1.Demolition - Method Statement
1.Demolition - Method Statement
REVISION
ISSUE DATE DESCRIPTION REVIEW / STATUS
HISTORY
00 07.02.2024 DEMOLITION
Table of Contents
1. Introduction .................................................................................................................................... 3
2. Scope ............................................................................................................................................... 3
2.1. Pre-demolition Planning: ........................................................................................................ 3
2.2. Site Assessment: ..................................................................................................................... 3
2.3. Utility Disconnect: ................................................................................................................... 3
2.4. Safety Measures:..................................................................................................................... 3
3. Equipment and Resources: ............................................................................................................. 3
3.1. Removal Tools: ........................................................................................................................ 3
3.2. Crane or Lifting Equipment: .................................................................................................... 3
3.3. Dump Trucks: .......................................................................................................................... 3
3.4. Personal Protective Equipment (PPE): .................................................................................... 4
4. Demolition Procedures: .................................................................................................................. 4
4.1. Disconnection: ........................................................................................................................ 4
4.2. Removal: ................................................................................................................................. 4
4.3. Demolition of Aboveground Components: ............................................................................. 4
4.4. Waste Management: .............................................................................................................. 4
5. Environmental Considerations:....................................................................................................... 4
6. Emergency Response and Communication: ................................................................................... 4
7. Quality Assurance and Documentation: ......................................................................................... 5
8. Conclusion: ...................................................................................................................................... 5
1. Introduction
This method statement provides a detailed plan for the safe and efficient demolition of
flooring, ceiling & partitions. Various items (VI) flooring, ceiling & partitions. The objective of
this method statement is to highlight the step-by-step procedures, safety measures, and
equipment requirements necessary to carry out demolition activities.
2. Scope
The scope of this method statement covers the demolition of flooring, ceiling & partitions
within a specified area. It includes the removal of aboveground components, disconnection
of utilities, and the safe disposal of demolished materials.
4. Demolition Procedures:
The following steps will be followed during the demolition process:
4.1. Disconnection:
After exposing the services, disconnection will be carried out as per the relevant utility
provider's guidelines. This includes shutting off the water supply, disconnecting electrical
lines, and cutting telecommunications cables.
4.2. Removal:
Once the services are disconnected, they will be removed using appropriate removal tools
and lifting equipment. Care will be taken to prevent any damage to nearby structures or
services that need to remain intact.
5. Environmental Considerations
Environmental considerations will be taken into account throughout the demolition process.
Measures will be implemented to minimize noise, dust, and other potential pollutants. Spill
containment measures will be in place, and proper disposal of hazardous substances will be
ensured.
8. Conclusion
This method statement outlines a systematic approach to the demolition of items,
emphasizing safety, efficiency, and environmental considerations. By following the outlined
procedures, utilizing the appropriate equipment, and implementing necessary safety
measures, demolition activities can be carried out successfully with minimal risks and
disruption to the surrounding environment.
9. Attachments
Risk Assessment