0% found this document useful (0 votes)
7 views

Shaurya Execution Plan

The SHAURYA Execution Plan outlines a timeline for various tasks from April 1st to April 16th, including infrastructure setup, material collection, and arena construction for shooting and events. Key activities include collecting materials starting April 9th, making the arena from April 12th to 16th, and preparing for staff club events from April 12th to 15th. Offline publicity efforts will continue until the exhibition.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
7 views

Shaurya Execution Plan

The SHAURYA Execution Plan outlines a timeline for various tasks from April 1st to April 16th, including infrastructure setup, material collection, and arena construction for shooting and events. Key activities include collecting materials starting April 9th, making the arena from April 12th to 16th, and preparing for staff club events from April 12th to 15th. Offline publicity efforts will continue until the exhibition.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

SHAURYA Execution Plan

Task/Work From To

Overall Infra 1st April 14th April

OT - Collecting Material 9th April onwards -

OT - Making Arena 12th April 15th April

Shooting - Collecting Material 9th April onwards -

Shooting - Making Arena 14th April 16th April

Documentary 1st April 15th April

Staff Club Events Prep


12th April 15th April
(Expo/Laser Tag, Flag Area,etc)

Offline Publicity 9th April Till Exhibition