House Renovation WORK PROGRAM Critical Path. PDF

The document outlines a construction work program and Gantt chart for a house renovation project scheduled from October 2024 to March 2025. It details various tasks including mobilization, permits, demolition, earthworks, structural works, and finishing tasks, along with their respective durations and timelines. Key milestones and dependencies are also indicated throughout the project schedule.

Uploaded by

kurtmet
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
34 views

House Renovation WORK PROGRAM Critical Path. PDF

The document outlines a construction work program and Gantt chart for a house renovation project scheduled from October 2024 to March 2025. It details various tasks including mobilization, permits, demolition, earthworks, structural works, and finishing tasks, along with their respective durations and timelines. Key milestones and dependencies are also indicated throughout the project schedule.

Uploaded by

kurtmet
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

CONSTRUCTION WORK PROGRAM & GANTT CHART

ID Task Name Duration Start Finish


Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025
Oct Nov Dec Jan Feb Mar Apr
1 House Renovation 141 days Thu 10/10/24 Mon 31/03/25
136.13 Thu 10/10/24 Wed 26/03/25
Mobilization/Demobilization
3 Mobilization/Demobilization 130 days Thu 10/10/24 Tue 18/03/25 10/10 18/03

4 Building permit, Occupancy Permit and LGU 0 days Mon 21/10/24 Mon 21/10/24 21/10

5 Building Administration Construction Permit 0 days Mon 21/10/24 Mon 21/10/24 21/10

6 Contractor's All Risk Insurance (CARI) 0 days Mon 21/10/24 Mon 21/10/24 21/10

7 Construction Bond, Security Deposit, etc. 0 days Mon 21/10/24 Mon 21/10/24 21/10
Lot Survey and Location Plan
8 Lot Survey and Location Plan 1 day Mon 21/10/24 Tue 22/10/24 21/10 22/10

9 Construction Drawings 0 days Mon 21/10/24 Mon 21/10/24 21/10

10 As-Built Drawings 0 days Wed 26/03/25 Wed 26/03/25 26/03


Demolition Works
11 Demolition Works 42 days Mon 21/10/24 Sat 07/12/24 21/10 07/12

12 Others 0 days Mon 21/10/24 Mon 21/10/24 21/10

13 Temporary Power Consumption 0 days Mon 21/10/24 Mon 21/10/24 21/10

14 Temporary Water Consumption 0 days Mon 21/10/24 Mon 21/10/24 21/10

15 Security Services 0 days Mon 21/10/24 Mon 21/10/24 21/10

16 Cleaning and Housekeeping 0 days Mon 21/10/24 Mon 21/10/24 21/10

17 Earthworks 48 days Mon 18/11/24 Sat 18/01/25


Site Clearing, Excavation
18 Site Clearing, Excavation 20 days Mon 18/11/24 Tue 10/12/24 18/11 10/12
Leveling, Backfill, and Compaction
19 Leveling, Backfill, and Compaction 5 days Thu 02/01/25 Tue 07/01/25 02/01 07/01
Soil Poisoning/ Termite Protection
20 Soil Poisoning/ Termite Protection 3 days Wed 08/01/25 Fri 10/01/25 08/01 10/01
Gravel Bedding
21 Gravel Bedding 5 days Sat 11/01/25 Thu 16/01/25 11/01 16/01
Vapor Barrier
22 Vapor Barrier 2 days Fri 17/01/25 Sat 18/01/25 17/01 18/01

23 Structural Works 70 days Wed 11/12/24 Mon 10/03/25


Footing
24 Footing 5 days Wed 11/12/24 Mon 16/12/24 11/12 16/12
Column
25 Column 4 days Tue 17/12/24 Fri 20/12/24 17/12 20/12
Footing Tie Beam
26 Footing Tie Beam 4 days Sat 21/12/24 Sat 28/12/24 21/12 28/12
Slab on Grade
27 Slab on Grade 7 days Mon 20/01/25 Mon 27/01/25 20/01 27/01
Light Steel Frames
28 Light Steel Frames 30 days Fri 24/01/25 Fri 28/02/25 24/01 28/02
Suspended slab
29 Suspended slab 10 days Wed 05/02/25 Sat 15/02/25 05/02 15/02
Main Stairs
30 Main Stairs 10 days Tue 28/01/25 Fri 07/02/25 28/01 07/02
Laundry Stairs
31 Laundry Stairs 10 days Sat 08/02/25 Wed 19/02/25 08/02 19/02
Roofing Works
32 Roofing Works 8 days Sat 01/03/25 Mon 10/03/25 01/03 10/03

33 Civil and Architectural Works 30 days Mon 17/02/25 Mon 24/03/25


Walls/Wall Finishes
34 Walls/Wall Finishes 15 days Mon 17/02/25 Thu 06/03/25 17/02 06/03
Ceiling/Ceiling Finishes
35 Ceiling/Ceiling Finishes 10 days Tue 11/03/25 Fri 21/03/25 11/03 21/03
Floor/Floor Finishes
36 Floor/Floor Finishes 25 days Sat 22/02/25 Mon 24/03/25 22/02 24/03
Doors and Windows
37 Doors and Windows 12 days Fri 07/03/25 Thu 20/03/25 07/03 20/03

38 Electrical Works 43 days Wed 11/12/24 Wed 05/02/25


Wires & Cables, Conduits, Fixtures, Wiring Devices
39 Wires & Cables, Conduits, Fixtures, Wiring 30 days Wed 11/12/24 Wed 05/02/25 11/12 05/02

40 Plumbing Works 10 days Wed 11/12/24 Sat 21/12/24


Waterline System
41 Waterline System 10 days Wed 11/12/24 Sat 21/12/24 11/12 21/12
Sanitary and Storm Line
42 Sanitary and Storm Line 10 days Wed 11/12/24 Sat 21/12/24 11/12 21/12
Catch Basin, Septic Vault, Grease Trap
43 Catch Basin, Septic Vault, Grease Trap 10 days Wed 11/12/24 Sat 21/12/24 11/12 21/12

44 Painting Works 50.88 Thu 30/01/25 Mon 31/03/25


Concrete Wall
45 Concrete Wall 13 days Fri 14/03/25 Sat 29/03/25 14/03 29/03
Steel Members
46 Steel Members 5 days Thu 30/01/25 Wed 05/02/25 30/01 05/02
Drywall Partition
47 Drywall Partition 8 days Mon 17/03/25 Wed 26/03/25 17/03 26/03
Ceiling
48 Ceiling 8 days Sat 22/03/25 Mon 31/03/25 22/03 31/03
Waterproofing Works
49 Waterproofing Works 5 days Mon 17/02/25 Fri 21/02/25 17/02 21/02

50 Completion 0 days Mon 31/03/25 Mon 31/03/25 31/03

Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Critical Split Manual Progress

Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Critical Progress