EI&E
EI&E
B. OBJECTIVE:
1. To write down detailed specification and numbers required of different materials.
2. To determine the size and material of conductor and cable from electrical and mechanical
consideration. As such to prepare a detailed list of materials with complete specifications.
D. COURSE CONTENTS
1. INDIAN ELECTRICITY RULES
1.1 Definitions, Ampere, Apparatus, Accessible, Bare, cablew, circuit, circuit breaker,
conductor voltage (low, medium, high, EH), live, dead, cut-out, conduit, system,
danger, Installation, earthing system, span, volt, switch gear, etc.
1.2 General safety precautions, rule 29, 30, 31, 32, 33, 34, 35, 36, 40, 41, 43, 44, 45, 46.
1.3 General conditions relating to supply and use of energy : rule 47, 48, 49, 50, 51, 54, 55,
56, 57, 58, 59, 60, 61, 62, 63, 64, 65, 66, 67, 68, 70.
1.4 OH lines : Rule 74, 75, 76, 77, 78, 79, 80, 86, 87, 88, 89, 90, 91
2. ELECTRICAL INSTALLATIONS
2. 1 Electrical installations, domestics, industrial, Wiring System, Internal distribution
of Electrical Energy. Methods of wiring, systems of wiring, wire and cable,
conductor materials used in cables, insulating materials mechanical protection.
Types of cables used in internal wiring, multi-stranded cables, voltage grinding
of cables, general specifications of cables.
2. 2 ACCESSORIES: Main switch and distribution boards, conduits, conduit
accessories and fittings, lighting accessories and fittings, fuses, important
definitions, determination of size of fuse – wire, fuse units. Earthing conductor,
earthing, IS specifications regarding earthing of electrical installations, points to
be earthed. Determination of size of earth wire and earth plate for domestic and
industrial installations. Material required for GI pipe earthing.
2. 3 LIGHTING SCHEME: Aspects of good lighting services. Types of lighting
schemes, design of lighting schemes, factory lighting, public lighting
installations, street lighting, general rules for wiring, determination of number of
points (light, fan, socket, outlets), determination of total load, determination of
Number of sub-circuits.
3. INTERNAL WIRING
3 . 1 Type of internal wiring, cleat wiring, CTS wiring, wooden casing capping, metal
sheathed wiring, conduit wiring, their advantage and disadvantages comparison
and applications.
3 . 2 Prepare one estimate of materials required for CTS wiring for small domestic
installation of one room and one verandah within 25 m 2 with given light, fan &
plug points.
3 . 3 Prepare one estimate of materials required for conduit wiring for small domestic
installation of one room and one verandha within 25 m 2 with given light, fan &
plug points.
3 . 4 Prepare one estimate of materials required for concealed wiring for domestic
installation of two rooms and one latrine, bath, kitchen & verandah within 80m2
with given light, fan & plug points.
3 . 5 Prepare one estimate of materials required for erection of conduct wiring to a
small workshop installation about 30m 2 and load within 10 KW.
4. OVER HEAD INSTALLATION
4.1 Main components of overhead lines, line supports, factors Governing Height of
pole, conductor materials, determination of size of conductor for overhead
transmission line, cross arms, pole brackets and clamps, guys and stays,
conductors configurations, spacing and clearances, span lengths, overhead line
insulators, types of insulators, lighting arresters, danger plates, anti-climbing
devices, bird guards, beads of jumpers, jumpers, tee-offs, guarding of overhead
lines.
4.2 Prepare an estimate of materials required for LT distribution line within load of
100 KW maximum and standard spans involving calculation of the size of
conductor (from conductor chart), current carrying capacity and voltage
regulation consideration using ACSR.
ELECTRICAL INSTALLATION & ESTIMATING
Learning Resources:
Sl.No Name of Authors Title of the Book Name of Publisher
CONTENT
SL NO TOPIC PAGE NO
2 ELECTRICAL INSTALLATIONS 06 – 12
3 INTERNAL WIRING 12 – 40
6 SUB-STATIONS 50 – 58
CABLE:- It means a length of insulated single conductor r. Such insulated conduct may not provided with
& overall mechanical protective covering.
CIRCUIT:- An arrangement of conductor for the purpose of conveying energy & forming a system.
CIRCUIT BREAKER:- It means a device capable of making & breaking the ckt under all conditions.
CONCENTRIC CABLE:- It means a composite cable comprising an inner conductor which is insulated.
CONDUCTOR:- It means any wire ,cable ,bar ,tube ,plate used for conducting energy & so arranged to
be electrically connected to a system.
CUT-OUT:- It means any appliance for automatically interrupting the transmission of energy through any
conductor when the current rises a predetermined amount & shall also include fusible cut-out.
GAURDED:- It means protected by means of suitable casings ,barriers or metal screens to remove the
possibility of dangerous contact.
LIGHTNING ARRESTOR:- It means a device which has the property of diverting to earth any electrical
surge of excessively high amplitude applied to its terminals.
OVER HEAD LINE:- It means any electric supply line which is placed above ground.
STREET BOX:- It means a totally enclosed structure either above or below ground containing ,switching
,controlling energy.
SWITCH GEAR:- It shall denote switches ,breakers ,cut-outs & other apparatus used for operation
,regulation & control of circuits.
LOW VOLTAGE:- Where the voltage does not exceed 250 volts under normal conditions.
MEDIUM VOLTAGE:- Where the voltage does not exceed 650 volts under normal conditions.
HIGH VOLTAGE:- Where the voltage does not exceed 33000 volts under normal conditions.
EXTRA HIGH VOLTAGE:- Where the voltage exceeds 33000 volts under normal conditions.
Rule 29- Construction, Installation, Protection, Operation & Maintenance Of Electric Supply Lines
& Apparatus
An electric supply lines & apparatus shall be sufficient in power, size & sufficient mechanical strength for
the work they may be required to do. It shall be constructed, installed, protected, worked & maintained in
accordance with standards for the Indian standards institution so as to prevent danger.
The supplier shall ensure that all electric supply lines ,wires ,fittings & apparatus belonging to him or
under his control which are on consumer’s premises in a safe condition & the suppliers shall take due
precautions to avoid danger arising on such premises.
The supplier shall provide a suitable cut-out in each conductor of every line other than the earth
conductor.
Incase of service line each consumer shall be provided with an independent cut-out the point of junction
to service line.
Every electric supply line other than earth & neutral conductor shall be protected by suitable conductor.
Rule 32- Identification Of Earthed & Earthed Neutral Conductor & Position Of Switches
A suitable earth terminal earth terminal should be used by the consumer at a suitable position.
For medium, high, extra high voltage, installation the consumer should have provision of independent
earthing & reasonable precaution to prevent mechanical damage to the earth terminal.
Where bare conductors are used in a building the owner of such conductors shall ensure that they are
inaccessible & provide in rapidly accessible position switches for dead whenever necessary.
The owner of every medium, high & extra high voltage installation shall a caution notice in Hindi & local
language of the district of a type approved by the Inspector on.
Street boxes shall not contain gas pipes & precautions shall be taken to prevent as far as reasonably
possibly say influx of water or gas & if any influx or accumulated is discovered the owner shall give
immediate notice to any authority.
The owner of every generating station, substation, junction box in which there are many circuit intended
for operation at different voltages.
The owner of all ckts shall so arrange them that there shall be no danger of any part there of becoming
accidentally charged to any voltage beyond the limits of voltage for which they are intended.
For a new or additional supply of energy & before connecting the supply or reconnecting the same after a
period of six months the supplier shall inspect & test the applicant’s installation.
The supplier shall maintain a record of test results, obtained at each supply point to a consumer in a form
to be approved by the Inspector.
If as a result of such installation & test the installation is likely to constitute danger he shall serve on the
applicant a notice in writing requiring him to make such modification as per necessary to render the
installation safe.
If the supplier declines to make connection under the provisions of sub rule (1) he shall serve upon the
applicant a notice in writing, stating his reason for so declining.
If the Inspector or the supplier has reason to believe that there is in the system of consumer leakage
which is likely to affect injuriously the use of energy by the supplier which is likely cause danger.
He may give the consumer reasonable notice in writing that he desires to inspect & test the consumer’s
installation.
A suitable ckt breaker of required capacity should be connected before the distribution of supply.
A suitable ckt breaker should be connected to the secondary side of the transformer incase of high or
extra high voltage installation.
Every ckt should be protected against excess energy by means of suitable cut-out or MCB to prevent
danger.
Each motor should be control by a suitable link switch or ckt breaker at a person adjacent to the motor.
Rule 51- Provision Applicable To Medium, High & Extra High Voltage Installation
All conductors shall be completely enclosed in mechanically strong metal casing or metallic covering
which is electrically & mechanically continuous & protected against damage.
A clear space of not less than 3 feet (91.44 cm) in width shall be provided in front of the switch board.
If there are any attachment or bare connections at the back of the switch board , the space behind the
switch board shall be either less than 9 inches (22.86 cm) or more than 30 inches (76.2 cm) in width
measured from the farthest outstanding part of any attachment or conductor.
If the space behind the switch board exceeds 30 inches (76.2 cm) in width , there shall be a passage way
from either end of the switch board clear to height of 6 feet (1.828 mtrs).
The cost of any inspection & test made by a Inspector at the request of the consumer unless the
Inspector directs.
The cost of each & every such inspection & test by whom so ever borne shall be calculated in accordance
with the scale specified by the control or the state government as the case may be in this behalf.
All conductors of OH lines shall have a breaking strength of not less than 317.51 kg(700 lbs).
Where voltage is low & the span is less than 50ft(15.24 mtr) & a conductor having an actual breaking
strength of not less than 300 lbs(135.08 kg).
Joints of conductor of OH lines shall be mechanically & electrically secure under the conditions of
operation.
The ultimate strength of joint shall not be less than 95% of that of the conductor & the electrical
conductivity not less than that of the conductor.
The owner of every OH lines shall ensure that it has the following factors of safety.
The minimum factor of safety for stay wires, guard wires shall be 2.5 based on the ultimate tensile
strength of the wire.
No conductor of an OH lines, including service lines, erected across a street shall at any part thereof be
at height less than
No conductor of an OH lines including service lines erected along any street shall at any part thereof be
at a height less than
No conductor of an OH lines including service, erected elsewhere than along cross across any street
shall be at a height less than
For low, medium & high voltage lines up to and including 11kv, if bare-15 ft(4.572 m)
For low, medium & high voltage lines up to including 11kv, if insulated- 13 ft(3.963 m)
For extra high voltage lines the clearance above ground shall not be less 17 ft(5.182 m) plus 1 ft (0.3048
m) for every 33kv.
Provide that the minimum clearance along or across any street shall not be less than 20ft(6.096 m)
1- Cleat Wiring
2- CTS or TRS Wiring
3- Conduit Wiring
4- Wooden Casing & Capping Wiring
5- Lead Sheathed Wiring
Cleat Wiring
Single core V.I.R or P.V.C cables are used in this type of wiring. This type of wiring is not practically for
permanent wiring & is only suitable for temporary wiring purpose of saving in labour & overall cost. It is
cheapest wiring. A little skill required to lay the wiring. This type of wiring can be dismantled easily.
Advantages:-
The whole wiring is replaced in short period of time & material of wiring is used on another place.
The alternation & additions are possible & inspection is very easy.
Because all cables are in open air, therefore fault is found easily & replaces it very quickly.
Disadvantages:-
The weather conditions are directly affected on cables & also mechanical injuries are directly affected on
the cables.
The fire risk is present because the cables are in open condition.
CTS full form is Cable Tyre Sheath & TRS full form is Tough Rubber Sheathed. The wires used in such
type of wiring are CTS or TRS. They are carried on wooden batten with clips. This wiring is suitable for
damp climate but cannot withstand much heat. So it is not suitable for places of very hot weather. This
type of wiring gives sufficient mechanical protection to the cable.
Advantages:-
Repairing is easy.
Disadvantages:-
Conduit Wiring
In this type of wiring P.V.C. wires are carried through P.V.C. pipes giving good protection from
mechanical injury or fire risks. There are two types of conduit wiring. (a) Surface Wiring (b) Concealed
Conduit Wiring
In surface conduit wiring the conduit run over the wall supported.
In concealed conduit wiring the conduit is embedded in the wall & ceiling by placing in the premade cavity
in them.
Advantage:-
Disadvantages:-
It is expensive wiring.
The casing is base which consists of wooden block. It has two grooves to accommodate wires. The
casing is fixed on the wall with the help of screws. After placing the wires in the grooves casing at the top
is covered its called capping. Now a days P.V.C. casing & capping are used. There is sufficient
mechanical & environmental protection to the wires.
Advantages:-
No risk of electric shock due to covered wires & cables in casing capping.
Disadvantages:-
This system of wiring is similar to CTS or TRS wiring. Only difference is that in this case VIR conductors
covered with lead alloy sheath. It can be installed in open space. It has longer life. It is relatively
expensive due to the cost of lead sheath. In this type of wiring skilled labour & proper supervision is
required.
Advantages:-
Disadvantages:-
It may not be suitable for places where chemical corrosion may occur.
Single wire which may bare or covered with insulation is known as wire.
Conductor or wire:- Aluminium or copper wire in single, double or several cores stranded together.
The outer covering:- It is used to cover installation for protection against mechanical damage & moisture.
CHOICE OF CONDUCTOR
(a) Current carrying capacity:- The current carrying capacity of the conductor size is the maximum
current, it can carry without overloading & overheating.
(b) Resistance & Impedance:- The conductor size must have low resistance per unit length so that
the losses are acceptable or with in limits. The configuration of conductors & insulators used must
result in to acceptable impedance.
(c) Mechanical Strength:- Must provide sufficient physical strength for installation without stretching
or bending.
(d) Termination:- The conductor selected for a particular situation should be large or small enough to
allow it to be terminated to the required connector or other device in a serviceable manner.
(e) Flexibility:- The conductor should be sufficiently flexible to withstand the installation stress without
becoming brittle & breaking.
(f) Conductor Configuration:- The conductor must have configuration that provides most efficient
transmission of power. The other consideration includes weight & cost which also affect choice of
conductor.
CONDUCTOR MATERIAL
Copper:- It is mechanically strong, hard, extremely tough, durable & ductile. It can withstand high
temperature & dampness. Tensile strength of copper is 40 kg/sq. mm. Melting point of copper is 1083
c.
Aluminium:- It is being used for power distribution for long distance. Aluminium is cheap as compare
to copper. Tensile strength of aluminium is 9 kg/sq. mm. Melting point of aluminium is 657 c.
SIZE OF CONDUCTOR
The minimum size of house wiring sub-circuits should be 1.5 sq.mm or 1.40 mm diameter for
aluminium conductor single strand. The minimum size of aluminium conductor for two core cable
should be 6 sq. mm & for three & four cores it should be less than 25 sq. mm. The minimum size of
house wiring sub-circuits should be 1 sq. mm or 1.12 mm dia for copper conductor single strand.
NOTE: The permission voltage drop from 1 phase supply should not exceed 2% +1 volt for light loads
& 5% for 3 phase supply domestic purpose. The voltage drop may not taken in to consideration. It
may be taken up for calculation for large buildings such as schools, college building wiring. The
voltage drop may only be taken in to account with heavy loads & long runs.
Size of conductor Two cable DC or 1 phase AC Three & Four cables balanced 3
phase
Nominal area No. & dia of Current rating Voltage drop Current rating Voltage drop
sq, mm wire in mm amp in mtr in amp in mtr
Size of conductor Two cable DC or 1 phase AC Three & Four cables 3 phase
Nominal area No. & dia of Current rating Voltage drop Current rating Voltage drop
sq, mm wire in mm amp in mtr in amp in mtr
Ex:-1
Calculate the size of wire of sub-ckt consisting of 10 light / fan points or 800w. The supply voltage is
taken at 230 v A.C at 50 cycles/ sec ?
So 1/1.12 mm or 1 sq. mm copper conductor & 1/1.40 mm or 1.5 sq. mm aluminium conductor are
used.
Ex:-2
A newly constructed house having a load of 45 amp is connected to single phase a.c supply. The
service pole from where connection to the house are to be given in situated 20 mts away using a
cable of 40 mts. Calculated the size of wire for the service connection ?
According to conductor table to carry 45 amp is 25 sq.mm or 7/2.24 mm dia which can carry 59 amp.
This voltage drop is less than the permissible volage drop of 5.6 volts, therefore wire having 25
sq.mm or 7/2.24mm
EARTHING
Earthing is the method of transmitting the instant electricity discharge directly to the ground through low
resistance wires or electrical cables..
The main intention of electrical earthing is to keep away from the danger of electric shock due to the
outflow of current from ground through the not preferred path as well as to make sure that the potential of
a conductor does not increase with respect to the ground than its planned insulation.
TYPES OF EARTHING
Plate Earthing
In this type of system, a plate is made up of copper or GI (galvanized iron) which are placed vertically in
the ground pit less than 3meters from the earth. For a better electrical grounding system, one should
maintain the earth moisture condition around the plate earthing system
Pipe Earthing
A galvanized steel based pipe is placed vertically in a wet is known as pipe earthing, and it is the most
common type of earthing system. The pipe size mainly depends on the soil type and magnitude of
current. Usually, for the ordinary soil, the pipe dimension should be 1.5 inches in diameter and 9feets in
length. For rocky or dry soil, the pipe diameter should be greater than the ordinary soil pipe. The soil
moisture will decide the pipe’s length to be placed in the earth.
Rod Earthing
This type of earthing system is similar to pipe earthing system. A copper rod with galvanized steel pipe is
placed upright in the ground physically or using a hammer. The embedded electrodes lengths in the earth
decrease the resistance of earth to a preferred value.
1. The place where the service connections from nearest pole are to be received should be selected
carefully. The place should be covered meter against rain, Sun & mechanical damage.
2. Generally energy meter ,main switch & main distribution board are installed close to each other &
near the commencement of supply.
3. The conductor used beyond distribution board in the whole of the building is of the same size i.e.
1.5 sq. mm or 1/1.40 mm for aluminium conductor.
4. The height of main board , switch board & meter board are to be installed 1.5 mts above the floor.
5. Every line i.e. phase wire should be protected by a fuse of suitable rating based on load.
6. The socket outlets for house wiring should be installed on the switch board along with other
switches but the socket in office building may installed close to floor 0.25 mts above floor.
7. Only 3 pin ,5 amp socket outlet are to be used in all light & fan sub-ckts. Also 3 pin, 15 amp
socket outlet are to be used in power sub-ckt.
8. In case an appliance such as single phase motor, X-ray machine, industrial heating process etc,
requiring the use of socket outlet of rating higher than 15 amp is to be used.
9. In both rooms the height of socket outlet should not be less than 1.5 mts in any case.
10. In small kitchen one light point & one 5 amp socket are sufficient. In large kitchen one light & one
15 amp socket are to be provided for general use.
11. For small, medium & high size rooms, all light points are to be placed on walls about 2.75 mts to
3 mts above the floor or horizontal run of batten running below ceiling.
12. Telephone socket & TV socket to be 0.25 mts above floor.
13. Bed light to be placed on 1.5 mts above floor level.
14. The height of fluorescent tube should be 2.75 mts above floor.
15. All ceiling fans are to be hung 2.75 mts above the floor.
16. Rthe load on each sub-ckt is to be restricted to 800 watts.
17. The fuse & switch are not to be provided on earthed conductor or earth wire.
18. 14 SWG, G.I. wire is to be used as earth wire for house wiring beyond main switch where single
supply is given to the building.
a. The 8 SWG G.I. earth wire is used to connect all sub main switches, main switches,
distribution boards to earth electrode buried deep in to earth.
19. In large buildings where 3 phase 4 wire supply is to be given the load is to be distributed equally
on all the phases
20. The height of ceiling for a normal residential building may be taken as 3.5 mts for estimation
purposes. The height of ceiling for large halls may be assumed to be 4 mts.
21. The height of batten running parallel to floor along vertical walls known as horizontal run (HR)
may be taken as 0.5 mts below ceiling, 3.0 mts above the floor or 1.5 mts above switch board
where height of ceiling is 3.5 mts..If the height of ceiling is assumed to be 4 mts above floor then
the HR may be taken 1 mts below ceiling.
22. Use of G.I. or copper thimbles is to be made where earth wire connection is to be made with main
switch, distribution board etc.
23. The maximum load permitted in a power circuit is 3000 w & lighting circuit is 800 w.
ESTIMATE: 8.1
Draw the electric circuit and estimate the quantity of material and total cost for PVC wiring
𝟏
system used in a hall of 15m × 6 m × 4 𝟐m height. The hall is to be fitted with fan points and light
points. Make your own assumption for the number of fan and light points and other missing data.
Taking 10 watts/m 2 of surface area as illumination requirements we will require 10 × 90 = 900 watts i.e.
10 lamps of `100 watts each will suffice, 4 ceiling fans of 60 watts each, will be fitted. Position of lamps
and fans is shown in fig. 8.3.
So 1/1.80 mm, single core, 650 V grade, aluminum conductor P V C cable having current carrying
capacity of 15 amperes will be used between meter board and main distribution board.
Since the maximum number of points in a circuit, must not exceed 10 and maximum load which
can be connected in one circuit is 800 watts, we will have two circuits, each of them having 7 points and a
load of 620 watts.
Since maximum load current is 5.2 amperes and there are two circuits, 240v, 16A, DPIC switch
fuse of any make approved by IS will be used as main switch.
2-way, 240 V, 16A/way, IC double pole distribution board of any make approved by IS will be
used as min distribution board.
620
Since full load current in each circuit = = 2.6 A
240
1/1.40 mm aluminum conductor, single core, 650 volt grade, PVC cable having current carrying capacity
of 10 amperes will be used as phase and neutral wire beyond the main distribution board. Others data
assumed are :
I. The height at which meter board, main switch board are to be fitted = 1.5 meters from ground
level.
II. The height at which conduit will be run = 3.5 meters from ground level
III. The meter board is to be fixed on entrance wall at a distance of 2 meters from the left hand side
wall.
Layout of wiring is shown in fig. 8.1
Circuit No. 1
Horizontal run along the wall above the main entrance = 2.2 m
Vertical drop along the left hand side wall up to switch boards SB1 and SB2= 2 + 2 = 4.0 m
Vertical run upto ceiling and run along the ceiling upto points L1, L2, L3, L4 and L5 = 5 × (1 + 1.5) = 12.5 m
Vertical run upto ceiling and run along the ceiling upto points F1 and F2 = 2 × (1 + 3) = 8.0 m
Circuit No. 2
Horizontal run along the right hand side wall upto L10 = 15 – 1.5 = 13.5 m
Vertical drop along the right hand side wall up to switch boards SB2 and SB4 = 2 + 2 = 4 m
Vertical run up to ceiling and run along the ceiling up to points L6 , L7, L8, L9 and L10
= 5 × (1 + 1.5) = 12.5 m
Vertical run up to ceiling and run along ceiling up to points F3 and F4 = 2 × (1 + 3 ) = 8.0 m
Total length of PVC conduit run = 0.2 + 2.0+ 2.2+13.5 + 4.0+ 12.5 +8.0 +3.8+ 13.5+ 4.0+12.5 +8.0 = 84.2
meters
Total length of PVC conduit required = 84.2 + 12.63 = 96.83 meters = 100 meters (say)
Length of 1/180 mm, single core, 650 V grade, aluminum conductor PVC cable from meter board to main
board
Length of 1/1.40 mm, aluminum conductor. Single core, 650 V grade PVC (phase wire) cable
Circuit No. 1
Circuit No 2
Circuit No 1.
Circuit No 2.
Total = 125.4 m
The method used for determining the length of phase and neutral wire is very laborious one. As a general
rule the length of phase wire, may be taken approximately two times and that of neutral wire
approximately equal to the length of the route (conduit) i.e. total length of cable required to be taken as
there times of the route (conduit length).
Then length of cable required from approximate formulae (mentioned above) = 3 × 100 =
300metres, the same as determined from the method adopted formerly.
Length of Earth Wire. Earth wire is required for socket outlets and main switch. Since no socket outlet is
being provided, earth wire of 14 SWG (GI) of 0.25 m length will be sufficient for earthing the main switch
and main distribution board.
MCB
i) 30 cm × 25 cm 1 do 60 00 do 60 00 Board
14 Wooden screws
Total 4604 50
Labour cost @ Rs. 30 per point 540 00 2 points
Say Rs 5400 00
Supply
Fixing
275 00 each
20
00 do 275 00
25 00
Supply
Fixing
425 00 do 425 00
31 00 do 32 00
Supply
7 00 do 28 00
Supply
Fixing
165 00 do 1650 00
45 00 do 450 00
Supply
220 00 do 880 00
Fixing
44 00 do 176 00
Total 4463 00
Contingencies 5 % 223 15
ESTIMATE 8.2
Draw the electrical circuit and estimate the quantity of materials and their cost required for PVC
casing –capping used in a house. The plan of which is shown in fig. 8.5. Assume the height of
ceiling as 3.6 meters and one plug point is to be provided in each room.
Solution: Given:
As per recommendation of ISI the wattage of each light, fan and plug socket (other than power sockets)
may be taken as 60 watts for the purpose of load estimation.
Since number of points to be connected is 8 (less than 10) and load is 480 watts (less than 800 watts),
one circuit is used and distribution board is not required.
480
Full load current, I = =2A
240
Hence 240 V, 16A, DPIC switch fuse of any standard make may be used as a main switch and 1/1.40
mm, aluminum conductor, single core, 650 V grade, PVC cable having current carrying of 10 amperes
may be used for phase and neutral connections.
Assumptions
Assume the height of main board and switch board = 1.5 meters
Connections are taken from SB1 to SB2 and from light point L4 to L5 through 19 mm conduit.
Hence length of conduit required = 0.25 +0.25 = 0.5 meter
Length of Phase Wire [1.5 mm2 aluminum conductor, single core, 650 V grade PVC cable]
From SB2 to light point L3 = 1.5 + 0.3 + 1.8 +0.6 +2.7 + 1.2 = 8.1 m
Leng
th of
Neutr
al
Wire
[1.5m
m2,
alumi
num
cond
uctor,
single
core
650 V
grade
PVC
cable]
From
From light point L2 to switch board SB1 = 1.2+ 2.4 +2.4 +2.1 = 8.1 m
Total length of aluminum conductor single core PVC cable of size 1.5mm 2 required (Phase + neutral) =
51.5 + 39.25 = 90.75 meters = 90 meters (say)
Total 1838 40
2138 40
Contingencies 5 % 107 00
Supply
Fixing
20 00 do 60 00
Fixing
56 00 each 280 00
12 00 do 60 00
Supply
Fixing
80 00 do 80 00
12 00 do 12 12
Supply
Fixing
56 00 each 112 00
7 00 do 14 00
Supply
Total 1748 00
87
Contingencies 5% 40
Estimate 9.2.
Two ac, 3 phases, 415 V, 50 Hz squirrel cage motors are to be installed in a workshop. The rated
output of the motors and their locations are shown in fig. 9.5. Star-delta starterssupplied with
each motor are to be installed on the wall. The supply company’s meter will be located at the
position marked. The wiring of the machines is to be carried out according to IE rules. Make a neat
sketch of the wiring scheme and size of cables used. Prepare also a list of material required for
the wiring including necessary earthing with GI plates 600 mm ×600 mm ×6.0 mm and estimate the
cost of the whole scheme.
Ans. Assuming efficiency of motor 85% and power factor 0.8, we have full load currents of motors.
15 ×735.5
I1 = = 22.5 A for 15 h p motor
√3 ×415 ×0.85 ×0.8
10 ×735.5
I2 = = 15.0 A for 10 h p motor
√3 ×415 ×0.85 ×0.8
Hence 3-core, PVC 1100 V grade 25 mm 2* aluminum conductor cable having current carrying capacity of
54 A will be used from meter board to main board.
The main switch and main distribution board will be mounted on main board of size 45 mm ×60 cm at a
height of 1.3 meters from the floor level and 0.25 m from the supply main board.
The main switch used should be capable of handling starting current of one motor (of highest
rating, plus full-load current of the other motor i.e. 22.5 ×2 + 15.0 = 60 A
Hence 100 A, 415 V grade TPIC switch shall be used as main switch.
As there are two circuits and starting current of one circuit (of highest rating) is 45 A, therefore 2 –way,
415 V, 63 A/way ICDB shall be used.
63 A, 415V, TPIC switch shall be installed for control of 15 hp (metric) motor and 32 A, 415 V, TPIC
switch shall be installed for control of 10 hp (metric) motor.
3 core, 1100 V grade, PVC, 16 mm2* aluminum conductor cable having current carrying capacity of 38 A
shall be used from main distribution board to 15 hp motor through its switch and starter.
3 core, 1100 V grade, PVC, 6 mm2 aluminum conductor cable having current carrying capacity of 24 A
shall used from main distribution board to 10 h p motor through its switch and starter.
Size of H G conduit, use from meter board to main board, required to accommodate 3-core cable of size
25 mm2 aluminum conductor, and 1100 V grade will be of size 50 mm.
Size of H G conduit used from main distribution board to control board for 15 h p motor, required to
accommodate 3 core cable of size 16 mm2 aluminum conductor, 1100 V grade will be of size 25 mm.
Size of H G conduit, used from control board to motor 15 h p, required to accommodate 2 cables of 16
mm2 aluminum conductor, 1100 V grade will be of size 50 mm.
Size of H G conduit, used from main distribution board to control board for 10h p motor, required to
accommodate 3 core cable of 6 mm2, aluminum conductor, and 1100 V grade will be of size 25 mm.
Size of H G conduit, used from control board to motor of 10 h p to accommodate 2 cables of 6 mm2,
aluminum conductor, and 1100 V grade will of size 31 mm.
Flexible conduits of size 50 mm and 31 mm shall be used for connecting H G conduits to 15 hp and 10 h
p motors respectively.
From control board to hp motor to ground, 0.2 m below it and then to motor foundation = 1.3+0.2+1+0.4 =
2.9 m
Total = 3 + 7 = 10 m
Wastage 10% = 1 m
Grand total = 10 + 1 = 11 m
Length of 25 mm flexible conduit required fro connecting switches to motor starters = 2 * 0.25 = 0.5 m
Length of 25 mm2, aluminum conductor, 3 core, 1100 V grade PVC cable = 0.35 m
Length of earth wire ( 6swg GI wire ) = 2 × (3.6 + 3.2 +11.0 + 1 + 1) = 40.6 m ≅ 40 meters (say) 5 kg
For 15 hp
(ii) 63 A, 415 V 1 do 1950 00 do 1950 00 motor
For 10 hp
motor
(iii) 32 A, 415 V 1 do 950 00 do 950 00
(i) 25 mm2
17 do 40 00 do 680 00
(i) 50 mm diameter
3.6 do 50 00 do 180 00
(ii) 31 mm diameter
3.2 do 25 00 do 78 00
(iii) 25 mm diameter
11 do 18 00 do 198 00
6 Flexible conduit
(i) 50 mm diameter 1 do 40 00 do 40 00
(ii) 31 mm diameter 1 do 25 00 do 25 00
7 Conduit bends
(ii) 31 mm diameter 2 do 7 00 do 14 00
(iii) 25 mm diameter 8 do 6 00 do 48 00
8 Conduit saddles
(i) 50 mm diameter 6 do 4 00 do 24 00
(ii) 31 mm diameter 3 do 2 50 do 7 50
(iii) 25 mm diameter 12 do 2 00 do 24 00
9 Wooden bushings
(i) 50 mm diameter 5 do 3 00 do 15 00
(ii) 31 mm diameter 3 do 2 00 do 6 00
(iii) 25 mm diameter 8 do 2 00 do 16 00
10 Conduit locknuts
(ii) 31 mm diameter 3 do 4 00 do 12 00
(iii) 25 mm diameter 8 do 3 00 do 24 00
(i) 50 mm diameter
(ii) 31 mm diameter 1 do 10 00 do 10 00
(iii) 25 mm diameter 1 do 5 00 do 5 00
4 do 4 00 100 16 00
(i) 50 mm diameter
1 do 10 00 do 10 00
(ii) 31 mm diameter
1 do 8 00 do 8 00
(5 kg)
18 Caution plates 3 do 25 00 do 75 00
Total 21500 00
Total 24200 00
Contingencies 5% 1210 00
Supply 1 no
Fixing
Supply 60 00 do 60 00
Fixing
1 no
1634 00 do 1634 00
60 00 do 60 00
Supply
Fixing
4430 00 each 4430 00
143 00 do 143 00
Supply
Fixing
Fixing 9 00 do 112 00
17 Do 82 00 do 1394 00
800 00 do 136 00
Supply 90 do
Fixing 4 50 m 405 00
1 00 do 90 00
5 Danger board 1 no
Supply 44 00 each 44 00
Fixing 5 00 do 5 00
Supply
Fixing 45 00 do 45 00
5 00 do 5 00
Supply
Fixing
(ii) GI pipe 12 mm
diameter
264 00 do 528 00
5.4 m
8 do 1040 00 Lump
sum
10 do provision
Total 27114 40
Contingencies 5%
1355 72
ESTIMATE 10.3
An overhead 11kV, 50 Hz line has to be erected using 27 kg, 10 meters long steel poles and
copper wire of size no 3/2.642 mm, with average span of 150 meters. Make a list of material
required and estimate the cost per kilometer.
Number of 27 kg, 10 meter long rail poles required per 1.5 km line
102
= 3 ×1000 × 100= 3060 meters
Total 252000 00
Contingencies 1% 2520
293320 00
Say 294000 00
Estimate 10.4. Estimate the quantity of material required and cost of 1 km of overhead 11kV. 50 Hz
line using steel poles of 11 meter height and ACSR conductor of 6/1 × 2.59 mm/ with an average
span of 120m.
Solution: Length of line = 1 km
Average span = 120 m
1000
Number of spans = =8
120
Length of 6/1 × 2.59 mm conductor required = 3 × length of line + 2% for sag
(as 3 conductors run in 3-phase 11kV line)
102
= 3 × 1000 × = 3060 meters
120
128
Weight of ACSR conductor 6/1.259 mm = Length of conductor × 1000
∵ 1 km weighs 128 kg
128
= 3060 × 1000= 391.68 kg say 390 kg
List of material required and cost is given below :
Total 142500 00
Contingencies 1% 1425 00
Total 165300 00
ESTIMATE 12.1.
Prepare a list of material and estimate the cost for providing service connections to single story
buildings at 240 V single phase 50 Hz having a light and fan load of 5 kW. The supply is to be
given from an overhead line 20 m away from building.
conduit upto
service board
and for
wastage
4 HG conduit 16 SWG 25 4 do 18 00 do 72 00
mm diameter
7 GI thimbles 3 do 10 00 do 30 00 2 for
connecting GI
wire to pole
and GI pipe
and one for
stay
9 Conduit reducers 50 1 do 10 00 do 10 00
mm ×25 mm
14 Conduit saddles
(i) 50 mm
4 do 3 00 do 12 00
(ii) 25 mm
8 do 2 00 do 16 00
16 Kit-kat 32 A 1 do 35 00 Do 35 00
17 Neutral link 1 do 5 00 Do 5 00
18 Aerial fuse 32 A 1 do 35 00 Do 35 00
capacity
22 Stay insulator 1 do 65 00 Do 65 00
24 Sand 5 bags 10 00 Do 50 00
Total 3364 50
Contingencies 1% 33 64
ESTIMATE 12.2.
Estimate the quantity of material and cost for providing connection to a double stored building
with a load of 4kW at 240 V 50 Hz. Separate meters are to be provided for the two floors. The
distance between pole and building is 12 m and between service bracket and service board is 10
m.
7 conduit bends 25 mm 2 do 6 00 Do 12 00
13 conduit saddles’ 25 8 do 2 00 do 16 00
mm
15 gi thimbles 2 do 10 00 Do 20 00
21 neutral link 2 do 5 do Do 10 00
23 sand 5 bags 10 00 Do 50 00
Total 4964 50
Contingencies 1% 49 65
CH-6 (SUB-STATION)
ESTIMATE 13.2.
Electric supply to a factory is taken from an 11kV overhead, 3-phase line, which terminates at 2-
pole (iron-pole) structure at a distance of 20 m from the main board of the factory. The supply is to
given through a 11,000 V/433 V, 3-phase transformer and the factory has a load of 80 kVA.
Estimate the quantity of material required and the total cost.
Solution: Factory load = 80 kVA
kVA × 1000 80 × 1000
Full load current on primary side, I1 = = = 4.2 A
√3.V1 √3×11000
kVA × 1000 80 × 1000
Full load current on secondary side, I2 = = = 111.3 A
√3.V2 √3× 415
The service connation will be given by installing 100kVA, 11/0.433 kV, 3-phase ,△/λ –connected, 50 Hz
outdoor transformer on two pole structure. 7/3.00 mm (50 mm2), 3 ½ core, aluminum conductor
underground cable having current carrying capacity of 158 A will be used for giving service connection.
Total length of cable required = Length along the pole upto ground + length along the trench +
vertical run along the wall upto cable box + for wastage and connections
= 6 + 20 + 2 + 1 + 1 = 30 meters
The quantity of material with cost is estimated as below :
S. Description of Material Quantity Rate Amount Rewards
No with Full Specifications Required
Fuses
1 set of 635 00 do 1575 00
three
Insulators do
1 50 00 m 1905 00
cubicle
at sl 12
25 × 30 cm
45 × 60 cm 1 no 250 00 do 250 00
1 do 550 00 do 550 00
Total 160562 60
ESTIMATE 13.3.
Estimate the quantity of material and cost for erection of a 250 kVA pole-mounting substation.
Solution:
250 × 1000
Primary current, I1 = = 13.12 A Assuming primary voltage to be 11kV
√3×11000
250 × 1000
Secondary current I2 = = 348 A Assuming secondary voltage to be 415 V
√3×415
ACSR conductor, 7/2.11 mm will be used for ht connection between overhead conductors and
transformer.
61/2.6 mm, 1100 V grade single core PVC cable will be used for connecting switch to transformer. It side
(phase conductors) and 19/1.63 mm, 1100V grade single core PVC cable will be used for connecting
switch to transformer it side (neutral conductor).
The quantity of material and cost for the erection of 250 kVA pole mounting substation is
estimated as follows:
Fuses
do
1 635 00 do 1905 00
For
GI pipe 64 mm diameter
15 5 m 180 00 do 900 00 supporting
heavy gauge
cable
Total 263952 60
Contingencies 1% 2639 52
EARTHING
Table 14.1
Type of loads and Size of earth lead Size of the earth electrode
installation
Copper GI Copper GI
Pole earthing of do do Do do do do
transmission or
distribution lines
Industrial load above copper strip 25.4 mm × 2.54 Not used 90 cm × 90 not used
100 Hp mm cm × 6.35 mm
Power houses and copper strip 25.4 mm × 2.54 not used 90 cm × 90 not used
sub-stations (chain of mm cm × 6.35 mm
several earthing sets
installed). Detail as
under : Capacity of
Transformer/
Generating set :
20 mm × 4 mm
copper strip
a) upto 300 kVA but
not exceeding 500
kVA
do
copper strip ---- ---- -----
b) Above 300 kVA but 20 mm × 4 mm
not exceeding 500kVA