SOP - Work at Height
SOP - Work at Height
Note: This standard is a reference for the safety precautions to be taken for work at height,
however a detailed method statement and job safety analysis submitted by the Contractor
performing the job to be reviewed in line to the project specific requirements considering
the associated hazards & risks before starting the activity at the project.
Contents
1. Scope and field of application
2. References
3. General definitions related to Height Work activities
4. Definitions used globally related to the persons involved in Height Work activities
5. Standards / Guidelines
5.1. Principles of Working at Heights
5.2. Identification of hazards and risk assessment
5.3. Planning and preparation
5.4. Working At Heights Protection Equipment
5.5. Special requirements
5.6. Execution
5.7. Inspection requirements:
5.8. Training
5.9. Other Situations
5.10.Fall protection Equipment
6. Management Systems
7. Fall arrest system checklist
2. References
2.1. OHSE manual – J001
2.2. OHSE Service Delivery Guidelines – J002
a. Scaffoldings
b. Confined Space Entry
c. Electrical safety
d. Façade activity
2.3. HIRA Master Document – K001
2.4. Relevant IS codes
5. Standards / Guidelines
c. The following hierarchy of control should be applied (in the order of preference)
when there is a need to work at height:
i) Eliminate the ‘Work at Height’ hazards.
ii) Reduce the risks to an acceptable level (through use of well designed and
engineered fixed platforms, ladders etc. or alternatively, through use of a
well-designed scaffold, as necessary)
iii) Use other required personal protective equipment (PPE) like a full body
safety harness
a. Guardrail System:
i) Installation of appropriate Guardrail System around the work area is
required for fall protection. Guardrail Systems must meet the following
minimum requirements:
ii) Top rail (handrail) must be minimum 1050 mm from the working surface.
Mid rails must be located at 525 mm (midway) between the top rail and the
working surface. Toe boards will be provided to prevent persons falling off
the working surface. Toe boards must be a minimum of 150 mm in vertical
height.
iii) Screens or paneling from the toe board to the mid or top rail will be required
when equipment or material is piled higher than the toe board and is
capable of being ejected from the working surface to the level below.
iv) Where gates or openings are required in the guardrail system to facilitate
material movement, personal fall arrest or restraint systems must be used.
v) Every floor opening including opening for temporary maintenance work, into
which any person can fall must be guarded by a standard guardrail system
or by a metallic grating duly fixed in position
ii) Shock absorbers are preferred to reduce the body injury by absorbing the
shock/impact arising in case of sudden fall. Anchor points for fall arresting
systems (including lifelines) must be capable of withstanding 2300 kg load
per person attached
iii) Safety nets are to be provided for protecting people below from human fall
and material fall. Hand tools used while working at height should be secured
to avoid free fall in case of accidental slippage.
iv) In general, a complete personal fall arrest system consists of three vital
components:
a) Anchorages
b) Body support
c) Connections
Figure: “ABC” of a personal fall arrest system – “A”: Anchorage, “B”: Body
Support, “C”: Connection.
c. Safety nets
Safety nets alone shall not be used as a fall protection system
i) All safety net systems shall meet the requirements of Indian Standard
(IS:11057- 1984)
ii) Safety net mesh openings shall have a maximum size of 10 cm x 10 cm and
be secured at each crossing to prevent elongation of the opening.
e. Cautionary Barricades
i) The barricades must be minimum 1.8 meter away from the edge of the
falling hazard (plastic tape & sign board). Barricading tape must be 750 mm
above the working surface
f. Protective Barricades
i) The barricades installed closer than 1.8 meter from the edge of the falling
hazard, must be hard barricade which can withstand 100 kg load / thrust
and free from sharp edges. Hard barricade shall have horizontal members at
525 mm and minimum 1050 mm respectively from the working floor with
adequate vertical supports. This provision can be considered by work
supervisor even for more than 1.8-meter distance if the situation so
demands.
ii) Barricades constructed with rope, chain or wire shall be provided with
warning sign.
h. Step Ladders
i) If working from a step ladder, with your feet less than 1.8 meter. above the
floor, use of fall protection equipment is not required, unless working
backwards, then fall protection is required.
ii) If working on a step ladder with your feet 1.8 meter or higher above the
floor, fall protection equipment shall be used. If no tie-off point is available,
the ladder shall be held by a second person to provide added stability.
Note: Fall protection (harness and lanyard) should always be attached to an
anchor point before tying off the ladder. It should be detached after untying
the ladder. If no tie off point is available, the ladder shall be continuously
held by a second person to provide added stability.
iii) When working from a ladder where harnesses are not being used, the
person on the ladder should avoid stretching to reach objects. A rule of
thumb is to not stretch so far that your belt buckle is outside the rails of the
ladder.
iv) Ladder shall not be used for jobs where leaning over ladder is required
v) 3- point of contact should be maintained i.e., 2 feet and 1 hand possible
i. Electrical Hazard
i) Insulated ladders to be used for working on electrical equipment
ii) Portable metal ladders and wooden ladders with metal reinforcements shall
be used only during de-energized conditions. Effective supervision shall be
provided if there is any proximate hazard of touching live electrical wire or
equipment is present.
iii) No metal ladders or wooden ladders with metal reinforcements should be
stored inside the electrical switchyards
j. Maintenance
i) Provision shall be made for routine inspection and maintenance of all
ladders. Broken or damaged ladders shall be promptly repaired or removed
and destroyed. Ladders ready for use should be tagged “Safe to use” on
green background while unsuitable ladders should be tagged “Not for use”
in red background.
n. Fixed Ladders
Permanently mounted ladder such as those on the side of buildings or
structures.
i) If working from a fixed ladder with your feet 1.8 meter or more above the
floor, tie-off is required. The fixed ladder may be used as a tie-off point.
ii) When a fixed ladder is being used by many people to access a work area (an
example would be for equipment / structure / vessel repairs during
maintenance or shutdown), consideration should be given to providing fall
protection equipment for the duration of that job.
iii) Fall protection is not required for normal day-to-day climbing of fixed
ladders.
o. Scaffolds
i) Fall protection is required whenever working from scaffolds 1.8 meter or
higher above the ground or floor level that have incomplete standard
handrails (1.1 meter) or standard mid-rails (0.6 meter) or is not completely
decked.
ii) Fall protection is required whenever working outside the plane of the
handrails or if working against the handrails with awkward body position.
Personnel shall not climb on, or work from, any scaffold handrail, mid-rail, or
bracing member and shall use ladders to get into the scaffold.
iii) On scaffolds of 3.6 meter (12 feet) or higher, fall protection shall be
considered for those climbing the scaffold ladder (based on number of
people on scaffold, number of climbs per day, etc.). Consideration should be
given to the amount of risk associated with installing the equipment versus
the risk involved in climbing the ladder without fall protection.
q. Lanyards
i) Lanyards shall be "Dacron" polyester rope or web material, or wire rope, and
shall be fitted with locking snap hooks. Use of other materials requires
approval from the Client.
r. Lifelines
i) Lifelines, if used, must be of sufficient strength to withstand the large forces
involved in falls. Lifelines are to be installed or modified only by Qualified
Installers. Lifelines shall be designed and installed so that they can support
2000Kg. per person. (This weight requirement refers to the thrust that
occurs in a fall. This must be load tested as required by IS code.) When more
than one person will be utilizing a lifeline simultaneously, the load allowance
requirement shall be qualified by a professional engineer with fall protection
systems expertise.
s. Self-retractable Lifelines
i) Self-Retractable lifelines can be used as a method of providing vertical
lifelines for ladders, scaffolds, etc.
ii) Self-retracting lifelines and lanyards that automatically limit free fall
distance to 600 mm or less shall be capable of sustaining a minimum tensile
load of 1350 Kg. applied to the device with the lifeline or lanyard in the fully
extended position.
Figure: An example of personal fall arrest system for roof works Structure
erection/ working on structures
Figure: Example of proper demarcation and travel restraint for worker during
temporary removal of edge protection
f. Confined Spaces
i) While working in confined space at height use of rescue harness and self-
retractable full body harness is a must.
Duration
Each permit shall identify the length of time for which it is valid. The permit shall
not last longer than the duration of the job. However, the permit must be
validated on shift basis.
g. Inspection of ladders
Type of Inspection Periodicity By Remarks
h. Inspection of Scaffolds
Type of Inspection Periodicity By Remarks
5.8. Training
a. All personnel who work at height must be initially given practical training on the
use of fall protection devices. Client / Contractor should work with the suppliers /
vendors of fall protection equipment’s to set up practical training sessions,
including demonstration on the proper use and storage.
b. Each project must also identify members for a rescue team and ensure that
appropriate practical training is provided to the rescue team members on a pre-
determined frequency decided by the project.
6. Management Systems
6.1. Management Records
a. Site Work permits and audit checklists records shall be retained for two years or
till the completion of the project, whichever is later.
b. Records to be maintained are as follows:
i) Periodic Inspections of full body harness with double lanyard for 6 months.
ii) Periodic Inspections of fall arresting devices for 6 months.
iii) Periodic Inspections of safety net for 6 months.
iv) Periodic Inspections of Man basket, Man lift, scissor lift’, Goods cum
passenger lift, Single/Twin Mast working Platform for 3 years.
v) Inspection records of various types of ladders for 6 months.
vi) Training of persons for working at height for two years