Scope , Equipment To Be Tested
SL NO. as per scheme, Test to be QUANTITY Cumulative ________ to ________ to
conducted /Bays progress ________ progress ________ - Plan
TRANSFORMERS
Core Insulation Checks
Insulation Resistance Measurement
Capacitance and Tan Delta For Bushing
Capacitance and Tan Delta For winding
Turns Ratio Measurement
Vector Group & Polarity Test
Winding Resistance Measurement
Magnetic Balance Test
1 Floating Neutral Point Measurement
Measurement of Short Circuit Impedance
Exciting / Magnetizing Current Characteristics
C & R PANELS
Scheme wire checking
10
Auxiliary relay checking
Protection Relay Checking
11
BPI
IR Measurement of Each LA Stack
LT panel
IR Measurement Test
16
16 Trip/ Close Coil Resistance Measurement
Opening/Closing Time Measurement Test
Main Circuit Contact Resistance Measurement
Bus Duct
Insulation resistance test
17
Contact resistance test
Hi- Pot Test
BATTERY
18 BATTERY CHARGER
Load Test
Insulation resistance test
19 DCDB
Insulation Resistance Test
Auxiliary relay & Protection relay Checking
DATE:
Balance Constraint
Guidelines for filling in the sheet
i Initially write the complete scope of the project mentioning all the ratings.
ii Enter the quantity and progress of the present week.
iii Also propose the planned activity in the PLAN head.
iv Keep a track of the cumulative progress.