TC-ST-15(Progress Report)

The document outlines the testing and inspection requirements for various electrical equipment, including transformers, circuit breakers, isolators, current transformers, and more. It specifies the tests to be conducted, the quantity of equipment, and the progress tracking for each test. Additionally, it provides guidelines for filling in the status sheet, emphasizing the need for complete project scope and planned activities.

Uploaded by

passionsaurabh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
4 views

TC-ST-15(Progress Report)

The document outlines the testing and inspection requirements for various electrical equipment, including transformers, circuit breakers, isolators, current transformers, and more. It specifies the tests to be conducted, the quantity of equipment, and the progress tracking for each test. Additionally, it provides guidelines for filling in the status sheet, emphasizing the need for complete project scope and planned activities.

Uploaded by

passionsaurabh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 7

T&C STATUS

Project Name :
Scope , Equipment To Be Tested
SL NO. as per scheme, Test to be QUANTITY Cumulative ________ to ________ to
conducted /Bays progress ________ progress ________ - Plan
TRANSFORMERS
Core Insulation Checks
Insulation Resistance Measurement
Capacitance and Tan Delta For Bushing
Capacitance and Tan Delta For winding
Turns Ratio Measurement
Vector Group & Polarity Test
Winding Resistance Measurement
Magnetic Balance Test
1 Floating Neutral Point Measurement
Measurement of Short Circuit Impedance
Exciting / Magnetizing Current Characteristics

Vibration Measurement of Oil Immersed Reactor

Stability of Differential / REF


Frequency Response Analysis Measurement
Dissolved Gas Analysis of Oil Sample
Thermovision Infrared Scanning
Checks on bushing CT's
CIRCUIT BREAKERS
IR Measurement Test
Trip/ Close Coil Resistance Measurement
2 Opening/Closing Time Measurement Test
Main Circuit Contact Resistance Measurement
DCRM & Timing Measurement
Dew Point Measurement of SF6 Gas
SF6 Gas Lockout / Low Alarm Test
ISOLATORS
IR Measurement Test
3 Contact Resistance Measurement
Motor Operation Current Measurement Checks
Opening/Closing Time Measurement Checks
CURRENT TRANSFORMERS
Polarity Test for CT
Magnetizing Characteristics of CT (Knee Point
Voltage)
Ratio Test for CT
IR Measurement of CT (Primary & Secondary)
4 DGA Test for CT oil
Continuity Test
Secondary Winding Resistance Test
Tan Delta / Capacitance Test
Primary Injection Test
Contact Resistance Measurement
Secondary Injection Test
VT
Polarity
Insulation Resistance Measurement Test
Continuity Test
5 Secondary Winding Resistance Test
Tan Delta/Capacitance Test
Contact Resistance Measurement Test for Connectors

Secondary Injection / Annunciation Test.


Ratio Test
LIGHTNING ARRESTORS
IR Measurement of Each LA Stack
6 Checking Operation of LA Counter
Third Harmonic Resistive Current(THRC) for Surge
Arrestor
Outdoor CVT
Polarity
Insulation Resistance Measurement Test
Continuity Test
7 Secondary Winding Resistance Test
Tan Delta/Capacitance Test

Contact Resistance Measurement Test for Connectors

Secondary Injection / Annunciation Test.


Ratio Test
LA
IR Measurement of Each LA Stack
8 Checking Operation of LA Counter
Third Harmonic Resistive Current(THRC) for Surge
Arrestor
WAVE TRAP
9 Insulation Resistance Measurement Test

Contact Resistance Measurement for connectors

C & R PANELS
Scheme wire checking
10
Auxiliary relay checking
Protection Relay Checking

11
BPI
IR Measurement of Each LA Stack

Scheme Checking and


Commissioning
12 Cable Continuity
Primary Injection
Busbar Stability
HV / EHV Cables
Insulation Resistance Test
13 Conductor resistance measurement
Sheath test
Partial Discharge Measurement
High voltage test (HIPOT)
Earthing
Earth pit Resistance measurement (Individual)
14
Earth pit Resistance measurement (Combined)
Earth mat Resistance measurement
HT Switch Gear with VCB
IR Measurement Test
Trip/ Close Coil Resistance Measurement
15
Opening/Closing Time Measurement Test
Main Circuit Contact Resistance Measurement

LT panel
IR Measurement Test
16
16 Trip/ Close Coil Resistance Measurement
Opening/Closing Time Measurement Test
Main Circuit Contact Resistance Measurement
Bus Duct
Insulation resistance test
17
Contact resistance test
Hi- Pot Test
BATTERY
18 BATTERY CHARGER
Load Test
Insulation resistance test
19 DCDB
Insulation Resistance Test
Auxiliary relay & Protection relay Checking
DATE:

Balance Constraint
Guidelines for filling in the sheet
i Initially write the complete scope of the project mentioning all the ratings.
ii Enter the quantity and progress of the present week.
iii Also propose the planned activity in the PLAN head.
iv Keep a track of the cumulative progress.