourcing and stationery.
facilities
management for
price estimates to be Market Price Index
used in tender June 2015.pdf
analysis.
Way Forward: We will
continuously check the
market prices of items that
are not included in the
PPOA market price index.
Responsibil Head
ity: Procuremen
t
Target Continuous
date:
7. Failure to rely on market price when procuring items Rating of internal audit
finding: High
market price is supposed to help the procurement manager request for purchases will be based on
asses the quotations from suppliers and confirm if prices quotations from market survey.
are within the market range. suppliers or engage
the cheaper supplier Responsibil Head
The department conducted a market survey on printer identified in the ity: Procuremen
ribbon ERC 31 in March 2015 and obtained the market price market survey. t
as Kshs. 450 from FranCrom. An LPO (Number 424) for 400
units was raised at a price of Kshs. 1,252.80 in July 2015. The department Target Continuous
Despite the unit being aware of the market price of the should consider date:
product, they then proceeded to procure the ribbons at blacklisting the
Kshs. 1,252.80 which was over twice the price discovered in supplier for over
the department’s survey. Ukulima and Naivasha branches pricing.
were able to purchase the item at an average of Kshs. 600
despite buying in low quantities. Comprehensive
market survey
Additionally reference to the market survey done in March should be conducted
was not made in analysing the below quotations. and reference made
to when conducting
Quotations for the supply of HP cartridge 6000A analysis.
were analysed in March and a recommendation to
purchase from Pacific stationers at Kshs. 7,482 made
while the department had identified a supplier (silver
eagle) at Kshs. 6,000 in the market survey.
Quotations for the supply of HP cartridge Q7553A
were analysed in March 2015 and recommendations
made to purchase the item from Brand spark at Kshs.
7,772 while the unit had identified a supplier selling
the same at Kshs. 6,300 in the market survey done in
Internal Audit Department
Page 21 of 67
Sourcing and Facilities Management Audit 2015
Private & Confidential
SOURCING AND FACILITIES MANAGEMENT AUDIT 2015
INTERNAL AUDIT REPORT AS AT July 2015
Finding and Risk (Implication) Recommendation Agreed management
action
Risk:
As per the Operations manual, the procurement unit is the Management should Response:
custodian of the local purchase order book. Supply of ensure that all Recommendations noted.
awarded tenders is authorized by issuance of a local awards to supply are
purchase order to the supplier. This should be done after authorised through Way Forward: Staff
approval of the supply by the relevant committees for the issuance of LPOs cautioned not to engage in
bank to enter in to the contract with the suppliers. before goods and such activities and to
There was an instance where a supplier delivered goods services are ensure that all awards are
before issuance of an LPO. This was; delivered by the through issuance of LPOs.
These were explained to occur due to the lengthy period it suppliers.
takes to process an LPO. Examples are; Responsibil Head
ity: Procuremen
LPO no. 198 dated 5/5/2015 awarded to Moringa Ltd to t.
supply 100 mail bag metal D-Locks at Kshs. 350.00 each.
Target Continuous
There was an email dated 17/4/2015 from Geoffrey date:
Nyamuro to Tabitha Makau advising her to receive the
locks at Kshs. 350.00 though the LPO was not ready.
Risk:
Circumventing controls that are put in place in relation
to purchases thereby creating room for frauds.
Lack of LPO number for recording keeping and tracking
of the order on delivery.
Lack of reference on the specification of items to be
supplied.
finding: Medium
As per the procurement manual on pages 13 & 14, section The management Response:
5.0 on supplier prequalification. "The suppliers shall be pre- should ensure that Recommendations noted.
qualified by the procurement unit and approved by the pre-qualification of
head - Sourcing and Facilities Management. It is the Bank's suppliers is done at Way Forward:
desire to have a supplier list which is as diverse as possible. least once annually Presentation to BOM
I.e. as many suppliers per category as possible. to ensure that the seeking to outsource pre-
Refreshments and review of the suppliers list should be Bank derives value qualification for 2015/2016
done on an annual basis". However the last comprehensive for money from a ongoing.
pre-qualification of suppliers was done in February 2014 current list of
and only seven suppliers have been added since then. We suppliers satisfying Responsibil Head
were informed that the reason the same has not been done the Bank's selection ity: Procuremen
was as a result of the staff being overwhelmed by criteria relating to t
workloads. their interest and
capability in Target 21st
Risk: supplying particular date: December
The Bank may not derive the best value for money on goods and/ or 2015.
goods and/ or services from an outdated list of suppliers. services.
While conducting supplier prequalification, due diligence on Procurement unit Response: We are
the supplier must be done which is part of the should following up with the
documentation that the department relies on while ranking suspend suppliers providers to give the
the suppliers. As per the prequalification questionnaire with incomplete documents.
2014-2015, the following documents are supposed to be documentation from
Way Forward: We will
Internal Audit Department
Page 24 of 67
Sourcing and Facilities Management Audit 2015
Private & Confidential
SOURCING AND FACILITIES MANAGEMENT AUDIT 2015
INTERNAL AUDIT REPORT AS AT July 2015
Finding and Risk (Implication) Recommendation Agreed management
action
Risk:
Possibility of dealing with illegitimate suppliers which
Internal Audit Department
Page 25 of 67
Sourcing and Facilities Management Audit 2015
Private & Confidential
SOURCING AND FACILITIES MANAGEMENT AUDIT 2015
INTERNAL AUDIT REPORT AS AT July 2015
Finding and Risk (Implication) Recommendation Agreed management
action
As per the Procurement Manual, the head Sourcing and The head Response: All tender
Facilities Management is the secretary of this committee. procurement should awards are issued as per
As the secretary, they are mandated to prepare the EMC ensure that no EMC approval.
minutes and track any recommendations and issues tender award is
discussed at the meeting. From our review, we noted issued without the Base Cards
instances where the EMC recommendations were not appropriate approval The Base Card RFP took
tracked for action and thus subsequent decisions to award to incur costs being a long time to close and
tenders was hampered. Examples were; in place. indeed was ongoing
during the dates
Base Cards The EMC committee pointed out.
On the 5/2/2015 EMC minutes, the committee approved the should ensure that It has since been closed
purchase of 19,000 base cards at a total cost of they do not give and awarded to a
$25,510.00. Further, they recommended the need for the contradicting different party.
bank to establish if an alternative supplier could be sought. approval
However, this was not done and a further purchase of base recommendations on POS Terminals
10,000 cards at a cost of $12,400.00 was approved as per EMC declined the
items.
the 6/3/2015 EMC minutes. request at the first
As at the audit date 27/08/2015, the evaluation for instance but approved
on appeal and gave
Internal Audit Department
Page 26 of 67
Sourcing and Facilities Management Audit 2015
Private & Confidential
SOURCING AND FACILITIES MANAGEMENT AUDIT 2015
INTERNAL AUDIT REPORT AS AT July 2015
Finding and Risk (Implication) Recommendation Agreed management
action
As per LPO no. 47 dated 20/02/2015 for the supply of 5,000 The head Response:
envelopes by Redox Services, the tender was awarded to procurement should
The B4 reinforced
Internal Audit Department
Page 27 of 67
Sourcing and Facilities Management Audit 2015
Private & Confidential
SOURCING AND FACILITIES MANAGEMENT AUDIT 2015
INTERNAL AUDIT REPORT AS AT July 2015
Finding and Risk (Implication) Recommendation Agreed management
action
Redox Services at Kshs. 16.24 each as opposed to Hill ensure that no envelopes cost by Hill
Converter’s (K) Ltd at Kshs. 8.12 each thus occasioning the tender award is Converters is Kes.81.20
bank a loss of Kshs. 40,600.00. issued without the against Redox’s price of
appropriate approval Kes.16.24
to incur costs being
Risk: in place. B4 normal envelopes
Loss of funds by the bank due to overvalued costs. cost by Hill Converters
The EMC committee is Kes.8.12 against
should ensure that Redox’s price of
they do not give Kes.6.90.
contradicting
approval The analysis is
recommendations on available for
items. confirmation.
Way Forward:
No loss but we shall
continue to monitor.
Responsibil Head
ity: Procuremen
t
Target Continuous
date:
finding: Medium
The Procurement Unit are the custodian of the Local The head Monitoring, Response: We have
purchase order book. The signing of all LPO’S are done Tracking and developed an LPO tracking
jointly between Procurement unit and Finance Department Reporting should report to aid in tracking
as per the signing limits. The supply for awarded tenders is ensure that a the age of LPOs once
authorized by; process is in place to issued.
a) Issuance of an order (LPO.) for goods & services or track issued LPOs for
b) Signing of a contract between the Bank and the prompt delivery and Way Forward: We are
successful bidder for works and projects payments. also expecting this feature
From our review, there were some LPOs that were long to be contained in the
outstanding after the 90 days validity period where items Any exceptions upcoming procurement
were still accepted without an appropriate approval. The should have an system.
team sited lack of system though the same could be done approved for receipt
manually. and payments. Responsibil Head
ity: Monitoring,
Examples were;- Tracking &
LPO no. 30921 dated 18/09/2014 awarded to Hill Reporting
Converters (K) Ltd to supply 10,000 LA4 (a) personal loans
application forms. The items were received as below; Target date: Done
09/07/2015 – 1,500
29/06/2015 – 8,000
19/06/2015 – 500
07/07/2015 – 276
03/07/2015 – 100
25/05/2015 – 168
Risk:
Stock-out of bank inventory which may hinder adequate
planning and sourcing.
The unit has no tracking mechanism of items approved for The head Monitoring, Response: We have
purchase, the vendor awarded and at what cost over a Tracking and developed an EMC
period of time. Reporting should tracking report for this
We noted a scenario where an item was recommended for institute measures to purpose, back dated to
approved to purchase on different EMC sittings but no track and produce year 2014. This is updated
query was raised some from the same supplier. Examples timely reports to the on a weekly basis.
were; EMC of items
historical costs for Way Forward: This report
TC Box Files adequate decision shall be incorporated in
On 11th May 2015 EMC minutes, the committee making. the Procurement system.
recommended approval of 900 TC box files at Kshs. 570.00
from Ricoh Systems. Responsibil Head
On 12th May 2015 EMC minutes, the committee ity: Monitoring
recommended approval of 400 TC box files at Kshs. 470.00 Reporting &
from Ricoh Systems. Tracking.
On 25th May 2015 EMC minutes, the committee
recommended approval of 900 TC box files at Kshs. 800.00 Target Done.
from Moringa Ltd. date:
Internal Audit Department
Page 30 of 67
Sourcing and Facilities Management Audit 2015
Private & Confidential
SOURCING AND FACILITIES MANAGEMENT AUDIT 2015
INTERNAL AUDIT REPORT AS AT July 2015
Finding and Risk (Implication) Recommendation Agreed management
action
Risk:
Poor decision making due to impaired costs metrics.
The department staff members were recently issued with The head of the Response: All desktops
laptops in place of desktop computers. This ultimately department should have since been
rendered the 20 desk tops in the unit redundant. On ensure that there is surrendered and re-
observation, the staff are still using both. The laptops were a proactive way of distributed to branches.
bought as per the LPO no. 321 dated 03/06/2015 and having the desk tops
delivered on 29/06/2015 after which they were issued to re-assigned where Way Forward: All staff
the staff. there is need. will only have a laptop and
On enquiry, the department has no immediate use of the no desktop.
desk tops as they have others lying idle at the store.
Responsibil Head
Risk: ity: Procuremen
Idle assets increases the bank's costs unnecessarily e.g. t
due to purchase costs, depreciation, insurance etc.
Target Done
date:
4. Incompletely filled taxi vouchers Rating of internal audit
finding: High
As per the bank's transport policy, use of taxis in The department Response: Faith Atoiti is
Internal Audit Department
Page 31 of 67
Sourcing and Facilities Management Audit 2015
Private & Confidential
SOURCING AND FACILITIES MANAGEMENT AUDIT 2015
INTERNAL AUDIT REPORT AS AT July 2015
Finding and Risk (Implication) Recommendation Agreed management
action
conducting bank business is via a taxi voucher authorized should consider a COU staff, and at that
by the head of department or branch manager. A valid surcharging staff point, she was working on
voucher should bear the name and signature of the officer, who have not Night shift.
signature and name of authorizing officer and valid bank indicated time of
stamp of respective branch or department. Also the staff usage. Way Forward: We have
using the cab is supposed to ensure all necessary fields are Sensitize branch however warned the staff
filled and sign. management to on omission of pick and
A review of some vouchers used especially by security ensure security drop time and mileage
officers did not contain the name of the officer being ferried personnel using taxis failure to which we shall
as per below examples. indicate their names. surcharge them.
All vouchers not fully
On 29/02/2015 Faith Atoiti used dial a cab to south C populated by staff will
(voucher no 26908) and failed to indicate both the henceforth be charged on
pick and drop time. the staff.
On 30/04/2015 Faith Atoiti used dial a cab to travel to
south C from co-opt rust and failed to indicate both Responsibil Head
pick up and drop time. ity: Monitoring
On 10/04/2015 Moses N. Munyu used dial a cab to Tracking &
travel to 3rd Ngong avenue (voucher no 27501) and Reporting
failed to indicate both the pick and drop time.
Target Done
Risk: date:
Lack of personal accountability on the taxi usage by
failing to indicate name of staff
Failure to indicate time of usage can leave room for
unscrupulous drivers to overcharge the bank
Difficulty in confirming if vouchers used to ferry staff
1. Lack of a proper method for determining re-order levels Rating of internal audit
finding: High
Our review of requisition forms (A105) from branches/ The management Response: Inventory
departments established several instances in which the unit should develop a Management team place
indicated that some items were not in stock (NIS) against method for stock replenishment
some orders. Re-orders points are indicated on bin cards (A determining re-order requests in good time with
record of receipt and issue of stock items) and whenever levels that will be enough buffer stocks to
the point is reached orders for replenishment are made able to forecast last a while. Long
with the procurement unit. However, the process used in usage during the procurement process lead
arriving at the re-order points/ levels is inadequate resulting replenishment lead times /long Suppliers
in stock outs for some stock items, some of which cannot time plus safety delivery lead times have
be source locally by branches such as cash deposit slips. stock. often lead to stock outs.
Examples of items that had stock outs are;-
Some of the highlighted
Nkrumah Road branch items have progressively
Date Order No Item been phased out since last
03/11/14 6307 A3 & A4 envelopes. year e.g. NHIF, Students
21/11/14 6302 A3 & A5 envelopes, Epson printer slip etc. and all deposit
ribbons, and tally Genicom ribbon slips hosted into intranet.
cartridge.
16/12/14 6305 Student deposit slips, cash deposit Way Forward: A Procure
slips and A3 envelopes. to pay System RFP has
08/01/15 6309 A3 envelopes, NHIF deposit slips and been done that would
carter for all inventory
Internal Audit Department
Page 33 of 67
Sourcing and Facilities Management Audit 2015
Private & Confidential
SOURCING AND FACILITIES MANAGEMENT AUDIT 2015
INTERNAL AUDIT REPORT AS AT July 2015
Finding and Risk (Implication) Recommendation Agreed management
action
Risk:
Stock outs that could hinder the smooth running of
branches or departments.
There were 53 outstanding re-orders as per the stationery status list as at 19 th August 2015 that had been
placed with the procurement unit but the items ordered are yet to be delivered at Inventory management unit.
Ideally when re-orders are approved by the evaluation committee (EMC), local purchase orders (LPOs) are
issued to the suppliers for them to supply the requested items within a period of 90 days. Examples of re-orders
that have taken unduly long are;-
Order No Date Item Quantity Status Priority
9495 26/03/14 Epson DFX-9000 printer 80 3 V. urgent
Ribbon – UK made.
Internal Audit Department
Page 34 of 67
Sourcing and Facilities Management Audit 2015
Private & Confidential
SOURCING AND FACILITIES MANAGEMENT AUDIT 2015
INTERNAL AUDIT REPORT AS AT July 2015
Finding and Risk (Implication) Recommendation Agreed management
action
Way Forward:
Implementation of an
efficient stock inventory
system that would
interlink IM & Procurement
to track movement of
stock orders, LPO’S,
suppliers, lead time etc to
ensure non stock out gaps.
The current Sharepoint
workflow process does not
adequately provide
tracking data.
Responsibil Head
ity: Inventory
Manageme
nt
Target 30/07/2016
date:
3. Receipt of overdue LPO deliveries Rating of internal audit
finding: High
Procurement unit issues LPOs to the successive bidder to The head Inventory Response:
supply the goods as earlier quoted as per the bid held. The Management and Recommendation noted.
LPOs forms issued under terms and conditions indicates Transport should
that they are valid for 90 days. The validity is pegged on seek approvals from Way Forward: To be
implemented immediately
Internal Audit Department
Page 36 of 67
Sourcing and Facilities Management Audit 2015
Private & Confidential
SOURCING AND FACILITIES MANAGEMENT AUDIT 2015
INTERNAL AUDIT REPORT AS AT July 2015
Finding and Risk (Implication) Recommendation Agreed management
action
Risk:
Possible dead stock as the goods or items could no longer
be in use hence loss of funds as payments are honoured for
goods received.
Inventory management Staff receive all stationery orders in The head Inventory Response:
form A 105, date stamp and forward them to Head- Management and Recommendation noted.
Supplies & Inventory management unit to assess the orders Transport should
and to ensure that they are reasonable before any issuance engage ICT and the Way Forward:
is made. vendor to enforce The bank to upgrade the
Upon satisfactory verification, these orders are passed to the maker checker sun system from 4.2 to
the Stores staff for processing. mechanism for all Version 6.2 for conclusive
system postings. reconciliation of stock
The original request form A105 is forwarded to the Head - balances.
Inventory Unit daily for posting of issued items in the Sun
Inventory system and debit the user Departments/Branches Responsibil Head
for their consumption costs. ity: Inventory
Manageme
We noted an instance where Credit Operations Unit was nt
charged with 100 tamper proof bags which had been
requested by Market and Communication Unit. This was Target 30/06/2016
requisition number 7514 dated 18/11/2014. date:
Risk:
Internal complaints where units/branches are expensed
unwarranted costs.
finding: High
The role of Inventory management unit is to ensure that The unit head to Response:
stocks for items centrally purchased and requested by ensure that prompt Recommendation noted.
departments and branches are available at all times. This purchase orders are
means the unit should have in place properly working placed immediately Way Forward: Review of
inventory management procedures to ensure that optimal the stock balances stock levels is a manual
inventory levels are maintained based on consumption hit the re-order continuous process
trends without occurrence of shortages in the bank as well levels. through the year where all
as without overstocking. However, from a sample of lead times have always
requisition forms from branches & departments and stock The unit to review all been major factors to be
levels at Inventory management unit, we established the stock re-order considered. However this
instances in which stocks for critical items used in the Bank levels in line with the will be further enhanced
network were being exhausted and taking extremely long procurement and when the bank upgrades
to be replenished as cited in below examples. delivery lead inventory sun system from
timelines and usage. 4.2 to Version 6.2 for
Requisition form no. 2958 and 2956 dated 07/06/2015 conclusive reconciliation of
and 25/05/2015 respectively from Co-op House branch stock balances and setting
to supply among other items 5 bundles of IPF forms of stock levels.
which went out of stock on 19/2/2015. None was yet to
be provided as at the audit date 25/08/2015. Reorder levels will be
determined by the system
A5 envelopes-The bank ran out of stock for two months once we do the upgrade as
from 19/01/2015 to 16/03/2015.This was despite the indicated in point above.
item being in high demand from branches .A sample of
HR and Kisumu branch requests indicated that the Head
two made requests for this item 6 times in this period Responsibil Inventory
without being supplied. ity: Manageme
nt
Internal Audit Department
Page 39 of 67
Sourcing and Facilities Management Audit 2015
Private & Confidential
SOURCING AND FACILITIES MANAGEMENT AUDIT 2015
INTERNAL AUDIT REPORT AS AT July 2015
Finding and Risk (Implication) Recommendation Agreed management
action
Black pens
A5 envelopes
Risk:
Stock-outs may hinder adequate business support and
continuity.
Possible high inventory purchase costs as each branch
and/or unit buys separately to bridge the gap as they do
not enjoy the discounts on economies of scale purchase.
At the Inventory management unit, each stationery item The head Inventory Response: Staff
has a bin stock card kept next to the respective stationery and Transport cautioned to be keener
and equally each stationery item has an account in the Sun Management should when issuing stationery
Inventory system. Both the card and the Sun Inventory ensure that all staff and ensure all transactions
record all stationery received/ issued from the store. The are trained on the are correctly posted out in
records in both should always agree and any discrepancy system use and the stock bin cards as is
reconciled. functionality for required.
Items issued from the Store must be knocked off from the business continuity.
bin card immediately while posting in the Sun inventory is Equally all posting to sun
done later, preferably the same day/week. However, we The head Inventory inventory be updated
within the shortest time
Internal Audit Department
Page 41 of 67
Sourcing and Facilities Management Audit 2015
Private & Confidential
SOURCING AND FACILITIES MANAGEMENT AUDIT 2015
INTERNAL AUDIT REPORT AS AT July 2015
Finding and Risk (Implication) Recommendation Agreed management
action
and Transport
noted that this was not always the case as there were Management should possible to ensure all
discrepancies between the bin cards and the system ensure that the bin records tally at all times.
records. cards and the
This was caused to a large extent by not posting the stock inventory system are Way Forward: Posting
movement in the Inventory System. updated immediately into Sun System to be
there is a stock done within two weeks.
The operating manual stipulates that posting for items movement.
issued should be done same day or week. We confirmed Responsibil Head
that postings had not been done for items issued from ity: Inventory
01/08/2015 to 25/08/2015. The explanation given was that Manageme
only the head Inventory management unit has access to nt &
the system and has been engaged in the reconciliation of Transport
stock items for the stock take conducted in July 2015.This
occasioned variations between the bin card records and the Target Continuous
SUN inventory system which had to be explained orally and date:
vouched on the requisitions to confirm accuracy.
In our opinion ,the provision in the manual to allow for
posting of entries in the system after issuing has been done
promotes reliance on manual systems of managing stock
which is cumbersome and prone to errors.
There were some bin cards where the running tally count
was incorrect as per the stock movements. This was
occasioned by the staff involved not outing the stock upon
issuance. Examples were;-
Risk:
Lack of counter ability on the bank's inventory.
Possible concealment of stock theft.
Stock take is usually conducted twice every year and as The head Inventory Response:
stipulated in the operating manual, the head Inventory management unit Recommendation noted.
management unit coordinates the stock take assisted by should ensure an Way Forward: As
casual staff provided by HRD count every item and stores independent recommended moving
clerk record the quantity on the bin card sign. We were supervisor is forward Head inventory
informed that stock take is usually conducted by the staff at involved to oversee Management will request
Inventory management unit assisted by casual staff the stock take and HRD to provide an
provided by the HR team after which reconciliation is done the same should be independent supervisor
and a stock take report prepared by the head Inventory updated in the from another unit
management unit and forwarded to the Head sourcing and manual alongside the casuals to
facilities department. carry out the stock takes
The objective of stock take is to confirm that proper and the supervisor to do a
controls over stock management are working including the report on the findings.
personnel dealing with the stock, hence the process needs
to be supervised by an independent personnel from another
unit in the bank .The manual has not made a provision for Responsibil Head
such and thus the staff at Inventory management unit do ity: Inventory
the whole process of receiving, issuing and maintaining Manageme
bank stock without a third party reviewing. nt &
Transport
Risk:
In case of collusion between the stores clerk and the unit Target End year
head, theft /vandalism of bank stock can occur undetected date: 2015 stock
as both manual and sun system data can be manipulated. take.
The unit uses SUN inventory system for managing the The department Response:
movement of goods; it has been in use since the year 2013. should consider Recommendations noted.
The system has had several challenges/ limitations that investing in a
have made the smooth running of operations difficult. I.e. reliable inventory Way Forward: The bank
management system to upgrade the sun system
Lack of system vendor support: - The system was that will show the from 4.2 to Version 6.2 for
from a vendor called ‘Advance one’ in the year 2013, visibility of goods conclusive reconciliation of
there has been no support from the vendor since the held at Inventory stock balances.
year 2005 and a call to their representative (Raju) by management unit,
the head inventory management on 4th August 2015 branches and Responsibil Head
confirmed that they no longer support Kenyan departments. The ity: Inventory
customers. This makes resolution of system issues process of ordering Manageme
difficult and rendering the system unreliable. and receiving of nt
goods should also be Target 31/06/2016
Lack of a working trigger for re-order:- We were automated. I.e. auto- date:
informed that the system has a trigger that should be reconciliation of
set of once the set the re-order level is reached but delivery notes
the same does not work. Once the stock levels reach against LPOs issued.
the re-order point in the system nothing happens.
Ideally there should be a trigger that prompts a re-
order once stock levels reach the re-order point.
Risk:
Unreliable system making the unit rely on the manual
process that is prone to abuse.
9. Lack of adequate fire suppression system in one store Rating of internal audit
finding: High
There was one store at Inventory management unit that is The management Response:
not fitted with overhead firefighting equipment. However, should implement an Recommendations noted.
there are portable fire extinguishers inside the side. This automatic
means that in case of a fire during times when the stores firefighting system in Way Forward: We shall
are not manned for example at night, the store does not the new store just pursue the matter with
have a way of extinguishing the fire. like the other stores. Projects & Facilities Unit.
In the meantime, place the
Risk: portable fire extinguishers
The stationery inside the store are exposed to the risk of outside the store.
fire, in case of a fire when staff are not on duty which could
lead to loses. Responsibil Head
ity: Inventory
Manageme
nt &
Transport
Target 31/03/2016
date:
Internal Audit Department
Page 48 of 67
Sourcing and Facilities Management Audit 2015
Private & Confidential
SOURCING AND FACILITIES MANAGEMENT AUDIT 2015
INTERNAL AUDIT REPORT AS AT July 2015
Finding and Risk (Implication) Recommendation Agreed management
action
10. Obsolete/ dead stock held at Inventory management unit Rating of internal audit
finding: Medium
Our review of stationery held at Inventory management The management Response: The currently
unit established items that have had minimal or no should ensure that implemented stationery
movement over a long period. This is attributed to users in branches and requisition work flow
branches and departments not being aware of their departments are provides a full inventory
existence or some becoming obsolete as a result of aware of stationery catalogue that enables
technological changes such as computer diskettes. The maintained at customers to view all that
head Sourcing and Facilities Management wrote to various Inventory we stock. We carried out a
heads of departments on 10th May 2015 for them to confirm management unit. 5 year stock movement
whether the items should be declared obsolete disposed of Once stationery analysis in Q1 aimed at
or not. However, as at the date of our review there was no items are declared identifying obsolete stock
feedback that had been received on the same. Some of the obsolete they should items/ fast moving etc.
items that have not had movement over a period of five be appropriately Memos in regard to
years are;- disposed. obsoletes identified were
done in Q2 to business
Item Stock at hand Date last owners to confirm
issued obsolescence and approve
Sony video tapes 210 17/01/05 disposal. We are still
Epson printer ribbon 8750 72 25/06/09 pursuing conclusion since
Kodak micro films 2,700 08/04/11 none has ever responded.
Goldfish photo cards 1,498 -
Umbrellas with Bank’s logo 66 01/12/11 Way Forward: Head IM to
push for concluded
Risk: decision to dispose.
Obsolete stationery amounts to loss of funds, since the
envisaged benefit arising from their intended usage is not Responsibil Head
ity: Inventory
Internal Audit Department
Page 49 of 67
Sourcing and Facilities Management Audit 2015
Private & Confidential
SOURCING AND FACILITIES MANAGEMENT AUDIT 2015
INTERNAL AUDIT REPORT AS AT July 2015
Finding and Risk (Implication) Recommendation Agreed management
action
realised. Manageme
nt &
Transport
Target 30/03/2016
date:
11. Idle printing press assets Rating of internal audit
finding: Medium
The Bank decommissioned the printing press at Inventory The decommissioned Response: Valuation done
management unit in January 2014 rendering the three printing press in Aug-14 but equipment
printing press machines idle. The machines are machines are note sold as the Bank did
accumulating dust and every day that passes their value gathering dust and not have staff in the Space
decreases without any benefit being accrued from them by their value decrease & Contracts Unit for 10
the Bank. On enquiry of the fate of the machines we were daily. The unit months.
informed that the machines have not been offered for sale should thus hasten
as a result of staffing challenges at Space & Contracts that the process of their Way Forward: Space and
manages disposals. There are also plans to handle their disposal so that the Contracts team to
disposal in October once the unit is fully resourced. Bank can derive the schedule for disposal in
get the best price for Q1-2016.
Risk: the machines.
Idle assets amounts to loss of funds. The bank may not get Responsibil Head space
the best price for the items when they are eventually sold. ity: & Contracts
Target 30/03/2016
date:
12. Execution of contract documents for car hire services Rating of internal audit
finding: High
Ten car hire companies were pre-qualified for the provision The department Response:
of car hire services to Bank’s staff on a need basis in should ensure that Recommendation noted.
October 2014. The companies executed contract contract documents
documents after tender awards and the same forwarded to are fully executed Way Forward: The
the Bank’s attorneys for execution. We were informed that and copies transport officer will be
once the documents were forwarded to the legal maintained by the ensuring all contracts
department, they later could not be traced and as such the department. entered are properly
companies were not issued with copies of duly executed executed immediately and
contract documents. In June 2015 the companies were copies of the duly
asked to sign fresh contract documents that are yet to be executed contract
fully executed noting that the contracts are due to expire documents forwarded to
on 30th October 2015. As a result this has made the the companies within the
processing of some payments difficult because the finance first quarter.
department request for duly signed contract documents to
process payments. Responsibil Head
ity: Inventory
Risk: Manageme
The Bank has no recourse in case of disputes when staff nt &
engage the pre-qualified companies for car hire services Transport
without valid contract documents being in place.
Target 31/01/2016
date:
13. Unsigned taxi service contract Rating of internal audit
finding: High
On 22/08/2014,the bank entered into a contract with three The head sourcing Response:
taxi companies for provision of taxi services to bank staff and facilities should Recommendation noted.
Risk:
Contract may be unenforceable by law.
Our review of the bank motor vehicle insurance covers, we The head Inventory Response: We sought
noted that the insurer normally does the valuation and Management and clarifications from CIC who
upon which they advise the bank on the premium to pay for Transport should confirmed that they held
the year. A sample analysis of the values given indicated seek clarifications on the correct valuations
that some of these values were the same or higher for the any valuation reports as attached and
following year implying that the vehicles were not extremes noted and the credit notes were
depreciating. On enquiry, we were informed that these document the same. passed as attached.
vehicles had been done some over wholes repairs or
bought at a discount of the buying value. The valuations
were accepted as presented with no queries raised with the Adobe Acrobat Microsoft Excel
insurer. Document 97-2003 Worksheet
These were;
Microsoft Excel
M/V Reg. NO. VALUATION AMOUNTS FOR PREMIUMS 97-2003 Worksheet
2013 2014 2015
KBC 237M 2,700,000.00 2,500,000.00 2,700,000.00 Way Forward: We will be
KBK 754D 2,600,000.00 2,400,000.00 2,600,000.00
requesting for copies of
KBB 979M 2,140,000.00 1,950,000.00 2,140,000.00
KBA 769T 1,260,000.0 1,170,000.00 1,260,000.00 valuations reports at the
0 beginning of every year so
KAT 534U 920,000.00 850,000.00 920,000.00 that any extremes are
KBN 286F 3,010,000.0 2,740,000.00 2,740,000.00 noted.
0
KBH 086C 2,330,000.00 2,110,000.00 2,110,000.00
KBH 379C 2,350,000.00 2,130,000.00 2,130,000.00
Responsibil Head
KBK 760D 2,380,000.00 2,140,000.00 2,140,000.00 ity: Inventory
KBK 755D 2,700,000.00 2,400,000.00 2,400,000.00 Manageme
nt &
Internal Audit Department
Page 53 of 67
Sourcing and Facilities Management Audit 2015
Private & Confidential
SOURCING AND FACILITIES MANAGEMENT AUDIT 2015
INTERNAL AUDIT REPORT AS AT July 2015
Finding and Risk (Implication) Recommendation Agreed management
action
Risk;
Possible loss of funds due to payment of high insurance
premiums.
HELP DESK
The department gets help desk calls from the branches and The head Sourcing Response: Call No
departments for all issues they need addressed through the and Facilities should 440654 was reported
department. Help desk is used in administering services, asimplore on the solved on 21.07.2015 by
a satisfaction tool to ensure all issues are resolved to various unit heads to Benard Oloo and thus
conclusion and user input is given consideration to promotereview and address closed the same day.
efficiency. However, we had instances where some calls all calls lodged on
had taken long to be addressed/ closed as indicated. help with prompt
feedback /actions
Documentation Centre reported on 17/02/2015, call indicated.
number 440654 of a leaking roof that needed repairs. As
at 28/08/2015, the roof was yet to be repaired. This was
Call No. 479137 was
Internal Audit Department
Page 54 of 67
Sourcing and Facilities Management Audit 2015
Private & Confidential
SOURCING AND FACILITIES MANAGEMENT AUDIT 2015
INTERNAL AUDIT REPORT AS AT July 2015
Finding and Risk (Implication) Recommendation Agreed management
action
reported again on 23/06/2015, call no. 479137 which are confirmed fixed by Vincent
yet to be closed. Adem on 11.08.2015 and
thus closed on the same
On the second call, the were comments that the day.
previous call was closed before the issue was sorted and
thus a second call on the issue.
Responsibil Head
ity: Monitoring
Tracking &
Reporting
Target 31/12/15
date: and
thereafter
Monthly
Our review of the procurement operating manual The management Response: The unit has
established the following sections that were not clear or should ensure that embarked on updating the
lacked pertinent details;- the procurement manual for the ambiguous
manual is reviewed clauses/ sections, with
The procurement manual on page 14 under section and all sections are guidance from BCM.
5.1 ‘operationalization of the Bank suppliers list’, part clearly elaborated
(h) states that “For those suppliers invited; there and detailed to act
should be a fair distribution among categories – A, B as a reference guide Way Forward: Once the
& C”. However, the categories referenced are not to staff when they exercise is done, the
defined or explained in the manual and thus the perform their roles. manual will be updated
composition of each category is not clear. The and hosted.
process of pre-qualification is not elaborated in the
manual; the manual states that the suppliers shall be Responsibil Head,
pre-qualified by the procurement unit and approved ity: Procuremen
Internal Audit Department
Page 56 of 67
Sourcing and Facilities Management Audit 2015
Private & Confidential
SOURCING AND FACILITIES MANAGEMENT AUDIT 2015
INTERNAL AUDIT REPORT AS AT July 2015
Finding and Risk (Implication) Recommendation Agreed management
action
t
by head sourcing and facilities management but does
not state how the same will be done; details on how Target 15th
the suppliers will be invited, how the they will be date: December,
ranked and the documents required for pre- 2015
qualification are not indicated. From a review of the
questionnaires for the last comprehensive pre-
qualifications done in February 2014, the main
categories noted are; A - score above 75%, B - score
between 50%-74% and C -score between 25%-
49% and not acceptable-score below 25%. For
the seven suppliers who have been pre-qualified in
the year 2015, no scoring was done at all. This is
attributable to lack of proper guidelines in the
operating manual and the staff in the unit being new
to the role.
Risk:
Unclear sections of the manual cannot be relied upon
by staff to perform their duties as required.
OTHERS
The management implemented 72% of the internal audit The management Response:
recommendations from the October, 2014 report. should fully Recommendations noted.
implement Internal
Please see Appendix I of this report for the summary. Audit Way Forward: We shall
recommendations in strive to implement all
Risk: both the current and recommendations moving
Risks still exist in areas where no implementation has been prior-year reports. forward.
done.
Responsibil Head
ity: Procureme
nt
Head
Monitoring
Tracking &
Reporting.
Head
Inventory
Manageme
nt &
Transport
Target Continuousl
date: y
For the May 2014 analysis, the whereabouts of the quotations should be
established and compared with the May 2014 analysis to ensure accuracy
and completeness of the information there in otherwise fresh quotations
and price discovery should be done.
13. Engaging Suppliers to supply items without LPOs
Management should ensure that all departments submit their requests for
supplies for analysis and issuance of LPOs before goods and services are
delivered by the suppliers.
14. Enforcement of contractual terms
The department should review the suppliers who have been engaged by
Shekele Communications Ltd to ascertain the price competitiveness.
15. Failure to ensure quotations are obtained from Marketing agents
The management should ensure that quotations are received from the
marketing agent on all productions done on behalf of the bank to achieve
the most competitive prices.
Where services are single sourced proper authorization should be sought by
the respective user departments.
16. Standardization of Printers in the Bank network
The Procurement unit in liaison with ICT and the business should come up
with categories of printers which can suit different department’s needs.
Since technology is dynamic and keeps on changing, the management
should ensure that printer consumables stored are minimal.
17. Errors in quotation analysis
The management should obtain and review all the quotation used to come
up with May 2014 analysis for the lowest suppliers.
Due diligence should be observed by the analyst, reviewers and approvers
to ensure accurate information is captured in all analysis before approval.
18. Delays by Suppliers to pick LPOs
Suppliers should be informed about awarded supplies and picking of the
prepared LPO. Follow up should be made with suppliers to pick the LPOs on
timely bases.
19. Inconsistent details in LPO
Management should ensure quantities captured on the LPO are correct
before authorizing the same.
20. Missing Quotation numbers/ Failure to capture quotation numbers
The procurement unit should ensure that all RFQs have a unique quotation
number which should also be captured on the analysis form when analysing
the quotations.
21. Differing details on Requests for quotation forms
The management should ensure that all requests for quotations are similar
for all suppliers in order to avoid differences during submission and analysis.
MONITORING, TRACKING AND REPORTING
Total = 61
Fully implemented - 41
Partially Implemented - 6
Not Implemented - 14