Tutorial 2-solutions updated
Tutorial 2-solutions updated
Tutorial 2
1. Design a suitable rectangular sedimentation tank (provided with mechanical cleaning
equipment) for treating the sewage from a city, provided with an assured public water
supply system, with a maximum daily demand of 15 million litres per day. Assume
suitable values of detention period and velocity of flow in the tank. Make any other
assumptions wherever needed.
Solution:
Given data, Maximum daily demand = 15 MLD (Million Litres per Day) = 15,000
m³/day
Assuming that 80% of water supplied to the city becomes sewage, we have the
quantity of sewage required to be treated per day (i. e, max daily)
= 0.8 x 15,000 m³/day
= 12,000 m³/day
Assume Detention time as 2 hours (standard range: 1.5 to 3 hours)
The quantity of sewage to be treated in 2 hours, i.e., the capacity of the tank required
= 12, 000 𝑋 2 / 24
= 1000 m3
Assume Depth as 3 m (standard range: 2 to 5 m)
1000
= 3
= 340 m2
Assume L/B = 3, L = 3B
3B2 = 340
B = 6.14 m
L = 3 X 6.14 = 18.14 m
12,000 𝑚3/𝑑
Surface overflow rate = Discharge/surface area = 340 𝑚2
=35.29 m3/d/m2 (S.O.R
is within the range of 30-50 m3/d/m2. Hence, Ok.
Since, the tank is provided with mechanical cleaning arrangement, no extra space at
the bottom is required for sludge zone.
Now, assuming a freeboard of 0.5 m, we have
The overall depth of the tank = 3+0.5 =3.5m
Hence a rectangular sedimentation tank with an overall size rounded off to 18.2 m
x 6.2 m x 3.5 m can be used.
2. In a wastewater treatment plant, primary circular sedimentation tank designed at an
overflow rate of 32.5 m3/day/m2 of dia 16 m. What is the weir loading rate (in m3/day/m)
Solution:
Given Data:
Perimeter = π x 16
32.5 𝑋 π 𝑥 (16)2
Q =SOR x Area = 4
= 6534.5 m³/day
𝑄
Weir Loading Rate = 𝑊𝑒𝑖𝑟 𝐿𝑒𝑛𝑔𝑡ℎ
6534.5
= π 𝑋 16
= 130 m³/day/m
3. Design a circular secondary sedimentation tank for treatment of 12 MLD effluent coming
from conventional ASP. If the surface overflow rate is 20 m3/m2.day. Provide detention time
of 2 h. calculate volume, area and depth of tank.
Solution:
Given Data:
Flow rate (Q) = 12 MLD = 12,000 m³/day
Surface Overflow Rate (SOR) = 20 m³/m²/day
Detention Time (DT) = 2 hours
12,000 𝑚³/𝑑𝑎𝑦
= 20 𝑚³/𝑚²/𝑑𝑎𝑦
= 600 m2
Compute the Volume of the Tank
Volume = 𝑄 𝑋 𝐷𝑇
12,000 𝑋 2
= 24
= 1000 m³
Compute Diameter of the Tank
π 𝑥 𝐷2
Area = 4
D² = 4 A / π = 4 X 600 / 3.14
Diameter = 27.6 m
Compute Depth of the Tank
Depth = volume/area
= 1000/600
= 1.67 m
4. Design secondary sedimentation tank for treatment of 10 MLD effluent coming from
conventional ASP. The MLSS in aeration tank is 3000 mg/L and peak flow factor is 2.0.
Adopt surface loading rate of 15 m3 / m2 .d at average flow.
Solution:
Given Data:
Flow rate (Q) = 10 MLD = 10,000 m³/day
Peak flow factor = 2.0
Mixed Liquor Suspended Solids (MLSS) = 3000 mg/L
Surface Overflow Rate (SOR) at average flow = 15 m³/m²/day
Compute Surface Area of the Tank
𝑄
Surface Area = 𝑆𝑂𝑅
10,000 𝑚³/𝑑𝑎𝑦
= 15 𝑚³/𝑚²/𝑑𝑎𝑦
= 667 m²
Compute Peak Flow and Check SOR at Peak Flow
Qpeak =Peak
Flow Factor × Q
=2.0×10,000
=20,000 𝑚³/𝑑𝑎𝑦
𝑄𝑝𝑒𝑎𝑘
SORpeak = 𝐴
20,000
= 667
= 30 𝑚³/𝑚²/𝑑𝑎𝑦
Since 30 m³/m²/day is within the acceptable range for peak SOR (typically 25-35 m³/m²/day
for secondary clarifiers), the surface area is adequate.
Compute Diameter of the Tank
π 𝑥 𝐷2
Area = 4
D² = 4 A / π = 4 X 667 / 3.14
Diameter = 29.15 m
Take D = 30 m for practical design.
Compute Depth of the Tank
Provide depth of 1.25 + 0.3 m for sludge accumulation and 0.4 m free board.
Hence total depth = 1.95 m
Check for weir loading:
Weir loading = 10000/(π * D) = 109.27 m3 /m.d, (< 250 m3 /m.d) hence safe.
5. Diameter of sewer is 45 cm, flow = 200 lit/s, n = 0.012. Find slope when flowing full.
2 1
1
Manning’s formula, v =( 𝑛
)* (𝑅) 3 *𝑠 2
i) What is the depth of the excavation if it were to flow by gravity (If the length of the sewer
in 50 km)?
Given Data:
Diameter of sewer (D) = 45 cm = 0.45 m
Flow rate (Q) = 200 L/s = 0.2 m³/s
Manning’s coefficient (n) = 0.012
Length of sewer (L) = 50 km = 50,000 m
● Manning’s formula:
A = 0.159 m2
R = D/4 = 0.45m/4
2 1
1
Mannings formula, v = ( 𝑛
)* (𝑅) *𝑠 3 2
2 1
1.258 = (
1
0.012
)* ( ) 0.45
4
3
*𝑠 2
S = 0.004
Depth of excavation
At 50 km = excavation 210 m
At 10 km = 42 m
At 20km = 84m
At 30km = 126m
At 40km = 168 m
At 50km = 210
If Slope = 0.004
At 50km = excavation 200m
Slope value = 0.00419 ( accurate) Slope value = 0.004( approximate)
At 50 km 210 200
At 40 km 164 160
At 30 km 126 120
At 20 km 84 80
At 10 km 42 40
6. Design a sanitary sewer to serve a population of 5,000 people, if the average water
consumption is 400 liters per capita per day (lpcd). The slope available for the sewer to be
laid
is 1 in 625. Assume 80 % of the water supplied is entering the sewer. Use "n" value of 0.013
in the Manning's formula
Given Data:
Population (P) = 5000 people
Per capita water consumption = 400 lpcd
Percentage of water entering sewer = 80%
Available slope (S) = 1/625
Manning’s coefficient (n) = 0.013
Given Data:
Sewage Flow Rate (Q) = 300 Lpm = 0.005 m³/s
Sewer Material = HDPE
Manning’s coefficient (n) = 0.012
Slope (S) = 6/1000 = 0.006
d/D ratio = 0.8 (to ensure flow under free surface conditions)
Manning’s Formula: v = 1/n R⅔ S1/2
Continuity Equation: Q = Av
Q partial = 300 L/m = 0.005 m3/s
R= A/P = D/4
For HDPE, D < 630 mm. Assume D =200 mm
R= 200/4 = 50 mm = 0.05 m
Pipe flowing full, Qf = Af Vf
Substituting for Vf in Manning’s Equation,
Qf = π (0.2)2/4 X 1/0.012 X (0.2/4) ⅔ (0.006)1/2
Qf = 0.0275 m3/s
QP /Qf = 0.005/0.275 = 0.182
From the table, interpolate the value for QP /Qf and find v/V
v/V = 0.75514
Solving, vf = 0.875m/s, v= 0.66 m/s
8) A wastewater treatment plant processes 3,550 m3/day of wastewater using an aerated
lagoon system. The influent BOD5 after primary clarification is 200 mg/L. The reaction
rate coefficient at 20°C is 0.35/day, and the operating temperature in summer is 35°C.
Assume a single-cell pond system with 85% removal efficiency of soluble BOD and a
pond depth of 2.0 m. The temperature coefficient (θ) is 1.06.
Find
1. Determine the surface area required for the aerated lagoon.
2. Calculate the total oxygen demand for BOD removal and nitrification.
3. Compute the power consumption per day, assuming an oxygen transfer efficiency of 1
kg O2 per 1 kWh.
Solution:
Given Data:
𝑘𝑇 𝑇−20
𝑘20
= ∅
𝑆 1 1
𝑆0
= 𝑉 = 1+𝑘θ
1+𝑘 𝑄
Solving for θ,
θ = 8. 12 𝑑𝑎𝑦𝑠
V = Q *θ
V=3,550×8.12
V = 28,826.2 m3
A= V/ H = 14,413.1 m2
BOD removed:
O2=603.5 kg/day
O2 total=603.5+653.2=1,256.7 kg O2/day