Method Statement of Sewerage Network Construction0918

This document outlines the method statement for the construction of a sewage network in Riyadh Sedra 2, detailing the purpose, scope of work, resources, construction procedures, quality control, and safety management. It includes specific steps such as material procurement, trench excavation, pipe installation, and backfilling, along with quality and safety requirements. The document serves as a guideline to ensure compliance with project specifications and standards.

Uploaded by

hasnainkhattak
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
68 views12 pages

Method Statement of Sewerage Network Construction0918

This document outlines the method statement for the construction of a sewage network in Riyadh Sedra 2, detailing the purpose, scope of work, resources, construction procedures, quality control, and safety management. It includes specific steps such as material procurement, trench excavation, pipe installation, and backfilling, along with quality and safety requirements. The document serves as a guideline to ensure compliance with project specifications and standards.

Uploaded by

hasnainkhattak
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 12

Document Method Statement of Sewage Network Construction

Revision 00
No. 00102-CHE-MST-00002

Infrastructure Works for


Riyadh Sedra 2

Method Statement of
Sewerage Network
Construction

Sep 18, Wang tz Wang Jibiao Jiang Weijie Issued For


00
22 Approval
Rev No. Date Prepared By Reviewed By Approved By Remarks
Content
1. Purpose of This Method Statement..............................................................................................1
2. Scope of Work...............................................................................................................................1
2.1 Objective.............................................................................................................................1
2.2 Content...............................................................................................................................1
3. Reference......................................................................................................................................1
4. Difinitions......................................................................................................................................2
5. Resources......................................................................................................................................3
5.1 Human resources................................................................................................................3
5.2 Equipment...........................................................................................................................4
6. Construction Procedures...............................................................................................................4
7. Detailed Construction Sequence...................................................................................................4
7.1 Material Procurement.........................................................................................................4
7.2 Surveying and Pipeline Axis Setting Out..............................................................................4
7.3 Trench Excavation................................................................................................................5
7.4 Pipe Installation...................................................................................................................6
7.5 Pipe Test..............................................................................................................................7
7.6 Backfilling............................................................................................................................7
8. Quality Requirements and Control................................................................................................7
8.1 Quality Control....................................................................................................................7
8.2 Quality Control Inspection and Testing...............................................................................8
9. Safety and Environment Management.........................................................................................8
9.1 General Policy.....................................................................................................................8
9.2 Induction.............................................................................................................................8
9.3 Personal Protective Equipment...........................................................................................8
9.4 Environment Protection......................................................................................................8
1. Purpose of This Method Statement
In accordance with project specifications and relevant requirements, for the purpose of providing
overall construction procedures as well as some specific construction methods with detailed
construction work craft, hereby CHEC prepare this construction method statement for the specific
guideline for this project.
2. Scope of Work
2.1 Objective
This scheme is based on the latest version of the drawing for the preliminary construction of the
sewage networks system. The main reference specifications are the British standard, American
standard and local Saudi standard. The manpower, equipment and materials is obtained by
comprehensive analysis based on the summary of local construction experience in Saudi Arabia.
2.2 Content
This Scope of WORK includes the following construction:
 The Material Procurement.
 Surveying and Pipeline Axis Setting Out.
 Trench Excavation
 Pipe Installation
 Pipe Test
 Backfilling
3. Reference
A The Tender Documents
1 Volume 0 - Project Brief
2 Volume 1 - General requirements
3 Volume 2 - Specs, MOM, and Vendor List
4 Volume 4 - Roshn's Delivery Program
B Investigation Design and Employer Documents
RIYADH SEDRA 2 PUBLIC FACILITIES 2A & 2B INFRA & Utility buildings BASIS OF
1
DESIGN REPORT
2 2A SEWAGE Network Drawings
3 2B SEWAGE Network Drawings
C Submitted file
1 Emergency Preparedness and Response (EPR) Plan

1
2 COVID-19 Pandemic Management (CPM) Plan
3 Survey Instrument Calibration Certificate
4 Lifting Management Plan
5 Equipment Mobilization Plan
D Laws, Regulations, Standards, Norms
BS 2494 Elastomeric seals for joints in pipework and pipelines
BS 2494 Methods of testing plastics
BS 3063 Dimensions of gaskets for pipe flanges
BS 3532 Method of specifying unsaturated polyester resin systems
BS 4346 Joints and fittings for use with un-plasticised PVC pressure pipe
BS 4660 Un-plasticised polyvinyl chloride (PVC-U) pipes and plastics fitings of nominal
sizes 110 and 160 for below ground gravity drainage and sewerage
ISO 4633 Rubber seals-Joint rings for water supply, drainage and sewerage pipelines --
Specification for materials
ISO 4435 Unplasticized poly (vinyl chloride) (PVC-U) pipes and fittings for buried drainage
and sewerage systems - Specifications
ASTM D 2583 Indentation hardness of rigid plastics by means of a Barcol Impresser.
ASTM D 638 Standard Test Method for tensile properties of Plastics.

Code of practice for design and construction of glass reinforced plastics (GRP)
BS 7159 piping systems for individual plants or sites.
BS 3749 Specification for E glass fiber woven roving fabrics for reinforcement of polyester
and epoxy resin systems.
BS 3396 Woven glass fiber fabrics for plastics reinforcement.
BS 3496 Specifications for E glass fiber chopped strand mat for reinforcement of polyester
and other liquid laminating systems.
4. Difinitions
This area is located in an undeveloped suburb of the city and there are few other buildings in the
construction site area (The underlying pipeline needs to be checked and re-checked before each
section of excavation construction to prevent the old embedment pipeline have been dig a broken).
According to the Tender Documents, we can know the soil quality of this area is well.
The work includes site clearance,excavation,backfilling and compaction of trench, installation of uPVC
pipe, VC pipe,GRP pipe, manholes and relevant pipe fittings, connection to the existing lines, concrete
encasement, set warning tape, installation of manholes, and pipe connection to manhole.

2
Drawing3-1 Layout of sewage network-2A

Drawing 3-2 Layout of sewage network-2B


5. Resources
5.1 Human resources

NO. Personnel Qty


1 Site engineer 1
2 Quality control 1
3 Foreman 2
4 Skilled labor 6
5 Labor 10
6 Surveyor 2
7 Electrician 2

3
8 Driver 4
9 Operator 6

5.2 Equipment
NO. Equipment Type Qty
1 Excavator / 1
2 Generator 36KW 1
3 Cutter 1
4 Road Vibration Roller 1
5 Pump 3KW 2
6 Mobile Crane 25t 1
7 Loaders 3 m3 2
8 Flat Compactor 15KN 2
9 Dump Truck 16m3 2
10 Trailer 12m 1

6. Construction Procedures
Material Procurement→ Surveying and bench mark Setting Out→ Trench Excavation →Construction of
Concrete Bedding (if required) → Pipe and Manholes Installation→ Pipe Test → Concrete
Encasement(if required) →Backfilling
7. Detailed Construction Sequence
7.1 Material Procurement
All the materials shall be inspected in accordance with the requirements of the Specification and
cannot be used unless they are proved qualified.

7.2 Surveying and Pipeline Axis Setting Out


With reference to the drawings, the central benchmark of the pipeline will be set by GPS surveying;
the locations of bends and valve chambers are marked and staked with GPS and level according to
benchmarks. The central axis of the pipeline in a portion of a straight line is marked with lime.
Where obstacles are found above or underground within the site, they shall be marked and removed
or be provided with protection measures while setting out.
All sewage pipelines shall be laid accurately to the lines, and levels gradients shown on the approved
drawings so that the pipeline is straight between successive manholes in the vertical and horizontal
planes.

4
Drawing 7-1 Setting Out (Indicative)

7.3 Trench Excavation


Trench excavation shall accord with the requirements of the Specification. Trench excavation is mainly
mechanical excavation assisted by manual. Mechanical excavation is carried out with
excavators. We will determine the form of excavation according to the geological survey report. ,such
as step excavation or slope excavation.

DRAWING 7-2 Diagram of Excavation Section

Earth excavated is laid 1.5m away from the top line of the slope. To avoid trench collapse after
excavation and delaying the work progress, pipe installation is executed immediately after excavation
for trench.
The specific excavation width is shown in the section.

5
DRAWING 7-3 PIPE TRENCH DETAIL
The general trench section is as section A shows.

Section A

Where the underground water level is high, CHEC shall adopt an open channel using a sewage pump
for dewatering.

After excavations have been completed to the design level and, the trench formation compacted, the
Contractor shall issue a formal notice to the Engineer that the trench formation is ready between
designated points for inspection. The Engineer will without unreasonable delay inspect the said trench
formation, unless he considers it unnecessary and advises the Contractor accordingly. Any rejection of
trench formation will be confirmed in writing by the Engineer.

6
Drawing 7-4 Trench Excavation Construction (Indicative)

7.4 Pipe Installation


Pipes shall be delivered to the construction area in batch based on the construction schedule. uPVC
pipes shall be flexibly jointed with rubber ring joints. GRP pipe shall be jointed with dual-bell coupling.
The quality of rubber joint rings and solvent cement used as well as the connection method for joints
must be in accordance with the Specification. The pipe is inserted until to the marked line with a chain
hoist or other drawing force machinery, aligning the spigot with the socket to ensure the portion to be
inserted is level. The pipe shall be aligned carefully in both the horizontal and vertical planes. During
laying operations, no debris, tools, cloth or other materials are allowed to enter the pipe. The
connection of pipe to manhole shall use approved epoxy grout for seal.
7.5 Pipe Test
All pipelines shall be tested between manholes or valve chambers not exceeding 400 m.On completion
of testing the section of pipeline shall be properly sealed to prevent the intrusion of any extraneous
matter, until connected to the pipeline network. All flexible pipelines shall be tested for deflection as
per this specification.
7.6 Backfilling
Backfilling shall be done immediately after finishing pipe installation and testing. Provide warning tape
located at 300 mm above the top of the pipe in all trenches.
Trench Backfilling (Within the Pipe Zone): Trench backfill shall contain no rocks or stones larger than 25
mm in the greatest dimension and shall be free of vegetation, trash, chunks of highly plastic clay, or
other unsatisfactory- material.
Trench backfilling consists of two procedures: a) Backfilling prior to Test. The trench shall be hand
tamped and backfilled with part of sand above the pipe and leave the pipe joints clean. The gap
between the bottom of the pipe and the trench bottom must be tamped and no backfilling is allowed
within 0.3m on each side of the connection for further test observation. b) Massive backfilling after the
pipe is approved quality fied with an ex-filtration test. Backfilling is executed on both sides of the pipe

7
simultaneously and the soil shall be compacted layer by layer.
8. Quality Requirements and Control
8.1 Quality Control
 The sewage activity shall follow as per the approved ITP, Drawing and project Specification.
 All material receiving inspection carried out and gets approved from ENGINEER.
 Inspection and Test by the Manufacturer: Pipe and fittings shall be thoroughly inspected by the
manufacturer before delivery.
 All pipes shall be inspection by a competent inspector employed by the purchaser
 Receiving Inspection of Materials shall be conducted by QCI through MIR.
 Storage, Handling and Preservation of Materials shall be maintained as per Manufacturer
Recommendations and project specification
 Rejected pipe shall not be defaces, but shall be replaced by the manufacturer or seller without
additional cost, with pipe that meets the requirements of this specification
 Quality Manager / Inspector shall monitor all activities to ensure that work is done as per
approved drawing.
 Quality control inspector shall do all required inspections as per approved ITP and project
Specifications.
 All the construction activities shall be done as per project specification and applicable Standards .
 All the WIRs shall be submitted as per approved ITP.
 Contractor Inspectors shall closely monitor and assure that all the activities are carried out.
 All the quality records and test reports shall be submitted for review and final acceptance.
8.2 Quality Control Inspection and Testing
 The QC Inspector shall have on site, all times, the necessary proper calibrated and maintained
testing and inspection instruments.
 Test certificates for all type tests and other tests specified in this Clause shall be submitted to the
Engineer.
9. Safety and Environment Management
9.1 General Policy
It is the general policy of CHEC to provide all employees, subcontractors and any other persons with
reason to attend our working place the following:
 Safe access to and from the working place;
 A safe place to work;
 A safe system of work.
 All CHEC staff involved in field work should constantly remind themselves of these requirements
and be aware that each of them has a role to play in bringing this about by the correct mental
approach. In particular, the following should be given careful consideration:
 Maintain good housekeeping;
 Teamwork is essential; be aware of the activities of others;
 Whilst working be aware of where your colleagues are working;

8
 Work in pairs whenever possible;
 Adhere to safe working practices;
 Plan and practice your escape routes and emergency procedures regularly;
9.2 Induction
Personnel on site shall undergo an initial site HSE induction from Contractor. Before entry to the
working areas are gained, this shall be site specific and details the hazards most likely present within
the site, the emergency procedures, and site-specific restrictions.
9.3 Personal Protective Equipment
Appropriate PPE shall always be worn by personnel when on site and involved in survey operations.
This will include, but not be limited to, coveralls, safety helmet, safety boots, and gloves if handling
wire or equipment.
Other items of PPE shall be worn as applicable.
9.4 Environment Protection
9.4.1 During surface clearance CHEC shall dispose vegetation and relevant rubbish to proper locations.
9.4.2 Upon slurry incurred during foundation excavation works, if not suitable for backfilling CHEC shall
dispose to proper locations.
9.4.3 During concrete casting CHEC shall strictly control the remaining concrete treatment and dump it
into proper locations.
9.4.4 CHEC shall check up all machinery equipment on a daily basis to avoid oil contamination.
9.4.5 Other requirements shall be referred to the Safety file.