Pmp@Qta@Lesson 3
Pmp@Qta@Lesson 3
LESSON 3
PMI® AUTHORIZED
PLAN THE PROJECT
• Planning Projects
• Scope
PMP® • Schedule
• Resources
• Budget
EXAM PREP COURSE • Risks
• Quality
• Integrate Plans
1
11/5/2024
Planning Projects
TOPIC A
What is Planning
In the context of the Project Management Institute (PMI) and project management,
Planning refers to the process of defining the project's objectives and determining the most effective
course of action to achieve those objectives.
Planning is one of the five process groups in the PMI's Project Management Body of Knowledge (PMBOK).
2
11/5/2024
What is Plan
الخطة عبارة عن اقتراح تفصيلﻲ أو مخطط تفصيلﻲ لكيفية تنفيذ مجموعة معينة
إنها وثيقة منظمة تعمل بمثابة. من اﻷنشطة أو المهام لتحقيق هدف أو غرض محدد
وكيف، ومتى يجب القيام به، توﻓر إرشادات حول ما يجب القيام به،خريطة طريق
. ومن سيكون مسؤوﻻً عن كل مهمة،سيتم القيام به
Project Plan
In the context of project management,
a project plan is a comprehensive document that outlines the entire
scope of a project and details the approach that will be taken to
execute it successfully.
This includes information on project objectives, scope, schedule,
budget, resources, quality standards, risk management,
communication strategies, and other relevant aspects.
تعد خطة المشروع وثيقة شاملة تحدد النطاق الكامل،ﻓﻲ سياق إدارة المشروع
للمشروع وتوضح بالتفصيل النهج الذي سيتم اتباعه لتنفيذه بنجاح
يتضمن ذلك معلومات حول أهداف المشروع ونطاقه والجدول الزمنﻲ والميزانية.
والموارد ومعايير الجودة وإدارة المخاطر واستراتيجيات اﻻتصال والجوانب اﻷخرى
ذات الصلة
3
11/5/2024
أسلوب تخطيط تكراري يتم من خﻼله التخطيط للعمل الذي سيتم إنجازه على المدى القريب
بينما يتم التخطيط للعمل اﻹضاﻓﻲ ﻓﻲ المستقبل على مستوى أعلى،بالتفصيل
4
11/5/2024
BASELINES
Scope baseline
Schedule baseline
Cost baseline
5
11/5/2024
Project
Documents
*وثائق المشروع
Documentation and content created by the team to plan and manage the
project effectively
12
6
11/5/2024
Collaborative
Planning
Product owner decides objectives according to customer
Adaptive and needs/wants; team executes work and helps product
Hybrid owner plan the work
Development
Approaches
Team members are local domain experts in integration
management — how work will be planned and completed
14
7
11/5/2024
Stakeholder
At specific milestones Regularly Continuously
Involvement
16
8
11/5/2024
Topic Coverage
Differentiation of planning in
predictive and adaptive
approaches
17
Scope
TOPIC B
18
9
11/5/2024
Click me!
Scope
PROJECT
SCOPE
can be defined as the range, detail, or a boundary of a term it is attached to
PRODUCT
SCOPE
Product scope
is about the product details. Product scope defines what the product will look like,
how will it work, its features, etc.
FIXED
. وما إلى ذلك، وميزاته، وكيف سيعمل،يحدد نطاق المنتج الشكل الذي سيبدو عليه المنتج. يتعلق بتفاصيل المنتج
FLEXIBLE
is the work required to create the product. It also defines what is in the scope and
whatnot, which helps you avoid scope creep.
. مما يساعدك على تجنب زحف النطاق،كما أنه يحدد أيضًا ما هو موجود ﻓﻲ النطاق وما هو غير ذلك. هو العمل المطلوب ﻹنشاء المنتج
19
10
11/5/2024
Product Roadmap*
• Envisions and plans the “big picture”
• Displays product strategy and direction
and the value to be delivered
• Leads with the overarching product
vision and uses progressive elaboration
to refine vision
• Uses themes (goals) to provide structure
and associations
• Provides short-term and long-term
visualization
11
11/5/2024
Milestones
العﻼمات المرجعية للمنتج او المشروع
• Markers for big events, reviews, due
dates, payments or decision-making
• Prompts for reporting requirements or
sponsor/customer approval
• Created by project managers, customers
or both
A milestone list identifies all milestones
and indicates which are:
• Mandatory - required by contract, or
• Optional (estimated on historical
information)
23
Scope Planning
24
12
11/5/2024
Project Planning
Create WBS—The process of subdividing project deliverables and project work into smaller,
more manageable components.
Monitoring &
Validate Scope—The process of formalizing acceptance of the completed project deliverables. Controlling
13
11/5/2024
Define Scope—The process of developing a detailed description of the project and product. Scope Statement
نطاق المشروع
Create WBS—The process of subdividing project deliverables and project work into smaller,
more manageable components.
Scope Baseline
الخط المرجعى للمشروع
Validate Scope—The process of formalizing acceptance of the completed project deliverables. Accepted Deliverables
التسليمات المقبولة
Scope Planning
Comparison of Processes
PRODUCT OWNER مالك المنتج
• Creates and refines release backlog for
PROJECT MANAGER مدير المشروع iteration planning meeting
• Facilitates the Collect Requirements • Explains each prioritized user story in
Process detail to the team
• Documents requirements in a:
• Scope statement (text/document) TEAM ﻓريق العمل
• Work breakdown structure (WBS) – • Estimates effort required and creates the
(visual) iteration baseline, selecting stories to meet
the expected velocity for the iteration.
• Develops schedule, budget, resource and
quality plans to deliver requirements • Places user stories from product backlog
into release backlog to support identified
features and functions
What might a hybrid scope • Uses a story map to sequence and
planning process look like? prioritize user stories in the release
backlog
28
14
11/5/2024
Scope • Review of the scope activities for the project and how that work will be
Management done
Plan* • Should include processes to prepare a project scope statement
• Enables the creation of the WBS from the detailed project scope
statement
• Establishes how the scope baseline will be approved and maintained
• Specifies how formal acceptance of the completed project deliverables
will be obtained
• Can be formal or informal, broadly framed or highly detailed
29
Requirements
• A requirement is one single measurable statement of a condition or
المتطلبات capability.
• It tells how a product, service or result satisfies a business need.
What Are They and
Why Do We Need المتطلب هو بيان واحد قابل للقياس لحالة أو قدرة على التنفيذ
Them? .ﻓهو يوضح كيف يلبﻲ المنتج أو الخدمة أو النتيجة احتياجات العمل.
30
15
11/5/2024
Document Requirements
قائمة متطلبات المشروع
• A simple format — e.g., a document
listing all requirements, categorized
by stakeholder and priority, OR
• More elaborate — e.g., executive
summary, detailed descriptions,
attachments
• Requirements traceability matrix
• قائمة تتبع المتطلبات
31
Types of Requirements
Type Describes the...
Features and characteristics of the product, service or result that will meet the business
and stakeholder requirements
Product • Functional – Product features
• Nonfunctional - Supplemental environmental conditions/qualities that make the product
effective
Transition/
Temporary capabilities needed to transition successfully to the desired future state
Readiness
32
16
11/5/2024
Collect
Requirements • Expert Judgment • Data Analysis
Process • Interpersonal/Team Skills • Document analysis
• Nominal group technique • Alternatives analysis
• Observation • Product analysis (if
deliverable is a product)
• Facilitation
• Decision-Making Techniques
• Data Gathering
• Voting
• Brainstorming
• Multi-criteria decision
• Interviews
analysis
• Focus groups
• Questionnaires and surveys • Data Representation
• Benchmarking • Mind mapping
• Affinity diagram
• Context or use case diagram
• Prototyping — e.g., storyboarding
33
34
17
11/5/2024
Now, assign weights to each criterion based on their importance. Let's say the weights are:
•Functionality: 40%
•Cost: 30%
•User-Friendliness: 30%
Example : out of PMP exam
Now, calculate the weighted scores for each software by multiplying the scores by the corresponding weights
and summing them up.
After calculating the total weighted scores for each software, you can compare them and make an
informed decision based on the criteria and their respective weights. The software with the highest
total weighted score is the most suitable choice according to the given criteria.
18
11/5/2024
Data Gathering
تجميع البيانات
Use Benchmarks to generate product requirements
• Requires best practices to make comparisons
• Evaluates and compares an organization’s or project’s practices
with others
• Identifies best practices in order to meet or exceed them
37
Represent Data
19
11/5/2024
HARDWARE, SOFTWARE
AND SUPPORT EDUCATIONAL SERVICES
EDUCATION
COMMUNITY
40
20
11/5/2024
Prototyping
النماذج اﻻولية للمنتج
• Evaluation and experimentation tool
• Enables early feedback for further
development and to develop a detailed
list of project requirements
• Storyboarding is a type of prototyping
that uses visuals or images to illustrate a
process or represent a project outcome.
41
42
21
11/5/2024
44
22
11/5/2024
MoSCoW
The MoSCoW prioritization
scheme, which was
popularized by DSDM,
derives its name from the
first letters of the following
labels:
Must have
Should have
Could have
Would like to have, but no t this time
Kano Model
23
11/5/2024
Project Scope
Statement
بيان نطاق المشروع Includes –
Once it has been approved and baselined, changes are only permitted
in accordance with the change management plan.
48
24
11/5/2024
Scope Planning
Create WBS
50
25
11/5/2024
Decompose Work
in the WBS
Steps:
تقسيم اﻻعمال 1. Identify deliverables and the
work/tasks needed to
Divide and subdivide the accomplish them
المهام الﻼزمة/تحديد التسليمات والعمل .1
project scope and 2. Structure and organize the WBS ﻹنجازها
deliverables into smaller, WBS هيكلة وتنظيم .2
more manageable parts 3. Decompose high-level WBS scope
components into low-level عالية المستوىWBS قم بتحليل مكونات نطاق .3
components إلى مكونات منخفضة المستوى
تطوير وتعيين رمز تعريف ﻓريد لكل مكون من .4
4. Develop and assign a unique رمز الحسابات
identification code to each قم بمراجعة تحليل حزم العمل والتحقق من .5
component from the code of تواﻓقها مع متطلبات المشروع
accounts
5. Review the decomposition of work
packages and verify that they align
with the project requirements
51
DMAIC Project
11/5/2024 52
26
11/5/2024
11/5/2024 54
27
11/5/2024
11/5/2024 55
11/5/2024 56
28
11/5/2024
WBS Dictionary
قاموس هيكل تجزئة العمل Decompose work and include:
• WBS code identifier
• Description of work
Provides detailed
• Assumptions and constraints
deliverable, activity
and scheduling • Responsible organization
information about • Schedule milestones
each component in • Associated schedule activities
the WBS
• Resources required to complete the work
يوﻓر معلومات مفصلة عن التسليم • Cost estimations
والنشاط والجدولة حول كل مكون • Quality requirements
WBS ﻓﻲ • Acceptance criteria
• Technical references
• Agreement information
57
29
11/5/2024
Scope Baseline • Approved version of a scope statement, WBS and its associated WBS
dictionary, that can be changed only using formal change control
الخط المرجعى للنطاق procedures
والتﻲ يمكن تغييرها ﻓقط باستخدام،المرتبط بهWBS وقاموسWBS ،• النسخة المعتمدة من بيان النطاق
إجراءات التحكم ﻓﻲ التغيير الرسمية
Components include:
59
Project Planning
30
11/5/2024
التحقق من النطاق هو عملية إضفاء الطابع الرسمﻲ على قبول مخرجات المشروع المكتملة
الميزة اﻷساسية لهذه العملية هﻲ أنها تضفﻲ الموضوعية على عملية القبول وتزيد من نسبة قبول.
المنتج النهائﻲ أو الخدمة أو النتيجة من خﻼل التحقق من صحة كل تسليم
61
DMAIC
Project
1.0 2.0 3.0 4.0 5.0
Decomposition Define Measure Analyze Improve Control
Project Scope
31
11/5/2024
32
11/5/2024
Don’t Forget to
Plan for Include activities to fulfill transition/implementation in the scope of work
• Consider all stakeholders, schedules, risks, budgets, and quality
Transitions / standards.
Handovers! • Identify deliverables/outputs
These can be delivered throughout the project, not just at the end!
Questions to consider:
• Will the work be new, or an update in the business
environment?
• How best to transition the product into a live environment?
• What about decommissioning or removing old systems,
processes or materials?
• Did you ensure training and knowledge transfer are
complete/satisfactory?
65
Plan Scope Management—The process of creating a scope management plan that Scope Management Plan
documents how the project and product scope will be defined, validated, and controlled.
Define Scope—The process of developing a detailed description of the project and product. Scope Statement
Create WBS—The process of subdividing project deliverables and project work into smaller,
more manageable components.
Scope Baseline
Validate Scope—The process of formalizing acceptance of the completed project deliverables. Accepted Deliverables
33
11/5/2024
11/5/2024 67
68
34
11/5/2024
Release and
Iteration
Planning Collaborative planning meetings that break scope into larger releases and
then iterations/sprints
Planning also At release planning ( عمليات اطﻼقor Agile release planning), decide:
takes place at • Number of iterations or sprints needed to complete each release
the standup • Features contained in the release
meeting when • Goal dates of each release
teams discuss
At iteration planning (تخطيط شوط او سبرنتor sprint planning):
details of work
in progress. • Review the highest prioritized user stories or key outcomes
• Ask questions
• Agree on effort required to complete the user story in the current
iteration
• Determine the activities required to deliver iteration objectives
69
A release schedule
usually lasts from 3-6
months.
Time-boxed iterations
or sprints typically last
1 - 4 weeks.
70
35
11/5/2024
• Adaptive Planning
Overview
Project Team
Project Manager
Product Owner
مالك المنتج Or Scrum Master
مدير اﻻسكرام Team
مدير المشروع ﻓريق العمل
Team
ﻓريق العمل
Product Owner
مالك المنتج
Project Manager
Or Scrum Master
مدير اﻻسكرام
مدير المشروع
36
11/5/2024
Backlogs
Example:
• Prioritized list of the
known scope of work A product owner creates a product backlog and identifies and adds
• Information presented stories in collaboration with the team and stakeholders. Work items
in story form describe desired product functionality through user stories.
• Continually updated • The product owner is responsible for prioritizing work according to
by the product owner value.
in collaboration with
teams • The product owner and team collaborate to move work items to the
iteration/sprint backlog.
73
37
11/5/2024
User Stories
A user story is a short, informal description of a software feature or requirement
written from the perspective of a user or customer. It is used in agile software
development to communicate the product backlog and to help the team
prioritize and plan their work.
A user story typically includes the following elements:
As a [user type] - Who is the person or role that will be using this feature?
I want - What does the user want to do?
So that - What is the benefit to the user?
FEATURE
A set of related requirements that allows the user to
satisfy a business objective or need.
EPIC
A large body of work that can be broken down into smaller
pieces—features and user stories. Epics can take months
to complete.
38
11/5/2024
Product Owner
مالك المنتج
39
11/5/2024
EPIC
EPIC
a major deliverable
FEATURE FEATURE
Delivers a capability that Groups related
can be estimated, tracked functionality together
USER STORY
and managed as a set to deliver value
FEATURE
Includes activities and efforts such as documentation,
bug fixes, testing and quality/defect repairs
79
MVP or MBI?
Planning for Work
Incrementally
80
40
11/5/2024
أصغر مجموعة من الميزات التﻲ يمكن تضمينها ﻓﻲ المنتج ليعتبرها العمﻼء مقبولة و تحقق
. الحد اﻷدنى المقبول من تنفيذ المنتج
It’s useful to understand what possibilities you have for creating an MVP. There are six
main ways to use the concept.
1. Software Prototypes
A prototype of a piece of software is one of the most complex, yet most common,
types of MVPs. It requires building software with just the core components.
2. Product Designs
There are a few different ways to use product design as an MVP, all of which are
especially useful for software, mobile apps, and other tech tools. The most simple is
a sketch, which you can do by hand or using a tool. Slightly more complex is a
wireframe, which will show things like user experience, hierarchy, and navigation.
Finally, you have a mockup, which can demonstrate exactly how your product will
work.
3. Demo Videos
Through a demo video, you explain what your product will do. Showing the video to
potential users allows you to see if it’s the kind of solution the market is looking for.
41
11/5/2024
Prioritize and
Refine the
Backlog
84
42
11/5/2024
Backlog Reprioritization
Product Owner
مالك المنتج
Project Manager
Or Scrum Master
مدير اﻻسكرام Team
مدير المشروع ﻓريق العمل
86
43
11/5/2024
Remem ber
Scope
Management Study Tips for
Final Exam
44
11/5/2024
Lesson 3: Scope
A product owner is invited to a sprint review meeting. At the end of the review, the product owner says that the
increment is ready to be delivered to the customer. What conclusion should the project manager come to with
regard to the product owner's statement?
A
1 The product owner will release the product to customers without showing them a demo
B The product owner does not have visibility into what the team has done in the product increment
C The product owner trusts the team and is marking the product as complete.
D The product owner has evaluated the product against the definition of done(DoD)
90
45
11/5/2024
Lesson 3: Scope
A company must implement a new regulation. The government has specified the date when the
regulation will be enforced but has only provided
high-level information on the regulation's requirements. Therefore, changes in definitions are to be
expected due to uncertainty.
Which life cycle should the project manager use for this project?
91
Lesson 3: Scope
In the initiating phase of a project, the project manager and team members are prioritizing the
product backlog along with the product owner.
What should the project manager do next?
A Produce a value-added product for the customer in each phase of the project.
3
B Produce a value-added product for the customer as continuously as possible.
C Produce a value-added product for the customer in the beginning of the project.
46
11/5/2024
Lesson 3: Scope
A project to implement a new online lending platform has started. After the first sprint, the project sponsor
requested a change. What should the project manager do next?
A
4 Validate the work completed
93
Lesson 3: Scope
A company is struggling to define the scope of a new project that has multiple phases with a high level of
dependency between the phases.
A Contract with a third-party company that specializes in helping businesses define scope of work on large
5 projects.
Work with project stakeholders to recommend an iterative approach that will then help to define the
B
project's scope.
C Construct a project management plan that provides extra time within the schedule, then seek to revise
the scope of work.
Suspend final delivery dates for the project in order to have time to revise the schedule once there is
D
clarity on the scope of work.
94
47
11/5/2024
Lesson 3: Scope
A project manager is working with a customer who repeatedly submits new feature requests for an
existing software product.
The project manager has already provided the completed scope definition for the product's next version
release to stakeholders.
Which step is appropriate for the project manager to take next?
A Hold a meeting with the product manager to request that the number of new requests be reduced.
6
B Define project boundaries immediately with the sponsor.
D Analyze the scope management plan and iterate it through the scope definition process.
95
Lesson 3: Scope
During an iteration demo, a customer noticed an enhancement they would like to make to the product.
What should the team do next?
A
7 Start working on the enhancement for the customer immediately
C Ask the product owner to prioritize the item with the customer
96
48
11/5/2024
ECO Coverage
97
49
11/5/2024
Schedule
TOPIC C
10
0
50
11/5/2024
• Resource overallocations are resolved • Works with product owner to refine the
backlog after each iteration and plan
• Schedule is compressed to meet any the next
constraints
101
Project Planning
51
11/5/2024
Schedule Planing
Plan Schedule
01 Management
02 Define Activities.
Planning
Schedule
03 Sequence Activities
05 Develop Schedule
52
11/5/2024
105
Benchmarking
• Compares current project schedule with
a similar product/service schedule
• Provides a good “starting point” for
estimation before detailed analysis
• Assesses feasibility in the initial stage of
scheduling
Historical data
Learn lessons from completed projects in
the organization
53
11/5/2024
Predictive
Schedule
Planning
The project manager:
• Breaks down a work package into the required activities
• Determines dependencies and precedence relationships
• Estimates the duration of activities based on average resources
• Determines the critical path
• Resolves resource overallocations
• Compresses the schedule, if needed, to meet constraints
107
Define Activities
54
11/5/2024
109
Top of WBS
1.0
Project name or
Project Name
primary deliverable
•Break Down
Control Account
schedule to compare to EV
1.1.2
Planning Package
Works needed further plan
Integrate scope, budget, and
schedule to compare to EV
Project
Planned works
Activities
1.1.1 1.1.2.1
Group scheduled and
Work Package Work Package
estimated activities
Activity
Activity
Activity
55
11/5/2024
Activity
Dependency DEPENDENCY TYPES
Types
Meaning Action by Project Manager
اﻻعتماديات بين Contractually required or
Must schedule it — No way
اﻷنشطة Mandatory inherent in the nature of
around this sequence
the work
Established because of Can be modified as needed,
best practices or a if replaceable with a better
Discretionary
specific sequence is sequence, or if schedule
desired compression is required
Activities performed
External outside the project team’s Limited or no control
work
In project work,
Internal Has control
contingent on inputs
111
Precedence
Relationships ARROW INDICATES WHICH
DRIVES THE OTHER
112
56
11/5/2024
ACTIVITY A ACTIVITY E
ACTIVITY C ACTIVITY D
ACTIVITY F ACTIVITY E
ACTIVITY D ACTIVITY F
113
ACTIVITY C
ACTIVITY F
114
57
11/5/2024
Activity
Duration
Estimate
Terminology Activity Duration Estimate المدة الزمنية لﻼزمة ﻻتمام العمل
• The quantitative assessment of the likely number of time periods
required to complete an activity
Effort
• The number of labor units required to complete a scheduled activity or
WBS component, often expressed in hours, days, or weeks; contrast
with duration
115
Estimating Techniques
116
58
11/5/2024
FORMULA FORMULA
E = (O + M + P) / 3 E = (O + 4M + P) / 6
• Optimistic = 3 weeks
• Most Likely = 5 weeks • Optimistic estimate = 3 weeks
• Pessimistic = 10 weeks • Weighted most likely estimate = 5 weeks
• Pessimistic estimate = 10 weeks
EQUATION
EQUATION
(3 + 5 + 10) / 3 = 6 weeks
[3 + 4 (5) + 10] / 6 = 5.5 weeks
117
تقدير الحد اﻷدنى لمدة المشروع وتحديد مقدار مرونة الجدول الزمنﻲ على مسارات الشبكة
المنطقية ضمن نموذج الجدول الزمنﻲ
59
11/5/2024
DEFINITION
Any activity on the critical path in a project schedule.
ACTIVITY 1 ACTIVITY 6
Sequence mandatory START
6 WEEKS 1 WEEK
FINISH
critical path activities to
find the longest path
through a project and to
ACTIVITY 3 ACTIVITY 5
determine the shortest 5 WEEKS 4 WEEKS
possible project
duration and the amount
of flexibility in the
schedule
1[6w] + 2[4w] + 4[3w] + 6[1w] = 14-weeks
120
60
11/5/2024
Activity
Node Activity Node
Float
• Float: The amount of time an activity can be delayed from its ES without delaying
the project finish date or the consecutive activities.
Activity 2 Activity 4
4 weeks 3 weeks
2 weeks
float
Activity 1 Activity 6
Start Finish
6 weeks 1 week
Activity 3 Activity 5
5 weeks 4 weeks
61
11/5/2024
Total Float
• Total float* The amount of time that a schedule activity can be delayed or
extended from its early start date without delaying the project finish date or
violating a schedule constraint.
( ﻓﺘﺮة الﺴﻤاح الكلية ) الﺘﻲ يﻤكن للﻨﺸاط ان يﺘأخﺮها دون تأخﺮ الﻤﺸﺮوع
• TF= ( LF – EF ) = ( LS – ES )
Free Float
• Free float* The amount of time that a schedule activity can be delayed
without delaying the early start date of any successor or violating a
schedule constraint.
ﻓترة السماح الحر التﻲ يمكن ﻓيها أن يﺘأخﺮها الﻨﺸاط دون تأخﺮ الﺒﺪاية
• الﻤﺒكﺮة للﻨﺸاط الﺘالﻲ A B
• FF = ES.B – EF.A
0 2 2 14 14 19
A B C
0 2 2 14 14 19
0 0 19 19
(0) (0) (0) Finish
Start
6 Days 7 Days 3 Days 19 19
0 0
0 6 6 13 13 16 (0)
Float = (0)
D E F
3 9 9 16 16 19
62
11/5/2024
The Project
Schedule
125
Schedule
Presentation
Formats
Select the type of schedule to suit your project!
صور تقديم الجدول
الزمنى
• Roadmap
• Gantt Chart
• Milestone Chart
• Project Schedule Network Diagram
126
63
11/5/2024
Gantt Chart
Visualize and Track the Project Over a Time Line
127
Milestone Schedule
Present Milestones with Planned Dates
30 Begin Phase 1
31 Deliverable A
32 Deliverable B
33 Phase Gate Review
34 Begin Phase 2
35 Deliverable C
36 Deliverable D
37 Phase Gate Review
64
11/5/2024
129
Resource Smoothing
Optimization • Adjusts the activities within predefined resource limits and within free
and total floats
• Does not change the critical path nor delay the completion date
• Method may not be able to optimize all resources
• يﺴﺘخﺪم اﻻسﺘغﻼل اﻷمثل للﻤوارد لﺘعﺪيل تواريخ بﺪاية ونهاية اﻷنﺸطة لﺘعﺪيل اﻻسﺘخﺪام الﻤخطط
للﻤوارد لكﻲ يﺘﺴاوى مع مﺴﺘوى توﻓﺮ أو قلة الﻤوارد
Levelling
• Adjusts start and finish dates based on resource constraints
• Goal is to balance demand for resources with available supply
• Use when shared or critically required resources have limited
availability or are over-allocated
• Can change the critical path
130
65
11/5/2024
Schedule
Compression
Techniques
Fast-tracking
• Perform activities in parallel to reduce time
• May result in rework, increased risk and increased cost
Crashing
• Shortens schedule duration for the least incremental cost by adding
resources – e.g., overtime, additional resources
• Works only for activities on the critical path
• Does not always produce a viable alternative and may result in
increased risk and/or cost
132
66
11/5/2024
11/5/2024 133
Schedule Baseline
*الخط المرجعى للجدول الزمنى
• Complete schedule planning activities
• Add the schedule baseline to the project
management plan
Ideally, this happens before the project
starts.
• Compare actual progress to the baseline
while the team works
• Use the formal change control process to
make changes to the baseline
134
134
67
11/5/2024
Special Intervals
Negotiate how and when required scheduled “down” time intervals will
take place
135
68
11/5/2024
Schedule
Management in
Adaptive
Environments
• Depends on team composition and life cycle
Guidelines • Project team works with the product owner to decide
• Develop the roadmap to show release functionality and timeframes
• Choose an approach:
• Time-boxed scheduling with backlog
• On-demand, continuous scheduling
• Project team selects activities for delivery within an iteration (or
sprint)
• Teams produce increments of value for delivery and feedback
137
138
69
11/5/2024
Agile Release
Planning MOST
IMPORTANT
Sequence of features needed in release
Story Mapping
Priority of user stories by feature
• Group stories by
sequence and priority
• Sequence features and
functions for the release
• Prioritize user stories in
the release backlog and
associate them with
features and functions
LEAST
IMPORTANT
70
11/5/2024
A release schedule
usually lasts from 3-6
months.
Time-boxed iterations
or sprints typically last
1 - 4 weeks.
Story Point
141
Relative sizing
• Compares effort of multiple user stories through assignment of values (XS, S, M, L, XL)
Story points
• Uses a relative measure – e.g., numbers in the Fibonacci
sequence – to identify the level of difficulty or complexity of
a user story or task
Planning poker
• Estimates effort or relative size of development effort
• Uses a deck of cards with modified Fibonacci numbers to vote on user stories
142
71
11/5/2024
T-Shirt Sizing
T-shirt sizing is a high-level estimating tool that is used to do the
initial estimates of the product features and user stories during
the initiation stage of a project.
Planning Poker
The card game that makes estimation simple and
collaborative for software teams.
72
11/5/2024
Definition of
Ready (DoR)*
Agile teams need to know when they can be “ready” to do the work and
and when that work is “done.”
Definition of
Done (DoD)* DoR - What needs to be in place so the team can begin work?
• Depends on the environment’s complexity and lessons learned from
past iterations.
• Use DoR checklist to communicate and collaborate with stakeholders
about readiness for work or progress.
145
73
11/5/2024
Reprioritize
Sprint / Iteration The product owner and team collaborate to move work items from a
release backlog to an iteration/sprint backlog for the upcoming sprint.
Backlog*
Team holds a sprint planning meeting before each sprint, which
typically lasts 2 weeks.
2-week interval
ITERATION 1
Sprint
ITERATION 2
...
Feedback
planning Backlog
Prioritization
Sprint
planning
147
Hybrid
Scheduling
Models
Project manager plans high-level project phases and milestones; scrum
Example master runs sprints using agile processes
• Identify project work types and try to break them down
• Create a prioritized work backlog which fulfils project phase or
achieves milestone
• Work in iterations/sprints of 2 - 4 weeks (use shorter sprints for less
Can you identify which
experienced team to facilitate alignment)
aspects of this
scheduling model are • Plan work before every iteration using prioritized backlog items
predictive and which are
adaptive? • Estimate every task to decide how many can fit in a single sprint
Can you identify who • Hold a retrospective at the end of every sprint; capture metrics to
does each of the tasks adjust timing and task estimate for next sprint
listed?
148
74
11/5/2024
Remem ber
Schedule
Management Study Tips for
Final Exam
75
11/5/2024
Lesson 3: Schedule
A project manager is working on a data center migration project and is developing the schedule management
plan . Per the project sponsor's request, the schedule must plan for all tasks as soon as possible. Additionally,
the project manager is presented with possible network paths that will not violate schedule constraints.
The project manager needs to select the appropriate leads and lags relationship for this situation.
Which type should the project manager choose?
76
11/5/2024
Lesson 3: Schedule
A project manager primarily works on implementation projects. Depending on the deliverable, the project
manager is able to estimate the timeline based on previous projects. The project manager now receives a project
that is different from the previous implementation projects. What should the project manager do next?
A Break down the project into smaller tasks and estimate the durations of the activities.
B Ask the project management office (PMO) by when the project can be completed and use that date as the project timeline.
C Refer to the previous project they worked on and base the estimate on that.
D Use expert judgment to estimate the schedule and then adjust the schedule as the project progresses.
153
Lesson 3: Schedule
The project charter was just approved and the project sponsor has given permission to proceed with the project. The
program manager has confirmed that one of the requested key resources is also needed on another project at the same
time. This will affect project delivery. What should the project manager do?
A Pay overtime to key resource to get the work done outside of working hours
B Have a meeting with project manager of the other project to find a resource optimization solution that works for both projects
C Talk to the program manager and about prioritizing this project over other projects so the key resources are available
D Speak with the client to see if the project delivery deadline can be delayed due to resource availability
154
77
11/5/2024
Lesson 3: Schedule
During an iteration, a project team encounters problems that may cause a delay in task completion.
Another team within the same project needs the task to be completed on time in order to meet their
schedule.
A Insist that the project team work a bit harder to complete on time, in order to avoid delaying the work of
other teams.
B Work with the product owner to reprioritize the iteration backlog, so that it does not delay work by other
teams.
C Increase the iteration length, and add additional resources to the project team, so that they can meet the
appropriate deadlines.
D Ask team members to perform to the best of their abilities during the iteration, and engage in a
retrospective after completion of the iteration.
155
Lesson 3: Schedule
A Finish-to-start (FS)
B Finish-to-finish (FF)
C Start-to-start (SS)
D Start-to-finish (SF)
156
78
11/5/2024
ECO Coverage
157
11/5/2024 158
79
11/5/2024
Resources
TOPIC D
Resources
People and Equipment
160
80
11/5/2024
Project Planning
81
11/5/2024
Assign
Resources and • Assign team members to project تعيين أعضاء الفريق للمشروع •
Allocate تحديد اﻷدوار والمسؤوليات •
Responsibilities • Decide roles and responsibilities
إنشاء دليل الفريق والمخطط التنظيمﻲ •
• Create team directory, organization والجدول الزمنﻲ
تعيين الموارد وتخصيص
chart and the schedule
المسؤوليات
Project schedules, resource assignments and budgets are all
interrelated and can be created at the same time
إن جداول المشروع وتعيينات الموارد والميزانيات كلها مترابطة ويمكن إنشاؤها ﻓﻲ نفس الوقت.
Use Resource
Calendars*
• Document resource availability (people, equipment, material, etc.)
*استخدام تقاويم الموارد during a planned activity period.
• Specifies when, and for how long, identified team and physical
resources will be available during the project
82
11/5/2024
Resource Calendars
Responsibility
Assignment RESPONSIBLE • Performs work to complete the task or create the deliverable
Tools A team member • Every task has at least one responsible person
83
11/5/2024
Adaptive
Resource
Planning
Quiz
Which of these are true? (Choose several)
84
11/5/2024
85
11/5/2024
Procurement
Documents • Statement of Work (SOW): Details of work required
Bid and Proposal • Request for quotation (RFQ): Bid/tender or quotation, including only
Activities cost
وثائق المشتريات • Invitation for Bid (IFB): Buyer requests expressions of interest in
work
Formal
Procurement
Processes
RFPs, Bidder
Conferences Organizations in highly regulated industries or government
Or, if a project needs specialist work or wants to find the best quality
available.
86
11/5/2024
Source Selection
Criteria* • Overall or life-cycle cost
87
11/5/2024
Contracts*
Contracts:
Negotiate
Productive • Legalize working agreements
Relationships • Give structure to working relationships
• Further collaboration with partners
• Consider risks associated with contract types
• Deliver benefits to the buyer - different benefits by type
• Can be tailored for the partnership
DETERMINATION
REQUEST PROPOSAL CONTRACT
OF NEED
Involves payments (cost reimbursements) to the seller for all legitimate actual
Contract Types costs incurred for completed work, plus a fee (seller profit)
(1 of 3) Cost plus • Reimburses seller for all allowable costs for performing contract
fixed fee work; fixed-fee payment calculated as a percentage of the initial
(CPFF) estimated project costs.
• Fee amounts do not change unless the project scope changes.
Cost-reimbursable Cost plus • Reimburses seller for all allowable costs for performing contract
contracts - For projects incentive work; predetermined incentive fee based for achieving contract-
with expected, significant fee (CPIF) specified performance objectives.
scope changes • Shares costs between buyer and seller if final costs are less or
greater than the original estimated costs
• Bases cost sharing on a pre-negotiated cost-sharing formula —
e.g., an 80/20 split over/under goal costs
Cost plus • Reimburses seller for all legitimate costs
award fee • Bases majority of fee on satisfying subjective performance criteria
(CPAF) defined and incorporated into the contract
• Determines fee based on buyer’s assessment of seller
performance and not subject to appeals
88
11/5/2024
Contract Types
(2 of 3) Firm fixed price Price of goods set at beginning; won’t change unless scope
(FFP) changes
Fixed price • Gives buyer and seller flexibility
incentive fee • Allows for deviation from performance — i.e., financial
Fixed-price contracts – (FPIF) incentives tied to achieving agreed-upon metrics (cost,
schedule, awesomeness)
sets a fixed total price
• Sets price ceiling; any further costs charged to seller
for a defined product,
service, or result; used Fixed price
when requirements are with economic
well defined and price
no significant scope adjustments
• Allows for special provisions for predefined final adjustments to
changes are expected. (FPEPA)
the contract price — e.g., inflation, cost increases (or
decreases) for specific commodities
Pre-approved
vendors or
international
payments
Contract Types
(3 of 3)
89
11/5/2024
Components of
Contracts
• Description of work - deliverables and scope
• Delivery date and schedule information
• Identification of authority, where appropriate
• Responsibilities of both parties
• Management of technical and business aspects
• Price and payment terms
• Provisions for termination
• Applicable guarantees and warranties
• Intellectual property
• Security, confidentiality, data privacy
ECO Coverage
90
11/5/2024
Remem ber
Resources
Management Study Tips for
Final Exam
91
11/5/2024
Lesson 3: Recourses
A new development project is about to start, and the project manager knows that a high-proof customer
makes very specific and frequent requests in all sprints. This project will demand contract coordination
with third parties, and the project manager must find a better way to manage customer and partner
expectations. What strategy should the project manager use?
A
1 Work very closely with the customer and third parties to meet their needs
C
Specify the scope and features to be deployed in the contract clearly
D Change the marketing and product management definitions to meet stakeholder needs
184
92
11/5/2024
Lesson 3: Recourses
An organization imports many of the materials for a product build. Due to global shipping delays,
some of the essential materials have yet to arrive, resulting in the inability to finish building the
product for the upcoming release. The project manager is meeting with stakeholders to discuss
options. What should the project manager recommend?
A
2 Update the project management plan, factoring in furloughs of the assembly team to reduce expenses
C Request marketing to launch an advertising campaign for the product that IS currently in stock
185
Lesson 3: Recourses
A company's PMO has been trying to implement an adaptive approach and a project manager
has been asked to use adaptive tools in their next project. This is not the first time the request
has been made, and the previous project failed when adaptive tools were implemented. What
should the project manager do?
A
3 Bring third-party company to develop and implement a hybrid framework for this specific project.
B Prepare a change request and seek approval from the steering committee regarding the new project framework.
C Recommend to the PMO that it’s not the right time to start implementing adaptive tools in projects.
D Conduct individual interviews with key stakeholders in order to understand all concerns then prepare a communication management plan.
186
93
11/5/2024
Lesson 3: Recourses
A project manager is made aware that there are defects in the parts provided by a supplier, which are
causing delays in the testing phase. The supplier claims that all parts have been delivered as per the
contract. If the defects are not fixed by the supplier within one week, the product release will be
impacted. What should the project manager do?
A
4 Review the procurement contract and ask the supplier to negotiate a solution.
B Escalate this issue to senior management, as the supplier is not following the procurement contract.
C Request a revision of the procurement contract to include specifications for the parts
D Request a cancellation of the procurement contract with the supplier and impose a penalty
187
94
11/5/2024
Budget
TOPIC E
Project Planning
95
11/5/2024
Budget Planning
Overview
Create budget in accordance with project life cycles:
Begin with fixed budget and amend with change control process
Consider:
• Cost as well as value
• Organization and Hybrid approaches add adaptability around surety
stakeholder attitudes
towards budget and
costs
Use burn rate
Predictive Budget
Planning • Create a cost management plan
• Employ estimating techniques to assign costs to activities
• Tailor a cost baseline
• Is used to monitor and measure cost performance throughout the
project (compares with actual results)
• Includes budget contingencies to address identified risks
• Can be changed only through formal change control procedures
هو مجموع. BAC (أعلى نقطة على خط اﻷساس للتكلفةBAC) تعد الميزانية عند اﻻكتمال
. أو قيمة إجمالﻲ العمل المخطط له،جميع الميزانيات الموضوعة
96
11/5/2024
Check with
Organization
Funding Limit
Reconciliation
• Compare planned
project expenditure
against funding limits
• Align
work/expenditures on
the schedule to level
the rate of
expenditures
Historical Data
Start with What’s Known
• Check lessons learned repository for
budgets, estimates from previous,
similar projects or data from the last
iteration
97
11/5/2024
Resource Costs
Estimate Costs
Estimate the cost for each activity or work Expecting the scope to change?
package in a project.
Use lightweight estimation methods for
Cost estimates should include: high-level estimating.
• Direct labor
• Materials
• Equipment
• Facilities
• Services
• Information technology
• Contingency reserves
Use:
• Rough order of magnitude (-25 to +75%)
• Definitive Estimate (-5 to +10%)
• Phased estimate
98
11/5/2024
Estimating Techniques –
Advantages and Disadvantages
197
Project Budget
• Include contingencies
to support risk
management
99
11/5/2024
Examples
• Focus on short-term budgeting and • Estimate budget based on current data, plus a forecast
metrics versus long-term algorithm that is based on historic data or expert guidance
— e.g., lean or Kanban
• Set time periods for work and
prioritize work within those time • Use a “top-down” approach, using gross-level estimation
periods. techniques such as planning poker and affinity grouping on
feature sets, then employing progressive elaboration and
• Base cost on the resources used for
rolling-wave planning methods to drill down to the task level
that time period
on a just-in-time basis (iteratively)
ECO Coverage
100
11/5/2024
Remem ber
Budget
Management Study Tips for
Final Exam
101
11/5/2024
A company is planning to utilize a new product that leverages innovative technologies and processes.
The project manager has verified that the component work packages have been defined, and constraints for each
Lesson 3: Cost
A Analogous
1
B Three-point
C Bottom-up
D Parametric
204
102
11/5/2024
Lesson 3: Cost
A project manager is leading a project which shows a trend to exceed the cost baseline.
What should the project manager do first to manage the budget?
A
2 Meet with the project team to analyze the actual cost to determine deviations
B Inform the stakeholders that the project will be finished over budget
C Ask the project sponsor for assistance in getting the budget back on track
205
Lesson 3: Cost
A project manager has taken over an existing project According to the previous project manager, the project is
on track and within budget, However, stakeholders are unhappy with the recent progress report since the
metrics show that the project is delayed and the cost is higher than expected.
What should the project manager do?
A
3 Conduct an earned value analysis (EVA)
206
103
11/5/2024
Risks
TOPIC F
208
104
11/5/2024
Project Planning
Risk
An uncertain event or condition that, if it
occurs, has a positive or negative effect
on one or more project objectives.
11/5/2024 210
105
11/5/2024
Positive (opportunities).
مخاطر ايجابية – فرص
Risk
Negative (threats).
مخاطر سلبية – تهديدات
Risk
Identification
11/5/2024 212
106
11/5/2024
Risk
TRIGGER CONDITION
Conditions of
Uncertainty
01 An event or situation that indicates
that a risk is about to occur.
OPPORTUNITY
02 A risk that, if developed, would create a
positive effect on one or more project
objectives.
THREAT
03 A risk that would have a negative effect
on one or more project objectives.
ISSUE
04 A current condition or situation that may
have an impact on the project objectives.
213
Risk appetite:
A degree of uncertainty that your organization is willing to
take on in anticipation of a reward.
Some organizations might take a high risk if the reward is high;
others may want to play it safe or be conservative.
If they take risks, it means that their risk appetite is high,
and the organization that play conservatively has a low-risk appetite.
11/5/2024 214
107
11/5/2024
Risk Appetite
Tolerance to risk is
proportional to the
amount of money at
stake Prefers an uncertain
Not likely to take a
outcome and may be
risk that is
willing to pay a
considered a high penalty to take a high
risk risk
(Financial markets,
IRR, Interest, ROI)
Risk Threshold
11/5/2024 216
108
11/5/2024
Trigger Condition
An event or situation that indicates that a risk is about to occur.
حدث أو موقف يشير إلى أن الخطر على وشك الحدوث
Project Management:
•Example: In project risk management, a trigger condition could be set to activate a contingency plan if
a key team member leaves the project unexpectedly. The trigger condition is: if key team member
resigns
217
218
109
11/5/2024
Project Risks
SLC Examples
Project Risks
219
Create Risk
Strategy
How would you describe the Management Guidelines
organization/ project’s risk • Use qualitative (high, medium,
appetite? low, etc.) or quantitative
(numerical) ratings
• Risk-seeking?
First, understand risk • Risk-neutral? • Set a maximum risk exposure
parameters for the • Risk-averse? level that can be managed
organization and the without escalation
project! The risk threshold is tied to
individual and organizational risk
appetites. Do you know:
• Which are too high to accept?
• Which are low enough to just be
accepted?
• What criteria determines
inclusion in the risk register?
220
110
11/5/2024
Define/Refine
Risk Set initial risk strategy, then define In the plan:
Management and refine it! • Risk strategy
Approach • Methodology
Factor in project characteristics: • Roles and responsibilities
• Size • Funding
• Complexity • Timing
• Importance • Risk categories
• Development approach • Stakeholder risk appetite
• Definition of risk probability and
impact
Create a risk management plan!
• Probability and impact matrix
• Reporting formats
• Tracking documents
221
Identify Risks—
The process of identifying individual project risks as well as sources of overall project risk,
and documenting their characteristics.
Monitor Risks—
The process of monitoring the implementation of agreed-upon risk response plans, tracking
identified risks, identifying and analyzing new risks, and evaluating risk process effectiveness
throughout the project.
11/5/2024 222
111
11/5/2024
Risk
Identification Data Gathering and Analysis
Techniques
تحديد المخاطر • Risk breakdown structure (RBS)
• Brainstorming
• Nominal group technique
• SWOT analysis
Use a prompt list to
evaluate the external • Affinity diagram
environment for risks.
• Assumption analysis
• Document review
• Delphi technique
• Monte Carlo simulation (larger organizations)
223
112
11/5/2024
Brainstorming
11/5/2024 225
Root-cause analysis
Root-cause analysis helps to identify additional, dependent risks.
The identified risks may be related because of their common root causes.
Root-cause analysis can be the basis for development of preventive and comprehensive
responses and can serve to reduce apparent complexity.
SWOT Analysis
11/5/2024 226
113
11/5/2024
Delphi technique
Uses a facilitated anonymous polling of subject matter experts to identify risks in their
area of expertise.
The facilitator gathers the experts' initial responses and circulates them without
attribution to the entire group
The group members may then revise their contributions based on those of others.
Designed to gather information and build consensus without requiring face-to-face
meetings.
Delphi technique to gather all stakeholder opinions.
11/5/2024 227
Expert judgment
Expert judgment is the contribution provided to risk identification based on expertise .
Historical Information
Historical records and data from past projects, programs, and portfolios help to identify
common risks and prevent repeating mistakes.
Interviews
Interviewing experienced project, program, or portfolio participants, stakeholders, and subject
matter experts can identify risks. Interviews are one of the main sources of risk identification data
gathering.
11/5/2024 228
114
11/5/2024
Questionnaire
Questionnaire techniques encourage broad thinking to identify risks; however, it
requires quality questions to be effective.
Prompt lists
Prompt lists enumerate risk categories with the purpose of detecting the most relevant to
the project, program, or portfolio.
11/5/2024 229
Risk
Classification
Approaches Schedule Cost Quality Scope
230
PMI® Authorized PMP® Exam Prep Course – PM. Khaled Abo Ali , PMP , PMI- ACP
115
11/5/2024
Risk
Classification
Approaches Internal External Technical
Non- Industry-
Generic
technical Specific
231
Assess Risks
Qualitative then
Quantitative
232
116
11/5/2024
VERY HIGH >70% >6 months >$5m Very significant impact on overall functionality
MEDIUM 31-50% 1-3 months $501k - $1m Some impact in key functional areas
233
1 2 3 4 5
PROBABILITY
VERY LOW
(LIKELIHOOD)
• Use numeric values 1 1 2 3 4 5
and/or colors
LOW
• If using numbers,
multiply them to give 2 2 4 6 8 10
a probability impact
MEDIUM
score – this makes
evaluating relative 3 3 6 9 12 15
priority easier!
HIGH
4 4 8 12 16 20
This is NOT a VERY HIGH
quantitative 5 5 10 15 20 25
evaluation.
234
117
11/5/2024
Risk Register*
Risk Score
Risk Impact Impact Level Probability Planned
(probability and Trigger Condition Owner
Description Description Score Level Score Response
impact multiplied)
What will
(IMPACT X
happen if the Rate Rate
PROBABILITY) What indicates the Who’s
risk is not 1 (LOW) to 1 (LOW) to Action plan
Address highest risk will occur. responsible
mitigated or 5 (HIGH) 5 (HIGH)
first.
eliminated
Supply chain
Supplier
issues for 5 1 5 L. De Souza
notification
correct bricks
Building code
5 2 10 Pre-checks fail K. Ayoung
compliance
Working with
new vendors
3 3 9 Delays or conflict K. Ayoung
and building
processes
235
Risk List
Probability Impact
Risk Magnitude
(1-10) (1-10)
• Working with new vendors and Teams can add (tailor)
5 6 30
building processes columns for:
• Supply chain issues for correct
5 10 50 • Owner
bricks
• Status
• Building code noncompliance 5 10 50
• Date identified
• Key stakeholder conflict (Josie
Bynoe) 4 6 24 • Date resolved
In addition to a risk list or a risk register, teams use information radiators and a
backlog refinement process with risks added, which are discussed at various
planning meetings.
236
118
11/5/2024
Quantitative Risk
Analysis Methods • Simulations - Use computer models to determine risk factors
237
Quantitative Risk
Analysis Methods Decision tree analysis
• Branches represent decisions or events, each with associated costs
(2 of 2) and risks
• The end-points of branches represent the outcome (negative or
positive)
• Simulations Influence diagrams
• Sensitivity analysis • Quality management graphical aid
• Decision tree analysis • Shows elements of uncertainty caused by risks using ranges or
probability distributions
• Influence diagrams
• Expected monetary Used when decision trees are too complex.
value (EMV)
238
119
11/5/2024
11/5/2024 239
4. Sensitivity Analysis
11/5/2024 240
120
11/5/2024
11/5/2024 241
11/5/2024 242
121
11/5/2024
Risk Response
Good Practice
Plan Risk
Response
Guidelines and • A trigger condition signals a risk can develop
Terminology
• Team implements a risk response
• Residual risk can remain after risk responses have been implemented
• The contingency reserve (or allowance) is the budget within the cost
baseline that is allocated for identified risks and their response
strategies
244
122
11/5/2024
TRANSFER SHARE
MITIGATE ENHANCE
ACCEPT ACCEPT
245
11/5/2024 246
123
11/5/2024
1. Escalation
is appropriate when a threat is outside of the portfolio, program, or project scope or when the
proposed response exceeds a given manager's authority.
Escalated risks are managed at the enterprise domain, portfolio domain, program domain, or
other relevant part of the organization.
11/5/2024 247
2. Risk avoidance
is when the portfolio, program, or project team acts to eliminate a threat
or protect activity from risk impact.
It may be appropriate for a high-priority threat with a high probability of occurrence and
a large negative impact.
Avoidance may involve changing some aspect of the management plan or changing
the objective that is in jeopardy in order to eliminate the threat impact entirely.
11/5/2024 248
124
11/5/2024
3. Transfer
involves shifting responsibility of a threat to a third party to manage the risk and to bear
the impact if the threat occurs.
Risk transfer often involves payment of a risk premium to the party taking on the threat.
Ex: Hire a licensed contractor to complete the work
11/5/2024 249
4. Mitigation
In risk mitigation, action is taken to reduce the probability of occurrence and/or impact of a threat.
■ Early mitigation action is often more effective than trying to repair the damage after the threat has
occurred.
Where it is not possible to reduce probability, a mitigation response might reduce the impact by
targeting factors that drive the severity.
11/5/2024 250
125
11/5/2024
5. acceptance
Risk acceptance acknowledges the existence of a threat, but no proactive action is taken.
Accept the risk When cannot outsource work nor eliminate the scope, cannot buy
insurance or mitigate the risk.
11/5/2024 251
11/5/2024 252
126
11/5/2024
1. Escalated
This risk response strategy is appropriate when an opportunity is outside the portfolio, program,
or project scope or when the proposed response exceeds a given manager's authority.
Escalated opportunities are managed at the program domain, portfolio domain, or other relevant
part of the organization. It is important that ownership of an escalated opportunity is accepted by the
relevant party in the organization.
2. Exploit
The exploit strategy may be selected for high-priority opportunities where the organization
wants to ensure that the opportunity is realized.
■ This strategy seeks to capture the benefit associated with a particular opportunity by
ensuring
that it definitely happens, increasing the probability of occurrence to 100%.
11/5/2024 253
3. Sharing
Sharing involves transferring ownership of an opportunity to a third party so that the third
party shares some of the benefit if the opportunity occurs.
It is important to carefully select the new owner of a shared opportunity to ensure capture of the
opportunity for the benefit of the portfolio, program, or project.
Risk sharing often involves payment of a risk premium to the party taking on the opportunity.
4. The enhance
The enhance strategy is used to increase the probability and/or impact of an opportunity.
Early enhancement action is often more effective than trying to improve the benefit after the opportunity
has occurred.
The probability of occurrence of an opportunity may be increased by focusing attention on its causes.
5. Acceptance
Accepting an opportunity acknowledges its existence, but no proactive action is taken.
This strategy may be appropriate for low-priority opportunities, and it may also be adopted
where it is not possible or cost effective to address an opportunity in any other way.
Acceptance can be either active or passive.
11/5/2024 254
127
11/5/2024
ECO Coverage
256
128
11/5/2024
Members of a project team are not taking their risk management responsibilities seriously.
They do not consider risk management as primary to the project's success and do not
believe that the benefits are significant. What should the risk manager do?
A. Motivate and in influence the project team with risk engagement activities like workshops
B. Ensure that the risk language used by all stakeholders is consistent with the risk
management plan
C. Schedule a meeting to review and develop realistic risk thresholds with the project team
D. Ensure that risk management responsibilities are clearly identified in the risk management plan.
11/5/2024 258
129
11/5/2024
A risk manager faces resistance as they try to implement the project's risk strategy.
Some members of the project team believe it is a waste of time and money. What
should the risk manager do?
11/5/2024 259
D. Accept the fact that there is a risk associated with this new technology
11/5/2024 260
130
11/5/2024
During a meeting to develop the risk management plan, the risk manager recognizes
that risks may be identified that could also impact other projects that the company is
pursuing. What should the risk manager do?
A. Contact the risk managers of the other projects and inform them
11/5/2024 261
The project manager and the risk manager o f a new project to develop an application to support
autonomous driving are meeting with the sponsor and key stakeholders to discuss the project.
During the meeting, it is identified that the transport authority is discussing new traffic regulations for
the industry that could be in place before the project ends. H ow should the project manager and the
risk manager handIe this situation?
B. Send a letter to the traffic authority with the general project information
C. Ensure the project complies with the current traffic regulations and laws
D. Meet with the traffic authority staff in charge of the new regulation
11/5/2024 262
131
11/5/2024
The project manager starts with developing the risk management plan.
What is the expected outcome of developing the risk management plan?
11/5/2024 263
What should be used to determine how often a project's risk register should be
updated or reviewed in a given year when the project is in an industry with a very
high business rhythm?
11/5/2024 264
132
11/5/2024
A risk manager of a major project facilitates a meeting to develop the risk management
plan. What two factors does the risk manager need to consider to ensure an effective
risk management plan is developed? (Choose two.)
11/5/2024 265
The project manager works with the project team to develop the risk handling
strategies for the Identified risks. How should the project manager work with these risk-
handling strategies?
11/5/2024 266
133
11/5/2024
The project manager for project X was expecting the mobilization of critical equipment from another
project, project Y. However, a day before the mobilization was scheduled, another project manager
notifies project X 's project manager that the equipment would not be available for at least another
month due to delayed activities for project Y. This has jeopardized meeting a critical milestone for
project X. How should project X 's project manager avoid this situation in the future ?
B. Request that the other project manager inform if any additional delays are expected
D. Ask the other project manager to officially confirm the new date in writing
11/5/2024 267
A. Risk mitigation
B. Risk avoidance
C. Risk acceptance
D. Risk transfer
11/5/2024 268
134
11/5/2024
A project manager is working on a construction project. Based on past experience, the project
manager identifies a nick that a supplier of a critical material may not deliver on time. The project
manager has already accounted for this risk in the risk management plan. If this risk materializes, the
project manager plans to procure the material from a different supplier. A potential risk in this plan is
that there may be differences in the material provided by the firs t and second supplier.
What type o f risk is this?
A. Secondary risk
B. Residual risk
C. Normal risk
D. Primary risk
11/5/2024 269
A project manager has determined that they cannot outsource work nor eliminate
the scope. They also discover that they cannot buy insurance or mitigate the risk.
What should the project manager do?
11/5/2024 270
135
11/5/2024
Quality
TOPIC G
27
2
136
11/5/2024
Project Planning
Quality
274
137
11/5/2024
Cost of Quality
(CoQ)
Money spent during project to avoid failure Money spent during/after project because
of failures
275
Stakeholder and
Customer
Expectations of
Quality PRODUCT/DELIVERABLE PROCESSES
276
138
11/5/2024
Compliance
Requirements
139
11/5/2024
Quality Example
De facto standards or Widely accepted and adopted Words are used widely in
regulations through use, but not yet. . .. groups, like slang or jargon.
279
Quality Metrics,
Checklists, and
Processes
Metrics measure desired quality attributes for your product or project
through testing, use of tools, processes.
Include a tolerance level that factors in what the customer will accept
and describe the desired quality level in the acceptance criteria and
DoD.
280
140
11/5/2024
Quality Methods
for Continuous
Improvement
Six Sigma (aka Lean Six Sigma) – DMAIC framework (Define, Measure,
Analyze, Improve, Control) – focus on removing waste
281
ECO Coverage
282
141
11/5/2024
Integrate Plans
TOPIC H
28
4
142
11/5/2024
Integrating Plans
An Important Step
Overall, the scope, schedule, budget, resources, quality and risk plans
must support desired outcomes.
285
Integrate Plans
At the end of the planning stage, combine all planning results
from knowledge areas.
286
143
11/5/2024
144
11/5/2024
ECO Coverage
289
End of Lesson 3
290
145