Module 06_Cost Management
Module 06_Cost Management
CTEC210
Fundamentals of
Project Management
Project Cost Management
2
Types of Costs
3
Types of Costs
Sunk cost Expense
Cannot be recovered Cost deducted against
Costs already expended income for current year
Related to operations
Opportunity costs Capital costs
Benefits not realized due
Not an expense,
to choosing a particular
alternative depreciated over time
Not a true cost, and Related to projects
difficult to confirm
4
Plan Cost Management
5
7.1 Plan Cost Management
Adapted from Figure 7-2, A Guide to the Project Management Body of Knowledge (PMBOK® 6
Guide) - Sixth Edition, Project Management Institute, Inc., 2017. Copyright and all rights reserved.
Material from this publication has been reproduced with the permission of PMI.
Cost Management Plan
7
Plan Cost Management: Outputs
9
Estimating Costs
10
7.2 Estimate Costs
Adapted from Figure 7-4, A Guide to the Project Management Body of Knowledge (PMBOK® 11
Guide) - Sixth Edition, Project Management Institute, Inc., 2017.Copyright and all rights reserved.
Material from this publication has been reproduced with the permission of PMI.
Definitive -5% to 10%
Budget -10% to +15%
Estimate Classes Order of Magnitude -50% to 100%
13
Analogous (Top-Down) Estimating
14
Detailed (Bottom-Up) Estimating
15
Typical Problems with IT Cost
Estimates
Estimates are done too quickly
Lack of estimating experience
Human beings are biased toward
underestimation
Management desires accuracy
16
Detailed Cost Estimating Process
17
7.3 Determine Budget
18
7.3 Determine Budget
Adapted from Figure 7-6, A Guide to the Project Management Body of Knowledge (PMBOK® 19
Guide) - Sixth Edition, Project Management Institute, Inc., 2017. Copyright and all rights reserved.
Material from this publication has been reproduced with the permission of PMI.
Determine Budget: Inputs
20
Determine Budget: Outputs
Cost baseline
Cumulative Cost
Time-phased
Tracks the
cumulative costs
Cost Baseline
S-curve usually
Why?
Time
Surveyor Pro Project Cost Estimate
22
Surveyor Pro Project Cost Baseline
23
Project Budget Components
24
7.4 Control Costs
25
Control Costs
Adapted from Figure 7-10, A Guide to the Project Management Body of Knowledge (PMBOK® 27
Guide) - Sixth Edition, Project Management Institute, Inc., 2017. Copyright and all rights reserved.
Material from this publication has been reproduced with the permission of PMI.
How are we doing?
A software development A bookstore chain company
company is three months Plans to install systems in
into a new project 12 outlets this year
The project manager totals Can complete one outlet
the staff hours per month
She finds them above her PM has separate contracts
estimates for each store
She complains to the team Six months into the year,
leaders only five are open
They reply that staff have Controller says that cash
been working hard and flow is as expected
doing really well VP has asked for status
Should the PM be report
concerned? What is the situation?
28
Actual vs. Plan can be Misleading
29
Earned Value Management
Earned value is useful for
Monitoring outside vendors and suppliers
Reporting project status to senior management
Assessing project trends
Determining schedule (ahead/behind)
True budget status (over/under)
Work packages are at the heart of EV system
A project is divided and subdivided into logical, measurable
work packages
Usually done from a work breakdown structure (WBS)
Work packages provide the units for comparing progress in
Work planned, funds spent and deliverables
30
Earned Value Management:
The Key Components
1 PLANNED VALUE (PV): What did we plan to achieve by now?
also called: the budgeted cost of the work scheduled (BCWS)
the portion of the approved cost estimate planned to be spent on
the activity during a given period
includes both direct and indirect costs
31
Earned Value Management:
The Key Components
3 ACTUAL COST (AC) What have we spent so far?
also called: the actual cost of the work performed (ACWP)
the total of direct and indirect costs incurred in accomplishing
work on the activity in a given period
A simple example...
Scope: develop a new software application
Budget: $100,000 including contingencies
Schedule: One year (four quarters) starting January 1
see diagram following...
A simple example Total Budget
100,000 $100,000
75,000 Planned
Dollar value
50,000
Planned Value
$25,000
Actual Cost
25,000 $22,000
Earned Value
$20,000
0
Q1 Q2 Q3 Q433
Financial Quarters
Earned Value Variance
Measures
Subtract the Actual Cost or Planned Value from
Earned Value to show deviation to date
What are the current variances for this example?
Cost Variance
CV = earned value - actual cost = BCWP - ACWP
CV = EV - AC
negative CV is the $ value that performance lags behind costs
Schedule Variance
SV = earned value - planned value = BCWP - BCWS
SV = EV - PV
negative SV is the $ value that performance is behind plan
34
Earned Value Performance
Indices
Divide the Earned Value by the Actual Cost or
Planned Value to indicate trends to date
What are the current indices for this example?
Cost Performance Index
CPI = earned value / actual cost = BCWP / ACWP
CPI = EV/AC
CPI gives performance as a ratio of actual costs to date
35
A Simple Example Total Budget
100,000 $100,000
50,000
Planned Value
$25,000
Actual Cost
25,000 $22,000
Earned Value
$20,000
0
Q1 Q2 Q3 Q436
Financial Quarters
Determining the Earned Value of a
Work Package
Not started: No earned value (of course)
Completed: Earned value is equal to the planned
value for that task
In progress: Different ways to calculate:
Percent complete – Based on reports from staff
Effort Left - Input from staff
The 0/100 Rule – No value given until task is complete
The 50/50 Rule – Task is given half the PV when started,
the balance when completed
Other approaches can be used for certain tasks
37
Actual Cost
Simple example $110,000
75,000
Dollar value
Earned Value
Assume this $100,000
50,000 situation
continues
Actual end
25,000 of project
Total
Budget
300,000 $400,000
Planned
Expenditures
Expenditures
Earned
200,000 Value
$120,000
Planned
Value
100,000 $100,000
Actual Cost
$80,000
0
Q1 Q2 Q3 Q4
Financial Quarters
Problem: The Quantum Project
43
Problem: Phase 1 Status Report
44
Problem: Phase 1 Status Report
Activity description Approved Budget Payments and Invoices Value of Tasks
Amounts to date Completed to date
Concept Development 100,000 120,000 100,000
E($600/$620)
47
Solution: Phase 1 Status Report
1. What activities have not been finished?
Secondary Analysis and Recommendations
2. What was the Budget for Phase 1?
$480,000
3. How much has been spent or committed so far in Phase 1?
$465,000
4. What is the value of the work that has been completed so far?
$450,000
5. Is this phase of the project on budget?
No, over budget CV = EV – AC = - 15,000
6. Is this phase of the project on schedule?
No, behind schedule SV = EV – AC = - 30,000
7. If the rest of the project proceeds like Phase 1, will it finish on
schedule?
No.
48