Electrical Esimate Water Supplier Facility
Electrical Esimate Water Supplier Facility
Project Name:
HIBUNAWAN WATER PUMP & MACHINERY
Location: DIVERSION ROAD, HIBUNAWAN, BAYBAY CITY, LEYTE
ITEM: 1
DESCRIPTION: Conduits, Boxes & Fittings
1) QUANTITY 1.00 Lumpsum
OUTPUT
2) Name and Specification Quantity Unit Unit Price (PhP) Total Cost (PhP)
Electrical Rough-ins
20 mm.DIA. SCHEDULE 40, CONDUIT(PVC) PIPE 31.00 L 108.00 3,348.00
25 mm.DIA. SCHEDULE 40, CONDUIT(PVC) PIPE 77.00 L 163.00 12,551.00
75 mm.DIA. SCHEDULE 80, CONDUIT(PVC) PIPE 28.00 L 670.00 18,760.00
25 mm.DIA. SCHEDULE 40, LONG ELBOW (PVC) 34.00 PCS 27.00 918.00
75 mm.DIA. SCHEDULE 80, LONG ELBOW (PVC) 13.00 PCS 85.00 1,105.00
M 20 mm.DIA. LOCKNUT AND BUSHING (PVC) 32.00 PCS 10.00 320.00
A
T 25 mm.DIA. LOCKNUT AND BUSHING (PVC) 30.00 PCS 15.00 450.00
E
R 75 mm.DIA. LOCKNUT AND BUSHING (PVC) 2.00 PCS 65.00 130.00
I
A PVC SOLVENT 3.00 PCS 56.00 168.00
L
S
PULL BOX, TIE WIRE, SUPPORT AND HANGERS, PVC CUP 1.00 LOT 5,000.00 5,000.00
-
-
-
-
-
Total Materials Cost 42,750.00
3) Name and Capacity No. of Units No. of Hours Hourly Rate Total Cost (PhP)
E
Q
U
I
P
M
E
N
T Total Equipment Cost -
4) Designation of Personnel No. of Men No. of Hours Hourly Rate Total Cost (PhP)
-
L
A Electrician 2 40 81.25 6,500.00
B Unskilled Laborer 2 40 68.75 5,500.00
O
R
ITEM: 2
DESCRIPTION: Wires and Wiring Devices
1) QUANTITY 1.00 Lumpsum
OUTPUT
2) Name and Specification Quantity Unit Unit Price (PhP) Total Cost (PhP)
5.5 mm2 THHN/THW STRANDED COPPER WIRE 1.00 BOX 7,650.00 7,650.00
14 mm2 THHN/THW STRANDED COPPER WIRE 4.00 BOXES 19,350.00 77,400.00
250 mm2 THHN/THW STRANDED COPPER WIRE 168.00 METERS 2,248.00 377,664.00
2.0 mm2 THHN/THW(G) STRANDED COPPER WIRE 1.00 BOX 3,000.00 3,000.00
3.5 mm2 THHN/THW(G) STRANDED COPPER WIRE 1.00 BOX 4,950.00 4,950.00
5.5 mm2 THHN/THW(G) STRANDED COPPER WIRE 2.00 BOXES 7,650.00 15,300.00
2 POLE SAFETY BREAKER -30A 6.00 PCS 326.00 1,956.00
2 POLE SAFETY BREAKER -40A 16.00 PCS 339.00 5,424.00
UTILITY BOX 30.00 PCS 35.00 1,050.00
SQUARE BOX 3.00 PCS 35.00 105.00
ELECTRICAL TAPE 2.00 PCS 35.00 70.00
GROUNDING ROD 5/8 x 5FT WITH CLAMP 4.00 PCS 850.00 3,400.00
-
-
-
-
-
-
-
Total Materials Cost 412,919.00
3) Name and Capacity No. of Units No. of Hours Hourly Rate Total Cost (PhP)
E
Q -
U
I
P
M
E
N
T Total Equipment Cost -
4) Designation of Personnel No. of Men No. of Hours Hourly Rate Total Cost (PhP)
L
A Electrician 2 412 81.25 66,950.00
B Unskilled Laborer 2 412 68.75 56,650.00
O
R
ITEM: 3
DESCRIPTION: Power Load Center, Switchgear and Panelboards
1) QUANTITY 1.00 Lumpsum
OUTPUT
2) Name and Specification Quantity Unit Unit Price (PhP) Total Cost (PhP)
C.01 PANEL MDP: SINGLE PHASE PANEL WITH GROUND TERMINATION, BOLT-
1.00 SET 67,907.94 67,907.94
ON TYPE
, SURFACE MOUNTED, ENCLOSED IN NEMA 1 ENCLOSURE WITH 24 HOL -
MAIN: 300AT/300AF,2P,22KAIC,MCCB -
BRANCHES: -
14-60AT/100AF,2P,12KAIC,MCCB -
1-30AT/50AF,2P,12KAIC,MCCB -
5-30AT/50AF,2P,8KAIC,MCCB -
1-20AT/100AF,2P,12KAIC,MCCB -
1-20AT/100AF,2P,15KAIC,MCCB -
C.02 PANEL PP1: SINGLE PHASE PANEL WITH GROUND TERMINATION, PLUG-
IN TYPE 1.00 SET 13,253.88 13,253.88
3) Name and Capacity No. of Units No. of Hours Hourly Rate Total Cost (PhP)
E
Q
U
I
P
M
E
N
T
Total Equipment Cost -
4) Designation of Personnel No. of Men No. of Hours Hourly Rate Total Cost (PhP)
L -
A
Electrician 2 240 81.25 39,000.00
B
O
Unskilled Laborer 2 240 68.75 33,000.00
R .
Total Labor Cost 72,000.00
5)
6) TOTAL MATERIAL COST 691,830.82
7) TOTAL LABOR COST 207,600.00
8) SUBTOTAL 899,430.82
9) MARKED UP 71,954.47
10) TOTAL ESTIMATED COST 971,385.29
PREPARED BY : APPROVED BY :
PEE OWNER