2.DRAINAGE - Method Statement
2.DRAINAGE - Method Statement
DRAINAGE WORK
Company Doc. No. Contractor Ref. No. Date Revision
HSE DOCS-MST-DR -01 HSE-DOCS-264R15 07.02.2024 00
REVISION
ISSUE DATE DESCRIPTION REVIEW / STATUS
HISTORY
00 07.02.2024 DRAINAGE WORK
Contents:
1. Objective
2. Scope
3. References
4. Material
6. Procedure of works
7. Test
1. Objective
• Scope
HAC shall supply and install in accordance with the specification of material and
workmanship of drainage & condensate piping.
HAC shall complete install works, testing, witness testing at the site by the engineer, testing
and commissioning of the drainage & plumbing work.
• References
• Contract Specifications.
• Material Submittal.
• Design Drawings.
• Shop Drawings.
• Material
• Upon approval of the material and shop drawing submittals, Contractor shall survey the
QTY including fittings as per approved shop drawing and purchase the material as per
project schedule.
• Upon delivery to site, all pipes and fittings shall be stored indoor, in a clean, dry and
ventilated place.
• Procedure of works
• HAC carries out works as per approved Method Statement, drawings etc.
• The working area shall be protected as per risk assessment and HS&E plan.
• Toilet details and mechanical pipe sleeves location for both indoor unit refrigeration
pipes and sanitary fixtures ventilation. Block work (except the shaft walls) and water
• Waiting pipes, stub pipes and fittings from risers and underground pipes should be
• Assign the location of pipes in the wall or floor that is exactly as mention on the approved
toilet details shop drawing. Mark with the line corresponds to the total area to bury the
• Use block cutter or simply portable grinder to cut a side of block continuously along the
line that had been marked. Absolute care should be done not to cut or damaged the pre-
• By using sharp- pointed steel rod and other proper chipping tools, chip the block side to
• Standard fittings and materials must be used and all pipes and fittings must be joined
using the approved glue. Sanitary tee fittings for vent be fixed inclined 45° or slope from
• Level of the slab should be identified by surveyor before proceeding installation. Also
locate points as alternative reference point for pipe and pipe fittings installation.
• Install / layout the pipes at designated height, location and slopes (1% slope for sanitary
fixtures and 0.5% slope for A/C drain). Sanitary fixtures outlet location should also be
• Connection of drainage pipes other than water closet drain (i.e. A/C drain, lavatory drain,
bathtub drain and shower tray drain) should be slope toward gully trap floor drain based
• Absolute care should be imposed not to damage the water proofing upon installation.
• Install sleeves for pipes passing through the concrete walls. Put sealant in between the
• Check the pipes securely fixed, joint and capped before leak testing.
• Test
• Leak test for the installed pipes is to be carried-out with presence of inspector Engineer.
• Cap end or plug as required and fill with water to produce 1.5 meters head (if applicable)
at highest point of section tested. Let stand with no loss of level for a period of four hours.
After the approval of Inspector Engineer, cover the pipes with cement plaster or sand to
where it is applicable