Construction Cost-Influencing Factors: Insights from a Survey of
Engineers in Saudi Arabia
Ibrahim Mosly
Abstract: Cost overruns represent a continuous challenge within the construction industry, fre-
quently affecting the success of projects. This study explores the factors influencing cost during
the construction phase in Saudi Arabia, utilizing data from a survey of 1076 engineers working in
the Saudi construction industry. The results identify a number of cost-related factors, including
inadequate project management, poor cost estimation, and design errors. Interestingly, some factors,
such as currency exchange rate fluctuations and social and cultural influences, were found to have a
limited impact on construction costs. Furthermore, the study highlights the role of experience and
education level in shaping engineers’ perceptions of these cost factors. The study employs statistical
analysis, including Pearson’s chi-squared test, to demonstrate associations between demographics,
project characteristics, and cost-influencing factors. The findings suggest the need for refined project
management practices, enhanced technical training, and the implementation of digital technologies
such as Construction 4.0 to mitigate cost-related risks. This research provides significant insights for
construction professionals and policymakers seeking to enhance cost management within the Saudi
construction sector, thereby contributing to the ongoing development initiatives aligned with Saudi
Arabia’s Vision 2030.
1. Introduction
Citation: Mosly, I. Construction
Cost-Influencing Factors: Insights
Although the construction industry has a crucial role in the continuous improvement
from a Survey of Engineers in Saudi
of the quality of human life, it has been noted that this industry has resulted in various
Arabia. Buildings 2024, 14, 3399. environmental complications that have impacted our world [1]. This dual impact makes the
https://doi.org/10.3390/ management of construction projects mostly challenging. Sophisticated and dynamic envi-
buildings14113399 ronments with many interrelated factors cause high uncertainty in construction projects [2].
This uncertainty is further compounded by the inherent complexity of construction projects.
Academic Editor: Pramen P. Shrestha
Construction projects are fundamentally complex and involve numerous variables that can
Received: 7 October 2024 significantly impact their costs. Cost is the most important factor in any business, including
Revised: 21 October 2024 the construction industry [3]. Therefore, effective cost management is not just important
Accepted: 23 October 2024 but essential. Managing these costs effectively is crucial for the successful completion of
Published: 25 October 2024 projects within budgetary constraints. To achieve this, it is essential to implement cost
management from the beginning of the project in order to accomplish it within budget and
ensure that it is on time and of high quality [4].
Construction projects play a pivotal role in economic development, yet they frequently
Copyright: © 2024 by the author.
encounter significant challenges that lead to cost overruns, impacting the overall success
Licensee MDPI, Basel, Switzerland.
and viability of projects. These challenges are a global phenomenon and not limited to any
This article is an open access article
distributed under the terms and
one region. The construction industry faces several major challenges, including developing
conditions of the Creative Commons
accurate estimates in context with recent technological and intelligence advancements, as
Attribution (CC BY) license (https:// well as effectively implementing projects within these cost budgets [5]. Despite advance-
creativecommons.org/licenses/by/ ments in technology and project management techniques, the majority of construction
4.0/). projects were completed at a significantly higher cost compared to the original contract
value [6]. This has led to a situation where many projects are not completed within the
allocated project budget, which eventually leads to cost overruns and causes a negative
effect on the client and the contractor–consultant relationship, leading to mistrust, litiga-
tion, and arbitration [7]. Nevertheless, the continuous advancement in digital construction
technologies, such as building information modeling (BIM), artificial intelligence (AI), and
automation, will provide strategies on how to reduce cost overruns. For instance, BIM can
be used to provide accurate quantities for procurement [8], which increases efficiencies in
cost estimation. Furthermore, AI can analyze historical project data and identify patterns
that lead to more accurate cost forecasts [9]. Moreover, automation and robotics can assist
in reducing labor costs and increasing efficiencies on construction sites [10].
In Saudi Arabia, the construction sector plays a vital role in the national economy,
driven by ambitious development plans and large-scale infrastructure projects. However,
this sector also faces challenges related to cost management. As is the case in other parts
of the world, cost overruns are common in the construction industry in Saudi Arabia [11].
Many factors are related to this cost overrun, ranging from technical issues, such as design
changes and equipment breakdowns, to external influences like economic fluctuations and
regulatory requirements. For instance, inflation affects construction project prices, causing
cost overruns that require budget adjustments [12]. Another significant factor is rework,
which contributed to 52% of a project’s cost growth and 26% of its variance [13]. Given
these challenges, understanding the factors that influence costs during the construction
phase is essential for project managers, contractors, and stakeholders to mitigate risks and
ensure financial sustainability.
Despite the extensive body of research on construction cost management [2,5,7,14–20],
there remains a need for region-specific studies that address the unique conditions and
challenges faced by the construction industry in Saudi Arabia. This research aims to fill this
gap by investigating the factors influencing construction costs during the construction phase
within the context of Saudi Arabia. This is due to the distinct nature of the construction
industry of Saudi Arabia, characterized by large-scale infrastructure projects driven by the
country’s Vision 2030 development plan. This context introduces unique challenges that
are not addressed in global studies. The construction phase was selected for this research
because most cost-intensive costs occur during this stage and it involves a high number
of uncertainties. This study aims to answer the following research questions: (1) How do
engineers’ demographics influence their perception of construction cost-influencing factors?
(2) How do project-specific characteristics affect engineers’ perceptions of cost-influencing
factors? and (3) What are the implications and policy recommendations for construction
industry practices? Furthermore, the study seeks to provide valuable insights and practical
recommendations for improving cost management practices in the construction industry.
To achieve this objective, a comprehensive literature review was conducted to identify
key factors influencing construction costs. Based on the findings, a detailed questionnaire
was developed and distributed to engineers in the construction industry using Google
Forms. The collected data were then analyzed using statistical methods to identify signifi-
cant factors and their impact on construction costs. The results of this study will contribute
to the existing body of knowledge and offer practical guidance for stakeholders involved
in construction projects in Saudi Arabia. This research addresses a critical aspect of con-
struction project management by focusing on the factors that influence costs during the
construction phase. The findings aim to enhance the understanding of cost management
in the Saudi Arabian construction industry, providing a foundation for better planning,
budgeting, and risk mitigation strategies.
2. Literature Review
2.1. Cost Overrun Issues in the Construction Industry Worldwide
The cost overruns in the residential construction sector range from 21% to 55.19% [20].
This statistic highlights the severity of the problem and its impact on the construction
Buildings 2024, 14, 3399 3 of 19
industry. A number of studies have been conducted across different countries to identify
the main factors contributing to these cost overruns.
A significant observation has been made regarding the challenges faced by the major-
ity of project managers and contractors in Egypt when it comes to managing construction
project costs [21]. These challenges arise from several issues such as change orders, design
changes, design errors, the deteriorating economic situation, project delays, and the increas-
ing price of materials [21]. These factors are not limited to Egypt; rather, cost overruns are
a global challenge in the construction industry.
In Malaysia, a study that involved 79 cost-influencing factors found that client re-
quirements on finishing quality were found to be the most critical influencing factor on
construction cost [19]. Additionally, another study in Malaysia that explored the factors
influencing cost variance during the construction phase resulted in identifying the high-
est influencing factors. The top five were, as follows: incomplete design drawings and
specifications; changes in client requirements; financial difficulties faced by the contractor;
fluctuations in material prices; and poor planning, scheduling, and monitoring [6]. These
findings outline the complexity of construction cost management and the various factors
that can cause deviations from the initial planned budget.
A study that involved experts from the Chinese construction industry showed that the
most critical and common factors influencing construction cost are, as follows: market price
changes; national policy changes; currency exchange rate fluctuations; inadequate contract
management; inadequate risk management; insufficient design; major infectious diseases;
natural disasters; project location limitations; design changes; poor drawing design; and
fraud behavior and rebate [7]. Similarly, the impact of external factors, such as market price
changes and national policy changes, cannot be overlooked.
Another study that took place in Trinidad and Tobago found that the top factor
that contributes to cost overruns in public sector construction projects is the selection of
politically aligned contractors [22]. This study highlights the influence of non-technical
factors on construction costs in certain countries.
A Saudi Arabian study has identified six types of construction materials and trades
that have significant impact on construction project costs, these are, as follows: thermal
and moisture protection; site work; concrete work; conveying systems; electrical work; and
mechanical work [23]. Material costs have a significant role in determining the total project
cost, as any fluctuation in their prices can lead to substantial cost overruns.
In certain types of construction projects, such as road projects, a study found that cost
underestimation is more predominant than cost overestimation [24]. This finding suggests
that initial project estimation usually fails to account for all possible cost triggers.
An Indonesian study found that the rise in fuel prices is considered the variable with
the highest impact on construction costs and may lead to an increase in costs of 20–40% of
the original contract value [25]. This reflects the sensitivity of construction project costs to
fluctuations in essential elements such as fuel.
In India, the Ministry of Statistics and Program Implementation identified the follow-
ing factors for construction overruns: time overruns; changes in foreign exchange rate;
expensive environmental protection and rehabilitation measures; high land acquisition
cost; project scope changes; bidders charging extra in certain areas; underestimation; and
increases in prices [16]. These factors emphasize the complicated nature of cost overruns,
involving both technical and external elements. Another study in India identified the
following as the most significant factors of cost overruns: rework; construction delays;
ineffective planning and monitoring; delays in decision-making; disputes; and inflation [26].
All these factors contribute directly to increased costs and are common in the construction
industry in other countries as well.
A study that investigated the factors leading to cost overruns in Vietnam found
that the top five factors are, as follows: (1) project implementation schedule extension;
(2) rapid increase in site worker demand; (3) contract suspension or arbitrary cancellation;
(4) contractors’ poor management and supervision of quantities; and (5) construction site
Buildings 2024, 14, 3399 4 of 19
handover delays and incompleteness [18]. This highlights the vital role of effective project
management and supervision in controlling construction costs.
3. Methodology
The methodology of this research involved a multi-step process to thoroughly under-
stand the factors influencing construction costs during the construction phase. Initially, a
comprehensive literature review was conducted using the Saudi Digital Library to gather
scholarly research on the relevant factors that exist in a global context. The focus was
given to peer-reviewed journal articles and conference papers that directly relate to the
study topic. Keywords such as ‘construction industry’, ‘cost overruns’, ‘factors’, and ‘Saudi
Arabia’ were used to search for relevant studies in the literature. Insights from this review
informed the development of a detailed questionnaire, which was designed to include de-
mographics and project-specific characteristics affecting construction costs. Google Forms
was selected for its ease of use, accessibility, and the need to collect data from a large
and geographically diverse sample across Saudi Arabia. The questionnaire was actively
collecting data from 28 November 2023 to 3 April 2024. However, data collection efforts ex-
ceeded expectations, resulting in 1211 responses. Incomplete responses were then excluded
from the study, and 1076 responses were deemed valid for analysis. To ensure a diverse
and representative sample, the questionnaire was distributed by visiting several random
locations where engineers can be found working, including, but not limited to, consulting
engineering offices, contracting companies, real estate development companies, and ongo-
ing construction projects. The selection of engineers was driven by their critical influence
on cost management, whether they were site engineers, project managers, construction
managers, designers, or hold any other role in their institution. They are directly involved
in decisions that impact project costs, making them the most relevant stakeholders for
assessing the factors influencing construction costs. Formal ethical approval was exempted
for this study by the Research Ethics Committee at King Abdulaziz University. Participants
were informed of the study purpose, and participation consent was obtained before they
started the questionnaire. Data were treated anonymously to protect participants’ identities,
and all responses were securely stored.
The collected data were then analyzed using SPSS 22 (Statistical Package for the Social
Sciences). It was chosen due to its vigorous capabilities in handling large datasets and
a wide range of statistical analyses. The analysis included frequency distributions and
percentages, as well as descriptive statistics to understand the central tendencies and
dispersion of the data by calculating the mean of each factor. To measure the consistency
of the questionnaire used for data collection in this study, a reliability analysis was used.
This was conducted using Cronbach’s alpha, which measures the scale of reliability and is
considered the most commonly used analysis method [49]. Cronbach’s alpha was calculated
for each of the multi-item scales representing the factors influencing construction costs.
Furthermore, Pearson’s chi-squared (χ2 ) test was used to compare the collected data to a
hypothetical model [50]. This was conducted to explore the relationship between categorical
variables [49], specifically exploring the association between participant demographics,
project-specific characteristics, and construction cost-influencing factors. For this reason,
the Pearson’s chi-squared (χ2 ) test represents an appropriate choice for analyzing the
relationships between variables in this study. The Pearson’s chi-squared (χ2 ) test was
conducted using Equations (1) and (2) [49], as follows:
2
Oij − Mij
2
χ = ∑ Mij
(1)
where
• χ2 represents the Pearson’s chi-squared statistic;
• i represents the row in the contingency table;
• j represents the columns in the contingency table;
• Oij represents the observed frequency;
• Mij represents the model frequency, as follows:
Buildings 2024, 14, 3399 6 of 19
d f = (r − 1)(c − 1) (2)
where
• df represents the degree of freedom;
• r represents the number of rows;
• c represents the number of columns.
The chi-squared (χ2 ) statistic was compared against a critical value from the chi-squared
distribution table at a significant level of 0.05 for the purpose of hypotheses testing. A p-value
less than 0.05 indicated a statistically significant association between the variables, leading to
the rejection of the null hypothesis (H0 ) in favor of the alternative hypotheses (H1 ).
This research aims to answer the following questions:
1. How do engineers’ demographics influence their perception of construction cost
influencing factors?
2. How do project-specific characteristics affect engineers’ perceptions of cost-influencing
factors?
3. What are the implications and policy recommendations for construction industry practices?
The main hypothesis for this research is as follows:
1. Engineers’ demographics vs. factors influencing construction cost.
H0 : There is no significant association between the engineers’ demographics and their
perception of factors influencing construction costs.
H1 : There is a significant association between the engineers’ demographics and their
perception of factors influencing construction costs;
2. Project-specific characteristics vs. factors influencing construction costs.
H0 : There is no significant association between the project-specific characteristic and
engineers’ perceptions of factors influencing construction costs.
H1 : There is a significant association between the project-specific characteristic and
engineers’ perceptions of factors influencing construction costs.
This structured methodology ensured a thorough investigation of the factors influencing
14, 3399 7 of 20
construction costs, providing reliable and valid results to inform future practices and policies
in the construction industry. Figure 1 represents the steps conducted to perform this study.
Litrature
review
Questionnaire
survey design
Data
collection
Data analysis
Research
findings
4. Results
4.1. Reliability Analysis
Cronbach’s alpha reliability analysis was carried out on the 18 factors influencing
construction costs in Saudi Arabia that form the basis of this study. The value of α = 0.911
Buildings 2024, 14, 3399 7 of 19
4. Results
4.1. Reliability Analysis
Cronbach’s alpha reliability analysis was carried out on the 18 factors influencing
construction costs in Saudi Arabia that form the basis of this study. The value of α = 0.911
for the 18 factors indicates a high level of consistency among these factors. A Cronbach’s
alpha value that is above 0.90 indicates excellent reliability [50]. Thus, confidence can be
given to the data and findings of this study due to the high reliability score.
The majority of participants in this study specialized in civil engineering (89.5%). Since
this study context is in the area of construction costs, a high participation of civil engineers
will ensure direct benefits and robust data collected in the same field. Engineers from other
specializations have also participated in this study in limited numbers, suggesting some
interdisciplinary input in probably very specific aspects of construction projects. Table 3
illustrates the specialization profiles of questionnaire participants.
Participants with bachelor’s degrees, at 81.5%, represent most of the sample size of
this study. Postgraduate studies holders of both master’s degrees and PhDs represent 18.6%
of the participants, indicating the involvement of professionals with managerial expertise
along with research backgrounds. Table 4 illustrates the academic qualifications profiles of
questionnaire participants.
Buildings 2024, 14, 3399 8 of 19
The findings show that 38.9% of participants work in the Saudi Arabian capital,
Riyadh, which is considered a major economic hub. The city of Jeddah follows, with
18.8% of participants working there. Riyadh and Jeddah are the largest cities in Saudi
Arabia in terms of size and population. Participants spread across various cities in Saudi
Arabia are represented in this study. This guarantees widespread geographical insights
into construction cost factors in Saudi Arabia. Table 8 illustrates the project locations that
questionnaire participants were involved in.
The study’s descriptive statistics identify the rankings of the factors influencing con-
struction costs in Saudi Arabia according to their means (see Table 9). The findings show
that inadequate management of project, contract, and communication is the highest in-
fluencing factor, with a mean score of 3.77. This indicates that inadequate contract man-
agement and poor communication among project stakeholders can greatly increase the
construction cost. Engineers could have perceived this factor as the most influential for sev-
eral reasons, including centralized decision-making, inconsistencies in project management
practices, and limited training in this factor aspect. This can be addressed by promot-
ing effective project management practices and providing extensive training programs to
improve management skills and communication.
Buildings 2024, 14, 3399 10 of 19
Table 9. Mean value for factors influencing construction costs during the construction phase.
Factor Mean
Inadequate management of project, contract, and communication 3.77
Inadequate cost estimation 3.68
Inadequate planning and scheduling 3.65
Design error/weakness 3.63
Design changes 3.61
Lack of technical knowledge and experience 3.57
Delay in project/owner payment 3.47
Rework 3.44
Economic fluctuation/market price changes 3.43
Staff corruption 3.23
Poor/unclear drawing 3.15
Legal disputes between various parties 3.12
Equipment breakdowns and inefficiencies 3.00
Force majeure and environmental issues 2.86
Safety issues and accidents 2.86
Governmental regulations 2.74
Currency exchange rate fluctuations 2.55
Social and cultural influences 2.39
The second highly influencing factor is inadequate cost estimation, with a mean score
of 3.68. Inaccurate estimations of costs can lead to budget overruns, schedule delays, and
the failure of projects. It is necessary to implement a robust estimation methodology that
utilizes historical data and incorporate contingency plans to improve cost estimates and
prevent unexpected expenses. Engineers could have perceived this factor as the second
most influential factor due to the limited availability of historical data or the complexity of
large-scale projects with numerous challenges.
Close to inadequate cost estimation is the factor inadequate planning and scheduling,
which has a mean score of 3.65, making it another major factor that greatly influences con-
struction costs in Saudi Arabia. Construction projects with poor planning and scheduling
also face delays and extra expenses. To mitigate this issue, it is essential to conduct proper
planning and scheduling via advanced software that assists in creating detailed project
timelines and tracking of activities with a continuous update option.
Factors that relate to design were also found to significantly influence construction
costs, including design error/weakness (mean score of 3.63) and design changes (mean
score of 3.61). Errors in design will lead to rework and variations, which in turn lead to
additional costs and time delays. This needs to be addressed by ensuring high-quality
designs. Furthermore, design changes during the construction phase should not be made
or at least be kept to a minimum to avoid extra costs.
Lack of technical knowledge and experience also appears among highly influencing
factors, with a score mean of 3.57. This emphasizes the importance of having competent
professionals on the construction team in order to reduce mistakes and increase cost
efficiencies. Project outcomes can be significantly improved by hiring skilled personnel and
providing adequate training to employees.
Interestingly, the findings show that factors, such as currency exchange rate fluctu-
ations (mean score of 2.55) and social and cultural influences (mean score of 2.39), are
perceived as less influential on construction costs by engineers working in Saudi Arabia.
Although several construction materials are imported and should be influenced by currency
exchange rate fluctuations, the pegging of the Saudi riyal to the U.S. dollar may have had a
role in reducing this influence and achieving these results. Moreover, Saudi culture is very
keen on the development of the country, which may have contributed to the social and
cultural influences factor ranking as the least influential among factors on the list.
Buildings 2024, 14, 3399 11 of 19
Table 10. Chi-squared test results for variables where the null hypothesis was rejected in favor of the
alternative hypothesis.
of the impact of governmental regulations on construction costs and the academic qual-
ifications of participants. The majority of bachelor’s degree holders perceive the impact
of governmental regulations as moderate. This is followed by master’s degree holders
who have a higher overall perception, followed by PhD holders, who have the highest
perception compared to the others. Thus, we can conclude that engineers with a bachelor’s
degree might see governmental regulations as substantial but manageable, that engineers
with a master’s degree have greater involvement in navigating regulatory requirements,
and that engineers with a PhD are involved in projects that are significantly influenced
by regulations.
Experience vs. Currency exchange rate fluctuations: Similar to age vs. currency
exchange rate fluctuations, the p-value (0.001) indicates a significant relationship between
the experience of the participants and their perception of the impact of currency exchange
rate fluctuations on construction costs. This could be due to different levels of exposure
to international markets and economies in their professional careers. The linear-by-linear
association (p-value = 0.000) suggests a trend related to the perception of the impact of
currency exchange rate fluctuations on construction costs and the experience of participants.
The majority of engineers with less than 5 years of experience perceive the impact of
currency exchange rate fluctuations on construction costs as very low; this is followed by
engineers with 5–10 years of experience who have a higher perception of the impact of
currency exchange rate fluctuations on construction costs. On the other hand, the majority
of engineers with more than 20 years of experience perceived the impact of currency
exchange rate fluctuations on construction costs to be the highest. Thus, we can conclude
that as engineers gain experience, they recognize the significance of currency exchange
rate fluctuations on construction costs due to their extensive experience with multi-projects
with economical changes.
Experience vs. Design error/weakness: The p-value (0.004) indicates a significant
relationship between the experience of the participants and their perception of the impact
of design error/weakness on construction costs. This could be due to different levels of
exposure to design challenges and ways to manage them in their professional experience.
Engineers with less experience might benefit from extensive design training, while more
experienced engineers could focus on advanced design reviews that can lead to better
cost management.
Experience vs. Staff Corruption: The p-value (0.033) indicates a significant relationship
between the experience of the participants and their perception of the impact of staff
corruption on construction costs. This could be due to different levels of exposure to
corruption-related issues during their professional career. The linear-by-linear association
(p-value = 0.007) suggests a trend related to the perception of the impact of staff corruption
on construction costs and the experience of participants. The results show that the more
experienced the engineer, the more he recognizes the significant influence of staff corruption
on construction costs.
Experience vs. Safety issues and accidents: Similar to age vs. safety issues and
accidents, the p-value (0.030) indicates a significant relationship between the experience
of the participants and their perception of the impact of safety issues and accidents on
construction costs. This could be due to different levels of exposure to safety protocols
and incidents involving risks and hazards during their professional careers. The linear-by-
linear association (p-value = 0.010) suggests a trend related to the perception of the impact
of safety issues and accidents on construction costs and the experience of participants.
The results show that highly experienced engineers recognize the significance of safety-
related problems but at the same time have developed the skills to manage and mitigate
safety concerns, while less experienced engineers, on the other hand, struggle more with
safety management.
Buildings 2024, 14, 3399 14 of 19
Project size vs. Economic fluctuation/market price changes: The p-value (0.028)
indicates a significant relationship between project size and the perception of the impact of
economic fluctuation/market price changes on construction costs. This could be due to
the different sensitivities of projects to international economic conditions based on their
scale. The linear-by-linear association (p-value = 0.007) suggests a trend related to the
perception of the impact of economic fluctuation/market price changes on construction
costs and project size. The results show that small-sized projects are impacted by economic
fluctuation/market price changes, but that their overall influence is less critical compared
to larger projects involving major investment, which are very sensitive to fluctuations
in prices.
Project size vs. Social and cultural influences: The p-value (0.021) indicates a significant
relationship between project size and the perception of the impact of social and cultural
influences on construction costs. This could be due to the different sensitivities of projects
to social and cultural factors based on their scale and scope. The linear-by-linear association
(p-value = 0.021) suggests a trend related to the perception of the impact of social and
cultural influences on construction costs and project size. The results show that small-sized
projects are impacted by social and cultural influences but that their overall influence is less
critical compared to larger projects involving significant interactions with several social
and cultural contexts, which require robust assessment and community engagement to
minimize risks.
Project location vs. Design changes: The p-value (0.044) indicates a significant rela-
tionship between project location and the perception of the impact of design changes on
construction costs. This could be due to the different design requirements and tasks for
these projects in different cities. The linear-by-linear association (p-value = 0.006) suggests
a trend related to the perception of the impact of design changes on construction costs
and project location. The results show that engineers perceive design changes to projects
in Riyadh city as impactful, likely because of the city size and project complexity. Fur-
thermore, engineers perceive design changes to projects in Neom and Red Sea projects as
also impactful, likely due to the large scale of these projects and their high profiles. Other
smaller cities, such as Rabigh, Taief, and Skaka have fewer respondents and show varying
perceptions with regard to the impact of design changes. Thus, even small cities can differ
significantly in terms of design change impact.
4.3.3. What Are the Implications and Policy Recommendations for Construction
Industry Practices?
The following are a number of policy recommendations that were derived from the
findings of this study and can help to mitigate the risks associated with cost overruns and
contribute to more efficient and sustainable project outcomes:
1. It is important to promote best practices in project management to address the inad-
equate management of project, contract, and communication, which is the highest
cost-influencing factor;
2. To ensure clear communications among stakeholders, it is important to establish
standardized communication protocols;
3. Robust cost estimation methodologies that integrate historical data and contingency
plans to enhance accuracy should be implemented;
4. The use of cutting-edge planning and scheduling software to generate comprehen-
sive project timelines and continuously monitor its activities should be promoted to
mitigate delays and control costs;
5. High-quality designs should be ensured by conducting frequent reviews and imple-
menting strict quality assurance protocols, which in turn will assist in reducing design
errors and weaknesses’
6. Guidelines should be set to minimize design changes during the construction phase.
To manage additional costs, it is important to perform a comprehensive impact
assessment and obtain approvals for required changes;
Buildings 2024, 14, 3399 16 of 19
5. Conclusions
The findings in this study reveal that inadequate management of projects, contracts,
and communication is the most significant factor contributing to cost overruns. Additional
significant factors included inadequate cost estimation, poor planning and scheduling,
design errors, and a lack of technical knowledge among professionals. In contrast, fac-
tors such as currency exchange rate fluctuations and social and cultural influences were
regarded as having a limited impact, probably owing to the distinct economic stability and
cultural context of Saudi Arabia.
The findings highlight the importance of enhancing project management practices, im-
plementing advanced cost estimation techniques, and using cutting-edge tools for planning
and scheduling. Moreover, the results indicate that encouraging a culture of knowledge-
sharing and mentorship within the construction industry could significantly enhance cost
efficiency. Furthermore, the extensive experience of senior engineers can significantly
contribute to minimizing errors and improving project outcomes.
This study has resulted in several findings that require further study to provide a
comprehensive overview of construction cost-influencing factors in Saudi Arabia. These
future studies may include understanding the limited impact on construction costs of
both currency exchange rate fluctuations and social and cultural influences. Furthermore,
due to the regional variations within Saudi Arabia, it would be beneficial to examine the
differences across regions or project types in terms of construction costs. This comparison
Buildings 2024, 14, 3399 17 of 19
could also be made with other countries that have similar economic and cultural contexts.
Moreover, there is a need to investigate how digital technology adoption may affect the
cost of construction in Saudi Arabia and which of these technologies have the highest
potential for cost reduction. In addition, longitudinal studies to track the evolution of
cost factors over time with the adoption of these technologies would provide valuable
insights. Sustainable development is a necessity these days; therefore, research on the
role of sustainability-related factors and their influence on construction costs is another
interesting topic for future studies.
References
1. Nasereddin, M.; Price, A. Addressing the capital cost barrier to sustainable construction. Dev. Built Environ. 2021, 7, 100049.
[CrossRef]
2. Zhao, L.; Mbachu, J.; Liu, Z. Identifying Significant Cost-Influencing Factors for Sustainable Development in Construction
Industry Using Structural Equation Modelling. Math. Probl. Eng. 2020, 2020, 4810136. [CrossRef]
3. Baria, N.; Yusuff, R.; Ismail, N.; Jaapar, A.; Ahmad, N. Factors Influencing the Construction Cost of Industrialised Building
System (IBS) Projects. Procedia-Soc. Behav. Sci. 2012, 35, 689–696. [CrossRef]
4. Albtoush, A.; Doh, S.; Abdul-Rahman, A. Factors Effecting the Cost Management in Construction Projects. Int. J. Civ. Eng. Technol.
2020, 11, 105–111. [CrossRef]
5. Tayyab, M.; Furkhan, M.; Rizwan, M.; Jameel, M.; Chadee, A. A Study on Factors Influencing Cost Overrun in High-Rise Building
Construction Across India. J. Smart Build. Constr. Technol. 2023, 5, 52–83. [CrossRef]
6. Jamaludin, S.; Mohammad, M.; Ahmad, K. Enhancing the Quality of Construction Environment by Minimizing the Cost Variance.
Procedia-Soc. Behav. Sci. 2014, 153, 70–78. [CrossRef]
7. Xie, W.; Deng, B.; Yin, Y.; Lv, X.; Deng, Z. Critical Factors Influencing Cost Overrun in Construction Projects: A Fuzzy Synthetic
Evaluation. Buildings 2022, 12, 2028. [CrossRef]
8. Valinejadshoubi, M.; Moselhi, O.; Iordanova, I.; Valdivieso, F.; Bagchi, A. Automated system for high-accuracy quantity takeoff
using BIM. Autom. Constr. 2024, 157, 105155. [CrossRef]
9. Shoushtari, F.; Daghighi, A.; Ghafourian, E. Application of Artificial Intelligence in Project Management. Int. J. Ind. Eng. Oper.
Res. 2024, 6, 49–63.
10. Dindorf, R.; Wos, P. Challenges of Robotic Technology in Sustainable Construction Practice. Sustainability 2024, 16, 5500. [CrossRef]
11. Al-Nahhas, Y.; Hadidi, L.; Islam, M.; Skitmore, M.; Abunada, Z. Modified Mamdani-fuzzy inference system for predicting the
cost overrun of construction projects. Appl. Soft Comput. 2024, 151, 111152. [CrossRef]
12. Musarat, M.; Alaloul, W.; Liew, M. Incorporating inflation rate in construction projects cost: Forecasting model. Heliyon 2024,
10, e26037. [CrossRef] [PubMed]
13. Love, P. Influence of Project Type and Procurement Method on Rework Costs in Building Construction Projects. J. Constr. Eng.
Manag. 2002, 128, 18–29. [CrossRef]
14. Wyke, S.; Lindhard, S.; Larsen, J. Using Principal component analysis to identify latent factors affecting cost- and time overrun in
public construction projects. Eng. Constr. Archit. Manag. 2024, 31, 2415–2436. [CrossRef]
15. Daoud, A.; Hefnawy, M.; Wefki, H. Investigation of critical factors affecting cost overruns and delays in Egyptian mega
construction projects. Alex. Eng. J. 2023, 83, 326–334. [CrossRef]
16. Kumar, T.; Priya, M.; Arthi, A.; Singh, V.; Bano, S. Factors Affecting Time and Cost Overruns in the Construction Projects and Its
Control Techniques. J. Balk. Tribol. Assoc. 2022, 28, 26–38.
17. Annamalaisami, C.; Kuppuswamy, A. Managing Cost Risks: Toward a Taxonomy of Cost Overrun Factors in Building Construc-
tion Projects. J. Risk Uncertain. Eng. Syst. Part A Civ. Eng. 2021, 7, 04021021. [CrossRef]
18. Vu, T.; Pham, C.; Nguyen, T.; Nguyen, P.; Phan, P.; Nguyen, Q. Factors Influencing Cost Overruns in Construction Projects of
International Contractors in Vietnam. J. Asian Financ. Econ. Bus. 2020, 7, 389–400. [CrossRef]
Buildings 2024, 14, 3399 18 of 19
19. Kamaruddeen, A.; Sung, C.; Wahi, W. A Study on Factors Causing Cost Overrun of Construction Projects in Sarawak, Malaysia.
Civ. Eng. Archit. 2020, 8, 191–199. [CrossRef]
20. Khodeir, L.; Ghandour, A. Examining the role of value management in controlling cost overrun [application on residential
construction projects in Egypt]. Ain Shams Eng. J. 2019, 10, 471–479. [CrossRef]
21. Aboelmagd, Y. Assessments of Barriers to Implementing Cost Control and Optimal Cost Reduction Techniques in Construction
Projects: A Case Study of Egypt. J. Eng. Sci. 2021, 49, 509–529.
22. Chadee, A.; Allis, C.; Rathnayake, U.; Martin, H.; Azamathulla, H. Data exploration on the factors associated with cost overrun
on social housing projects in Trinidad and Tobago. Data Brief 2024, 52, 109966. [CrossRef] [PubMed]
23. Alkhattabi, L.; Alkhard, A.; Gouda, A. Effects of change orders on the budget of the public sector construction projects in the
kingdom of Saudi Arabia. Results Eng. 2023, 20, 101628. [CrossRef]
24. Mahamid, I. Effects of project’s physical characteristics on cost deviation in road construction. J. King Saud Univ.–Eng. Sci. 2013,
25, 81–88. [CrossRef]
25. Mubarak, M.; Husin, S.; Oktaviati, M. External risk factors affecting construction costs. In Proceedings of the 3rd Interna-
tional Conference on Construction and Building Engineering (ICONBUILD 2017), Palembang, South Sumatera, Indonesia, 14
November 2017.
26. Devi, A.; Ananthanarayanan, K. Factors influencing cost over-run in Indian construction projects. In Proceedings of the
International Conference on Advances in Sustainable Construction Materials & Civil Engineering Systems (ASCMCES-17),
Sharjah, United Arab Emirates, 18–20 April 2017; p. 8.
27. Ndunguru, D.; Niyonyungu, F.; Yang, X. Quantification of the Influence of Factors Causing Time and Cost Overruns in Tanzanian
Construction Projects. Open J. Bus. Manag. 2020, 8, 2133–2147. [CrossRef]
28. Rajput, B.; Agarwal, A.; Yadav, S. Risk Factors Causing Cost Overrun in Highway Construction Projects. IUP J. Manag. Res. 2020,
XIX, 7–22.
29. Kavuma, A.; Ock, J.; Jang, H. Factors influencing Time and Cost Overruns on Freeform Construction Projects. KSCE J. Civ. Eng.
2019, 23, 1442–1450. [CrossRef]
30. Ali, Z.; Zhu, F.; Hussain, S. Identification and Assessment of Uncertainty Factors that Influence the Transaction Cost in Public
Sector Construction Projects in Pakistan. Buldings 2018, 8, 18. [CrossRef]
31. Muianga, E.; Granja, A.; Ruiz, J. Influence Factors on Cost and Time Overruns in Mozambicans Construction Projects: Preliminary
Findings. In Proceedings of the International Conference on Engineering, Project, and Production Management, Port Elizabeth,
South Africa, 26–28 November 2014; pp. 10–21.
32. Rathi, A.; Khandve, P. Study of Factors Influencing Cost Overruns: An Overview. Int. J. Sci. Res. 2016, 5, 334–336.
33. Niazia, G.; Painting, N. Significant Factors Causing Cost Overruns in the Construction Industry in Afghanistan. Procedia Eng.
2017, 182, 510–517. [CrossRef]
34. Bakri, A.; Razak, M.; Shukor, A. Identification of Factors Influencing Time and Cost Risks in Highway Construction Projects. Int.
J. Sustain. Constr. Eng. Technol. 2021, 12, 280–288. [CrossRef]
35. Bhavsar, V.; Alex, S.; Vaishnav, P.K.; Jose, A.; Koshy, N.; Atiwadkar, S. Investigation of critical factors influencing construction of
airports: The case of India. Int. J. Constr. Manag. 2022, 22, 2905–2913. [CrossRef]
36. Chadee, A.; Hernandez, S.; Martin, H. The Influence of Optimism Bias on Time and Cost on Construction Projects. Emerg. Sci. J.
2021, 5, 429–442. [CrossRef]
37. Amusan, L.; Afolabi, A.; Ojelabi, R.; Omuha, I.; Okagbue, H. Data exploration on factors that influences construction cost and
time performance on construction project sites. Data Brief 2018, 17, 1320–1325. [CrossRef]
38. Kaming, P.; Olomolaiye, P.; Holt, G.; Harris, F. Factors influencing construction time and cost overruns on high-rise projects in
Indonesia. Constr. Manag. Econ. 1997, 15, 83–94. [CrossRef]
39. Alfahad, B.; Alabdullah, S.; Ahmad, M. Investigation of the Critical Factors Influencing Low-Cost Green Sustainable Housing
Projects in Iraq. Math. Stat. Eng. Appl. 2022, 71, 310–329.
40. Haslinda, A.; Xian, T.; Norfarahayu, K.; Hanafi, R.; Fikri, H. Investigation on the Factors Influencing Construction Time and Cost
Overrun for High-Rise Building Projects In Penang. In Proceedings of the International Seminar on Mathematics and Physics in
Sciences and Technology 2017 (ISMAP 2017), Batu Pahat, Malaysia, 28–29 October 2017; pp. 1–11.
41. Lapidus, A.; Topchiy, D.; Kuzmina, T.; Chapidze, O. Influence of the Construction Risks on the Cost and Duration of a Project.
Buildings 2022, 12, 484. [CrossRef]
42. Yunna, W.; Qing, B.; Ping, L. The ISM Analysis on Influence Factors of Cost Control in the Wind Power Construction Project.
Phys. Procedia 2012, 24, 587–590. [CrossRef]
43. Tawfek, H.; Mohammed, H.; Razek, M. Assessment of the expected cost of quality (COQ) in construction projects in Egypt using
artificial neural network model. HBRC J. 2012, 8, 132–143. [CrossRef]
44. Jafari, A.; Rodchua, S. Survey research on quality costs and problems in the construction environment. Total Qual. Manag. 2013,
25, 1–13. [CrossRef]
45. Mashwama, N.; Aigbavboa, C.; Thwala, D. Investigation of construction stakeholders’ perception on the effects & cost of
construction dispute in Swaziland. Procedia Eng. 2016, 164, 196–205.
46. Antoniou, F.; Tsioulpa, A. Assessing the Delay, Cost, and Quality Risks of Claims on Construction Contract Performance. Buildings
2024, 14, 333. [CrossRef]
Buildings 2024, 14, 3399 19 of 19
47. Mashwama, N.; Aigbavboa, C.; Thwala, D. An Assessment of the Critical Success factor for the Reduction of Cost of Poor Quality
in Construction Projects in Swaziland. Procedia Eng. 2017, 196, 447–453. [CrossRef]
48. Love, P.; Matthews, J.; Sing, M.; Porter, S.; Fang, W. State of Science: Why Does Rework Occur in Construction? What Are Its
Consequences? And What Can be Done to Mitigate Its Occurrence? Engineering 2022, 18, 246–258. [CrossRef]
49. Field, A. Discovering Statistics Using Spss, 3rd ed.; SAGE Publications: London, UK, 2009.
50. Hinton, P.; McMurray, I.; Brownlow, C. SPSS Explained; Routledge: New York, NY, USA, 2014.
51. Beste, T.; Klakegg, O. Strategic change towards cost-efficient public construction projects. Int. J. Proj. Manag. 2022, 40, 372–384.
[CrossRef]
52. Scott, E.; Bommu, R. Efficient Construction Management: AI-Driven Strategies to Combat Cost Overruns. Int. J. Adv. Eng. Technol.
Innov. 2024, 1, 222–240.
53. Yilmaz, G.; Salter, L.; McFarlane, D.; Schonfu, B. Low-cost (Shoestring) digital solution areas for enabling digitalisation in
construction SMEs. Comput. Ind. 2023, 150, 103941. [CrossRef]
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual
author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to
people or property resulting from any ideas, methods, instructions or products referred to in the content.