re
re
Purpose of visit:
1. To assess the existing site condition and evaluate its suitability for construction activities.
2. To verify the feasibility of protection pile depth and location.
3. To identify and address any potential obstruction prior to commencement of structural
work.
Observation:
1. The eastern side of the site is in close proximity to high tension tower exposing potential
risk to the foundation excavation and the erection of reinforcement in some grids.
2. The eastern side of the site is approximately one storey lower to adjacent land requiring
construction of shear wall upto the ground floor level with the basement 2.4 meters
below the actual road level.
Supporting Images:
Figure 1 The heap of old construction site as observed on Figure 2 The east side of proposed building showing high
northern site tension tower
Figure 3 The heap of soil excavation placed at western side Figure 4 The southside of proposed building showing high
of the site tension tower
Recommendation:
1. The site protection work can be optimized by reducing excavation depth from 3.075m to
2.4m below the road level.
2. This adjustment ensures a gentler ramp access while minimizing the need for extensive
protection works and reducing overall man hours.