TI Checklist_V5_QOS sites
TI Checklist_V5_QOS sites
Site ID:
Site Name:
Site Type:
Date of Check:
IMPLEMENTATION IP
S.N.
RAN Devices
Mandatory IMPLEMENTATION IP RAN Devices Implementation OK NOT OK N/A Reference(Guideline) REMARKS
11 Cabling Implementation
The cables are bound well.
12 Cabling M The cables have no obvious damage or break. Implementation
13 Cabling M The redundant Power cable is Labled 1 & 2 Implementation 1 for main and 2 redundant
14 Cabling Implementation
The Grounding cable is Labled
15 Implementation
Cabling M The LAN cable is Labled
16 Cabling M The Fiber cable is Labled With Link Direction Implementation
17 Cabling M ODF to ATN patch cord shoulde be Oudoor patch or kept inside spiral for indoor Implementation
18 Power Connectivity Power Connectivity Implementation 1.2.3.1, Pg-82
19 Power Connectivity M Redundant power connectivity is provided to the IP RAN devices Implementation
Power connectivity is done as per the design requirement and connected to critical
20 Power Connectivity M Implementation
LVD
Proper rating of MCB/Air switch/Fuse and specification is used for power
21 Power Connectivity M Implementation Ncell Standard should be followed
connectivity
22 Power Connectivity M Redundant power connectivity is working properly Implementation
Optical Power Will be application as per scope of
23 Optical power should be in range as per threshold defined for different category. Implementation
Confirmation work
Optical Power Will be application as per scope of
24 Error ( CRC-Error) in Optical ports should be clear . Implementation
Confirmation work
REMARKS:
Site ID:
Site Name:
Site Type:
Date of Check:
S.N. IMPLEMENTATION BTS Mandatory IMPLEMENTATION BTS Implementation OK NOT OK N/A Reference(Guideline)
INSTALLATION M The racks shall be connected with their bases firmly. Implementation 3.2 Pg. 109
3
33 ASSEMBLY,LABEL AND OTHERS Labelling should be done as per labelling guideline Implementation Labelling guideline
The equipment room shall be clean and orderly, and
34 ASSEMBLY,LABEL AND OTHERS wastes such as packing boxes shall be removed. The Implementation General standard
spare parts shall be placed tidily.
35 HARDWARE TEST RECORD HARDWARE TEST RECORD Implementation
36 BTS BOARD TEST M Implementation
37 BTS BOARD TEST M Implementation
38 BTS BOARD TEST M Implementation
39 BTS BOARD TEST M Implementation
40 BTS BOARD TEST M Implementation
41 SLOT TEST M Implementation
42 SLOT TEST M Implementation
43 SLOT TEST M Implementation
44 SLOT TEST M Implementation
45 SLOT TEST M Implementation
REMARKS:
REMARKS
Pre-approval from PM
required if dummy is
not available for
Reuse equipment
installed board
should be mention
in D column and all
Alarm should be
clear while checking
in EMS/U2000
MW installation Primary Check List
Site ID:
Site Name:
Site Type:
Date of Check:
Reference
S.N. IMPLEMENTATION MICROWAVE SYSTEM Mandatory IMPLEMENTATION MICROWAVE SYSTEM Implementation OK NOT OK N/A Remark
(Guideline)
1 CATEGORY DETAILS Implementation
2 Antenna installation M Antenna must be stable and firm. Implementation 4.2.1
The spacing of main antenna and diversity antenna must meet the
3 Antenna installation Implementation 4.2.1
requirements of project design.
The antenna must be installed within the protection range of the
4 Antenna installation M Implementation 4.2.1
lightning rod.
Link ID, Polarization and Azimuth must be mentioned at the
5 Antenna installation M Implementation 4.2.1
backside of antenna.
For 1.2m or higher antenna, the additional supporting rod must be
6 Antenna installation M Implementation 4.2.1
used and properly tighten to protect from the wind.
7 Antenna polarity mode M Verify whether the antenna is single-polarized or dual-polarized. Implementation 4.2.1
Record antenna diameter and frequency, at the same time, verify
whether they meet design requirements or not.
8 Antenna diameter and frequency M Implementation 4.2.1
For dual-polarized antenna, record the frequency of each polarity
direction
Verify the antenna is horizontal-polarized or vertical-polarized in
9 Polarity direction of single-polarized antenna M polarity direction. Implementation 4.2.1
(Do not apply to dual-polarized antenna.)
ODU/ODR installation position complies with project design
10 ODR installation M Implementation 4.2.1
requirements. Take care of polarization direction.
Joint point with ODR and cable must have good contact and covered
12 Outdoor Cable Installation M Implementation 4.2.2
gland with water-proofing tapes.
The routing of cables must be tidy without crossover, twist or
13 Outdoor Cable Installation M Implementation 4.2.2
damage. Use a fastener to fasten the lines every 1.2m.
14 Outdoor Cable Installation M Attach labels of "Link ID" to both extremities of cable Implementation 4.2.2
POE/PI must be installed as per supplier design. Cables must be
15 POE/PI Cabinet installation M Implementation 4.6
routed properly
IP address and Link ID details must be sticked in POE/PI in printed
16 POE/PI Cabinet installation M Implementation 4.6
form
POE/PI must be installed in sunshade/mounting bracket/side of rack
17 POE/PI Cabinet installation M Implementation 4.6
with metallic tie/plastic tie.
Outdoor Power & ethernet cable should be grounded and
18 POE/PI Cabinet installation M cut/opening portion should be shiled & taped as per product Implementation Product spec
specification.
Propoer grounding of ODR in tower's busbar and POE/PI in the
19 Checking grounding system M Implementation 4.3
cabinet's busbar with Lugs must be done
The ground wiring in equipment room must meet the requirements of
20 Checking grounding system M Implementation 4.3
project design.
Both work ground and protection ground must use wires of a whole
21 Checking grounding system M piece, yellow-green wires as per supply. Multiple connections are Implementation 4.3
not allowed.
Each ground line from the grounding bus is connected with only one As per Availabilty of
22 Checking grounding system Implementation 4.3
set of equipment. busbar holes
The grounding point must be in good contact without looseness, and
23 Checking grounding system M Implementation 4.3
anti-oxidation measures must be taken.
Proper labeling of link must be attached in cables connected to POE
24 LAN cable connection M Implementation 4.2.2
and IPRAN boxes
The DC power supply is connected to the power terminal on a rack,
25 Power line installation M Implementation 4.5
with the anode and cathode connected correctly.
The copper lugs of power lines must be used & it must be firm and
26 Power line installation Implementation 4.5
upright.
MW and IPRAN system must be connected to BLVD or LLVD
27 Power line installation M Implementation 4.5
system to retain transmission live at lower voltage
MCB rating & specification should be as per installation
28 Power line installation M Product spec
specification & Ncell standard
29 Power line installation M Power lines and signal lines must be separated. Implementation 4.5
IPRAN Cables lines, power lines and cat5 cables
30 Power line installation M Implementation 4.5
are all correctly labeled.
31 Hardware damaged or not M All hardware equipments and modules are in good condition. Implementation 4.1
32 Cables connection M All cables are connected correctly. Implementation 4.1
33 TEST RECORD TEST RECORD Implementation
DC power test with IPRAN device, MW POE with LED glow after
34 Power Supply Test M Implementation 4.7
connection
35 Test operation & maintenance functions Parameter setting function with snaphot to be taken Implementation 4.7
36 Test operation & maintenance functions System monitoring functions Implementation 4.7
37 Test operation & maintenance functions User management function Implementation 4.7
38 Test operation & maintenance functions Log query function Implementation 4.7
39 System performance test M Transmission power test Implementation 4.7
40 System performance test M Receiving signal level performance table/graph Implementation 4.7
41 System performance test M Transmission frequency record Implementation 4.7
42 System performance test M Receiving frequency record Implementation 4.7
43 Local Access test Local login from defined port of ATN Implementation
REMARKS: