PTR 01 Introduction
PTR 01 Introduction
Looking at structure of the electrical network we see that power transformers are an elementary asset in the network grid.
Their main role (besides others) is to step-up and step-down the voltage for transmission purposes. You can see the
importance of an uninterrupted operation as an unexpected breakdown can have a disastrous outcome. Furthermore power
transformers are not stock items readily available to power utilities in the event of a breakdown. Maintenance and revisions
have to be planned way in advance.
Depending on the insulation technology (resin-based or oil-based impregnation) you can see a list of common defects above.
The reason for all those defects will be discussed in detail at a later stage.
OLTCs may be found in high voltage windings and low voltage windings (mainly U.S.) and depends on customer
requirements. Most common reasons for problems are listed above which are discussed later.
Breakdowns of power transformers can have serious consequences such as hazardous fire (examples above) due to the
high temperatures and flammable components (e.g. insulation oil). Further damage in the substation can be a consequence
causing major damage and interruption of the energy supply.
First example reveals a breakdown of a low voltage winding in phase a1 / X1 after removing the high voltage winding of the
same phase. The defect could be detected earlier by performing winding resistance measurement.
Reasons for defects of the winding can be overvoltage's or high short circuit currents, which sometimes do not influence the
performance initially. Damaged areas (shorted or interrupted) cause higher losses in the winding and lead to an increase of
the oil temperature at this particular spot. This often have an influence on the cooling and insulating capability.
A mechanical breakdown caused a displacement of contacts and cracks in the OLTC compartment, which led to heavy arcing
in the tap changer, and ingress of dissolved gasses in the main tank which led to high gas concentration in the transformer
oil.
Thermal stress: The temperature rises in the case of overload. Many temperature shifts lead to premature aging of the
paper insulation and pressboard
Electrical stress: Besides nominal voltage the insulation is also stressed by over-voltage due to electrical faults
Ambient stress: Includes moisture, aggressive and reactive chemicals (gas, acids) and foreign particles (metal parts,
carbonized particles,...)
Mechanical stress: Short-circuit stresses on windings, transportation damage and seismic activities can lead to winding
deformation or collapse
Abstract: In this contribution the results of a failure data survey of 20 utilities in Germany, Swiss, Austria and the Netherlands
based on a newly developed questionnaire are presented. The investigated transformer population covers more than 23800
unit-years and reveals a failure rate of 0.3% for 110kV and 0.6% for 220kV and 380kV for major failures shows considerable
failure statistic for a transformer age below 30 years. Tap changer and windings are with one third each the main components
leading to major failures.
Continuous monitoring requires permanent installation of measurement setup often done with the commissioning of the
asset. Thereby permanent analyzation of parameter such as dissipation factor or partial discharge can prevent outages.
Threshold levels has to be set for a suitable alarming within time. Disadvantage: higher efforts and costs than for offline
testing or temporary monitoring.