1.Demolition - Method Statement

This method statement outlines the procedures for the safe and efficient demolition of flooring, ceiling, and partitions, detailing pre-demolition planning, site assessment, utility disconnection, and safety measures. It specifies the necessary equipment and resources, including removal tools and personal protective equipment, and emphasizes waste management and environmental considerations. The document also includes emergency response plans and quality assurance measures to ensure compliance with safety standards.

Uploaded by

waseem hallak
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
5 views5 pages

1.Demolition - Method Statement

This method statement outlines the procedures for the safe and efficient demolition of flooring, ceiling, and partitions, detailing pre-demolition planning, site assessment, utility disconnection, and safety measures. It specifies the necessary equipment and resources, including removal tools and personal protective equipment, and emphasizes waste management and environmental considerations. The document also includes emergency response plans and quality assurance measures to ensure compliance with safety standards.

Uploaded by

waseem hallak
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 5

METHOD STATEMENT Page 1 of 5

Demolition of Flooring, Ceiling & Partitions


Company Doc. No. Contractor Ref. No. Date Revision
HSE DOCS-MST-DEM -01 HSE-DOCS-264R15 07.02.2024 00

METHOD STATEMENT FOR DEMOLITION FLOORING, CEILING


& PARTITIONS

Project No: 264R15

REVISION
ISSUE DATE DESCRIPTION REVIEW / STATUS
HISTORY
00 07.02.2024 DEMOLITION

PREPARED BY: REVIEWED & APPROVED BY:


A.REFAI W.HALLAK

QA QC ENGINEER PROJECT MANAGER

HSE Documents-Method Statement for Demolition of Flooring, Ceiling & Partitions


METHOD STATEMENT Page 2 of 5
Demolition of Flooring, Ceiling & Partitions
Company Doc. No. Contractor Ref. No. Date Revision
HSE DOCS-MST-DEM -01 HSE-DOCS-264R15 07.02.2024 00

Table of Contents
1. Introduction .................................................................................................................................... 3
2. Scope ............................................................................................................................................... 3
2.1. Pre-demolition Planning: ........................................................................................................ 3
2.2. Site Assessment: ..................................................................................................................... 3
2.3. Utility Disconnect: ................................................................................................................... 3
2.4. Safety Measures:..................................................................................................................... 3
3. Equipment and Resources: ............................................................................................................. 3
3.1. Removal Tools: ........................................................................................................................ 3
3.2. Crane or Lifting Equipment: .................................................................................................... 3
3.3. Dump Trucks: .......................................................................................................................... 3
3.4. Personal Protective Equipment (PPE): .................................................................................... 4
4. Demolition Procedures: .................................................................................................................. 4
4.1. Disconnection: ........................................................................................................................ 4
4.2. Removal: ................................................................................................................................. 4
4.3. Demolition of Aboveground Components: ............................................................................. 4
4.4. Waste Management: .............................................................................................................. 4
5. Environmental Considerations:....................................................................................................... 4
6. Emergency Response and Communication: ................................................................................... 4
7. Quality Assurance and Documentation: ......................................................................................... 5
8. Conclusion: ...................................................................................................................................... 5

HSE Documents-Method Statement for Demolition of Flooring, Ceiling & Partitions


METHOD STATEMENT Page 3 of 5
Demolition of Flooring, Ceiling & Partitions
Company Doc. No. Contractor Ref. No. Date Revision
HSE DOCS-MST-DEM -01 HSE-DOCS-264R15 07.02.2024 00

1. Introduction
This method statement provides a detailed plan for the safe and efficient demolition of
flooring, ceiling & partitions. Various items (VI) flooring, ceiling & partitions. The objective of
this method statement is to highlight the step-by-step procedures, safety measures, and
equipment requirements necessary to carry out demolition activities.

2. Scope
The scope of this method statement covers the demolition of flooring, ceiling & partitions
within a specified area. It includes the removal of aboveground components, disconnection
of utilities, and the safe disposal of demolished materials.

2.1. Pre-demolition Planning:


Before commencing any demolition work, thorough planning is essential. The following
steps will be undertaken:

2.2. Site Assessment:


A detailed assessment of the site will be conducted to identify the location of existing
services, their condition, and potential hazards.

2.3. Utility Disconnect:


Proper coordination will be made with relevant utility providers to disconnect and isolate
the services. Permits and approvals will be obtained, and temporary utility services will be
arranged if necessary.

2.4. Safety Measures:


Safety plans and risk assessments will be prepared to identify potential hazards and
implement necessary control measures. This includes ensuring proper personal protective
equipment (PPE) for workers.

3. Equipment and Resources:


The following equipment and resources will be required for the demolition of services:

3.1. Removal Tools:


Removal tools such as saws, grinders, jack hummer, and shears will be used for remove
flooring, pipes, cables, and conduits.

3.2. Lifting Equipment:


If necessary, lifting equipment will be employed for the safe removal of heavy components.

3.3. Dump Trucks:


Dump trucks will be used for the transportation and disposal of demolished materials.

HSE Documents-Method Statement for Demolition of Flooring, Ceiling & Partitions


METHOD STATEMENT Page 4 of 5
Demolition of Flooring, Ceiling & Partitions
Company Doc. No. Contractor Ref. No. Date Revision
HSE DOCS-MST-DEM -01 HSE-DOCS-264R15 07.02.2024 00

3.4. Personal Protective Equipment (PPE):


All personnel involved in the demolition activities will be provided with appropriate PPE,
including hard hats, safety goggles, gloves, and safety boots.

4. Demolition Procedures:
The following steps will be followed during the demolition process:

4.1. Disconnection:
After exposing the services, disconnection will be carried out as per the relevant utility
provider's guidelines. This includes shutting off the water supply, disconnecting electrical
lines, and cutting telecommunications cables.

4.2. Removal:
Once the services are disconnected, they will be removed using appropriate removal tools
and lifting equipment. Care will be taken to prevent any damage to nearby structures or
services that need to remain intact.

4.3. Demolition of Aboveground Components:


Aboveground components such as ceiling, partition & screed will be demolished following
safe demolition practices. This may involve the use of removal tools, or other appropriate
equipment.

4.4. Waste Management:


Demolished materials will be sorted and appropriately disposed of non-recyclable materials
will be disposed of following country and local regulations.

5. Environmental Considerations
Environmental considerations will be taken into account throughout the demolition process.
Measures will be implemented to minimize noise, dust, and other potential pollutants. Spill
containment measures will be in place, and proper disposal of hazardous substances will be
ensured.

6. Emergency Response and Communication


Emergency Response Plans (ERP) will be developed, and all people involved will be
appropriately briefed on emergency procedures. Communication channels will be
established to enable prompt response and coordination in case of any incidents or
emergencies.

HSE Documents-Method Statement for Demolition of Flooring, Ceiling & Partitions


METHOD STATEMENT Page 5 of 5
Demolition of Flooring, Ceiling & Partitions
Company Doc. No. Contractor Ref. No. Date Revision
HSE DOCS-MST-DEM -01 HSE-DOCS-264R15 07.02.2024 00

7. Quality Assurance and Documentation


Routine and frequent, planned or unplanned inspections will be carried out to make sure
compliance with occupational health safety and environmental standards and the quality of
work. Proper and essential documentation, including daily progress reports, photographs,
and any relevant certificates or permits, will be maintained to ensure traceability and
recordkeeping.

8. Conclusion
This method statement outlines a systematic approach to the demolition of items,
emphasizing safety, efficiency, and environmental considerations. By following the outlined
procedures, utilizing the appropriate equipment, and implementing necessary safety
measures, demolition activities can be carried out successfully with minimal risks and
disruption to the surrounding environment.

9. Attachments
Risk Assessment

HSE Documents-Method Statement for Demolition of Flooring, Ceiling & Partitions