0% found this document useful (0 votes)
8 views

HDBFS-Weekly Status update report - 19-July-21 to 25-July-21

The weekly project status report for the HDBFS FireEye implementation indicates that 80% of the project is complete, but a technical error prevented the successful integration of DC FireEye devices with the HDBFS network. The project remains on track, with no risks identified, and upcoming work includes the cutover of FireEye devices and knowledge transfer scheduled for the following week. All resources and timelines are being adhered to as per the agreed scope of work.

Uploaded by

Raj Khanna
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
8 views

HDBFS-Weekly Status update report - 19-July-21 to 25-July-21

The weekly project status report for the HDBFS FireEye implementation indicates that 80% of the project is complete, but a technical error prevented the successful integration of DC FireEye devices with the HDBFS network. The project remains on track, with no risks identified, and upcoming work includes the cutover of FireEye devices and knowledge transfer scheduled for the following week. All resources and timelines are being adhered to as per the agreed scope of work.

Uploaded by

Raj Khanna
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 4

WEEKLY PROJECT STATUS REPORT

HDBFS FW INTEGRATION MIGRATION AND START DATE OF


PROJECT NAME
PROJECT
20-May-21
FIREYE IMPLEMENTATION
PROJECT DATE OF STATUS
MANAGER
Ankur Dharia - Softcell Technologies ENTRY
25-Jul-21

PROJECTED DATE
PERIOD COVERED 19-Jul-2021 to 25-July-2021 OF COMPLETION POTENTIAL RISK

ON TRA

PROJECT STATUS THIS WEEK - 19-July-2021 to 25-July-2021


This week, HDBFS team and Softcell team went
ahead with the execution of bringing DC FireEye
devices inline with HDBFS network. But there was a
technical error and the activity could not be
completed. 80% of Project execution is now
over.All devices in DR are now cut off and in
OVERALL line with HDBFS network. In the coming week,
PROJECT ON TRACK SUMMARY once FIreEye team gives calender slot, FireEye team
STATUS will cut over and bring all DC devices inline and do a
thorough knowledge transfer to HDBFS team, along
with document submission. Once, FireEye devices are
inline, HA activity for Fortigate FW will be taken up
for execution.

MILESTONES
No milestones were acheved in this week.

WEEKLY
MILESTONES

PROJECT COMPONENTS

COMPONENT STATUS OWNER / TEAM NOTES

All resources assigned on the project are working as


RESOURCES ON TRACK Softcell
per the agreed SOW and timelines.

Project is progressing as per the agreed timeline


TIMELINE ON TRACK Softcell
agreed between Softcell and HDBFS.

The scope has been freezed and now there will not be
SCOPE ON TRACK Softcell any change in existing scope of Softcell deliverables
to client.

WORK ACCOMPLISHED / DELAYED

DATE DESCRIPTION OWNER / TEAM LOCATION

HDBFS team tried to bring DC FireEye devices inline


23-Jul-21 with the HDBFS network. But there was a technical Softcell/FireEye Remote- WebEx
glitch and the activity did not succeed.
RISKS AND ROADBLOCKS

RISK TYPE DESCRIPTION OWNER / TEAM FIX

There are no risks to the project as of today which


NO RISK / can lead to delay of execution or a road block which
can halt the project. Project is being executed as per Softcell/HDBFS Not applicable.
DELAY
the agreed timelines.

HIGHLIGHTS AND KEY TAKEAWAYS


HDBFS team decided to bring DC FireEye devices inline with the HDBFS network. But a technical problem prevented the GO live activity. Logs have
been shared with FireEye team for analysis.
HDBFS team to take help from FireEye team in the coming week for DC NX & SV cut-over. HDBFS to let FireEye know the dates in 2-3 week’s in
advance to assign a Consultant for cut-over & test cases.

UPCOMING WORK NEXT WEEK - 26-July-21 to 01-Aug-21

DATE STATUS DETAILS

Cutover of DC NX and SV FireEye devices and bringing it Inline with


27-Jul-21 ON TRACK HDBFS network.
Testing of FireEye device working, after successful cutover.
28-Jul-21 ON TRACK
Knowledge transfer on CM, NX and SV and Solution deployment report
31-Jul-21 ON TRACK submission to HDBFS team.
PROJECT START
DATE
03/04/2021