Unit_3
Unit_3
Electric vehicles (EVs) are increasingly deployed and may become the main private
and public transportation mode in many countries in the future. This is the result
of the clean energy programs promoted by many governments all over the world
to deal with climate change, where incentives are offered for low- or zero-carbon
emission vehicles to reduce the greenhouse gas emission from the road transport
sector. Such incentives encourage automakers to increase EV production capacity.
Following widespread deployment of EVs, it is envisaged that EV charging may
become a dominant load in the power grid due to the high power required to charge
the EV battery, particularly when EVs can be charged whenever they are parked at
home or in parking lots. In such a scenario, the grid may experience an unpredict-
ably large variation in the load demand that can lead to various technical issues, such
as voltage regulation, harmonic contamination, and frequency variations. These will
bring significant challenges to the operation and management of the power utili-
ties. Therefore, to keep up with the increasing penetration of EVs, the distribution
grid needs to be upgraded to increase its capacity to meet the new demand from
EV charging. Unfortunately, such upgrades will take time and will slow down the
deployment of EVs.
This chapter presents the solution of using solar photovoltaic (PV) and an energy
storage unit to mitigate the effects of the high impact of EVs in all levels of charging
from Level 1 to Level 3 of the EV charging system. The chapter is organized as fol-
lows: Section 6.1 presents an overview of the EV charging configurations. Section 6.2
presents the solution for mitigating the effects of high penetration of EVs with the
Level 1 and Level 2 charging system. Section 6.3 proposes the solution for mitigat-
ing the effects of EVs with the Level 3 charging system. Conclusions are drawn in
Section 6.4.
Australia
164 Cable based and wireless charging systems for electric vehicles
EV charging systems are increasingly being installed in public areas to facilitate the
widespread use of EVs in the public domain [1, 2]. However, the high penetration of
EVs can bring undesirable impacts on the distribution grid [3–7]. These may bring
unexpected challenges for the power utilities for the operation and management of
the grid system. Therefore, EV charging systems are continuously being improved
to keep up with the increasing penetration of EVs. According to the charging stand-
ard [8], the maximum power at Level 1 and Level 2 charging is 19.2 kW. However,
the power rating of a Level 1 portable charging cable that can be plugged directly
into an electric power point is normally far lower than the standard maximum power
allowable at Level 1, which is about 1–2.4 kW, which can comply with the maxi-
mum current rating of standard power points (10 A) in residential homes, offices, or
shopping centers. Level 3 charging refers to a dc charging system that has a charging
power rating ranging from 30 kW up to hundreds of kW.
device in place of a power diode [9, 15]. However, the lack of isolation in them
results in difficulty to achieve high power transfer. To solve this issue, a DAB is a
suitable converter as it has a high-frequency transformer acting as an isolator. This
makes it able to achieve high power and bidirectional power flow. However, the
control of DAB is more complicated because of the required high-computational
algorithm [18, 19].
To control the charging procedure, electric vehicle service equipment (EVSE)
is needed. The EVSE will have the function of turning on/off the ac power from
the grid when the electric vehicle battery (EVB) gets fully charged and provide a
charging fee or bill. The dc power in the dc link can also be used to supply the elec-
tronic loads in the car through the dc-dc converter denoted as (1) in Figure 6.1. The
off-board charger is a Level 3 dc fast charger and is located in the charging station.
The converter of the off-board charger, denoted as (5) in Figure 6.1, is a high-power
dc-dc converter, which can be a multilevel converter or a cascaded converter. The
converter denoted as (6) in Figure 6.1 is a three-phase PFC rectifier or a bidirectional
converter that not only can charge the EV batteries but also can send power back to
the grid.
The integration of Level 1 and Level 2 EV charging into the home solar PV (EVC-
HSP) system is shown in Figure 6.2. The power transfer between the HSP system
and EV battery is implemented based on a power conditioning system (PCS), which
consists of three power converters sharing a dc bus. The charging dc connector is
based on the CHAdeMO standard as it allows EVB to be interfaced with the dc
bus of the HSP system via a power dc-dc converter named EVB converter. The PV
converter is deployed by a power boost converter to track the maximum power point
(MPP) of the HSP system. The grid converter (GC) is implemented by a full-bridge
converter to interface with the grid. It is noted that a conventional HSP system con-
sists of a PV converter and GC. In this configuration, the GC is a unidirectional
166 Cable based and wireless charging systems for electric vehicles
converter that only injects the generated HSP power into the grid. However, in the
ECV-HSP configuration, the GC is a bidirectional converter where the power can
be transferred back and forth from the grid. By adding an EVB converter into the
dc bus of the conventional HSP system, the ECV-HSP system is formed. The EVB
converter is a unidirectional converter or bidirectional converter. If the EVB gets
charged only from the HSP and grid, it can be designated as a unidirectional Boost
converter. If the EVB has a function of supporting the grid, it can be designated
as a bidirectional Buck/Boost converter. The output of the EVB converter is con-
nected to the CHAdeMO connector. The mechanism of the handshaking signals of
the CHAdeMO is presented in Figure 6.3. A control board is used to control the
power flow of the EVC-HSP system. With this control mechanism, the effective
power management of the EVC-HSP is obtained.
Mode I: The EV is on the road and the home load is low. This mode may happen
at any time during the daytime when people drive the EVs for doing their day-to-day
works. The generated HSP power directly injected into the grid is given by (6.1),
where is the efficiency of the PCS, Pg is the grid power, and Ppv is the PV power:
Pg = Ppv (6.1)
Mode II: The EV is charged from the HSP power. Depending on the pre-defined
ref
maximum charging power, the EVB charging power reference PEVB is calculated
according to (6.2) with the constraints of the maximum EVB state-of-charge
(SoCmax).
8̂
1 max
ˆ
< Ppv if Ppv k PEVB , SoC SoCmax
ref
PEVB = Pmax if Ppv > Pmax
EVB , SoC SoCmax (6.2)
ˆ EVB
:̂ 0 if SoC > SoCmax
Mode III: The EVB is used to support the home load demand at peak time. This
not only helps reduce the stress on the grid at the peak demand but also helps save
the electricity bills for the EV owners. The EVB discharging power reference is
calculated based on (6.3), where PL is the home load power with the minimum EVB
state-of-charge (SoCmin).
168 Cable based and wireless charging systems for electric vehicles
(a)
(b)
(c)
ref
PEVB = PL Ppv , SoC SoC min (6.3)
req
Mode IV: The EVB is used to support the grid with the required power Pg . The
EVB discharging power reference is calculated based on (7.4).
ref
PEVB = PL + Preq
g , SoC SoCRes (6.4)
where SoCRes is the reserved energy of the EVB. This mode can be achieved through
the request from the grid operator, and it is a smart function of the smart grid where
multi-sources are interconnected and cooperated.
The grid-connected converter is controlled through the dc bus Vdc to achieve a bidi-
rectional power flow. The control for the GC is shown in Figure 6.4(b). The control
signals of the GC, dvdc, and dig, respectively, are calculated according to (6.6) and
ref ref
(6.7), where V dc is the grid
dc is the voltage reference of the dc bus voltage and V
current reference.
p kivdc ref
dvdc = kvdc + Vdc Vdc (6.6)
s
!
p kiig ref
dig = kig + Ig I g (6.7)
s
The EVB is charged and discharged through the EVB converter. The control of the
EVB converter is shown in Figure 6.4(c), where the constant current control is used
for both charging and discharging processes. The current controller is following
(6.8), where dcc is the control signal, kpcc and kicc are PI3 controller parameters, and kicc
is the EVB charging/discharging current reference.
p kicc ref
dcc = kcc + IEVB IEVB (6.8)
s
The constant voltage (CV) control is used when the EVB reaches its gassing voltage
and the EVB is kept to the EVB CV until the EVB is fully charged. The control vari-
able dvc of the voltage controller is the EVB current reference as given according to
ref
(6.9), where kpvc and kivc are PI4 parameters, respectively, and V
EVB is the EVB voltage
reference.
p kivc ref
dvc = kvc + VEVB VEVB (6.9)
s
Figure 6.5 Simulation results of the EVC-HSP system in four operation modes
Figure 6.6 Simulation results of the EVB power in four operation modes
Reducing grid dependency of EV charging 171
Figure 6.7 SoC, current, and voltage of the EVB in operation modes
voltage is maintained at 220 V with the grid voltage is set as 127 V. Two resistive
loads of 60 Ω and 110 Ω, respectively, are considered as the home loads.
Figure 6.10 depicts the performance of the EVC-HSP system through the charg-
ing and the discharging procedure of the EV battery. Period (a) shows the charging
of the EVB from the PV power and the period (b) shows the discharging of the EVB
when it supports the local load. The EVB is charged in period (c) and it is discharged
in period (d) when there is no PV power.
Figure 6.8 Grid voltage and current of the EVC-HSP system in four operation
modes
172 Cable based and wireless charging systems for electric vehicles
Figure 6.9 The detailed experimental setup of the laboratory scale of the EVC-
HSP system
converters will share the same dc power bus. The number of EVs that can be charged
concurrently depends on the number of EVB converters connected to the dc bus.
The power flow in the proposed FCI is shown in Figure 6.11.
The PV power (PPV) will flow into EBU, EVB, and the distribution grid. The
EBU power (PEBU), EVB power (PEVB), and grid power (Pg) will flow back and forth
between EBU, EVB, and the distribution grid because the EBU converter, EVB con-
verter, and GC are bidirectional. As the power rating per charge ranges from several
dozen kilowatts up to hundreds of kilowatts, if a few EVs are charged concurrently,
the FCI power rating will be a few hundred kilowatts. The power rating is consid-
ered as the design criteria for FCI. To achieve reliable operation in any scenario,
the power rating of the GC should be designed in such a way that it can handle the
power flow in the FCI. The power rating of the GC depends on the power rating of
the PV converter, EBU converter, and EVB converter, and it can be designed based
on (6.10) or (6.11).
P
i=n
Pmax max max
GC = PPV + PEBU + Pmax
EVB (6.10)
( i=1 )
P
i=n
Pmax max max
GC = Max PPV , PEBU , Pmax
EVB (6.11)
i=1
where Pmax max max max
GC , PPV , PEBU , and PEVB are maximum power that GC, PV converter,
EBU converter, and EVB converter can deliver, and n is the number of EVB
converters.
174 Cable based and wireless charging systems for electric vehicles
8̂
ˆ
ˆ PA = PPV ˛0 = 0
ˆ
ˆ
ˆ
ˆ
< PB = PA ˛1 = 0; ˛2 = 0
PC = PB + PDis ˛3 = 0; ˛4 = 1 (6.20)
ˆ
ˆ
EBU
ˆ
ˆ P = P ˛5 = 0
ˆ
ˆ D C
:̂ P = P + PDis ˛6 = 0, ˛7 = 1
L D EVB
Mode 9: Grid support is required during the peak demand. The power flow at the
power8̂nodes can be expressed by (6.21).
ˆ
ˆ PA = PPV ˛0 = 0
ˆ
ˆ
ˆ PB = P A
ˆ ˛1 = 0; ˛2 = 0
<
Dis
PC = PB + PEBU ˛3 = 0; ˛4 = 1
ˆ
ˆ
ˆ
ˆ P = PC ˛5 = 0
ˆ
ˆ D
:̂ P PE + PDis = 0 ˛6 = 1, ˛7 = 1
D g EVB (6.21)
The summary of the operation modes of the FCI presented above is shown in
Table 6.1.
The transition between the modes is shown in Figure 6.13 shows that αi = 0 at
all modes, this is because the FCI will have the functionality of changing the EBU
from the grid when the electricity price is low. However, in this chapter, this mode is
not considered, as the idea is to utilize the generated PV power as much as possible.
6.3.1.1 Grid converter
The GC will play a key role in the FCI to achieve reliable operation. As discussed
in the previous analysis, the power rating of the GC should be chosen based on
(6.12) or (6.13). The three-level neutral point clamped (3L-NPC) topology is chosen
as it shows the benefit of having a lower current total harmonic distortion, con-
sequently facilitating the reduced volume of grid filter. The 3L-NPC inverter has
been chosen for the GC as it has been proven for its high frequency, high voltage,
and high power in the power system applications with the power ranging up to a
few hundred kilowatts per single topology. In the past, only power IGBTs can han-
dle this level of power; however, with the fast development of the silicon carbide
metal-oxide-semiconductor field-effect transistors (MOSFETs), having the voltage
and current rating about 1 kV and 100 A, respectively, the required level of power
can be achieved. Also, using this topology, the power level can be upgraded easily
by connecting more MOSFETs in parallel at each leg of the 3L-NPC topology. The
GC based on 3L-NPC topology is shown in Figure 6.14.
6.3.1.2 PV converter
The PV boost converter is to track the maximum power from the PV arrays. However,
for a high-power application, the boost converter will require a big inductor, which
will result in having a high-power loss thereby reducing the overall efficiency. To
overcome this disadvantage, an interleaved boost converter is utilized for the pro-
posed PV converter. This helps increase system efficiency by reducing the core size
of the inductor. Also, the inductor current ripple is reduced significantly. The PV
converter is shown in Figure 6.14.
charging and discharging of the EBU and EVB. The EBU and EVB converters are
shown in Figure 6.14.
status of the grid, PV power, EBU power, and EVB power. The detailed control of
each power converter is discussed in this section.
The duty cycle dpv is calculated based on (6.24), where K2p and K2i are parameters of
the current controller CIL(s). The duty cycle of the compensated switch K2p is calcu-
lated based on (6.25).
K2
ref ref
dpv = K2p IL IL + i IL IL (6.24)
s
N
dpv = 1 dpv (6.25)
and reactive power, and the outer loop controls the dc-link voltage Vdc. All the con-
trollers are designed in the d-q frame as given by (6.32)–(6.34) with id, where id is
the grid current in the d-q frame, dvdc is the control variable of the dc-link voltage
control, and ugd and ugq are the control variables of the grid control in the d-q frame.
p kivdc ref
dvdc = kvdc + Vdc Vdc (6.32)
s
i
p k ref
ugd = kd + d id id (6.33)
s
!
p
kiq ref
ugq = kq + iq i q (6.34)
s
In the standalone mode, the GC acts as an inverter that converts the dc power to ac
power to supply the local load. This is represented as mode 8, shown in the flowchart
of Figure 6.15. The detailed control of the GC in the standalone mode is shown in
Figure 6.19. The outer loop is the output voltage of the GC, vL,abc. All the controllers
are designed in the d-q frame with iLd and iLq are the load current in the d-q frame,
and vLd and vLq are the load voltage in the d-q frame.
Reducing grid dependency of EV charging 183
ref p ki ref
iLd = kLd + Ld vLd vLd (6.35)
s
!
k i
ref p Lq ref
iLq = kLq + vLq vLq (6.36)
s
i
p k ref
uLd = kLd + Ld iLd iLd (6.37)
s
!
k i
p Lq ref
uLq = kLq + iLq iLq (6.38)
s
EVB
ˆ t
EVB 1
SoC t = SoC0 + EVB iEVB t dt (6.39)
C t0
ˆ t
1
SoCEBU t = SoCEBU 0 + EBU
iEBU t dt (6.40)
C t0
where C EVB EBU
0 and C0 are the initial SoC at t = t0, C is the nominal EVB and EBU
capacities, and iEVB (t) and iEBU (t) are the EVB and EBU currents at time t. The simu-
lation results of modes 4–7 are shown in Figures 6.20 and 6.21.
In mode 7, the EVB is charged from the grid only, which starts from t = 0 s
to t = 1 s. Mode 6 starts from t = 1 s to t = 2 s when the EVB is charged directly
from the EBU without the PV power while there is no requirement for grid support.
Mode 5 starts from t = 2 s to t = 3 s, which shows the charging power of the EVB
is taken from the grid and the PV while the EBU is assumed to have entered the low
SoC mode. The period from t = 3 s to t = 4 s represents mode 4, where the EVB is
charged from the EBU and PV power. The simulation results of the modes 1, 2, 3, 8,
and 9 are shown in Figures 6.22 and 6.23.
In mode 1, the EBU is charged directly from the PV power only, which starts
from t = 0 s to t = 1 s. Mode 2 starts from t = 1 s to t = 2 s when the EVB is absent
or not in the operating modes, where the PV power is injected into the grid. Mode 3
starts from t = 2 s to t = 3 s, where the charging power of the EVB is drawn from
PV only. The period from t = 3 s to t = 4 s represents mode 8, which is the load sup-
port mode where the grid is disconnected. All the distributed powers will support
the local load. The period from t = 4 s to t = 5 s represents mode 9, which is the
grid support mode, where the grid is at the peak demand and needs support. All the
distributed powers will inject the power into the grid as per request.
The simulation results show that with the proposed efficient energy manage-
ment of the distributed powers and grid power, the grid will not be tremendously
affected by the EV fast-charging. The distribution grid can also handle the increas-
ingly high penetration of EVs. The simulation results show that, in a future smart
grid, where the grid is to be controlled for being smarter, the proposed energy man-
agement will be more effective as the PV power generation and load demand curves
can be forecasted dynamically. This ensures that the EVB power reference can be
produced more accurately.
6.4 Conclusions
in the field of renewable energy to choose suitable configurations and power con-
verters for their systems.
References
[1] Tran V.T., Islam M.R., Muttaqi K.M., Sutanto D. ‘An on-board V2X elec-
tric vehicle charger based on amorphous alloy high-frequency magnetic-link
and SiC power devices’. IEEE Industry Applications Society Annual Meeting.
USA: Baltimore, MD; 2019. pp. 1–6.
[2] Lutsey N. Power play: how goverments are spurring the electric vehicle
industry, the inter. coun. clean transport [online]. Available from https://
theicct.org/sites/default/files/publications/EV_Government_WhitePaper_
20180514.pdf [Accessed 20 Feb 2020].
[3] Clement-Nyns K., Haesen E., Driesen J. ‘The impact of charging plug-in hy-
brid electric vehicles on a residential distribution grid’. IEEE Transactions on
Power Systems. 2010, vol. 25(1), pp. 371–80.
[4] Qian K., Zhou C., Allan M., Yuan Y. ‘Modeling of load demand due to EV bat-
tery charging in distribution systems’. IEEE Transactions on Power Systems.
2011, vol. 26(2), pp. 802–10.
[5] Yilmaz M., Krein P.T. ‘Review of the impact of vehicle-to-grid technologies
on distribution systems and utility interfaces’. IEEE Transactions on Power
Electronics. 2013, vol. 28(12), pp. 5673–89.
[6] Dubey A., Santoso S. ‘Electric vehicle charging on residential distribution
systems: impacts and mitigations’. IEEE Access. 2015, vol. 3, pp. 1871–93.
[7] Farzin H., Moeini-Aghtaie M., Fotuhi-Firuzabad M. ‘Reliability studies
of distribution systems integrated with electric vehicles under battery-
exchange mode’. IEEE Transactions on Power Delivery. 2016, vol. 31(6),
pp. 2473–82.
[8] International S. SAE’s J1772 ‘combo connector’ for ac and dc charging
advances with IEEE’s help [online]. Available from http://articles.sae.org/
10128/ [Accessed 20 Feb 2020].
[9] Kisacikoglu M.C., Kesler M., Tolbert L.M. ‘Single-phase on-board bidirec-
tional PEV charger for V2G reactive power operation’. IEEE Transactions on
Smart Grid. 2015, vol. 6(2), pp. 767–75.
[10] Haoyu W., Dusmez S., Khaligh A. ‘Design and analysis of a full-bridge
LLC-based PEV charger optimized for wide battery voltage range’. IEEE
Transactions on Vehicular Technology. 2014, vol. 63(4), pp. 1603–13.
[11] Musavi F., Edington M., Eberle W., Dunford W.G. ‘Evaluation and efficiency
comparison of front end AC-DC plug-in hybrid charger topologies’. IEEE
Transactions on Smart Grid. 2012, vol. 3(1), pp. 413–21.
[12] Shi C., Wang H., Dusmez S., Khaligh A. ‘A SiC-based high-efficiency iso-
lated onboard PEV charger with ultrawide DC-link voltage range’. IEEE
Transactions on Industry Applications. 2017, vol. 53(1), pp. 501–11.
Reducing grid dependency of EV charging 187
[13] Restrepo M., Morris J., Kazerani M., Canizares C. ‘Modeling and testing of
a bidirectional smart charger for distribution system EV integration’. IEEE
transactions on smart grid. 2016,1.
[14] Gautam D.S., Musavi F., Edington M., Eberle W., Dunford W.G. ‘An au-
tomotive onboard 3.3-kW battery charger for PHEV application’. IEEE
Transactions on Vehicular Technology. 2012, vol. 61(8), pp. 3466–74.
[15] Kesler M., Kisacikoglu M.C., Tolbert L.M. ‘Vehicle-to-grid reactive power
operation using plug-in electric vehicle bidirectional offboard charger’. IEEE
Transactions on Industrial Electronics. 2014, vol. 61(12), pp. 6778–84.
[16] Zhang J., Lai J.-S., Kim R.-Y., Yu W. ‘High-power density design of a soft-
switching high-power bidirectional dc–dc converter’. IEEE Transactions on
Power Electronics. 2007, vol. 22(4), pp. 1145–53.
[17] Buja G., Bertoluzzo M., Fontana C. ‘Reactive power compensation ca-
pabilities of V2G-enabled electric vehicles’. IEEE Transactions on Power
Electronics. 2017, vol. 32(12), pp. 9447–59.
[18] Tan L., Wu B., Yaramasu V., Rivera S., Guo X. ‘Effective voltage balance
control for bipolar-DC-bus-fed EV charging station with three-level DC–DC
fast charger’. IEEE Transactions on Industrial Electronics. 2016, vol. 63(7),
pp. 4031–41.
[19] Rivera S., Wu B. ‘Electric vehicle charging station with an energy storage
stage for split-DC bus voltage balancing’. IEEE Transactions on Power
Electronics. 2017, vol. 32(3), pp. 2376–86.
[20] Cao Y., Tang S., Li C. ‘An optimized EV charging model considering TOU
price and SOC curve’. IEEE Transactions on Smart Grid. 2012, vol. 3(1), pp.
388–93.
[21] Richardson P., Flynn D., Keane A. ‘Optimal charging of electric vehicles in
low-voltage distribution systems’. IEEE Transactions on Power Systems.
2012, vol. 27(1), pp. 268–79.
[22] Deilami S., Masoum A.S., Moses P.S., Masoum M.A.S. ‘Real-time coordina-
tion of plug-in electric vehicle charging in smart grids to minimize power
losses and improve voltage profile’. IEEE Transactions on Smart Grid. 2011,
vol. 2(3), pp. 456–67.
[23] Chukwu U.C., Mahajan S.M. ‘V2G parking lot with PV rooftop for capac-
ity enhancement of a distribution system’. IEEE Transactions on Sustainable
Energy. 2014, vol. 5(1), pp. 119–27.
[24] Alam M.J.E., Muttaqi K.M., Sutanto D. ‘Effective utilization of available
PEV battery capacity for mitigation of solar PV impact and grid support with
integrated V2G functionality’. IEEE Transactions on Smart Grid. 2016, vol.
7(3), pp. 1562–71.
[25] Foster J.M., Trevino G., Kuss M., Caramanis M.C. ‘Plug-in electric vehi-
cle and voltage support for distributed solar: theory and application’. IEEE
Systems Journal. 2013, vol. 7(4), pp. 881–8.
[26] Badawy M.O., Sozer Y. ‘Power flow management of a grid tied PV-battery
system for electric vehicles charging’. IEEE Transactions on Industry
Applications. 2017, vol. 53(2), pp. 1347–57.
188 Cable based and wireless charging systems for electric vehicles