savvopoulos2019
savvopoulos2019
Services Markets
Nikolaos Savvopoulos, Theodoros Konstantinou and Nikos Hatziargyriou
School of Electrical and Computer Engineering,
National Technical University of Athens (NTUA), Athens, Greece
Emails: [email protected], [email protected], [email protected]
Cost of AS [$]
2
300 3
0
200 0
−2
−4 100 −3
−6 0 −6
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Look ahead time [hrs] Hour
wrong prediction for clouds during these hours. On the the congestion of the distribution lines. If there is no constraint
contrary, the forecast related to solar generation at distribution violation, as happening in the remaining hours of the day,
network D2 presents an overestimation in comparison with the the cost of ancillary services represents only the balancing
actual observations of generation. Although load demand is requirement and shows similar results to the single AS market,
variable and uncertain, it can be considered predictable due to since the balancing problem is solved by the market run by
the extensive investigation of load forecasting techniques over the TSO.
the past decades. Therefore, the unbalances occurred by load The shared balancing responsibility AS market model
forecasting are neglected. proposes a market scheme where each system operator is
responsible for both balancing and congestion management
B. Results using only resources located at its own network. The resulting
The total unbalances in MW that need to be covered in AS costs, as shown in Fig. 4, are higher compared to the
the AS market are depicted in Fig. 3 and are calculated as other two market models since the separate markets are fully
the difference between the forecast (used in the DA market decoupled and the reserve resources are not pooled.
clearing) and the observation (used in the real time market). The active power dispatch of each flexibility resource within
Positive values correspond to upward regulation (system the investigated market schemes is presented in Fig. 5. The
operator buys electricity), while negative values correspond to results in Fig. 5(a), which correspond to the centralized AS
downward regulation (system operator sells electricity). Apart market, serve as a reference, since they represent the optimal
from the energy balance, the AS market may offer congestion solution. For several time points at the results of Fig. 5(a), we
management services, since DA does not necessarily consider note an simultaneous activation of both upward and downward
the whole transmission and distribution system constraints. regulation. At these time points, the system operator requires
The cost for AS for each hour of the day is presented upward regulation to tackle the distribution line congestion and
in Fig. 4. In the single AS market, the TSO can contract downward regulation for the balancing of the whole system.
directly ancillary services from all available sources, regardless During the hours that there is no line congestion we
the system they are connected (transmission or distribution). identify similar solution layouts between centralized, single
Therefore, the market result can achieve the most economic and local AS market, since a single system operator has the
point, reaching a total cost of 833.7 $, as shown in Table III. responsibility of balancing the whole system (transmission and
Nevertheless, in this coordination scheme the market operator, distribution). On the contrary, in local AS market scheme,
namely the TSO, is not considering the constraint violation of shown in Fig. 5(c), and during the hours that lines are
the distribution grid. For the specific day a total amount of congested, the generator located in bus 1017 increases its
10.87 MW needs to be redispatched or curtailed during the generation set-point to limit the overloading of distribution
real time operation of the network. The cost of this energy to line 1013-1015. Depending on the sign of balancing and
be covered is difficult to be estimated and compared to the AS congestion requirements, we identify an increase of the
market cost, since it might affect critical residential loads, but balancing requirement in case they are of opposite signs like
it can surely be assumed that it will be way higher than the in hours 9-11, or a decrease in case they are of the same sign
AS market cost. like in hours 12-19.
In the local AS, the DSOs are clearing a market for The active power dispatch of the AS resources for the
local congestion management and then the TSO is clearing shared balancing responsibility market model are shown in
a market for transmission system congestion management as Fig. 5(d), indicating higher utilization of all the AS resources.
well as balancing of the whole system. DER, located in the This is mainly driven by the balancing requirement that
distribution network, are participating in both markets; directly enforces each system operator to balance its system using only
in the local AS market of their distribution network and local resources. Additionally, in several moments during the
indirectly in the TSO AS market as an aggregated bid by day we identify both upward and downward regulation at a
the DSO. In Fig. 4, local AS market indicates higher cost, subsystem, since line congestion enforces activation of upward
especially during 8-19 hour. This increased cost is driven by regulation and balancing of the subsystem enforces activation
1017 (D1) 1017 (D1) 1017 (D1) 1017 (D1)
8 1005 (D1) 8 1005 (D1) 8 1005 (D1) 8 1005 (D1)
1 (TN) 1 (TN) 1 (TN) 1 (TN)
6 4 (TN) 6 4 (TN) 6 4 (TN) 6 4 (TN)
2012 (D2) 2012 (D2) 2012 (D2) 2012 (D2)
AS Dispatch [MW]
AS Dispatch [MW]
AS Dispatch [MW]
AS Dispatch [MW]
4 2004 (D2) 4 2004 (D2) 4 2004 (D2) 4 2004 (D2)
2 2 2 2
0 0 0 0
−2 −2 −2 −2
−4 −4 −4 −4
−6 −6 −6 −6
−8 −8 −8 −8
0 2 4 6 8 10 12 14 16 18 20 22 24 0 2 4 6 8 10 12 14 16 18 20 22 24 0 2 4 6 8 10 12 14 16 18 20 22 24 0 2 4 6 8 10 12 14 16 18 20 22 24
Hour [hrs] Hour [hrs] Hour [hrs] Hour [hrs]
TABLE III and the transmission and distribution line thermal rating.
C OST OF A NCILLARY S ERVICES Single AS market does not consider the distribution network
constraints and therefore cannot guarantee a feasible solution.
System Centr. AS Single AS Local AS Shared Bal AS
TN 1801.6 833.7 714.1 3455.5 Local AS market achieves the most efficient results which are
D1 - - 1087.5 2634.0 comparable to the one provided by the centralizes AS market
D2 - - 0 72.0 model. Finally, assuming adequate reserves in the distribution
Total 1801.6 833.7 1801.6 6161.5 system, shared balancing responsibility model will not violate
physical constraints, however it appears to be the least efficient
solution.
of downward regulation. These are considered as the main
reasons for the increased additional cost for ancillary services R EFERENCES
within this market scheme, as shown in Table III [1] REN 21 Steering Committee, Renewables 2018, Global Status Report.
The general performance of the three investigated AS Renewable Energy Policy Network for the 21st Century, 2018.
[2] Fraunhofer ISE. (2018) Energy charts. [Online]. Available:
market schemes shows that the single AS market can https://www.energy-charts.de/
achieve the most economic point but cannot guarantee [3] H. Wirth, Recent Facts about Photovoltaics in Germany. Fraunhofer
the prevention of distribution line constraint violation. Institute for Solar Energy Systems ISE, 2018.
[4] M. Birk, J. Caves-Avila, T. Gomez, and R. Tabors, “TSO/ DSO
For the cases that distribution lines are not congested, coordination in a context of distributed energy resource penetration,”
local AS market model may achieve results of the same in MIT Energy Initiative Reports, 2017.
economic performance, but extensive communication between [5] M. Caramanis, E. Ntakou, W. W. Hogan, A. Chakrabortty, and
J. Schoene, “Co-optimization of power and reserves in dynamic
the various system operators is required. Finally, the T&D power markets with nondispatchable renewable generation and
shared balancing responsibility model has limited real-time distributed energy resources,” Proceedings of the IEEE, vol. 104, no. 4,
communication requirements and this is depicted in the pp. 807–836, April 2016.
[6] A. Saint-Pierre and P. Mancarella, “Active distribution system
high operational AS cost for both balancing and congestion management: A dual-horizon scheduling framework for DSO/TSO
management. interface under uncertainty,” IEEE Transactions on Smart Grid, vol. 8,
no. 5, pp. 2186–2197, Sep. 2017.
IV. C ONCLUSION [7] Z. Yuan and M. Reza Hesamzadeh, “Hierarchical coordination of
TSO-DSO economic dispatch considering large-scale integration of
Derived by the necessity of developing local electricity distributed energy resources,” Applied Energy, vol. 195, pp. 600 – 615,
markets to increase the procurement of AS, we investigate 2017.
in this paper four types of AS market models, focusing on [8] N. Natale, F. Pilo, G. Pisano, G. G. Soma, M. Coppo, R. Turri,
G. Petretto, M. Cant, and G. Gigliucci, “Assessment of price and quantity
coordination schemes between DSO and TSO. The main of ancillary services provided by active distribution systems at the
goal is to increase the procurement of AS by facilitating TSO/DSO interface,” in CIRED Workshop 2016, June 2016.
distributed energy resources (DERs), flexible consumers and [9] A. Papavasiliou and I. Mezghani, “Coordination schemes for the
integration of transmission and distribution system operations,” in 2018
prosumers in distribution grids. The ideal market model of Power Systems Computation Conference (PSCC), June 2018.
a centralized AS market controlling the whole system is [10] Y. Tohidi, M. Farrokhseresht, and M. Gibescu, “A review on
compared to a single AS market, where the TSO activates coordination schemes between local and central electricity markets,” in
2018 15th International Conference on the European Energy Market
the DER for balancing and transmission system congestion (EEM), June 2018.
management, to a local AS market scheme, which promotes [11] R. D. Zimmerman, C. E. Murillo-Sanchez, and R. J. Thomas,
the participation of the DSO, and to a shared balancing “Matpower: Steady-state operations, planning, and analysis tools for
power systems research and education,” IEEE Transactions on Power
responsibility market scheme, where each system operator is Systems, vol. 26, no. 1, pp. 12–19, Feb 2011.
responsible for balancing and congestion management of its [12] F. Li and R. Bo, “Small test systems for power system economic studies,”
own system. The problem is formulated as a DC optimal in IEEE PES General Meeting, July 2010.
[13] W. M. Grady, M. J. Samotyj, and A. H. Noyola, “Minimizing network
power flow adopting cost-based objective function to identify harmonic voltage distortion with an active power line conditioner,” IEEE
the most economically beneficial plan, redispatching the DA Transactions on Power Delivery, vol. 6, no. 4, pp. 1690–1697, Oct 1991.
clearing results, while respecting the balancing of the system