0% found this document useful (0 votes)
7 views

Report 4

The Daily Site Report for the Labour Accommodation project at Al Hamra Industrial Zone details the manpower, subcontractors, and equipment on site as of June 19, 2024. Key activities include ongoing block work and steel reinforcement for various raft blocks, with plans for continued work on carpentry and concrete preparation. The report highlights a total of 56 manpower and 40 pieces of equipment currently engaged in the project.

Uploaded by

ringwala.anish
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
7 views

Report 4

The Daily Site Report for the Labour Accommodation project at Al Hamra Industrial Zone details the manpower, subcontractors, and equipment on site as of June 19, 2024. Key activities include ongoing block work and steel reinforcement for various raft blocks, with plans for continued work on carpentry and concrete preparation. The report highlights a total of 56 manpower and 40 pieces of equipment currently engaged in the project.

Uploaded by

ringwala.anish
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 8

Daily Site Report

Project Name: LABOUR ACCOMMODATION AT AL HAMRA INDUSTRIAL ZONE


Client: RAKEZ Date: 19-Jun-24
Consultant: GEO-GLOBAL ENGINEERING OFFICE

Contractor: GULF CO FOR CONT &GENERAL ENTERPRISES Ref.No JR 0003-Civil-090

Project Commencement Date: 01-Apr-24 Passed Days


Building Permit Date: Remaining Days
Project Completion Date: Weather: Sunny Day
Manpower Subcontractors Equipment
Trade No. Trade No. Company C S M H total Type No. Type No.
Project Director (P.T) 1 Charge Hand 2 al forsa al dhahbia 6 6 3 15 Generator 2 Power Float
Project Manager 1 Timekeeper AL-Raqim 20 6 26 Roller Compactor 1 Tower Light
Project Tech Manager (P.T) 0 Steel Fixer al bab al salb 22 8 30 Backhoe Loader (JCB) Air compressor
MEP (PM) (P.T) 1 Carpenter 9 block work 5 5 Skid loaders (Bobcat) 1 Automatic Level

Construction Manager 0 Mason 8 water proof 11 11 BullDozer 0 Total Station 1

Proj. engneer 1 Labor 4 Shovel 2 Manlift


Planning Eng (Part Time) 0 Electrician 3 Pick-up 1 Labor Bus
Construction Manager (Steel) 0 Plumber 3 Mini Bus/ 7 Seater 1 Trucks
QA/QC Eng. 1 Welder Mobile Crane 1 Scissor Lift
Safety Eng. (P.T) 0 Office Boy Baby Roller 1 Concrete Mixer M/C
Safety Officers 1 Watchman 1 Dumper truck Welding M/C
Draftsman 1 Drivers 1 Boom Loader 2
Doc.Controller/Sec. 1 Operators 5 Wood Cutter 2
Surveyor 1 Asst Foreman 1 Steel Cutting Machine 6
Asst. Surveyor 2 Asst Storekeeper 1 Steel Bending Machine 6
Safety Marshal 0 Rest Room Cleaner 0 Vibrator 7
Storekeeper 1 Chain Man Excavator
QS Engineer (Part time) 0 Rigger 0 Six Wheel Truck
Foreman 1 AC Technician 0 Grader 1
Scaffolder Cube Checker Water tanker 5
Flagman 1 Document Asst
MEP Foreman 1 Painter 3
Total Manpower 56 Total 87 Total Equipment 40
Activities Remarks
Yesterday Activities Actual Activities Planned for Tomorrow

1- continu steel works bottom steel for raft 1 block


1 1-continu block work for strips of raft no 2 for block 1 and 2 1- block work for strips of raft no 2 for block 1 and 2
no 2.

2-continu steel works bottom steel for raft 1 block


2 2- repar of concrete pcc for canteen. 2- water proof for raft 1 block no 1 and 2 .
no 1

3- continu steel works bottom steel for raft 1 block no 2. 3- continu steel works bottom steel for raft 1 block no 2. 3-carpinter will start shutter for footing

4- started bottom steel for raft 1 block no 1 4- continu steel works bottom steel for raft 1 block no 1 4- carpenter work prior to start pcc for block 3.

5 5-

8
9
10
11

12

Concerns

Project Manager: Engineer Received Signature:

You might also like